lecture 9 project scheduling: networks, duration...

33
Lecture 9 Project Scheduling: Networks, Duration Estimation, and Critical Path By : Prof. Lili Saghafi Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 1

Upload: phamhanh

Post on 25-Mar-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Lecture 9

Project Scheduling: Networks,

Duration Estimation, and

Critical Path

By : Prof. Lili Saghafi

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 1

Page 2: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Learning Objectives

After completing this chapter, students will be able to:

� Understand and apply key scheduling terminology.

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

terminology.

� Apply the logic used to create activity networks, including predecessor and successor tasks.

� Develop an activity network using Activity-on-Node (AON) techniques.

� Perform activity duration estimation based on the use of probabilistic estimating techniques.

09-02

Page 3: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Learning Objectives

After completing this chapter, students will be able to:

� Construct the critical path for a project schedule network using forward and backward passes.

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

network using forward and backward passes.

� Identify activity float and the manner in which it is determined.

� Calculate the probability of a project finishing on time under PERT estimates.

� Understand the steps that can be employed to reduce the critical path.

09-03

Page 4: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Project Scheduling

� Project scheduling requires us to follow some carefully laid-out steps, in order, for the schedule to take shape.

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

� Project planning, as it relates to the scheduling process, has been defined by the PMBoK as:

The identification of the project objectives and the ordered activity necessary to complete the project including the identification of resource types and quantities required to carry out each activity or task.

09-04

Page 5: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Project Scheduling Terms

�Successors

�Predecessors

�Network diagram

�Serial activities

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

�Serial activities

�Concurrent activities

ED

C

B

A F

09-05

Page 6: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Project Scheduling Terms

• Merge activities

• Burst activities

• Node

• Path

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

ED

C

B

A F

• Path

• Critical Path

09-06

Page 7: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Network Diagrams

FIGURE 9.2 Alternative Activity Networks for Term Paper Assignment Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

09-07

Page 8: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

AOA Versus AON

The same mini-project is shown with activities on arc…

E

C

DB F

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

C

ED

B F

C

…and activities on node.

09-08

Page 9: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Node Labels

Early Start ID Number Early Finish

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Activity FloatActivity Descriptor

Late Start Activity Duration Late Finish

09-9

Page 10: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Activity Node Labels Using MS Project 2010

FIGURE 9.4

09-10Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 11: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Serial Activities

Serial activities are those that flow from one to the next, in sequence.

FIGURE 9.5

09-11Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 12: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Activities Linked in Parallel (Concurrent)

When the nature of the work allows for more than one activityto be accomplished at the same time, these activities are calledconcurrent and parallel project paths are constructed through thenetwork.

FIGURE 9.6

09-12Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 13: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Merge Activity

FIGURE 9.7

09-13Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 14: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Burst Activity

FIGURE 9.8

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-14

Page 15: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Complete Activity Network

FIGURE 9.10

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-15

Page 16: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Developing the Activity Network Using MS

Project 2010

FIGURE 9.11

09-16Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 17: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Duration Estimation Methods

� Past experience

� Expert opinion

� Mathematical derivation – Beta distribution

� Most likely (m)

� Most pessimistic (b)

� Most optimistic (a)

2

2 = 6

b aActivity Variance s

− =

4 = TE

6

a m bActivity Duration

+ +=

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-17

Page 18: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

FIGURE 9.14 Symmetrical (Normal) Distribution for

Activity Duration Estimation

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-18

Page 19: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

FIGURE 9.15 Asymmetrical (Beta) Distribution for Activity Duration Estimation

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-19

Page 20: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Activity Duration and VarianceName: Project Delta

Durations are listed in weeks

Activity Description Optimistic Likely Pessimistic

A Contract signing 3 4 11

Table 9.2

09-20

B Questionnaire design 2 5 8

C Target market ID 3 6 9

D Survey sample 8 12 20

E Develop presentation 3 5 12

F Analyze results 2 4 7

G Demographic analysis 6 9 14

H Presentation to client 1 2 4

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 21: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Constructing the Critical Path

� Forward pass – an additive move through the network from start to finish

� Backward pass – a subtractive move through the

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

� Backward pass – a subtractive move through the network from finish to start

� Critical path – the longest path from end to end which determines the shortest project length

09-21

Page 22: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Rules for Forward/Backward Pass

Forward Pass Rules (ES & EF)� ES + Duration = EF

� EF of predecessor = ES of successor

� Largest preceding EF at a merge point becomes EF for

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

� Largest preceding EF at a merge point becomes EF for successor

Backward Pass Rules (LS & LF)� LF – Duration = LS

� LS of successor = LF of predecessor

� Smallest succeeding LS at a burst point becomes LF for predecessor

09-22

Page 23: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Project Delta Information

Project Delta

Activity Description Predecessors Estimated Duration

A Contract signing None 5

Table 9.4

09-23

B Questionnaire design A 5

C Target market ID A 6

D Survey sample B, C 13

E Develop presentation B 6

F Analyze results D 4

G Demographic analysis C 9

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 24: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

FIGURE 9.16 Partial Project Activity Network with Task Durations

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-24

Page 25: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

FIGURE 9.18 Activity Network with Forward Pass

09-25Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 26: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

FIGURE 9.19 Activity Network with Backward Pass

09-26Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 27: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

FIGURE 9.20 Project Network with Activity Slack and Critical Path

Note: Critical path is indicated with bold arrows.

09-27Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 28: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

AON Network with Laddering Effect

FIGURE 9.24

09-28Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 29: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Laddering ActivitiesProject ABC can be completed more efficiently if subtasks are used

A(3) B(6) C(9) ABC=18 days

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Laddered ABC=12 days

A1(1) A2(1) A3(1)

B1(2) B2(2) B3(2)

C1(3) C2(3) C3(3)

09-29

Page 30: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Example of a Hammock Activity

FIGURE 9.25

09-30Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Page 31: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Reducing the Critical Path

� Eliminate tasks on the CP

� Convert serial paths to parallel when possible

� Overlap sequential tasks

Shorten the duration on critical path tasks

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

� Shorten the duration on critical path tasks

� Shorten

� early tasks

� longest tasks

� easiest tasks

� tasks that cost the least to speed up

09-31

Page 32: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Summary

1. Understand and apply key scheduling terminology.

2. Apply the logic used to create activity networks, including predecessor and successor tasks.

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

including predecessor and successor tasks.

3. Develop an activity network using Activity-on-Node (AON) techniques.

4. Perform activity duration estimation based on the use of probabilistic estimating techniques.

09-32

Page 33: Lecture 9 Project Scheduling: Networks, Duration …wordpress.viu.ca/profsaghafiprojectmanagement/files/2014/...Title Project Management Author Professor Lili Saghafi Created Date

Summary

5. Construct the critical path for a project schedule network using forward and backward passes.

6. Identify activity float and the manner in which it is determined.

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

is determined.

7. Calculate the probability of a project finishing on time under PERT estimates.

8. Understand the steps that can be employed to reduce the critical path.

09-33