L.Mandelli CSN1 Trieste 20 Settembre 06 1
Overall ATLAS Status – September 06
• Status of the detector and schedule
• ATLAS financial situation
• Atlas organization toward the Data Taking period
• ATLAS – It 2007 Budget
• Conclusions
L.Mandelli CSN1 Trieste 20 Settembre 06 2NB: It’s the first cryogenic magnet operated underground at LHC !
Central Solenoid
All cryogenic and control connections done.
Cooled down first at 75K with shield refrigerator and after at 4K with the main refrigerator (17/23 May- 5 days)
Preliminary exitation tets done in July at 1kA (0.26T))
After closing the EC ( 26 July) the solenoid was excited in steps up to the nominal I=7330 A (2T)A limit of 8 kA was reached followed by a Slow Dump (discharge on the RDU without quench)
The Field Mapping followed in August (2-8/08)
The solenoid is commissioned
connections
L.Mandelli CSN1 Trieste 20 Settembre 06 3
7995 A7330Asd
current Voltage
Solenoid: cooling down excitation
L.Mandelli CSN1 Trieste 20 Settembre 06 4
Solenoid Field Mapping
oThe field is mainly due to the coil. The effect of the Tile Cal iron is of the order of 4.5% and slowly varying with z
oThe tracker need a precision of 5 10-4 on the bending power requiring a precision of 10 G on the field
oTwo arms at 90° rotating and moving in z bring 48 Hall probes
o4 NMR probes are fixed on the warm wall of the cryostat for permanent monitor (BT field)
o181 (z) X 16(phi) x 48 = 139k meas ( 6/dm3 + special runs (middle and end) + runs at 5kA,7kA and 7.85kA
L.Mandelli CSN1 Trieste 20 Settembre 06 5
Solenoid Mapping - Preliminary
Z position
R=12cm
R=120 cm
Bc-Bm
Bc-Bm
10G
20G
• The mapping campaign worked very well, in all together 50 hours the magnetic field was measured on 250.000 points inside the solenoid volume (4 different current values)
• Dispersion of measurments is of few Gauss
• Furthermore results are compared with models of coils + magnetized iron
• Preliminary results with an idealised coil gives already agreement < 20G
• The aim to deliver a field map of the ATLAS solenoid with an absolute precision of 5 10-4
will certainly be reached after an extensive analysis of the data
L.Mandelli CSN1 Trieste 20 Settembre 06 6
L.Mandelli CSN1 Trieste 20 Settembre 06 7
Barrel Toroid Status
Vacuum < 5 10-5mbar reached after leaks repair Cooling down. At 4K 30 Aug
11 16 21 26 31 36 41 46 51 56 61 66 71Timedays50
100
150
200
250
300
350
TemperatureK 1st Cool Down
Max DT ~ 40 K
Guasto a una turbina del
refrigeratore
Ripresa raffreddamento
Temperatura schermi termici
Temperatura bobine
60 d
L.Mandelli CSN1 Trieste 20 Settembre 06 8
Barrel Toroid test programRemind: all new items: Cryoring, Current Lead Cryostat, bottom Valve box, need to be tested!Phase 1: BT Characterization & commissioning test 1 week ( from 23d September)1- RRR measurement and Self inductance measurement - Ramp up current to 200 A - 2- Magnetic measurement on BT - steady state at 300 A - 4 - Commissioning test of main USA15 power supplyPhase 2: Commissioning test / current 1kA - 5kA Phase 2: Commissioning test / current 1kA - 5kA : : 2.5 weeks - Beginning October1- Current up to 5 kA2- Check Quench Heaters3- Check Magnet Safety System4- Check mechanics deformationPhase 3: Full power BT current test / current 10kA to 20.5kA by steps : over 1 month from end October1.Current uo 20.5KA only after accurate cavern cleaning (20 ottobre) 2.Current raised in steps 10, 15 kA, 20kA3.Check mechanics and quench system
-
L.Mandelli CSN1 Trieste 20 Settembre 06 9
ECT-A Status July
• Story• Design and engineering by RAL• Vessel and cold mass contracted
by Nikhef• The firm in charged failed• Peaces at CERN in 04 with 2 years
delay
At present cold mass inserted in vacuum vessel.
• Next: transfer load on vessel, Complete mechanics and cryo (turret & services, thermal shield on end plate, JT shielding)
• Close and vacuum test• Test at 80K in front of B180• Transport and lower in cavern
middle Sept. An adventure in itself !
• Many unknown. Critical. If delay Big Wheel-A will delay
L.Mandelli CSN1 Trieste 20 Settembre 06 10
End Cap Toroid A- 2 Severe proble found in the engeeniring
of the mechanics which trasfers the forces acting on the cold mass to the cryostat
ECT cold mass is pulled into the BT with ~260 tons taken by 16 tie rods that transfer load to the vessel and then to the 8 BT vessels trough the 8 AFT connection points
Design assumed infinite stiffness of vessel during integration and 0.5mm tolerances. Impossible to align and furthermore they would brake!
Redesign to make them adjustable after closing, transport, cooling down in cavern
Bring the AFT connections through the end plate to the outside, 32 new feed-troughs
Problem solved, But takes time…….
Tie rods
L.Mandelli CSN1 Trieste 20 Settembre 06 11
ECT – New Schedule
ECT-AECT-A• Closing vessel Oct-Dec 06• Vacuum test during X-mass• Transport to 80K test (outside B180) on 1 Feb• Transport to point 1 in March 07. Connections in cavern Mar-Jun 07
Details of installation, shield & muon chambers to be studied
ECT-CECT-C• Cold mass ready by Dec 06 in B191; vessel opening can not be done
before ECT-A is out of B191• Cryostat integration Feb-Apr 07• Vacuum test and preparations for transport May 07• 80K test in May-June• Transport to point 1 by end of Jun 07
• This totally upset the Mu-EC assembly. New planning under study
L.Mandelli CSN1 Trieste 20 Settembre 06 12
Mu End Caps and End Caps Toroids – First thoughts
L.Mandelli CSN1 Trieste 20 Settembre 06 13
Status of Barrel chamber installation• 424 out of 656 barrel chambers
installed
• -> 65% . It was foreseen 72% end of August
• Main problem has been either access and crane availability or the actual installation of the chambers on the rails than the chamber availability.
• Lot of problems inside the detector when moving the chambers to their final positions: services out of envelope, poor access, scaffolding in front of the chambers, etc.
• During the last two months an average rate of 3.5 chambers per day was reached.
• RPC BOL completed- About 10 BML remain to be retrofitted
Muon barrel chambers (all)
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
14-Dec-05 02-Feb-06 24-Mar-06 13-May-06 02-Jul-06 21-Aug-06 10-Oct-06 29-Nov-06 18-Jan-07
Extrapolation assumes 3.7 ch/d
End November
L.Mandelli CSN1 Trieste 20 Settembre 06 14
LV1 Trigger ( only Mu)
All 800 Splitter boxes and PAD processors produced
LV1 work ongoing in BB5 in parallel to stations commissioning. All chamber tested with test–pulses before installation
PAD integration on chambers previously installed brought forward
Common data taking with LV1 ( RPC; MuCTPI;MUCTP) , RPC and MDT performed with 3 middle and 3 outer stations.
Laboratory tests of LV1 RPC Sector Logic and ROD ongoing
L.Mandelli CSN1 Trieste 20 Settembre 06 15
L.Mandelli CSN1 Trieste 20 Settembre 06 16
Night 14.08.06
RPC provided trigger from sector 13A at ~ 40Hz coincidence between two middle planes (yellow) in both eta and phi
Large RPC (green) is also read out
Tile reads
ROS + event building
Muons +Tile Combined
L.Mandelli CSN1 Trieste 20 Settembre 06 17
L.Mandelli CSN1 Trieste 20 Settembre 06 18
Mu spectrometer EC
staged
Big wheel1 MDT3 TGC
Inner/Small Wheel EOWall Wheel
L.Mandelli CSN1 Trieste 20 Settembre 06 19
Mu wheels
Sectors assembly was on critical path. Now ok thanks to extra manpower (3 sector/w)
Side-C SectorsSide-C Sectors
TGC-1, TGC-2, MDT completed
TGC-3 4/12 sectors done. Completed in November
Side-A Sectors Side-A Sectors
MDT-1 3/16 sectors done. Completed mid October tooling for TG’s
TGC-1 1/12 sectors done. Completed in parallel wit TG-C-3
Assembly of sectors in wheels on the end wall (HO). Wheel1 Completed
Once one wheel completed put on chariot.
Assembly of small wheels started in B191 and will be mounted in front of the ECT’s in summer 07
EO Wheels is following
L.Mandelli CSN1 Trieste 20 Settembre 06 20
Installation of TGC-1-C
TGC-C-1 completed !
L.Mandelli CSN1 Trieste 20 Settembre 06 21
Calorimetry – Barrel-LArIn June barrel was cooled down and filled with LAr
Calo:HV test gave 18 single sided and 1 double sided shorts. Upsetting ! ( were 7 in B180)
Presampler: 15 single side shorts (like B180)
Attempt of burning only partly succesfull: 4/4 on preshower 1/8 Calo
Decision to empty and refill with condensation (to move “dust”). Done
At present at 16 KV: Calo: 10ss and 2ds – Preshower 7s
Commissioning Phase1 completed
CR taken with tile trigger
Tiles Follow well. Phase1 terminated
LVPS still on critical path. Phase2 and 3 Commissioning started
A double side short gives a 0.2% acceptance loss
L.Mandelli CSN1 Trieste 20 Settembre 06 22
Calo End Caps (LAr+Tiles)
Both EC are in the pit with the Tile EB assembled.
EC-A ( lowered in the pit in March) will be the first to becooled down (Oct 06)Comm. Phase1 well advanced
EC-C will start cool down in Jan. 07
Gap, cryo and MBS mounted on both EC
EC-C in parking position
L.Mandelli CSN1 Trieste 20 Settembre 06 23
Prev | Index | Next
ID-B Status Pixel
Congratulations !
Layer 2 half shell
L.Mandelli CSN1 Trieste 20 Settembre 06 24
ID-B Status SCT & TRT Insertion of SCT in TRT already reported
From then intensive test and commissioning of services
All reported leakage problems solved
CR run in SR1 with 1/8 of TRT and 1/4 SCT. 450k events collected with combined read out. No Xtalk and noise increase observed.
SCT+TRT inserted in August after B field measurement
Connections of services and commissiong phase1 will take about 4 months.
Delicate since when EC inserted almost unaccessible
L.Mandelli CSN1 Trieste 20 Settembre 06 25
Prev | Index | Next
L.Mandelli CSN1 Trieste 20 Settembre 06 26
Prev | Index | Next
L.Mandelli CSN1 Trieste 20 Settembre 06 27
Prev | Index | Next
Congratulations !!!
L.Mandelli CSN1 Trieste 20 Settembre 06 28
ID- EC StatusID-C and ID-A will be tested and commissioned in SR1
Both EC’s RFI in December
Pixel insertion aroud April
ECT problem requires to define schedule details
L.Mandelli CSN1 Trieste 20 Settembre 06 29
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
ID B
ID A J
N
Cold tests
Limited access (ECT partially inside, half truck)
ID C
Pix
el
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
Endcap Cal. A services
Cold tests
ID Barrel connection and testing (side C access via lift only!)
Sep '07 Oct '07
EO, side A
Oct '07
JF
Sep '07Oct '06
Jun '07
Big Wheels in park position
JD
Tru
ck
clos
ing
Big Wheel tooling
Endcap Cal. services
Muon Barrel C
LAr C cool down
Aug '07
Jul '07 Aug '07
VT
VT
JF
VJ
Barrel
Muon Barrel C completion
VA
Global Commissioning
EO, side CSmall
Wheel C
Jul '07
Side A
Glo
bal C
omm
issi
onin
g
glob
al te
sts,
pum
p do
wn
& b
ake
out
Side C
VJ
JF
Limited access
JFSide C
Barrel
Side A
ID services along Barrel & through Muons
Chains
May '07 Jun '07
VA
Small Wheel A
Big Wheel A (TGC1 +MDT+TGC2+TGC3)
Mar '07Feb '07Jan '07 Apr '07
ECT on beam line, partially inside (half truck)
Dec '06Nov '06
Nov '06 Jan '07Dec '06
Tru
ck
JT
Mar '07
Endcap Toroid A cooldown
& test
May '07Jul '06 Feb '07Sep '06 Oct '06Aug '06 Apr '07Jun '06
Sep '06Jul '06
Services 1st fix
open
clos
e
Jun '06 Aug '06
open
ing
Barrel Calo testing and commissioning
ID access via lift only
map
ping
Fie
ld
Cable chains
BT pumping, cooling, testing
Endcap Toroid C cooldown & test
(Park pos.)
Endcap Toroid C
open
ing
TGC1
Endcap Cal. C testing & commissioning
ID A connection and testingPixel connection and testing
Endcap Toroid A
Muon Barrel AJT
Big Wheels C (TGC1+MDT +TGC2 +TGC3)
IDC connection and testing
LAr A cool down
BT test Magnet test
L.Mandelli CSN1 Trieste 20 Settembre 06 30
SDX1
USA15
UX15
ATLAS Trigger / DAQ Data Flow
ATLASdetector
Read-Out
Drivers(RODs) First-
leveltrigger
Read-OutSubsystems
(ROSs)
UX15
USA15
Dedicated links
Timing Trigger Control (TTC)
1600Read-OutLinks
Gig
abit
Eth
erne
t
RoIBuilder
pROSR
egio
ns O
f Int
eres
t
VME~150PCs
Data of events acceptedby first-level trigger
Eve
nt d
ata
requ
ests
Del
ete
com
man
ds
Req
uest
ed e
vent
dat
a
stores LVL2output
Event data pushed @ ≤ 100 kHz, 1600 fragments of ~ 1 kByte each
Second-leveltrigger
LVL2Super-visor
SDX1CERN computer centre
DataFlowManager
EventFilter(EF)
pROS
~ 500 ~1600
stores LVL2output
dual-CPU nodes
~100 ~30
Network switches
Event data pulled:partial events @ ≤ 100 kHz, full events @ ~ 3 kHz
Event rate ~ 200 HzData
storage
LocalStorage
SubFarmOutputs
(SFOs)
LVL2 farm
Network switches
EventBuilderSubFarm
Inputs
(SFIs)
L.Mandelli CSN1 Trieste 20 Settembre 06 31
HLT/DAQ – Where we are
All Read-Out System (ROS) bought and in advanced phase of installation and commissioning
Purchasing of other components in an advanced state taking into account the new LHC schedule ( in particular LV2 and EF farm)
Pre-Serie (10%) installed and very useful for debugging and understanding the system the Algoritms to be used and a realistic trigger Menu
Continous interactions with SW, Performance and Physics Groups needed- Trigger& Physics Weeks very useful- CSC notes will contain detailed trigger simulation
L.Mandelli CSN1 Trieste 20 Settembre 06 32
SW and Computing seen from farSw and computing will be a major effort toward Data Taking
complementary to the Detector CommissioningThe present line of activity is:1- Simulate O(20M) events with the “ as installed misaligned/miscalibrated
geometry “. To:- Prepare the CSC notes equivalent to revising/updating the Physics TDR. Step one will use a “ as installed detector with known distortions/miscalibrations.- Calibration Data Challenge (CDC) exercise to demonstrate the capabilty to calibrate/align the detector and understand systematic effects ( B-field, materials etc.)
2- Before start of data taking try “ Dress Reharsal Exercise” O(10M) to : Simulate a data stream as from the EF to completely exercise the full chain of distributed analysis ( data streaming- calibrations-Tier1-Tier2- ESD-AOD etc) Very ambitous !
3- Stress the distributed computing infrastructure and gradually bring it towards the 40Hz goal. Will require more simulations. Useful also for particular physics channels
NB. At 200 Hz 10M events will be collected in 1d (5 104s). 2M to be simulated
L.Mandelli CSN1 Trieste 20 Settembre 06 33
Physics
top cross-section Cobal h->gamma gamma Carminati h->4l Nisati A/H->tau tau Resconi Inclusive SUSY Polesello Exclusive SUSY Lari mu from pi/K Di Mattia Btag: HLT Schiavi pion CTB Cavasinni Jet Calib Vivarelli In situ Jet Calib Roda Etmiss Cavalli mucomb: Trigger Biglietti egamma: HLT track Parodi
It’s difficult to summarise the very intense effort which is going on in preparing to data analyses. On a short range the main activity will concentrate on the mentioned CSC notes( 82 ). The italian community is very active as shown by the number of notes with italian editors. To this of course one has to add a rilevant number of contributions to the other notes
L.Mandelli CSN1 Trieste 20 Settembre 06 34
Atlas Comments on the new LHC machine schedule
The presented ATLAS schedule V8.0 fits the new schedule presented at the SPC and CERN Council which foresees the beam pipe closure at the end of August 07 with the following remark:
The schedule strategy should be such that the useful integrated luminosity at 14 TeV at the end of 2008 will be maximized (1-3fb-1 ??).
Primarily the run in 2007 will be a detector and computing commissioning run, and not a physics run
L.Mandelli CSN1 Trieste 20 Settembre 06 35
L.Mandelli CSN1 Trieste 20 Settembre 06 36
Overall financial situation
ATLAS construction budget initial MoU 1995475 MCHF
Updated baseline contributions 468 MCHF
Cost-to-Completion (CtC) evaluation for the initial detector 68 MCHF
Main funding issues today
There are remaining outstanding contributions to the baselineCommon Fund (Russia; JINR;Canada;...) 9 MCHF
Pledged CTC contributions 62.7 MCHF. Missing 5.3 MCHF (NB: Situation only looks rather good due to 5 MCHF more given by CERN; Missing pledged contribution from USA; Russia...)
L.Mandelli CSN1 Trieste 20 Settembre 06 37
Unfortunately as already warned at the April 2006 RRB there are new extra cost for a total of 4.4 MCHF.
CB chair ha nominated an audit Committee ( Bethke; Mandelli; Oram) who looked into the overcosts (report available)
System Item
Item Over Run
System Over Run
System Total Cost
System Over Cost
MCHF MCHF MCHF %
Magnet 1.76 158.2 1.1%
Technical Coordination 2.39 49.6 4.8%
Muon Big Wheels 1.39
TCn installation manpower efforts at Point 1. 1.00
LArCC project 0.25 38.7 0.6%
ATLAS 4.40 536 0.8%
Further delays in installation work beyond August 2007 could require additional resources for manpower to be paid.
L.Mandelli CSN1 Trieste 20 Settembre 06 38
What to do:
Make all efforts such that all FAs would provide the full approved contributions (baseline + CtC). There are indications that about 50% of the baseline missing contributions could be recovered.
Otherwise:
Extend the Institute fees (12.5kCHF/y) up to three years
Atlas will present the situation at the October RRB and will ask for a decision at the April one
OTSMOU
– Last but not least. A group is working to define in details all the tasks needed to operate and mantain ATLAS, to study a mechanism to share the duties and costs between the agencies and to understand the implications with the M&O.
L.Mandelli CSN1 Trieste 20 Settembre 06 39
Executive Board
ATLAS management: SP, Deputy SP, RC, TCCollaboration Management, experiment execution, strategy, publications, resources, upgrades, etc.
PublicationCommittee,Speaker Committee
CB
Detector Operation (Run Coordinator)Detector operation during data taking, online data quality, …
Trigger (Trigger Coordinator)Trigger data quality,performance, menu tables, new triggers, ..
Data Preparation (Data Preparation Coordinator)Offline data quality, first reconstruction of physics objects, calibration, alignment (e.g. with Zll data)
Computing (Computing Coordinator)Core Software, operation of offline computing, …
Physics (Physics Coordinator)optimization of algorithms for physics objects, physics channels
(Sub)-systems:Responsible for operation and calibration of their sub-detector and for sub-system specific software
TMB
New Atlas Organization toward the Data Taking EraCB approved the guidelines but not the formal document. Implementation step by step
I.HinchliffeK.Jacobs (D)
C.GuyotA. Hoecker (D)
L. Mapelli
N.Ellis
L.Mandelli CSN1 Trieste 20 Settembre 06 40
BILANCIO 2007- Richiesta (DB)
• MI ME Cons Trasp Inv CA Tot
• 2007 223.9 3255.2 1687.9 11 323.2 2707.2 8208.4
• 2006 296.6 3186 2095 48 450 5458.4 11443
• Di Cui:•
2007 MOF-A 715 (with Core Comp.)
• 2007 MOF-B 435 (was 490.6)
• 2007 CtC 1471• 2007 Calcolo (Tier2) 600
Ric.: 205 (167 FTE ; 117 100%) Tecn.: 47( 25.7 FTE ; 14 100%)Total 2007 252 ( 192.7 FTE) Total 2006 : 245 (185 FTE)
L.Mandelli CSN1 Trieste 20 Settembre 06 41
Conclusioni
ATLAS sta andando bene. Molte luci e un’ ombra (ECT) Comunque nei primi mesi del 2007 avremo la parte
centrale (IDB;ID-EC, CaloB;Calo-EC, MuB) assemblati ed in fase di commissioning con CR.
Gli EC Mu (camere) procedono bene. Con il commissioning dei rivelatori il TDAQ passa dalla fase
di test alla messa in funzione. Nel 2006-07 si dovrebbe avere un test significativo del CM Una presa dati è possibile nel 2007 eventualmente senza
gli ECT eccitati L’ organizzazione della Collaborazione verso il periodo di
presa dati è in atto La situazione economica non è floridissima ma attenzione
con ATLAS si potrebbe anche tentare di guadagnare......!
L.Mandelli CSN1 Trieste 20 Settembre 06 42
L.Mandelli CSN1 Trieste 20 Settembre 06 43
SPARESSPARES
L.Mandelli CSN1 Trieste 20 Settembre 06 44
H
L
T
DATAFLOW
40 MHz
75 kHz
~2 kHz
~ 200 Hz
120 GB/s
~ 300 MB/s
~2+4 GB/s
Event Building N/workDataflow Manager
Sub-Farm Input
Event Builder
EB
SFI
EBNDFMLvl2 acc = ~2 kHz
Event Filter N/work
Sub-Farm Output
Event FilterProcessors EFN
SFO
Event FilterEFP
EFPEFP
EFP
~ sec~
4 G
B/s
EFacc = ~0.2 kHz
Trigger DAQ
RoI BuilderL2 Supervisor
L2 N/workL2 Proc Unit
Read-Out Drivers
FE Pipelines
Read-Out Sub-systems
Read-Out Buffers
Read-Out Links
ROS
120 GB/s
ROB ROB ROB
LVL1
DE
T R/O
2.5
s
Calo MuTrChOther detectors
Lvl1 acc = 75 kHz
40 MHz
RODRODROD
LVL2 ~ 10 ms
ROIB
L2P
L2SV
L2N
RoI
RoI data = 1-2%
RoI requests
Trigger, DAQ and Detector Control