leaders in the design, implementation and operation of markets for electricity, gas and water....

18
Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael Wagner Mathematics in the management of energy systems 29 January 2008

Upload: juan-mcelroy

Post on 01-Apr-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Leaders in the design, implementation and operation of markets for electricity, gas and water.

Portfolio Generation Investment Under Uncertainty

Michael Wagner

Mathematics in the management of energy systems29 January 2008

Page 2: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Agenda

• Investment Rationale• Balancing Generation and Demand• Generation Investment

− Coal vs Gas Generation

• Competitor Analysis• Construction & Operation Risk• Conclusions

Page 3: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Investment Rationale

• Major power companies− Vertically integrated utilities− Generation investment considered in context

• Generation & customer portfolio• Optimising generation-demand balance• Balancing commodity & carbon price risk exposure

− Maintaining portfolio competitiveness• Relative cost structures• Relative risk profiles

− Maximising returns on portfolio assets• Balance sheet financing

Page 4: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Generation-Demand Balance

• Managing generation demand balance− Strategy to source significant proportion of supply

from own generation

• Portfolio balance driver for generation investment− Examine both energy requirements & ability to

meet load profiles • Plant technology & economics• Plant flexibility

Page 5: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Example GB Portfolio Balances

• Example graphs in here??− long/short UK portfolio’s..

RWE average week day generation/demand profile in JanuaryAverage week day generation = 5,740MW, average week day demand = 6,841MW

0

2,000

4,000

6,000

8,000

10,000

1 5 9 13 17 21 25 29 33 37 41 45

Half-hour period

MW

Non-FGD Coal CCGT CHP Other Demand

EdF Average week day generation/demand profile in JanuaryAverage week day generation = 4,097MW, average week day demand = 7,241MW

0

2,000

4,000

6,000

8,000

10,000

1 5 9 13 17 21 25 29 33 37 41 45

Half-hour period

MW

Non-FGD Coal CCGT FGD Coal Gasoil Demand

Page 6: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

GB Example Portfolio Balances

Weekday Average - January 2007

-8000

-6000

-4000

-2000

0

2000

4000

6000

1 5 9 13 17 21 25 29 33 37 41 45Half-Hour Period

MW

Lo

ng

Others (Range) BE Centrica EdF

British Energy: Long Baseload

Centrica: Short Baseload & Shape

EDF: Short Baseload

EON, RWE SSE, SP:

~Balanced

Page 7: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Maintaining Generation-Demand Balance

• Future requirement for new generation capacity• Generation closures

− Most plant life can be extended• Investment requirements vary but typically less than new build

− Emissions restrictions (LCPD)• Closure of coal plant due to sulphur emissions

− Nuclear plant• Planned lifetimes - although extensions likely

− Hunterston & Hinkley Point recently granted extensions− Closures provide brown field sites

• Re-use existing infrastructure

• Load growth− Mature supply market

• Significant market share penetration unlikely − Load growth slowing

• Increasing energy efficiency

Page 8: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Investing in Generation Technologies• Range of generation technology options

− Nuclear• Supported by Government policy• Significant capital investment & long development timescales

− Need to build a fleet?− Too much technology exposure for single utility− Could utilities work together to develop nuclear build programme?

− Renewables (EU Targets)• Dependent upon financial support• Limited availability of sites & transmission

• Gas or coal still key technologies− Relatively rapid project development

• Particularly for CCGT plant

− Similar risk structures• Commodity price exposure• Carbon price/allocation exposure• Capital costs

− Coal significantly greater cost than CCGT

Page 9: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Coal vs Gas Competitiveness

• Relativity of gas, coal and carbon prices− No one technology guaranteed to always

be high merit• Competition between technologies

− Seasonality of gas prices• Competitiveness varies across year

− Volatile commodity prices• Coal plant particularly sensitive to carbon price

• Position varies across asset life

• Competition within technology merit order

Page 10: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Coal vs Gas CompetitivenessGB Power Sector Modelling

Coal vs Gas - High Case Scenario

Apr

-10

Apr

-11

Apr

-12

Apr

-13

Apr

-14

Apr

-15

Apr

-16

Apr

-17

Apr

-18

Apr

-19

Apr

-20

Mar

gina

l Cos

t £/M

Wh(

e)

Gas (eff=41-55%) Coal (eff=40%) Coal (eff=33%)

Coal vs Gas - Low Case Scenario

Apr

-10

Apr

-11

Apr

-12

Apr

-13

Apr

-14

Apr

-15

Apr

-16

Apr

-17

Apr

-18

Apr

-19

Apr

-20

Mar

gina

l Cos

t £/M

Wh(

e)

Gas (eff=41-55%) Coal (eff=40%) Coal (eff=33%)

New Coal Plant - Range of Load Factors

0.5

0.6

0.7

0.8

0.9

1.0

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

LF

Range of Scenarios

New CCGT Plant - Range of Load Factors

0.5

0.6

0.7

0.8

0.9

1.0

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

LF

Range of Scenarios

Page 11: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Investment DecisionsGB Power Sector Modelling

• Return on investment− Analysis of fully built-up project costs

• Coal or CCGT could provide returns under different commodity price scenarios

• Coal plant significantly greater capital cost than CCGT− Retrofitting reduces capital expenditure by reusing infrastructure

− Capital is a limited resource

• Portfolio balance sheet investment

• Project financing provides capital flexibility but with stricter terms

Difference in Fully Built Up Costs Across Range of Scenarios

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

Retro

fit C

oal

- G

as

(£/M

Wh

)Gas more competitive

Coal more competitive

Page 12: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Competitor Analysis

• Generation Investment for Utilities − Additional issues relative to merchant plant valuation

• Investments need to show economic returns

• Managing competitiveness of portfolio− Managing supply-demand balance

• Power and energy requirements across year

− Managing portfolio generation mix• Minimise portfolio costs

• Hedging portfolio power price risk

• Manage commodity and carbon price risk

• Significant driver of investment decisions− Understand portfolio commodity & power price risk

• Explore exposures under commodity scenarios

Page 13: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

GB Portfolio ExposureGB Power Sector Modelling

EDF Annual Generation

0%

10%

20%

30%

40%

50%

60%

70%

80%

2010 2014 2017 2020 2010 2014 2017 2020

High Gas High Coal

Pro

po

rti

on

of

Dem

an

d

FGD Coal Gas

SSE Annual Generation

0%

10%

20%

30%

40%

50%

60%

70%

80%

2010 2014 2017 2020 2010 2014 2017 2020

High Gas High Coal

Pro

po

rti

on

of

Dem

an

d

FGD Coal Gas

• EDF− Short

generation

− Dependence on coal plant

− Exposed under high coal scenario

• SSE− More balanced

− Mix of coal & gas plant

− Less exposed to commodity price volatility

Page 14: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Construction & Operation Risk

• CCGT projects− Established technology− Fixed price turnkey EPC contracts − Manufacturer O&M contracts with performance guarantees

• Coal Projects− Retrofit, Super-critical, IGCC− Relatively little recent European experience− Developers may have to share construction & operation risk− Significant restrictions in industry capacity

• Need for new plant to be flexible− May need to sacrifice thermal efficiency to achieve flexibility− Designs may not target high risk new technology

• Manufacturer guarantees on flexibility

Page 15: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Conclusions

• Portfolio generation investment decisions− Differences to merchant plant development

• Timing & technology decisions

− Managing portfolio supply-demand balance• Hedging portfolio power price risk

− Managing portfolio generation mix• Minimise portfolio costs• Manage commodity and carbon price risk

Page 16: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Conclusions

• GB Power market− Gas and coal generation likely to provide major capacity

additions• Relatively rapid project development

• Number of potential sites

• 16GW CCGT & 12GW coal project developments

• No clear technology winner− Coal or gas could provide returns under different scenarios

• Relativity of gas, coal and carbon prices & allocations

• CCGT projects− Established technology− Significantly lower development risk− Lower capital cost

Page 17: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Conclusions

• Man-marking between major portfolios− Mixed generation portfolios

• Minimising portfolio generation costs• Hedge against volatile coal, gas and carbon prices

− Move toward balance own generation and demand• Hedging exposure to power price

− Similar risk structures

• Investment decisions based on portfolio contribution− Relative competitiveness− Relative portfolio risk structure− Different portfolios have different generation investment

requirements• Portfolios will continue to develop range of projects

− Many will not be developed to completion− Real optionality in projects under development

Page 18: Leaders in the design, implementation and operation of markets for electricity, gas and water. Portfolio Generation Investment Under Uncertainty Michael

Thank You

Michael Wagner

[email protected]

IPA Energy + Water Consulting

41 Manor Place

Edinburgh

EH3 7EB

+44 131 240 0840