    ANDHRA PRADESH GRAM PANCHAYATLAND DEVELOPMENT(LAY OUT&

    BUILDING) RULES,2002

    By

    G.Satya Vani, FACULTYEXTENTION TRAININGCENTRE,

    RAJENDRANAGAR, HYD-30

  • 8/22/2019 Lauout&Buildings

    2/37

    G.O.MS.NO.67 PR&RD DEPT. DATED :26.02.2002

    Short Title: APGPLD(L&B)Rules,2002.

    Commencement: Dated: 26.02.2002.

    Applicability: All GPS except the areas falling in

    UDA, SPECIAL Development Areas, Municipal

    corporations.

    These rules, shall apply to the extent of : levy of

    fees, inspections, monitoring, taking action onunauthorized developments & building permissions.

  • 8/22/2019 Lauout&Buildings

    3/37

    PART-A ; LAYOUT RULE-3

    APPLICATION IN LAYOUT

    PERMISSION:

    Every person, corporate body, Govt.,

    Private corporate body intends to

    undertake layout shall apply in writing to

    Executive Authority in annexure-A.

    Pattas prepared by Revenue dept. for the

    weaker section shall be in accordance

    with these rules.

  • 8/22/2019 Lauout&Buildings

    4/37

    APPLICATION FOR PERMISSION SHALL BE

    ACCOMPANIED BY

    Site plan: scale not < 1:1000 showing all physical

    details of land i.e., surrounding existing

    layouts/lands, existing approach roads.

    Layout plan: scale not < 1:500 showing boundaries

    of land, proposed no. of plots with dimensions,

    width of the proposed roads, area of open place.

    A statement of details: Dimensions of each plot, %

    of area under open spaces, roads, amenities, area of

    plot.

  • 8/22/2019 Lauout&Buildings

    5/37

    CONTD

    High tension / low tension electricity lines, watermains, sewer lines, telephone lines, alignment, rightto way of NHW, SHW, major/minor/district roadspassing through the layout site.

    Certificate of undertaking in prescribed form jointlyby owner & qualified surveyor.

    Copy of the ownership document.

    Copy of Non-encumbrance certificate.

    Certificate of demarcation of site by AD. Layout scrutiny charges and inspection charges as

    prescribed in the DTCP.

    Security deposit as prescribed by the Govt.

  • 8/22/2019 Lauout&Buildings

    6/37

    MINIMUM REQUIREMENTS FOR APPROVAL

    LAYOUT RULE-4

    Shall have approach through an existing road not < 10

    mts

    Minimum width of proposed roads in layout shall be

    10 mts for residential & 12 mts for others. Minimum open space at the rate of 10% of the total

    site area.

    Minimum plot size for Non residential layouts shall be300 sq mts & 18 sq mts for commercial buildings.

    If the land is abutting to NHW having < 60 mts width

    road, a service road of 10mts width shall be provided.

  • 8/22/2019 Lauout&Buildings

    7/37

    REQUIRED SPECIFICATIONS & CONDITIONS

    LAYOUT RULE-5 The owner of a site shall undertake the works under the

    supervision of E.O after intimation of approval by the

    E.O

    Leveling with suitable gradients.

    Formation of roads with sub-surface curbstones,

    metalling of the carriage way etc.

    Construction of drains and channelization of nalas.

    Undertake greenery.

    Fencing of open place.

    Street lighting.

    Protected water supply system.

  • 8/22/2019 Lauout&Buildings

    8/37

    APPLICATION SCRUTINY FEES & OTHER

    CHARGES

    The application scrutiny fee shall be paid to

    the DTCP as prescribed by Govt. from time totime.

    At present Rs.100/- per acre or minimumRs.1000/- up to 10 acres.

    Other charges: In addition to the above the EAshall levy development charges andbetterment charges as specified by thecollector/Govt.

  • 8/22/2019 Lauout&Buildings

    9/37

    SANCTION OR REFUSAL OF PERMISSION

    LAYOUT RULE-6

    Layout proposal fulfilling all conditionsmay be sanctioned with or with outmodification with in 90 days.

    If not disposed off with in a period of 90days from the date of receipt in the GPoffice shall deemed to have beensanctioned.

    How ever any construction/developmentof layout under deemed provision cannotbe in contravention of layout rules.

  • 8/22/2019 Lauout&Buildings

    10/37

    DURATION OF SANCTION

    LAY OUT RULE-7

    The permission for layout development

    shall remain valid for 2 years.

    If not completed with in the time shall

    be revalidated on application and onpayment of 10% of the fee & charges.

  • 8/22/2019 Lauout&Buildings

    11/37

    REVOKING OF PERMISSION

    LAY OUT RULE-8

    The Executive Authority/

    DPO may revoke any

    permission issued under

    these rules when ever it

    found false or wrong or

    any misinterpretation of

    facts and rules.

  • 8/22/2019 Lauout&Buildings

    12/37

    DEVIATIONS DURING CONSTRUCTION/

    UNDERTAKING OF LAYOUT WORKS

    LAY OUT RULE-9

    During the execution of any

    layout any deviation is madefrom the sanctioned plan the

    owner shall obtain revised

    sanction as per the aboveprocedure.

  • 8/22/2019 Lauout&Buildings

    13/37

    RESPONSIBILITIES AND DUTIES OF OWNER

    LAY OUT RULT-10

    The owner who has been

    given sanction shall be

    wholly and solely

    responsible for the quality

    of work and for ensuringsafety during the

    construction.

  • 8/22/2019 Lauout&Buildings

    14/37

    COMPETENT AUTHORITY FOR TECHNICAL

    APPROVAL

    LAY OUT RULE-11

    The DT&CP officer is the competent

    authority to accord technical approvals.

    The DT&CP officer shall accord tentatively

    approved layout with in 30 days.

    The E.O shall communicate the tentatively

    approved layout to the owner with in 15

    days.

    The applicant shall return his acceptance or

    further modifications if any with in 10 days.

  • 8/22/2019 Lauout&Buildings

    15/37

    TRANSFER OF OPEN SPACE

    All the roads and open spaces

    such as parks and playgrounds

    earmarked in accordance with

    these rules in a layout which is

    approved by the GP shall

    automatically stand transferred

    free of cost and vested with theGP free from all

    encumbrances.

  • 8/22/2019 Lauout&Buildings

    16/37

    SANCTION MAY BE REFUSED ON THE

    GROUNDS

    Application not received in the prescribed formand not accompanied by the documentsmentioned in rule 3.

    If the proposed roads or streets in the layout doesnot confine to the provisions of the act.

    If the proposed streets are not so planned as toconnect at least at one end with the street whichis already open.

    If adequate area has not been set apart for publicpurposes.

  • 8/22/2019 Lauout&Buildings

    17/37

    OFFENCES AND PENALTIES

    Any person who contravenes any of theprovisions of these rules be punished with a fineas prescribed by the government.

    In case of continuing offence a daily fine shallbe imposed until the contravention made goodor removed.

    Executive Authority shall request owner to take

    suitable actions including demolition. Take suitable action against technical personnel

    which include prosecution or debarring himfrom further practice up to five years.

  • 8/22/2019 Lauout&Buildings

    18/37

    IN CASE OF UNAUTHORIZED LAYOUTS

    The district panchayat officeror his officers may take any ofthe above actions and issue

    suitable instructions to theExecutive Officers or any other

    body for necessary actionagainst the unauthorized layouts, besides taking action onthe E O.

  • 8/22/2019 Lauout&Buildings

    19/37

    STATUS OF EXISTING GPS PREVIOUSLY

    APPROVED LAYOUTS

    Unauthorized layouts shall be got regularizedfrom the collector except the areas falling inUDA, SPECIAL Development Areas, Municipalcorporations.

    Without which no building permission shall beentertained or accorded.

    The regularization would be based on levy of prorata charges for shortfall of open spaces.

    Collection of pro rata betterment anddevelopment charges and improvement of theroads and drainage etc has to be born by theowner or colony.

  • 8/22/2019 Lauout&Buildings

    20/37

    BUILDING RULES

    PART-B

    Application for permission to construct

    building shall be accompanied with a site

    plan drawn to scale of 1:500.

    The existing approach road or means ofaccess.

    The boundaries giving the dimensions of the

    site. All existing buildings position in the site.

    The position of the site in relation to

    neighboring streets.

  • 8/22/2019 Lauout&Buildings

    21/37

    Space to be left about the building to securefree circulation of air, admission of light andaccess to scavenging purposes.

    Any existing physical features such as wells,

    drains and trees etc. The ground area of the whole property and the

    built up area

    The plans of the building drawn to a scale of1:100

    General specifications of proposed buildingand type of material used.

    CONTD

  • 8/22/2019 Lauout&Buildings

    22/37

    NO APPLICATION SHALL BE NECESSARY

    FOR THE FOLLOWING ALTERATIONS

    Providing or closing of a window or door orventilator not opening towards othersproperty.

    Undertaking fencing or construction ofcompound wall.

    Providing intercommunication doors.

    White washing /painting. Plastering and patch work.

    Re-flooring.

  • 8/22/2019 Lauout&Buildings

    23/37

    EXEMPTED BUILDINGS

    Railways National highways, state highways and major district

    roads.

    Works undertaking by the district administration/Zilla

    Praja Parishad/Mandal Parishad /Gram panchayat.

    Waterways.

    Ports.

    Airways and Aerodromes. Defense.

    Any other service which the government may declare to

    be a public utility services from time to time for the

    propose of this clause.

  • 8/22/2019 Lauout&Buildings

    24/37

    SITES CONSIDERED FOR BUILDING

    ACTIVITY:

    No Sites or parcel of land shall be used

    for building unless it is approved by

    the DT&CP but these rules shall not

    applicable in the case of :

    Sites and properties in existing

    settlement area.

    Farm buildings.

    Industrial and non-residential buildings

    abutting to highways/main roads.

  • 8/22/2019 Lauout&Buildings

    25/37

    MINIMUM PLOT REQUIREMENTS

    The minimum requirement of plotarea for non-residential, industrialbuildings and the buildingproposed consisting of G.F + 2floors and above exceptcommercial or mercantilebuildings shall be 300 sq. meters.

    The minimum requirement of plotarea for residential Apartments,Complexes shall be 335 sq mts.

  • 8/22/2019 Lauout&Buildings

    26/37

    MEANS OF ACCESS FOR BUILDING

    PERMISSION

    In Grama Khantam/ Settlementarea shall be 3.6 mts.

    Out side settlement area shall be

    10 mts. All residential/ non-residential

    buildings shall be 12 mts.

    Proximity of electricity supplylines withholding permission(Indian Elec. Act 1910).

  • 8/22/2019 Lauout&Buildings

    27/37

    PERMISSIBLE HEIGHT AND SETBACK

    REQUIREMENTS IN MINOR GP

    Height permissible 9mts for G + 2 floors

    in Gram Khantam and 13mts for G + 3

    floors in Revenue survey numbered areas

    in GPs. SETBACKS: front setback 1.50 mts, Rear

    setback 1.00 mts in Grama Khantam.

    REVENUE SURVEY NUMBERS: frontsetback 3.00mts, Rear setback 2.00 mts,

    Side Setbacks 1.50 mts on each side.

  • 8/22/2019 Lauout&Buildings

    28/37

    PERMISSIBLE HEIGHT AND SETBACK

    REQUIREMENTS IN MAJOR GP

    In Gram Khantam/ Settlement areas: Height

    permissible 9metres for G +2 floors

    SETBACKS: Front Setback 1.50 mts, Rear Setback

    2.00 mts. REVENUE SURVEY NUMBERS: Height permissible

    13 Mts for G + 3 floors for Residential & 15mts for G

    + 4 floors for Non-residential areas.

    For building abutting highways a building line of 6

    mts shall be maintained irrespective of the plot size .

    In case of corner plot the front building setback shall

    be left on all sides abutting the roads.

  • 8/22/2019 Lauout&Buildings

    29/37

    SETBACKS AND COVERAGE PERMISSIBLE

    Plot size (in sq mts) Minimum set backs (in meters)

    Road side Rear Sides

    (1) (2) (3) (4)

    Up to 50 0.75 0 0

    51 and up to 100 1.00 1.00 0.50

    101 and up to 150 1.50 1.50 1.00

    Above 151 and up to

    300

    1.50 2.00 2.00

    Above 301 and up to

    500

    3.00 2.00 2.00

    Above 501 3.00 3.00 3.00

  • 8/22/2019 Lauout&Buildings

    30/37

    RESTRICTIONS OF BUILDING ACTIVITY IN

    VICINITY OF CERTAIN AREAS

    No building shall be allowed in the bed of

    water bodies, rivers ,lake, pond or nala etc.

    No building activity shall be carried out within

    30 meters from the boundary of River and lake

    of surface area.

    15 mts from the boundary of lakes of surface

    area for less than 10 hec.

    9mts from Nalas, Canals etc.

  • 8/22/2019 Lauout&Buildings

    31/37

    .

    For building activity within the restrictedzone near airport or Defense areasnecessary clearance from the concernedauthorities.

    In case of sites in vicinity of high tensionelectricity transmission lines minimumsafety distance 3 mts .

    In case of Railway line, a minimum distanceof (30) mts shall be maintained from theedge of the Railway property.

  • 8/22/2019 Lauout&Buildings

    32/37

    PROJECTIONS AND EXEMPTIONS IN OPEN

    SPACES

    Chajjas/ weather sheds of width notexceeding 60 cm shall be allowed in thesetbacks.

    In case of plots more than 300 sq mts, a cowshed, open staircase may be allowed inresidential areas. Non residential area

    parking sheds, guardroom, overhead tank,sump, septic tank, well, balconies shall beallowed in Rear or Front setbacks.

  • 8/22/2019 Lauout&Buildings

    33/37

    PARKING REQUIREMENTS

    Category of building activity Parking area as percentage

    of total build-up area.

    (1) (2)

    Residential complexes, hotels,restaurants, lodges, cinema

    halls, business buildings,

    commercial buildings, kalyana

    mandapams, Offices.

    20%

    Hospitals, Institutional

    building, industrial schools,

    colleges and other educational

    buildings.

    10%

  • 8/22/2019 Lauout&Buildings

    34/37

    APPLICATION SCRUTINY FEES AND

    OTHER CHARGES TO BE LEVIED

    The Executive Authority shall levy application

    and scrutiny fees for all applications except

    weaker section housing.

    In addition to the above the EO shall levy

    development charges, Betterment charges asspecified by the collector or government.

  • 8/22/2019 Lauout&Buildings

    35/37

    SANCTION OR REFUSAL OF PERMISSION

    15 days in case of residential building

    permission and 30 days for other buildings

    Duration of sanction valid for 1 year.

    Revoking of permission: The E.O or DPO

    may revoke any permission.

    If any deviations made in sanctioned plan,

    the owner shall obtain revised sanction. The owner shall be wholly and solely

    responsible for development and safety.

  • 8/22/2019 Lauout&Buildings

    36/37

    PRIOR TECHNICAL APPROVAL

    All building permissions for complexes.

    All building permissions heights more than

    3 floors or 9 mts.

    All cinema Theaters, Petrol pumps, LPG

    Storage godowns, cellars, stilt constructions.

    All layouts.

    All commercial buildings, shops other than

    residential.

    .