lifting the lid on the doa/poa arrangement ... · doa/easa, but this is a backstop to a good...
TRANSCRIPT
Lifting the lid on the DOA/POA arrangement … Administrative chore or key document for Performance ?
Mark Barker 21st March 2017
Introduction
Mark Barker
Principal Airworthiness Surveyor Production, SAFA and Military Sector
EASA Production Organisation Approvals (POA) Manager CAA Focal for MAA Design Approved Organisation Scheme (DAOS)
2
Subjects
What are we finding ?
The DOA/POA arrangement – Key requirements
Important Role of the Manufacturing/Production Engineer
Quality Escapes, Concessions and the Performance Conversation
Comparison of Findings to key risks from the Prime and SME Manufacturing Groups
5
8
2016
0
5
10
15
20
25
30
35
40
45
50
55
60
Subcon C
ontrol
Design Interface
Process C
ontrol
Quality Audit
Exposition
Facilities
Form 1 C
ompletion
Records/R
ecord Work
Personnel Q
ualification
Tooling
Facilities
Ident & Traceability
Issues Reports
Design Interface Findings
Always in the Top Three …
In 2016 alone, 51 findings directly allocated by Surveyors
Just outside the Top 12, but increasing …
20 findings of POAs unable to demonstrate manufacture to Approved Data
19 findings of lack of effective control of Concessions
Taken together, Link with Design is the subject generating the highest level of non-conformance across POA
9
Requirement Areas:-
Entry Criteria for POA
Demonstration of links to Approved Design Data
Direct Delivery Authority – Key for FAA, protection against suspect unapproved parts
No direct equivalent in other Industries
One of the Part 21 ‘deltas’ to ISO9000
10
Eligibility – 21.A.133
11
– The applicant shall:
a) justify that for a defined scope of work, an Approval under this subpart is appropriate for the purpose of showing conformity with a specific design; and
b) holds or has applied for an Approval of that specific design; or
c) have ensured, through an appropriate arrangement with the applicant for, or holder of, an Approval of that specific design, satisfactory co-ordination between production and design.
Links to Design – 21.A.133
12
• 133b/c Does the Applicant have suitably documented arrangements (see AMC No 2 to 21.A.133b&c) with a DOA to ensure satisfactory co-ordination including:
• 133b/c The timely transfer of all airworthiness and design data (Specifications, Drawings, Service Bulletins etc.)
• 133b/c The responsibilities & procedures of the applicant for developing and validating manufacturing data against design & airworthiness data supplied
Links to Design – 21.A.145
13
• 145b2 Does the applicant have an adequate and effective
procedure covering verification of production data with applicable airworthiness and design data . Where the POA develops its own manufacturing data from the design package, procedures are required to demonstrate correct transcription of the design data.
• 145b2 Is there an adequate and effective procedure to define traceability of such data to each product, part & appliance for the purpose of certifying safe operation and conformity
Receipt of Design Data is the start point
14
• Production often represented as ‘build to print’ – too simplistic.
• Design data is rarely sufficient to actually manufacture without generating and validating further data.
• In effect, design ‘activity’ without holding a design approval – Production/Manufacturing Engineering.
• May not be reviewed under external QMS approvals.
Process Works
Instructions CNC/CMM
Programmes Involvement in
FAIRs Bill of
Materials
Manufacturing Drawings
Routings/ Travellers
Manufacturing Sequences
Process Layouts
Involvement in Concessions
Purchase Order
Descriptions
Tooling Drawings Build Manuals
PRODUCTION/ MANUFACTURING
ENGINEERING
Welding Processes
Continuous Improvement
MRP Item Masters
Obsolescence Management
Production Methods
What are we looking for ?
16
• Regardless of whether the manufacture is conventional machining/assembly, CNC, composite layup or ALM, the question set is the same:-
• Who has approved the new/changed process/document ?
• Are they authorised in the Company procedures ?
• Is there evidence of validation of the change to the Design Data ?
• To what extent does the design organisation (i.e. the DOA) expect to be involved in this process ?
Links to Design – 21.A.133
17
• 133b/c Which persons or offices are responsible for
controlling the above arrangements and associated data
• 133b/c Acknowledgment by the holder of the TC/STC/repair or change approval/ETSO authorisation that the approved design data provided, controlled and modified in accordance with the arrangement are recognised as approved.
• AMC No. 1 references Intermediate Production Organisation (IPO) as allowed provided overall control is maintained.
• AMC No. 2 permits demonstration of interface via internal company procedures where the DOA and POA are the same legal entity but the arrangement must still be documented.
Intermediate Production Organisation
18
• Evidence that the Design Holder has visibility of the
lower-tier arrangement either directly or via flow-down
• POA awareness and access to the associated procedures, otherwise how does the organisation know how to work and where to report problems ?
• In case of FAA PMA, the PMA Holder may not own the design date - ‘licensing’. Has the ability to accept changes been delegated to the IPO or not ?
Why is all this important ?
At the very least, if an effective arrangement cannot be demonstrated the POA will be unable to make further EASA Form 1 releases of that part until addressed.
Immediate impact on business
Reduction of confidence in performance
If a systemic issue or if affecting parts with immediate airworthiness implications, then Level 1 Finding with wider effect on the approval – Limitation or Suspension
19
Safety Severity and Level 1
All findings are ranked for Safety Severity:- High, Moderate and Low.
Of the 594 Production Findings, 29 (4.8%) were ranked as High.
6 relating to Approved Data 3 relating to Design Links
CAA Project on consistent approach to Level 1
findings, results agreed by EASA.
20
Level 1 decision process
Is it a significant non-compliance with the requirement?
• Non-airworthy • Non-conformity • Fundamental • Systematic • Likely to happen
again
• Incompetence • Questionable character/culture • System/process failure • Resources • Inadvertent exposure of question
database
Level 1 decision process
Is it a significant non-compliance with the requirements?
Does it lower safety standards and hazards flight safety?
• Focus on the Non-conformance (not solely on the evidence of the non-conformance)
• Non-airworthy condition • Release of a part not
complying with design data • Compromised training
• A Hazard to flight safety will not always lead to a catastrophic event , consider critical parts
Level 1 decision process Discuss the potential level 1 with Sector Manager /
Principal (Immediate action required: revoke, limit or suspend)
• Advise org that a significant non-conformance has been identified • Discuss with manager prior to raising as a level 1 with org • Possible restrictions – approval/ratings/scope/locations/ • Corrective action plan timelines • Formal Closure process engaging with Sector Management
• The organisation cannot demonstrate that an item is in conformity with approved design data and is safe to fly • Design data not available
• Manufacturing processes not i.a.w. approved data • Incorrect/damaged tooling not i.a.w. approved data
• The organisation is not adequate to support the approval or part thereof due to: • Lack of Accountable Manager/nominated personnel • Competence of staff • Escalation of level 2 findings
• Falsification of records • Failure to respond to high safety severity findings within the agreed timescales • Denied access (after 1 written request) • Repeat significant finding
Consider the implications of the systemic breakdown of the quality system
Areas that could result in a Part 21G Level 1
• Both …
• Poor definition of who is responsible for what has been a feature of several recent reportable incidents, leading to uncontrolled introduction of changes into the field and subsequent restrictions of approvals.
• We will be sampling as part of our product audits, and we need a better view when judging POA performance.
So, DOA/POA Interface:- Key Document or Administrative Chore ?
25
Links to Design – 21.A.133
26
• 133b/c & 139b1 The arrangements to assist the DOA with airworthiness matters (i.e. traceability of parts & processes, retrofitting, technical information, deviations etc.)
• 133b/c Part 21 requirements such as 21.A.145b, 21.A.165c, f and g (compliance to design, DOA/POA interface requirements)
• 133b/c The arrangements to assist the DOA in showing compliance prior to type certification
• 133b/c & 139b1 The procedures to deal adequately with non-conforming parts (i.e. parts that do not conform to design data)
Escapes, Concessions and Occurrences
27
• Several recent incidents where NAAs (not just CAA) first became aware of production issues as a result of an EASA Airworthiness Direction with no prior communication from the POA.
• Addition to current NPA (2016-19) Rule Change to include need to advise NAAs on Occurrence Reports as well as the DOA/EASA, but this is a backstop to a good relationship between the National Authority and the POA.
• As the prime purpose of the POA is to manufacture to the approved Design Data, a Quality Escape or Concession is an important indicator of performance.
The Performance Conversation
28
• Specific meetings with Accountable Manager established with Entities as part of the CAA Performance Based Regulation (PBR) process.
• Includes specifics of company performance in complying to POA requirements, trends in Occurrence Reporting, Concessions, First Time Pass Rates, Scrap Costs etc.
• Entities concept currently restricted to larger organisations approvals with multiple approvals, but we need an understanding of overall POA performance in this area to support surveillance planning.
Amendment to Expositions
29
• Where an Occurrence Report to EASA/DOA is made as a result of production non-compliance, the National Authority should be advised.
• Using a similar approach to Leaflet C-180 on Suppliers, Exposition section on Procedures for Non-Conforming Product to include a trend statement for external escapes/concessions.
2014 – X 2015 – Y 2016 – Z
Amendment to Expositions
30
• Data expected to be available from Organisation’s internal Management Review.
• No specifics to maintain confidentiality.
• Does not include planned Production Permits or where change is initiated by Design Holder.
• Will be discussed during oversight audits (Root Cause and Prevention of Recurrence) and to inform surveillance planning.
Subjects
What are we finding ?
The DOA/POA arrangement – Key requirements
Important Role of the Manufacturing/Production Engineer
Quality Escapes, Concessions and the Performance Conversation
Comparison of Findings to key risks from the Prime and SME Manufacturing Groups
32
33
2016
0
5
10
15
20
25
30
35
40
45
50
55
60
Subcon C
ontrol
Design Interface
Process C
ontrol
Quality Audit
Exposition
Facilities
Form 1 C
ompletion
Records/R
ecord Work
Personnel Q
ualification
Tooling
Facilities
Ident & Traceability
Issues Reports
PAMG High Top 10
35
Risk Industry + CAA High Response
9. Tier 2/Tier 3 Supply 77 (1st) 106 (1st) 9 (1st)
23. Lack of Risk Management for Supply 70 (2nd) 95 (2nd) 7 (2nd =)
7. Emergent Technology incl. ALM 67 (3rd) 94 (3rd) 6 (3rd)
18. Incoming Competency levels 63 (4th) 86 (4th) 7 (2nd =)
8. Special processes, NADCAP, Crimp .. 62 (5th) 83 (5th) 4 (5th =)
19. NDT Skills, competence/retirement 59 (6th) 80 (7th) 5 (4th =)
12. Common approach on non-EU release 59 (6th) 70 (13th) 5 (4th =)
13.Policing of intent of design data/IPR 59 (6th) 77 (8th) 4 (5th =)
14. PMA +NAA training in acceptance 59 (6th) 72 (12th) 4 (5th =)
26. Lack of Lateral View of Escapes 58 (7th) 81 (6th) 4 (5th =)
SME Top 10 Areas
36
Risk Score
Raw Material Supply 74
Subcontractor Control 63
Capacity/Availability of Subcontractors 46
Production Competence 42
Supplier N/C to Purchase Order 41
Procurement not Involving Engineering 38
Flow down of treatment requirements 32
Legacy Support/Obsolescence 28
Single Source Supply 26
Competency Incoming 25
Proliferation of prime requirements 24
Correlation Areas
Several areas selected for Agenda Items today
Competency:-
22 direct findings on Competency 20 on Authorisations 13 on Certifying Staff 12 on Continuation Training …
Where do you think the challenge areas are ?
You all use other POAs – are we looking in the right
areas affecting you ?
37