loans 3159/3160-pak: trimmu and panjnad barrages … · 2017-10-30 · biannual environmental...
TRANSCRIPT
Bi-annual Environmental Monitoring Report
October 2017
Loans 3159/3160-PAK: Trimmu and Panjnad
Barrages Improvement Project
Prepared by the Project Management Office, Irrigation Department,
Government of Punjab.
The bi-annual environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
Islamic Republic of Pakistan
Bi-Annual Environmental Monitoring Report
ADB LOAN NO. 3159/3160-PAK
Project Number: 1037-PAK
(January to June 2017)
Rehabilitation and Upgrading of Trimmu Barrage Project
(TPBIP/ICB-01)
Prepared by: Muhammad Saleem Falak Trimmu Panjnad Barrage Consultants (TPBC)
Initial Review: Engr. Anwar Hussain Mujahid Environmental Specialist TPBC
For: Project Management Office, Irrigation Department, and Government of
the Punjab
Reviewed by: Malik Pervaiz Arif, Acting Director Environment & Social PMO Barrages,
Canal Bank, Mustafabad, Lahore
Consultants: Joint Venture of NESPAK (Pvt) Ltd., SMEC Pty Int’l, Engineering General
Consultants (EGC) Ltd.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) i
TRIMMU AND PANJNAD BARRAGE IMPROVEMENT PROJECT
Bi-Annual Environmental Monitoring Report
Table of Contents
1. Chapter One .................................................................................................................... 3
1.1. Introduction ........................................................................................................ 3
1.2. Project Background ............................................................................................ 3
1.3. Salient Features of Barrage ............................................................................... 4
1.4. Project Scope of Work........................................................................................ 5
1.4.1. Civil Works ................................................................................................ 5
1.4.2. Mechanical and Electrical Works (M & E) .................................................. 6
1.4.3. Building Works .......................................................................................... 6
1.5. Construction Activities ........................................................................................ 6
1.6. Table 1-2 presents the overall progress about HSE Issues ................................ 7
1.7. Changes in Contractor’s HSE Organogram ........................................................ 7
1.8. Relationship with the PMO, TPBC & Contractor ................................................. 7
1.9. Site Specific Environmental Management Plan (SSEMP) .................................. 8
1.10. EMP Performance Monitoring ............................................................................ 8
1.11. Environmental Checklists for Monitoring ............................................................ 8
1.12. PMO & Consultant Monitoring ............................................................................ 9
1.12.1. Assessment of Trees Cutting/Uprooting from RGB, RMB, Rangpur Canal L/R side, Jhang-Bhakkar Road and lot no. 17 of Trimmu Barrage Project........ 9
1.12.2. Instrumental Monitoring Performance at Trimmu Barrage Project ........... 10
1.12.3. Environmental Progress Review Meetings (EPRMs) in the Reported Period ................................................................................................................ 10
1.12.4. Field Visit by Environment & Social Team of Asian Development Bank ... 11
1.12.5. PMO, TPBC & Contractor’s Staff Site Visit to Check Environment and Safety Arrangements .......................................................................................... 12
1.13. Institutional Arrangements of Trimmu Barrage Project ..................................... 15
1.13.1. Project Management Office (PMO) .......................................................... 15
1.13.2. Construction Supervision Consultants ..................................................... 16
1.13.3. Contractor ............................................................................................... 16
1.14. World Environment Day June 5, 2017 Celebrations ......................................... 17
2. Environment Monitoring Performance ............................................................................ 19
2.1. Environmental Monitoring Summary ................................................................. 19
2.2. Types of Monitoring .......................................................................................... 19
2.3. Internal Monitoring ........................................................................................... 19
2.3.1. Noise & Vibration Monitoring ................................................................... 19
2.3.2. Surface Water Quality Monitoring ............................................................ 22
2.4. Instrumental Monitoring/External Monitoring .................................................... 25
2.4.1. Drinking Water Quality Monitoring ........................................................... 25
2.4.2. Waste Water Analysis ............................................................................. 30
2.4.3. Ambient Air Quality Monitoring ................................................................ 30
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) ii
3. Environmental & Social Management ............................................................................ 31
3.1. Flora & Fauna .................................................................................................. 31
3.2. Borrow Area ..................................................................................................... 31
3.3. Traffic Management Plan Implementation ........................................................ 33
3.3.1. Installation of Sign Boards, Diversion Signs ............................................ 34
3.4. Dust Abatement & Air Emission Monitoring ...................................................... 35
3.5. Tree Plantation Plan ......................................................................................... 35
3.6. Oil Spill Management ....................................................................................... 36
3.7. Fuel Station Area ............................................................................................. 36
3.8. Environmental Management and Monitoring Plan (EMMP) .............................. 37
3.9. Campsite Management & Labor Accommodation ............................................. 38
3.10. Field Visits by PMO Director E & S Malik Pervaiz ............................................. 39
3.11. Grievance Redressal Committee ...................................................................... 39
3.12. Complaint Register ........................................................................................... 40
3.13. Employment Status .......................................................................................... 40
3.14. Social Framework Agreement .......................................................................... 41
3.15. Waste Management ......................................................................................... 41
3.15.1. Waste Water Collection & Disposal ......................................................... 41
3.15.2. Solid Waste Collection ............................................................................ 42
3.15.3. Segregated Waste Management ............................................................. 42
4. Occupational Health & Safety ........................................................................................ 46
4.1. Health, Safety & Construction Works Management .......................................... 46
4.1.1. First Aid Center & First Aid Box ............................................................... 46
4.1.2. Zero Accident Campaigns ....................................................................... 47
4.1.3. Housekeeping ......................................................................................... 47
4.1.4. Firefighting Arrangements Vis-à-Vis Welding .......................................... 47
4.1.5. Safety Air Compressor Tanks .................................................................. 48
4.1.6. Provision of PPEs.................................................................................... 48
4.1.7. Safety Sign Boards .................................................................................. 49
4.1.8. Safety Trainings ...................................................................................... 49
4.1.9. Swimmer & Boating Arrangements .......................................................... 50
4.1.10. Unsafe Acts & Unsafe Conditions (UA/UC System) ................................. 50
4.1.11. Electrical Components ............................................................................ 50
4.1.12. Accident/Incident Statistics ...................................................................... 50
4.1.13. Status of Non-Compliances (NC) ............................................................ 51
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) iii
List of Tables
Table 1-1: Salient Features of Trimmu Barrage ............................................................... 4
Table 1-2: Overall Progress of HSE Issues ...................................................................... 7
Table 1-3: Status of Environmental Plans related to Trimmu Barrage Project ..................... 8
Table 1-4: EPRM ........................................................................................................... 10
Table 2-1: Surface Water Monitoring Results ................................................................. 22
Table 2-2: M/s. Sinohydro Main Camp First result .......................................................... 27
Table 2-3: Groundwater Analysis of Labor Camp ........................................................... 28
Table 2-4: Retesting Results of Main Camp ................................................................... 29
Table 3-1: Tree Plantation Status ................................................................................... 36
Table 3-2: Employment Status of Labor ......................................................................... 41
Table 3-3: Non-Hazardous Waste (Tons) ....................................................................... 43
Table 3-4: Hazardous Waste (Tons) .............................................................................. 43
Table 4-1: HSE Score – May 2017 ................................................................................. 50
Table 4-2: Type of Non-Compliance & Its Priority........................................................... 51
Table 4-3: Out-Standing Issues ...................................................................................... 54
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) iv
List of Figures
Figure 1-1: Location Map of Trimmu Barrage .................................................................... 3
Figure 1-2: Flow Chart of Major Rivers of Pakistan ........................................................... 5
Figure 1-3: Rehabilitation Works of Trimmu Barrage ......................................................... 6
Figure 1-4: Presentation of TMP by Senior Env. TPBC Chinese Camp Visit ................... 12
Figure 1-5: Double Bunker Interview with Labor .............................................................. 12
Figure 1-6: Cooling & Heating Facilities in Labor Camp .................................................. 13
Figure 1-7: Food Quality Inspection of Labor Camp by PMO Director E&S ..................... 13
Figure 1-8: Senior Environmentalist of TPBC Briefing After Lean Concrete..................... 14
Figure 1-9: Working Area ................................................................................................ 14
Figure 1-10: Good Housekeeping in Batching Plant Area.................................................. 15
Figure 1-11: Organogram of Trimmu Barrage Project ....................................................... 15
Figure 1-12: Contractor’s Organogram ............................................................................... 17
Figure 1-13: World Environment Day Celebration on June 5, 2017 ................................... 18
Figure 2-1: Noise Level Meter & Noise Level Monitoring ................................................. 20
Figure 2-2: Environmental Indicator(s) .............................................................................. 26
Figure 3-1: Borrow Area Restoration in Progress ............................................................ 32
Figure 3-2: Traffic Diversion ............................................................................................ 33
Figure 3-3: Traffic Management Plan of Trimmu Barrage ................................................ 34
Figure 3-4: Speed Limit Board & Flagmen Working on Diversion .................................... 35
Figure 3-5: Water Sprinkling in Operation at Cofferdam & Diversion Board ..................... 35
Figure 3-6: Concrete Pad Beneath Generators & Director E&S Monitoring Generator .... 36
Figure 3-7: Before & After Fuel Station ............................................................................ 37
Figure 3-8: Labor Camp Mosque & Accommodation Block ............................................. 39
Figure 3-9: PMO Monitoring the Site & First Aid Center .................................................. 39
Figure 3-10: GRC Board Meeting in Progress ................................................................... 40
Figure 3-11: Complaint Register........................................................................................ 40
Figure 3-12: Over Flow of Waste Water ............................................................................ 41
Figure 3-13: Waste Bins in Labor Camp ............................................................................ 42
Figure 4-1: Ambulance and Training on HIV/AIDs ........................................................... 46
Figure 4-2: Zero Accident Campaign ............................................................................... 47
Figure 4-3: Fire Extinguisher and Flashback Arrestors with Cylinder ............................... 48
Figure 4-4: Chicago Coupling Missing with Air Compressor ............................................ 48
Figure 4-5: Non-Compliance of PPEs at Site ................................................................... 49
Figure 4-6: TBT in Progress at Site ................................................................................. 49
Figure 4-7: Standby Boat and Swimmer .......................................................................... 50
Figure 4-8: %age of Resolved and Pending Issues ......................................................... 52
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) v
Figure 4-9: Overall Priority of HSE Issues ....................................................................... 52
Figure 4-10: Overall Pending and NC Issues .................................................................... 53
List of Graphs
Graph 2-1: Noise Monitoring Result of January 2017 ...................................................... 20
Graph 2-2: Noise Monitoring result of February 2017 ...................................................... 21
Graph 2-3: Noise Monitoring result of March 2017 .......................................................... 21
Graph 2-4: Noise Monitoring Result of April 2017 ........................................................... 21
Graph 2-5: Surface Water Quality Result of January 2017 .............................................. 22
Graph 2-6: Surface Water Quality Result of February 2017 ............................................ 23
Graph 2-7: Surface Water Quality Result of March 2017 ................................................. 23
Graph 2-8: Surface Water Quality Result of April 2017 ................................................... 24
Graph 2-9: Surface Water Quality Result of May 2017 .................................................... 24
Graph 2-10: Surface Water Quality Result of June 2017 ................................................... 25
Graph 2-11: Groundwater Results of Main Camp ............................................................. 28
Graph 2-12: Ground Water Results of Main Camp ............................................................ 29
Graph 3-1: Non-Hazardous Waste .................................................................................. 43
Graph 3-2: Hazardous Waste ......................................................................................... 44
Graph 3-3: Recycled Waste ............................................................................................ 44
Graph 3-4: Recycled Waste ............................................................................................ 45
Graph 3-5: Recycled Waste ............................................................................................ 45
Graph 4-1: HSE Statistics ............................................................................................... 51
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) vi
List of Annexures
Annex-I Approval of SSEMP
Annex-II Filled Checklists
Annex-III EPRM
Annex-IV Detail of Irrigation Trees
Annex-V Detail of Forest Trees
Annex-VI Surface Water Results
Annex-VII TPBC letter regarding unsuitability of drinking water
Annex-VIII PCSIR Drinking Water Reports
Annex-IX Stability of Coffer Dams for Traffic
Annex-X Layout Plan of Main Camp
Annex-XI Layout Plan of Labor Camp
Annex-XII Social Framework Agreement
Annex-XIII Kitchen Hygiene Checklist
Annex-XIV TPBC letter on HSE
Annex-XV Vehicular Inspection Checklist
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) vii
List of Abbreviations
3Rs Reduce, Reuse, Recycle
ADB Asian Development Bank
AFFF Aqueous Film Forming Foam
As Arsenic
BAEMR Bi-Annual Environmental Monitoring Report
CCA Cultural Command Area
DCP Dry Chemical Power
DO Dissolved Oxygen
EC Electrical Conductivity
EGC Engineering General Consultants
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EMMP Environmental Management Monitoring Plan
EPA Environmental Protection Agency
EPRM Environmental Progress Review Meeting
ERP Emergency Response Plan
ESIA Environmental & Social Impact Assessment
GEL Global Environment Lab
GCC General Conditions of Contract
HSE Health, Safety & Environment
IPC Interim Payment Certificate
LTI Loss Time Injury
M&E Monitoring & Evaluation
MTC Medical Treatment Case
NEQS National Environmental Quality Standards
NESPAK National Engineering Services Pakistan (Pvt) Ltd.
NOC No Objection Certificate
PAPs Project Affected Persons
PCSIR Pakistan Council of Scientific & Industrial Research
PEPA Pakistan Environmental Protection Act
PID Punjab Irrigation Department
PMO Project Management Office
PPEs Personal Protective Equipment
RD Reduced Distance
RGB Right Guide Bank
RMB Right Marginal Bund
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) viii
ROW Right of Way
RWI Restricted Work Injury
SCL Sinohydro Corporation Limited
SMEC SMEC International Pty. Limited
SP Special Provision
SSEMP Site Specific Environmental Management Plan
SWMP Solid Waste Management Plan
TBT Tool Box Talk
TDS Total Dissolve Solid
TMP Traffic Management Plan
TPBC Trimmu Panjnad Barrages Consultants
TRIR Total Recordable Injury Rate
TS Trimmu Sidhnai
UA/UC Unsafe Act/Unsafe Condition
WED World Environment Day
WHO World Health Organization
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 1
EXECUTIVE SUMMARY
The Environmental monitoring for the Rehabilitation and Upgrading of Trimmu Barrage remained in
progress during the period of January to June 2017. The Construction of this project is being carried
out by the M/s. Sinohydro Corporation Limited (SCL) under the supervision of a Joint Venture of
Consultants namely National Engineering Services of Pakistan (NESPAK) (Pvt) Ltd, SMEC Int’l Pty and Engineering General Consultants (EGC) (Pvt)Ltd. The Construction of Trimmu Barrage was
started in the month of May 31, 2016 and overall progress of work has remained satisfactory during
the reporting period.
Environmental Management Plan (EMP) is an integral component of Trimmu Barrage Project as
part of the Project’s Contract Agreement. The Trimmu Barrage’s Environmental Impact Assessment (EIA) has been duly approved by the Environmental Protection Agency (EPA) Punjab. During the
reporting period, keeping in view the provisions of the EMP, Instrumental/Effects Monitoring &
Compliance Monitoring were performed to determine the environmental impact of the Project’s
construction activities. Director Environmental & Social PMO, the Engineer and Contractor’s HSE team worked in close coordination to resolve various issues such as non-availability of Personal
Protective Equipment (PPEs) and abysmal housekeeping at the workplace area(s) for which
significant improvement was observed after adoption of necessary mitigation measures.
Overall environmental management of the Project Area remained satisfactory due to stringent
efforts made by the Consultants Environmental Team. The Contractor overall responded positively
towards environment, health and safety issues at site and adverse impacts were minimized. Due to
huge construction activities such as excavation of additional bays, removal of bela, Rangpur Canal
diversion excavation vis-à-vis and movement of Project heavy machinery caused intensive
emissions of dust particles in the working area. The impact of dust was reduced by regular waster
sprinkling. Ambient air quality monitoring however revealed that, the PM10, SOx, NOx and CO2
remained within National Environmental Quality Standards (NEQS).
Traffic Management Plan (TMP) was a necessary tool and highly significant for Trimmu Barrage
Project and proper implementation of this Plan was made possible by effective coordination of PMO,
Consultant and the Contractor’s team joint efforts. Several results oriented meeting(s) were held
with local administration for heavy traffic diversion from Trimmu Barrage and alternate
arrangements were finalized for passing of light vehicles through the Project Area. Necessary traffic
sign boards and sufficient flagmen were deployed at nodal points for smooth flow of traffic from the
Project Area. This was itself a mammoth task by itself in which success was achieved with the
cooperation of all concerned.
The Contractor constructed two camps for its labor and staff residence. For the Management Staff,
a Main Camp was established near the Irrigation Canal Colony on the left side of the Barrage while
the Labor Camp was constructed on the right side of the Barrage. Proper sewerage system
comprising of septic tank and soakage pit was constructed and solid waste system based on the
3Rs technique i.e. Reduce, Reuse and Recycle. Recyclable waste was handed over to the private
vendor and organic solid waste was segregated and disposed off at designated disposal area left
side of the Rangpur Canal.
According to EMP requirements, the Contractor submitted a Tree Plantation Plan for the first phase
of the Project in which the Contractor had to plant around 1,000 saplings but due to unknown
reasons, only 600 species were planted. However, in next phase PMO and TPBC will ensure that
complete plantation of around 5,000 trees is carried out in the Project Area.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 2
The overall Health Safety and Environment (HSE) implementation were satisfactory due to
continuous efforts by the supervisory staff at site. Furthermore, the Contractor were pressed hard
to follow the HSE guidelines in true letter and spirit. At initial stage, the Consultant and the
Contractor’s team prepared a “gap analysis” of the Project about hazards like methods of
excavation, chemical safety, mechanical hazards, noise hazards, electrical issues, movement of
machinery, batching plants hazards, work at height risks etc. and mitigation measures were
accordingly identified and adhered to. Through effective trainings and awareness campaigns, HSE
culture was promoted among the Contractor’s labor and staff. Thereafter all working staff
demonstrated positive response and no major accident happened at site until now. Due to stannous
efforts by the PMO, TPBC and the Contractor, project conditions are improving and PMI/Engineer’s
target is to achieve zero Loss Time Injury Rate.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 3
1. CHAPTER ONE
1.1. Introduction
This is the first “Bi-Annual Environmental Monitoring Report” (BAEMR) of the “Rehabilitation and
Upgrading of Trimmu Barrage Project”. As per project requirements, this report has been prepared
by the Supervisor of Consultant i.e. NESPAK, SMEC & EGC joint venture for onward review and
approval by the Client. Thereafter the approval report shall be transmitted to the Asian Development
Bank (ADB). This BAEMP provides the overall status of implementation of Environmental
Management Plan (EMP), Site Specific Environmental Management Plan (SSEMP) and various
Sub-Plans i.e. Traffic Management Plan, Health Safety & Environment Plan, Waste Management
Plan, Borrow Area Plan, Tree Plantation Plan and Emergency Response Plan. Also, valid for
application will be the, Asian Development Bank (ADB) Environmental Safeguard Policies (2009),
EIA, and Environmental Conditionality stipulated by EPA Punjab. Equally pertinent are the Contract
specifications like Special Provisions (SP), General Conditions of the Contract (GCC) regarding
Health & Safety procedures and Environmental Protection’s statutory requirements, legislations and international best practices. In case of any violations of the Contractual stipulations, approved plans,
the Contractor was intimated through, letters, emails, field memos, meetings, and monthly reports.
1.2. Project Background
Trimmu Barrage holds a strategic position in the agricultural economy of Pakistan. It was
constructed in 1937-39. The Barrage was designed for safe discharge capacity of 645,000 cusecs.
During high floods, the excess flows are managed to pass through the breaching section, provided
on the right marginal bund at RD 16-18 to safeguard the Main Barrage. A remodelling plan of the
Barrage was under taken as a consequence of the Indus Water Treaty and a new head regulator
for the Trimmu Sidhnai (T.S.) Link Canal was constructed in 1961-62 with a capacity of 12,500
cusec for feeding lower Ravi and Sutlej River commands. The Barrage is located downstream of
the confluence of the Chenab River and the Jhelum River about 25 Km. South West of Jhang City
on Jhang Bhakkar Road at Latitude 310 11’N and Longitude 720 08E. The location of the Barrage
has been shown in Figure 1-1. The Jhelum – Chenab River confluence lies 3 Km. upstream of
Trimmu Barrage. The command areas of this barrage falls in a semi-arid zone with Thal Desert on
its right and Rachna Doab on its left side. Trimmu Barrage is located around 206 Km. and 268 Km.
downstream of Qadirabad and Rasul Barrages, respectively.
Figure 1-1: Location Map of Trimmu Barrage
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 4
1.3. Salient Features of Barrage
Salient features along with physical data for the Barrage and associated canals are presented in
Table 1-1.
Table 1-1: Salient Features of Trimmu Barrage
Barrage Data
Design capacity 645,000 cusecs
Main weir 502,000 cusecs
Left undersluice 82,000 cusecs
Right undersluice 61,000 cusecs
Total width between abutments
3,025 ft.
No. of bays Main weir 37 No. (each 60 ft. wide)
Left undersluice 08 No. (each 30 ft. wide)
Right undersluice 06 No. (each 30 ft. wide)
Highest Flood Level Upstream RL 494.30
Downstream RL 490.50
Pond level Summer RL 491.50
Winter RL 490.00
Crest R.L. Main weir RL 477.50
Left undersluice RL 472.00
Right undersluice RL 472.00
Upstream floor level Main weir RL 470.00
Undersluices RL 468.00
Downstream floor level Main weir RL 468.00
Undersluices RL 464.00
Upstream floor lengths Main weir 0.00 ft.
Undersluices 274.00 ft.
Downstream floor lengths Main weir 68.00 ft.
Undersluices 80.00 ft.
Off-Taking Canal Data
Haveli Main Line Designed discharge 5,170 cusecs
Crest R.L. 481.0
Head Regulator 5 Nos. bays of width 24 ft. each (5 x 24 = 120 ft.)
Trimmu Sidhnai Link Designed discharge 12,500 cusecs
Crest R.L. 481.0
Rangpur Canal Head Regulator 10 Nos. bays of width 24 ft. each (10 x 24 = 240 ft.)
Designed discharge 2,710 / 1,800 cusec
Crest R.L. 483.50
Head Regulator 03 Nos. bays of width of 24 ft. each (3 x 24 = 72 ft.)
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 5
Three canals with the total with drawing capacity of 20,380 cusec off-take from the Barrage Rangpur
Canal emanates from the right flank, whereas Haveli Main Line Canal and T.S. Link Canal off-take
from the left flank. Haveli Canal irrigates 1.017 million acres (__ hectors) in Jhang and Multan
Districts, whereas, Rangpur Canal feeds 345,000 acres (__ hectors) in Jhang and Muzaffargarh
Districts. Water conveyed to the Ravi River through T.S. Link Canal is then diverted through Sidhnai
Mailsi (S.M.) Link Canal and serves an area of about 1.715 million acres (__ hectors) in Bahawalpur,
Vehari & Lodhran Districts. The overall CCA of the Trimmu Barrage canal command is 2.68 million
acres that is 13.19% of the total CCA (20.31 million acres) of the Punjab and 7.05% of the entire
CCA of the country (38 million acres). Figure 1-2 shows the Flow Chart of Major Rivers of Pakistan.
Figure 1-2: Flow Chart of Major Rivers of Pakistan
1.4. Project Scope of Work
1.4.1. Civil Works
• Construction of 13 no. additional bays of 800 ft., length gated structure with all
appurtenances
• Construction of 800 ft. long new Road Bridge Structure
• Dismantling of old Right Guide Bank and construction of Right Guide Bank
• Remodelling of upstream river training works
• Dismantling of old and construction of new Head Regulator of Rangpur Canal
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 6
• Rehabilitation of existing barrage structure including bridge and floors etc. shown in Figure
1-3.
Figure 1-3: Rehabilitation Works of Trimmu Barrage
1.4.2. Mechanical and Electrical Works (M & E)
• Repair of Barrage gates hoisting system and steel decking
• Coupling and installation of electric motors
• Mechanical and electrical work of gates and hoisting system of 13 no. additional bays
• Mechanical and electrical work of Head Regulator of Rangpur Canal
• Automation of gates through centralized gate operation from control room
• Water discharge monitoring in the control room and communication network for barrage and
off-taking canals
1.4.3. Building Works
• Construction of Employer/Engineer office
• Construction of SDO residence
• Construction of Junior and Senior quarters
• Public park
1.5. Construction Activities
The work in progress
The present status of project work is given as under:
Overall progress (until June 2017)
Planned Physical Progress 34.94%
Achieved Progress 32.32%
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 7
1.6. Table 1-2 presents the overall progress about HSE Issues
Table 1-2: Overall Progress of HSE Issues
Sr. No. Health Status Qty. Contractor’s response
1 MBBS doctor Appointed 01 Done
2 Paramedic staff
Appointed 02 Done
3 First aid center
One first aid center established at site
01 Done
4 Ambulance Ambulance dedicated for emergency cases.
01 Done
Site based instrumental Monitoring
Sr. No. Instrument Name Qty. Contractor’s response
1 Noise Meter 01 Available at site.
2 Multi-meter 01 – do –
3 Do meter 01 – do –
EMP Implementation staff
Sr. No. Designation Qty. Contractor’s response
1 HSE Director 01 Done
2 HSE Manager 01 Done
3 Environmentalist 01 Done
4 HSE Officer 01 Done
5 HSE Supervisor 01 Done
6 HSE Assistant 02 Done
7 Flagmen 17 Done
1.7. Changes in Contractor’s HSE Organogram
The Contractor has hired sufficient HSE staff and flagmen for adequate supervision and ownership
of the EMP thought the first phase of the Project. However, after completion of the first phase of the
Project around mid June 2017, the Contractor’s work on the existing barrage was completed, they
demobilized 09 flagmen and 01 safety assistant. It was ensured to the Consultant that, when second
stage works will start, the Contractor will hire the services of same experienced staff.
1.8. Relationship with the PMO, TPBC & Contractor
A cordial relationship was maintained among the Contractor and the Engineer during execution of
the Project. The Contractor’s representative(s) had been informed about the Environmental
Management Plan and monitoring activities. Environmental non-compliances/violation of contract
were notified to the Contractor for mitigation measures. The Consultants Environmental Team
apprised the Contractor for strict implementation of the Environmental Regulations. A daily checklist
has been prepared by the Engineer’s Representative which is dully filled in by the Contractor and
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 8
Consultant staff. Monthly Environment Report is being submitted each month by the Contractor for
the Engineer’s review and information.
1.9. Site Specific Environmental Management Plan (SSEMP)
The Trimmu Barrage Contract was awarded to M/s Sinohydro on June 10, 2016 thereafter, the
Contractor was advised by the Supervisory Consultant to develop the Site Specific Environmental
Management Plan (SSEMP) and get approval from the Engineer before physical mobilization at
site. Initially, the SSEMP was not in line with ADB and Contractual guidelines, the Consultant’s representative and PMO Environment team assisted the Contractor for finalization of this stand
alone document. After approval of the SSEMP, remaining subplans were submitted and approved
by the Engineer. The approved letter of SSEMP is attached as Annex-I. The status of approval of
various other plans is shown in Table 1-3.
Table 1-3: Status of Environmental Plans related to Trimmu Barrage Project
Name of Plan Date of first Submission
Resubmission No. 1 (Date)
Approval Date
SSEMP Main Barrage 1-Jun-16 - 10-Jun-16
Field HSE Plan 2-Sep-16 3-Sep-16 5-Sep-16
Traffic Management Plan (TMP) 21-Aug-16 8-Sep-16 22-Oct-16
Borrow Area Management Plan
5-Sept-16 7-Nov-16 1-Dec-16
Solid Waste Management Plan (SWMP)
31-Aug-16 9-Sep-16 6-Oct-16
Emergency Response Plan 28-Oct-16 - 3-Nov-16
Tree Plantation Plan 4-April-17 - 30-April-17
1.10. EMP Performance Monitoring
Environmental Management Plan (EMP) is required to comply with PEPA regulations, (2000) and
ADB’s safe guard policy statement (2009). The Environmental Management Plan framework
includes various aspects of the project activities such as excavation works, selection of camps,
noise hazard, chemicals hazard, flora and fauna of the Project, health aspects, ground water and
waste water disposal vis-à-vis reporting procedures. The EMP is stand alone document used by
the Contractor in the field to manage the environmental aspects during the construction phase of
the Project. The Consultant will ensure the efficient implementation of EMP, in case the Contractor
fails to rectify any damage to the Environment, the Engineer will advise the Contractor for immediate
mitigation measures otherwise the Contractor’s payment may be deducted from Interim Payment
Certificate (IPC).
1.11. Environmental Checklists for Monitoring
For effective implementation and ownership of the EMP, a comprehensive checklist has been
developed mutually by the PMO, Consultant and the Contractor’s staff encompassing all aspects
of the Project. The checklist is being filled by the Contractor and Consultant staff and cross checked
by Director Environment & Social PMO. A filled checklist from January to June 2017 is attached as
Annex-II.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 9
1.12. PMO & Consultant Monitoring
The Engineer’s Sr. Environmentalist has been mobilized at site on full time basis for monitoring of
the EMP. The Engineer’s representative is responsible to oversee the Contractor’s performance against the stipulated compliance of Environmental Management Plan, Traffic Management Plan,
HSE Plan and Solid Waste Management Plan in the field. The Contractor has also hired
experienced and technically qualified HSE Staff for proper implementation of EMP during
construction phase of the Project. During site inspections if any non-compliance/violation is
observed by the Consultant staff, it is conveyed to the Contractor for immediate compliance. In case
the matter is not resolved by the HSE staff, then Site Manager is notified about the issue through
the Consultant’s Site Incharge i.e. Chief Resident Engineer for prompt action.
The PMO has deputed a full time Deputy Director Social & Resettlement at site, his duty is to liase
with the Contractor and Consultant team on regular basis and performing pivotal role in
implementation of the social and resettlement issues. Director Environment & Social PMO and
Monitoring & Evaluation (M&E) Expert of PMO have been regularly visiting the Project Area in the
reporting period almost every month for supporting and reviewing the performance of Engineer’s Environment & Social Team, Implementation of EMP and other plans by M/s. Sinohydro. It is
prudent to highlight that PMO’s Environment team has developed an innovative mechanism to
check the performance of EMP and occupational health and safety protocols through conducting
Environmental Progress Review Meetings (EPRM). A copy of EPRM # 5 is attached as Annex-III.
1.12.1. Assessment of Trees Cutting/Uprooting from RGB, RMB, Rangpur Canal L/R side, Jhang-Bhakkar Road and lot no. 17 of Trimmu Barrage Project
For construction of new additional bays, Right Guide Bank (RGB), Right Marginal Bund (RMB),
Rangpur Canal Diversion Channel excavation and construction of Employer/Engineer’s Office and
in order to provide obstruction free site to the Contractor, the Client advised to prepare a complete
Inventory List of Trees which could cause possible hindrance in the project activities. Consultant
and PMO environment team engaged the Jhang and Shorkot Forest Divisions for preparation of the
inventory for trees removal/uprooting. The concerned Forest Division, PMO and Consultant team
prepared a list of trees which belonged to the Forest Department and a separate list of trees that
belonged to the Irrigation Department as provided in Annex-IV. The detail of 155 trees owned by
the Punjab Irrigation Department is as follows:
• Rangpur Canal (Left Bank) = 43
• Rangpur Canal (Right Bank) = 50
• Between Road and Canal = 26
• Lot No. 17 = 17
• Employer/Engineer’s Office = 19
However, the final list of trees has been prepared by the Forest Department for auction purposes.
The final list of trees verified and duly signed by the PMO, TPBC, Contractor & Forest staff was
sent to DFO Multan for verification and for unit price rate. After final calculations and fixing of unit
price rate. The auction of the trees took place in the Executive Engineer Office. The detail of forest
trees is attached as Annex-V and also given below.
• RMB (Right Side) = 9
• RMB (Left Side) = 17
• Lahore-Bhakkar Road (Left Side) = 11
• RGB (Left Side) = 184
• RGB (Right Side) = 84
• Rangpur Canal (Right Side) = 14
• Rangpur Canal (Left Side) = 29
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 10
1.12.2. Instrumental Monitoring Performance at Trimmu Barrage Project
The Environmental Management Plan (EMP) is a stand alone document which was adopted by the
Contractor for implementation of Environmental Provisions at site, while Engineer’s Senior Environmentalist regularly and strictly monitored the compliance related to the environmental and
safety issues. PMO ESU has the overall responsibility for monitoring of compliance related to
environmental aspects of the Project. Third Party External Instrumental Monitoring for the
environmental parameters i.e. physical, biological and chemical testing of water, vehicular
emissions analysis, and ambient air monitoring was carried out on quarterly basis as stipulated in
the Contract of Trimmu Barrage Project. First round of external monitoring of Ambient air, Vehicular
emissions analysis and diesel operated generators testing was performed in October 2016 by the
Contractor through, M/s. Global Environmental Laboratory, Lahore. The ground water testing/
checking was carried out by the PCSIR Lab-Lahore.
In compliance to EMP requirements, the Contractor purchased the following instruments for site
based monitoring:
• Dissolved Oxygen Meter
• Multi Meter (Temperature, pH, Electrical Conductivity & Total Dissolved Solids)
• Noise Level Meter
Internal instrumental monitoring of environmental parameters of river water quality was also carried
out in the reporting period jointly by the Engineer’s Environmental representative and
M/s. Sinohydro staff, upstream and downstream of the Cofferdam.
In high noise generating areas i.e. generators, vibro hammer, cranes, transit mixers, dumpers, hilty
machine, concrete vibrators etc. the noise level was measured and appropriate measures were
taken to avoid any untoward harm to the workers.
During the reporting period, the Contractor constructed the Cofferdam on the left side of the
Barrage. The Cofferdam was constructed mostly with silty clay material collected from heaps of T.S
Link Canal & Haveli Canal. This material however can degrade the water quality in the form of
turbidity which can cause adverse impact on the aquatic life especially fish downstream of the
Barrage. The river water quality upstream and downstream of the Cofferdam was analyzed
frequently (before and during dismantling and construction phase of the Cofferdam), which was
found to be satisfactory. During the internal instrumental monitoring of River Chenab and Jhelum,
it was noted that the concentration of average dissolved oxygen (DO) in the river was more than 7
mg/L whereas minimum dissolved oxygen for existence of aquatic life/fish threshold is 4.0 mg/L.
Moreover, the value of EC, Temp, TDS and pH remained with in permissible limits.
1.12.3. Environmental Progress Review Meetings (EPRMs) in the Reported Period
During the reported period from January to June 2017, the PMO conducted three (03)
Environmental Progress Review Meetings. The detail of EPRM is provided in Table 1-4.
Table 1-4: EPRM
Sr. No. Agenda Location Date
1 EPRM # 03 M/s. Sinohydro Conference Hall 13-02-17
2 EPRM # 04 M/s. Sinohydro Conference Hall 22-04-17
3 EPRM # 05 Consultant Conference Hall 20-05-17
All the issues related to site were discussed threadbare and amicable solutions were reached
consequent to the EPRM. The highlighted issues were assigned to the concerned section for
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 11
necessary action and compliance. After necessary action by the Contractor, compliance reports
were disseminated among all the participants.
1.12.4. Field Visit by Environment & Social Team of Asian Development Bank
During the reporting period, a site visit for the ADB delegation was arranged by the Project
Management Office (PMO). Following participated in the said visit:
• ADB: Environmental Specialist (Ms. Safia Shafique), Gender Specialist (Ms. Uzma Altaf)
• PMO: Director E & S (Malik Parviz Arif), Deputy Director Resettlement (Mr. Shabib Hussain)
Deputy Director E & S (Ms. Naila Jabeen Faizi)
• TPBC: Monitoring & Evaluation Expert (Mr. Nazim Hussain) Senior Environmentalist
(Mr. Saleem Falak), M&E Officer (Ms. Anam Zahra)
• Sinohydro: Director HSE (Mr. Lee), Environmentalist (Mr. Ammar)
The Environment & Social Team of ADB and PMO visited the site on December 23, 2016 in the
company of Director E&S and other team members of Trimmu Project. The Delegation of ADB and
PMO arrived at Contractor’s site office site around 11:45 a.m. PMO Deputy Director Resettlement,
TPBC’s Senior Environmentalist and Sinohydro’s staff received them and proceeded to the
Conference Hall for briefing about the Project. Chief Resident Engineer (CRE) TPBC and Site
Manager SCL joined ADB Mission in the Conference Room where a comprehensive presentation
was arranged by the TPBC Senior Environmentalist on Traffic Management Plan (TMP). ADB and
PMO representatives were apprised about the traffic arrangement at site, which was one of the key
critical issues facing the Trimmu Barrage Project. At the end of presentation, all visitors paid a visit
to the Chinese Camp, petrol pump area and then had a glimpse of additional bays activities.
Director Environment and Social delivered a talk on ongoing site works to ADB Mission at the
additional bay area. Then the visitors headed toward the fuelling area where ADB Environmental
Specialist (Ms. Safia Shafique) raised her concern over the petrol pump safety arrangements and
restricted access. The Contractor agreed to comply with the instructions forthwith and the necessary
action was accordingly taken. A detailed brochure about the Environment and safety works was
handed over to ADB delegation for their information.
ADB Gender Specialist (Ms. Uzma Altaf) desired to meet the Project Affected (Persons PAPs). All
visitors approached the newly resettled community area named as Basti Bakash Muhammad to
know about their concerns and to check the new houses. PAPs Committee Chairman elaborated
various proceedings about the resettlement of PAPs and expressed 100% satisfaction regarding
the relocation payment and endorsed his full cooperation to the PMO, TPBC and SCL. ADB Gender
Specialist inquired about the PAPs jobs, the Contractor responded that, they have already hired
services of PAPs and further hiring preferably will be done from PAPs and local community. Local
women were also consulted by the Gender Specialist about their lives and traditional skills. Mostly
women were uneducated and they worked at home particularly household works.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 12
Figure 1-4: Presentation of TMP by Senior Env. TPBC Chinese Camp Visit
1.12.5. PMO, TPBC & Contractor’s Staff Site Visit to Check Environment and Safety Arrangements
It is normal practice that, after each EPRM, a joint visit is carried out to check the adequacy of
Health Safety and Environment arrangements for the Contractor’s labor and staff. After EPRM #
05, a joint visit was made to inspect the Labor Camp Area, Borrow Area, Additional Bays, First Aid
Center and the Construction Yard Area. Followings observations were made:
• M/s. Sinohydro provided double bunker in Labor Barracks which pose serious hazard for
labor while climbing up the bunker which can cause any dire incident. After Consultants
perusal, the Contractor replaced the ceiling fan(s) with bracket fan(s).
Figure 1-5: Double Bunker Interview with Labor
• Flyproof door has not been provided in the kitchen, the Contractor was advised for the
needful which is in progress.
• In winter, the Contractor was pressed hard for provisions of geysers, same was provided
for labor bathing and washing facilities.
• The Contractor was advised to improve the housekeeping of rooms, toilets and kitchen.
• On labor request, laundry facilities have been provided for the labor to facilitate them for
cloth washing.
• For adequate collection of waste, the Contractor was instructed to put more waste bins
inside the camp area, the Contractor agreed and provided bins as desired.
• In the Labor Camp, the residents were inquired about the issues inside the Camp. They
responded that the due to high ambient temperature, cooling facilities should be made
Fan replaced with
bracket fan
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 13
in labor camp like desert coolers. The Contractor was advised accordingly and room
coolers were installed in each room.
Figure 1-6: Cooling & Heating Facilities in Labor Camp
• the second issue was raised by the labor regarding provision of hygienic quality food and
change of menu. Director Environment and Social, Deputy Director Resettlement and
Consultant’s Environmentalist amended the menu as wished by majority of laborers.
Figure 1-7: Food Quality Inspection of Labor Camp by PMO Director E&S
Similarly, after the Labor Camp’s inspection, the Project work site was visited and following pertinent
points were noted:
• In order to check the compliance of PPEs, steel yard, mechanical workshop, petrol pump
areas were visited. Provision of PPEs remained satisfactory, however the Contractor was
advised to keep monitoring to avoid any untoward incident.
• Petrol pump area was monitored which was not compacted and no proper firefighting
arrangement was made. At the instructions of the visit team of PMO and the Consultants,
the “petrol pump area” was compacted by the Contractor with lean concrete and sand heap
and fire extinguishers were placed to tackle any fire hazard.
Geyser installed in Labor
Camps
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 14
Figure 1-8: Senior Environmentalist of TPBC Briefing After Lean Concrete
The Mechanical Workshop was also visited where all laborers were wearing PPEs and minor oil
spillage was identified. The Contractor was advised to remove it or cover it with sand.
the Batching Plant was also visited and abysmal housekeeping was observed, the Contractor’s HSE staff took prompt action and admonished the plant staff for poor housekeeping. Thereafter
Housekeeping at the Batching Plan has seen a considerable improvement.
Figure 1-9: Working Area
Minor
Spillage in
Workshop
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 15
Figure 1-10: Good Housekeeping in Batching Plant Area
1.13. Institutional Arrangements of Trimmu Barrage Project
The organizational structure for the environment management/monitoring implementation is
discussed in Section 1.13.1. The organization chart is presented in Figure 1-11.
1.13.1. Project Management Office (PMO)
The overall responsibility for the implementation of Environmental Management Plan rests with the
Head PMO along with the assistance of Environmental & Social Unit (ESU) of PMO. The detailed
organogram is presented below:
Figure 1-11: Organogram of Trimmu Barrage Project
Project Management Office (PMO) Project Director (PD) Trimmu Barrage
Environmental and Social Unit
PMO Support Consultants
Construction Supervision Consultants
Deputy Director
(Environment)
Environmental Specialist
Monitoring and Evaluation
Expert
M&E Officer
Jr. Environmentalist
Deputy Director (Sociology)
Deputy Director
(Community Relations)
Deputy Director (Social
Safeguards)
Environmental Inspector
Contractor
Environmental Manager
Director (Engineering)
Director (Environment and
Social)
Senior Environ-mentalist
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 16
• PMO ensures that the Contractor and the Supervision Consultants appoint dedicated and
competent environmental officer(s) and allied staff. PMO also ensures that all environmental
personnel are authorized to implement the environmental and social policies and requirements
of the EMP.
• ESU co-ordinates with relevant government departments and stakeholders on concerned
environmental and social/ resettlement issues.
• ESU has a mandate to inspect and monitor residual impacts of the project and record
documentation of the impacts during the project.
• ESU will also inspect the significance of impacts in case of any unanticipated change in the
scope of the project.
• Any major change in the project shall be reported to ADB before its execution.
• Directorate of Environment PMO acts as the Environmental Management Office.
• PMO will ensure that consultant’s team has an unhindered access to all relevant documents, persons and places to enable it to perform its functions effectively and efficiently.
1.13.2. Construction Supervision Consultants
The Consultants Senior Environmentalist Mr. Muhammad Saleem Falak was mobilized on February
25, 2016 at Trimmu Barrage Project Head Office in Lahore. Initially all pertinent plans were
scrutinized closely and comments were furnished for refinement in plans submitted by the
Contractor. On August 1, 2016, Senior Environmentalist was transferred at site to monitor the
construction works on full time basis. Presently, Senior Environmentalist has been monitoring all the
project activities on regular basis and preparing reports for information of the PMO and Team Leader.
All possible efforts are being made by the Consultant to supervise ongoing construction activities under
the guidance of EMP terms and conditions. The site based activities are brought into knowledge of
Chief Resident Engineer who participate efficiently and effectively to resolve the issues in case of non-
compliance/violation of contractual obligations.
Until now, the work is going smoothly and no major accident/incident has happened at site.
However, it is desirable that one safety inspector is provided for assistance and close supervision
of various activities.
1.13.3. Contractor
The Contractor is responsible for execution of the construction activities and for environmental
protection through its environmental and social field staff. The Contractor is subject to
environmental protection liabilities under environmental laws of Pakistan and the Project’s ESIA/EMP provisions under its Contract with the Punjab Irrigation Department (PID). The
Contractor is also responsible for communicating environmental & social information and for
imparting of necessary training of staff in all aspects of the EMP. The Contractor’s organogram is
presented in Figure 1-12.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 17
Contractor’s Organogram
Site Manager
Habib-ur-Rahman
Incharge HSE
Shahid Iqbal
Sr. HSE Officer Environmentalist MBBS Doctor
Iqbal Malik Muhammad Ammar Javed Iqbal
HSE Supervisor HSE Assistant
Nayyer Ahsan M. Rizwan Paramedic (Day) Paramedic (Night)
M. Yousaf M. Mushtaq
HSE Assistant Flagmen
Gulistan
Junaid Shabbir
Flagmen Khursheed Ahmad
Saqlain Abbas
M. Baqir Tariq Saeed
M. Attique Jafir Ali
Khizar Hayyat Aqib Javid
Rafiq Tahir Siddiqui
Zeeshan M. Ashraf
Imran Fazal Abbas
M. Shoaib Waheed Ahmad
M. Ishfaq M. Imran
Figure 1-12: Contractor’s Organogram
1.14. World Environment Day June 5, 2017 Celebrations
It is worth mentioning that World Environment Day (WED) was celebrated at site on June 5, 2017.
A comprehensive presentation on this year’s theme “Contacting People to Nature” was delivered
by the TPBC Senior Environmentalist which was attended by the Contractor’s staff and workers. It
was emphasized that all the project staff shall protect the environment its true letter and spirit and
the ideology of “Local Action & Global Impact” will be adopted. After presentation, tree saplings
were planted by the Site Manager, Construction Manager and TPBC Environmentalist. TPBC and
Contractor staff conducted a site walk about awareness of the Environment Day among the masses.
At site, a short lecture was delivered about the importance of Environment and how to protect it.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 18
Figure 1-13: World Environment Day Celebration on June 5, 2017
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 19
2. ENVIRONMENT MONITORING PERFORMANCE
2.1. Environmental Monitoring Summary
Qualitative Environmental Monitoring is the site based observations in which the Contractor’s construction activities are monitored and verified to ensure that these activities are in accordance
to the requirement set forth in EMP/EIA & SSEMP. To achieve those objectives, the Contractor has
made an agreement with a Third Party Lab. i.e. M/s. Global Environmental Lab (GEL) for quarterly
monitoring. Comprehensive Environmental Monitoring was carried out in October 2016, wherein
required parameters were tested such as ambient air quality, noise monitoring, diesel operated
generators stack emissions etc. Ground water samples of three camps were collected and tested
by PCSIR Laboratories Lahore.
2.2. Types of Monitoring
Two types of monitoring is being carried out at site as discussed below:
• Instrumental Monitoring/Effects Monitoring/External Monitoring: This monitoring is
performed by a Third Party External lab which includes, ambient air quality monitoring (SOx,
NOx, CO2, PM10), noise measurement, water and waste water analysis.
• Compliance Monitoring/Internal Monitoring: Internal monitoring is carried out by the site
staff which includes surface water analysis (Electrical Conductivity, Total Dissolved Solids
Temperature & pH), Dissolved Oxygen (DO) upstream and downstream of the Barrage,
noise level measurement and safety arrangements.
2.3. Internal Monitoring
2.3.1. Noise & Vibration Monitoring
Noise level monitoring is performed at site thru the noise level meter at site by the Contractor and
Consultant’s representative on daily basis or as required. Noise is measured from high noise
generating areas such as generators, air blowers, vibrators, heavy equipment etc. in case if noise
is beyond the permissible limits of NEQS 75dBA then the Contractor’s concerned staff is instructed for prompt action for keeping the machinery like excavators, grader, cranes, generators, air blowers,
in good working condition. Furthermore, the Engineer’s Environmentalist ensures that in high noise
generating areas, the workforce is wearing proper PPEs i.e. ear plugs/ear protection equipment to
minimize the impact of noise.
At start of the Project, the Contractor was clearly informed by the Engineer about the construction
of camps away from workplace so that noise could not create nuisance for labor and staff.
Following steps are advised to minimize the noise impact:
• Vehicles are periodically checked for noise level and necessary repair and maintenance
done.
• In camps generators are covered with canopies.
Graphical representation is shown in Graph 2-1 along with photographic evidence in Figure 2-1.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 20
Figure 2-1: Noise Level Meter & Noise Level Monitoring
Graph 2-1: Noise Monitoring Result of January 2017
67
75
62
80.3
88.2
70.174.3
0
10
20
30
40
50
60
70
80
90
100
1
Va
lue
s d
(BA
)
Noise Measurement dB(A) in Project Area
Base values (Lmax) NEQS Standard E & P workshop area
Coffer dam Generator Batching plant Generator ICE plant
Additional bay area
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 21
Graph 2-2: Noise Monitoring result of February 2017
Graph 2-3: Noise Monitoring result of March 2017
Graph 2-4: Noise Monitoring Result of April 2017
6775
6272
98.9
69 71
0
20
40
60
80
100
120
1
Va
lue
s d
(BA
)
Noise Measurement dB(A) in Project Area
Base values (Lmax) NEQS Standard E & P workshop area
Batching Plant #1 inside cabin Hilty Generator near HR
Steel Yard
6775
62
80.1 79.9 81 80.9
0
20
40
60
80
100
1
Va
lue
s d
(BA
)
Noise Measurement dB(A) in Project Area
Base values (Lmax) NEQS Standard E & P workshop area Air Belower
Jack Hammer PC yard vibrator Dewatering Generator
6775
6267.1
97.8
81
66.4
0
20
40
60
80
100
120
1
Va
lue
s d
(BA
)
Noise Measurement dB(A) in Project Area
Base values (Lmax) NEQS Standard E & P workshop area
Batching Plant #2 inside cabin Air belower PC yard vibrator
Transit Mixer # 04
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 22
2.3.2. Surface Water Quality Monitoring
According to EMP requirements quality of surface water is of paramount important for sustenance
of aquatic life prevailing at Trimmu Barrage. Surface water quality is being monitoring jointly by the
Consultant and Contractors representative upstream and downstream of the right side of the
Barrage with multi-meter (Electrical Conductivity, Total Dissolved Solids Temperature & pH) and
Dissolved Oxygen (DO meter). The results of surface water monitoring are provided in Table 2-1
and reports attached as Annex-VI.
Table 2-1: Surface Water Monitoring Results
Sr.
No. Parameter Unit NEQS
Jan-17 Feb-17 March-17 April-17 May-17 June-17
U/s D/s U/s D/s U/s D/s U/s D/s U/s D/s U/s D/s
1 Temperature C0 <=30 23.1 26.2 29.9 25.5 26.4 29.6 24.1 23.5 19.8 16.7 17 17.4
2 pH - 6.6-8.5 6.7 7.4 6.9 7.8 8.1 8.0 7.8 7.4 7.3 7.9 8.1 7.8
3 Total Dissolved
Solids (TDS) mg/l 3500 540 580 510 603 420 380 180 150 190 135 205 215
4 Electrical
Conductivity (EC) µs/cm 1055 1130 940 1020 992 920 860 340 310 355 325 340 310
5 Dissolved
Oxygen (DO) mg/l 4-9 6.5 6.3 5.3 6.1 7.00 7.8 6.4 7.5 6.7 5.6 6.7 7.6
Graph 2-5: Surface Water Quality Result of January 2017
Surface water quality results are presented in Graphs 2-5 to 2-10 for the period from January to
June 2017.
-100
100
300
500
700
900
1100
1300
pH EC (uS/cm) TDS (mg/l)
Base values 7.1 890 420
NEQS 7.5 1055 1000
Current values U/s 6.7 1130 540
Current values D/s 7.4 940 580
V
a
l
u
e
s
Parameters
Surface Water Analysis January 2017
Base values
NEQS
Current values U/s
Current values D/s
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 23
Graph 2-6: Surface Water Quality Result of February 2017
Graph 2-7: Surface Water Quality Result of March 2017
-100100300500700900
1100
pH EC (uS/cm) TDS (mg/l)
Base values 7.1 890 420
NEQS 7.5 1055 1000
Current values U/s 6.9 1020 510
Current values D/s 7.8 992 603
V
a
l
u
e
s
Parameters
Surface Water Analysis February 2017
Base values
NEQS
Current values U/s
Current values D/s
-100100300500700900
1100
pH EC (uS/cm) TDS (mg/l)
Base values 7.1 890 420
NEQS 7.5 1055 1000
Current values U/s 8.1 920 420
Current values D/s 8 860 380
V
a
l
u
e
s
Parameters
Surface Water Analysis March 2017
Base values
NEQS
Current values U/s
Current values D/s
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 24
Graph 2-8: Surface Water Quality Result of April 2017
Graph 2-9: Surface Water Quality Result of May 2017
-100
400
900
1400
pH EC
(uS/cm)
TDS
(mg/l)
Base values 7.22 649 439
NEQS 7.5 1055 1000
Current values U/s 7.8 340 180
Current values D/s 7.4 310 150
V
a
l
u
e
s
Parameters
Surface Water Analysis April 2017
Base values
NEQS
Current values U/s
Current values D/s
-100
100
300
500
700
900
1100
pH EC (uS/cm) TDS (mg/l)
Base values 7.5 75 114
NEQS 7.5 355 1000
Current values U/s 8.1 340 205
Current values D/s 7.8 310 215
V
a
l
u
e
s
Parameters
Surface Water Analysis May 2017
Base values
NEQS
Current values U/s
Current values D/s
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 25
Graph 2-10: Surface Water Quality Result of June 2017
Note: Please note that, changes in values are due to seasonal variations. Construction activities
has not caused any adverse impact on the river water quality. Also, it has been noted that, in River
Chenab huge effluents are discharged from Faisalabad Industrial Area and Chiniot’s Waste Water
which may deteriorate the quality of river water.
Whereas as the Dissolved Oxygen minimum level for survival of fish is 4.8 mg/l and the measured
DO was always within permissible limits and higher than the minimum sustenance level of aquatic
life.
2.4. Instrumental Monitoring/External Monitoring
2.4.1. Drinking Water Quality Monitoring
The surface and groundwater in the Project Area are likely to be polluted due to project activities
for which necessary preventive measures must be adopted by the Contractor. Human beings are
the most concerned about the direct effects of pollutants upon their health. Environmental Indicators
of Trimmu Barrage are shown in Figure 2-2.
-100
100
300
500
700
900
1100
pH EC (uS/cm) TDS (mg/l)
Base values 7.5 75 114
NEQS 7.5 355 1000
Current values U/s 8.1 340 205
Current values D/s 7.8 310 215
V
a
l
u
e
s
Parameters
Surface Water Analysis June 2017
Base values
NEQS
Current values U/s
Current values D/s
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 26
Figure 2-2: Environmental Indicator(s)
As per requirement of EMP, in the first round of external monitoring, ground water samples were
collected from the Main Camp & Labor Camp by the Engineer and Contractor’s concerned staff and submitted in PCSIR Lahore for physical, biological and chemical analysis on March 2, 2017.
Biologically water was not fit for drinking purposes as it exceeded the Total Plat Count, Total
Coliforms, Fecal Coliforms and E. Coli limits whereas chemically the Contractor’s Main Camp
ground water was also not recommended by the PCSIR according to WHO Guidelines due to
presence of Arsenic (As) contamination 50ug/L. Similarly, the ground water quality of Consultant
residence was also contaminated with Arsenic of 30ug/L and Biologically unfit.
In the Labor Camp, water was suitable biologically but was found unfit chemically due to presence
of Arsenic (As) contamination i.e. 30ug/L. The Engineer promptly advised the Contractor for
immediate arrangements for alternate source of water for the labor and staff. Thereafter an
emergency meeting was arranged by the PMO and TPBC with the Contractor staff to decide about
the drinking water issue. At the end of meeting, all the participants agreed for new borehole in the
Main Camp, if the quality of this water was found free of Arsenic then other boreholes in Labor
Camp shall be started. However, a new borehole was excavated up to 200 ft. and ground water
was resampled for retesting/rechecking from PCSIR. Water sample was submitted on May 10, 2017
and result received in the Consultant office on May 19, 2017. According to result delivered by the
PCSIR Lahore, water was found to be suitable Biologically but declared unfit Chemically due to
again Arsenic contamination of 60ug/L.
Meanwhile, the Contractor was very clearly advised to make an alternate arrangement for clean
and pure drinking water for the labor and staff till completion of any new borehole. However, the
Consultant made agreement with local water supplier named as Pure Nature and the Engineer’s outfits are consuming clean water. The Engineer conveyed the Contractor for arsenic based filter
Sand column, Fe (OH)3 & activated carbon based filter should be used to reduce the quantity of
arsenic in ground water or pure water such as Gourmet, Nestle, Pure nature or Kinlay should be
procured from the local market which is readily available. The Contractor has not made any
alternate water source arrangements despite of the Engineer hectic perusal.
Upstream of Barrage location
for Surface water monitoring
Downstream of Barrage location
for Surface water monitoring
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 27
Furthermore, the labor and staff members were consulted due to consumption of as contaminated
water, they apprised about minor hair fall, stomach issues and no major issue notified like hair
follicles, skin allergy, washing and bathing issues. A correspondence with the Contractor regarding
clean water is attached as Annex-VII.
The PCSIR results of water are provided in below Table 2-2 & Table 2-3 and reports are attached
as Annex-VIII.
Groundwater Quality comparison with WHO Standards (2011)
Table 2-2: M/s. Sinohydro Main Camp First result
Sr.
No. Parameter
Results of
M/s. Sinohydro Camp
WHO (2011)
(Drinking Water)
1 pH @ 250 0C 7.66 6.5-8.5
2 Total Alkalinity as CaCo3 (meq/l) 4 NGVS
3 Carbonate (mg/l) 200 NGVS
4 Bicarbonate (mg/l) 244 NGVS
5 Total Hardness as CaCo3 (mg/l) 249 500
6 Calcium hardness as CaCo3 (mg/l) 100 NGVS
7 Magnesium hardness as CaCo3 (mg/l) 149 NGVS
8 Total Suspended Solids (mg/l) 0 NGVS
9 TDS (mg/l) 355 1000
10 Calcium as Ca(mg/l) 40 NGVS
11 Magnesium as Mg (mg/l) 35 12
12 Potassium as K (mg/l) 5 NGVS
13 Sodium as Na (mg/l) 80 200
14 Chloride as Cl (mg/l) 43.98 250
15 Sulphate as So4 (mg/l) 69.05 250
16 Conductivity at 25C (Us/cm) 606 NGVS
17 Nitrate as No3 (mg/l) 1.38 50
18 Nitrite as No2 (mg/l) 0 0.5
19 Fluoride (mg/l) 0.27 1.5
20 Arsenic (ug/l) 50 10
Arsenic value is higher than WHO standards and water is not recommended for dinking
purposes as per WHO recommendations/guidelines
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 28
Graph 2-11: Groundwater Results of Main Camp
Table 2-3: Groundwater Analysis of Labor Camp
Sr.
No. Parameter
Results of
Labor Camp
WHO (2011)
(Drinking Water)
1 pH @ 250 0C 7.78 6.5-8.5
2 Total Alkalinity as CaCo3 (meq/l) 3.6 NGVS
3 Carbonate (mg/l) 180 NGVS
4 Bicarbonate (mg/l) 219 NGVS
5 Total Hardness as CaCo3 (mg/l) 122 500
6 Calcium hardness as CaCo3 (mg/l) 75 NGVS
7 Magnesium hardness as CaCo3 (mg/l) 47 NGVS
8 Total Suspended Solids (mg/l) 0 NGVS
9 TDS (mg/l) 211 1000
10 Calcium as Ca(mg/l) 30 NGVS
11 Magnesium as Mg (mg/l) 11.28 12
12 Potassium as K (mg/l) 3 NGVS
1.180 0.26
30
50
0.51.5
10
0
10
20
30
40
50
60
Nitrate as No3 (mg/l) Nitirte as No2 (mg/l) Fluride (mg/l) Arsenic (ug/l)
1st round 7.78 3.6 180 219 122 75 47 0 211 30 11.28 3 70 58 40.29 357
WHO guidelines 2011 6.5-8.5 NGVS NGVS NGVS 500 NGVS NGVS NGVS 1000 NGVS 12 NGVS 200 250 250 NGVS
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 29
Sr.
No. Parameter
Results of
Labor Camp
WHO (2011)
(Drinking Water)
13 Sodium as Na (mg/l) 70 200
14 Chloride as Cl (mg/l) 58 250
15 Sulphate as So4 (mg/l) 40.29 250
16 Conductivity at 25C (Us/cm) 357 NGVS
17 Nitrate as No3 (mg/l) 1.18 50
18 Nitrite as No2 (mg/l) 0 0.5
19 Fluoride (mg/l) 0.26 1.5
20 Arsenic (ug/l) 30 10
Arsenic value is higher than WHO standards and water is not recommended for dinking
purposes as per WHO recommendations/guidelines
Graph 2-12: Ground Water Results of Main Camp
Only Arsenic parameter was suggested in retesting and result has depicted in Table 2-4.
Table 2-4: Retesting Results of Main Camp
Parameter Reported Value WHO Guidelines 2011
Arsenic (ug/L) 60.00 10
Arsenic value is higher than WHO standards and water is not recommended for dinking
purposes as per WHO recommendations/guidelines.
1.180 0.26
30
50
0.5 1.5
10
0
10
20
30
40
50
60
Nitrate as No3 (mg/l) Nitirte as No2 (mg/l) Fluride (mg/l) Arsenic (ug/l)
1st round 7.78 3.6 180 219 122 75 47 0 211 30 11.28 3 70 58 40.29 357
WHO guidelines 2011 6.5-8.5 NGVS NGVS NGVS 500 NGVS NGVS NGVS 1000 NGVS 12 NGVS 200 250 250 NGVS
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 30
2.4.2. Waste Water Analysis
The Contractor has established two camps, one on right side of the Barrage for Labor and the other
on left side of the Barrage for management staff. Proper sewerage system has been constructed in
both camps which comprises of septic tank and soakage pit. The waste water which generate from
both camps is being collected by water bowser and sprinkled away from the camp area. No
complaints registered or heard about the waste water disposal from the local community.
We have been pursuing the Contractor for waste water testing since instrumental monitoring has
started. So far, the waste water monitoring has not been carried out despite the Consultant hectic
perusal. PMO has been notified about this violation of Contract agreement and the matter is still
under consideration.
2.4.3. Ambient Air Quality Monitoring
First round of instrumental monitoring was carried out in the month of October 2016 and following
parameters were tested
• Ambient Air Monitoring: NOx, Sox, CO2 & PM10
• Vehicular analysis: Smoke Density by Ringle Man scale
• Diesel Operated Generators: Smoke Density by Ringle Man Scale
The details of results were provided in the Quarterly Progress Report from October to December
2016 and second round of monitoring was supposed to performed on February 22, 2017.
As per EMP requirements, the Contractor is required to carry out ambient air monitoring on quarterly
basis. However, it is regretfully stated that inspite of the Senior Environmentalist’s best possible efforts, the Contractor has not been able to arrange for the 2nd & 3rd Quarterly Monitoring which are
now overdue.
The matter was brought to the knowledge of Project Management Office thru Director Environment
and Social Malik Pervaiz, he has discussed the issue in EPRM # 3,4 & 5 but no cogent action has
been taken by the Contractor as yet.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 31
3. ENVIRONMENTAL & SOCIAL MANAGEMENT
3.1. Flora & Fauna
During the reported period, no flora and fauna was disturbed by the construction activities. No
mortality of animal was reported and no wildlife or bird sanctuary or protected area lies within
jurisdiction of RoW. The Contractor started Bela removal work inside the river after preparing
adequate route for the same.
3.2. Borrow Area
The area from where soil is being taken for construction of the Cofferdam is called the Borrow Area.
The ditch that is dug to excavate the borrow material is called the borrow pit. The Contractor
selected borrow material from the common bank of Haveli and T.S. Link Canal where heaps of silty
clay material were used for the construction of cofferdams located on left side of the Barrage. The
selected area lied in the Right of Way (RoW) of Trimmu Barrage, therefore no agreement was
deemed necessary.
According to EMP guidelines, the Contractor was advised to excavate the borrow area up to 3 ft.
maximum removing of 6” fertile soil layers. Thereafter, the Contractor requested that with 3 ft. depth,
construction of Cofferdam will be difficult as no sufficient suitable material is available in the vicinity
of the Barrage. Due to the urgency of construction of the Cofferdam, the Contractor was instructed
to excavate the borrow material up to 6 ft. and over excavated area shall be reinstated. Furthermore,
the Contractor was advised to protect the adjacent land and that natural profile of the borrow area
should be restored after utilization.
During the construction of cofferdams, the Contractor utilized the heavy dumpers for carrying the
borrow material. Due to frequent movement of dumper(s), there was risk of accident with local
transport on the main road. Also, the dust emissions caused a serious problem for the commuters.
By collective efforts of PMO and TPBC, the Contractor was advised to utilize the common bank for
movement of the heavy dumpers, the Contractor completed with the instructions and maintained a
separate route for heavy vehicles. By adopting adequate measure, no accident occurred at site due
to movement of the heavy vehicles/traffic.
The Engineer’s Sr. Environmentalist kept regular monitoring of the borrow area and delivered
necessary instructions in order to avoid soil erosion. However, the Contractor excavated the borrow
area more than desired depth. After consistent perusal by the PMO and TPBC, now the common
bank borrow area has been restored and same was witnessed by the Director E&S PMO Malik
Pervaiz. Borrow area on left side of the T.S. Link Canal has been restored, but PMO and TPBC has
advised the Contractor for improvement. The Contractor has agreed to restore the areas in due
course of time. Photographs are shown in Figure 3-1.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 32
Figure 3-1: Borrow Area Restoration in Progress
PMO, TPBC & SCL visit Machinery in progress in Borrow Area
Slope of Borrow Area
maintained
During borrow area restoration,
bird’s eggs found which saved by the Contractor staff on instruction of
PMO & TPBC
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 33
3.3. Traffic Management Plan Implementation
Traffic Management Plan is a stand alone document of Trimmu Barrage Project which is adopted
by the Contractor and approved by the PMO and TPBC for implementation. Prior to divert the public
transport on diversion roads, the PMO, TPBC and SCL had arranged numerous meetings with local
administration of Jhang. During our meeting with Deputy Commissioner Jhang and Farmer
Organizations, they suggested that to allow the tractor trollies passage till November 20, 2016. The
PMO, TPBC and SCL allowed and diversion of traffic plan postponed till that date.
Before actual diversion of the traffic, Secretary Road and Transport Mr. Mohsin Riaz visited the site
and expressed satisfaction over arrangements made by the Contractor. During a subsequent
meeting, it was decided by all the participants that the heavy traffic shall be diverted from Jhang
side, the traffic will be diverted Mohlu More to Shorkot and Athra Hazari to Ghar Maharaja Bridge
to Jhang. A notification issued by the District Coordination Officer (DCO) for diversion of traffic is
shown in Figure 3-2.
Figure 3-2: Traffic Diversion
For smooth flow of traffic from the Project Area, adequate arrangements were made in terms of
hiring of 27 No. flagmen installation of sign boards, diversion plans etc. Performance of the
Contractor in compliance of the TMP was overall satisfactory with some exceptions. Traffic was
passed from coffer dams crest from left side of the Barrage then diverted on Rangpur Canal
diversion. It was very tedious work to maintain the flow of traffic in the Project Area, the Contractor
was impressed hard for maintenance of diversion routes and regular water sprinkling was carried
out to suppress dust emission in project premises. Overall plan of traffic management is provided
in Figure 3-3.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 34
Figure 3-3: Traffic Management Plan of Trimmu Barrage
Traffic Diversion
3.3.1. Installation of Sign Boards, Diversion Signs
However, project vehicles i.e. dumpers, trollies etc. were found over speeding in the Project Area.
The Engineer has advised the Contractor for speed limit signboard installation at various project
locations and more stringent enforcement mechanism such as to take punitive action against the
driver who violates the speed limit inside the Project Area. Presently, the Contractor has deployed
21 flagmen in the Project Area to control the traffic in day and night shift. On regular intervals, the
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 35
trainings of flagmen are arranged on traffic management by the Engineer and Contractor’s
Environment team. Safety caution boards have been provided as shown in Figure 3-4.
Figure 3-4: Speed Limit Board & Flagmen Working on Diversion
Sometime the Contractor showed carelessness in water sprinkling and maintenance of the
diversion roads, the Engineer issued letter to the Contactor for immediate compliance. Those letters
are attached as Annex-IX.
3.4. Dust Abatement & Air Emission Monitoring
The construction activities of the Project generates huge dust emissions due to excavation works.
Diesel and other petroleum products are used for the operation of construction machinery and
transportation which emit the unburnt carbon, constituent of SOx, NOx that cause air pollution.
Proper mitigation measures are being practiced at site. Vehicle maintenance works are being done
on daily basis to minimize the impact on environment. Equipment and Plant Supervisor has been
advised to get the vehicles repaired within seven (7) days otherwise the same machinery will not
be allowed to work at site. Moreover, for dust emissions, regular water sprinkling is being performed
in dust prone areas as shown in Figure 3-5.
Figure 3-5: Water Sprinkling in Operation at Cofferdam & Diversion Board
3.5. Tree Plantation Plan
Under the EMP Guidelines, the Contractor was advised to plant at least 1,000 species in the first
stage of the Project. However, the Contractor planted only 871 species of plants at various locations
i.e. Irrigation Canal Colony, Girls Middle School, Executive Engineer Rest House, Haveli Canal and
Labor Camps etc. However, the Contractor has promised to plant around 5,000 species in upcoming
season. In this phase, the Contractor’s performance has remained unsatisfactory as per Tree
Plantation Plan. The current plants growth rate has been presented in Table 3-1.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 36
Table 3-1: Tree Plantation Status
Sr. No. Location Type of Specie Qty. Current Growth
1 Xen Rest House Sufaida & Kikar 170 & 30 70
2 Girls Middle School Kikar 50 50
3 Labor Camp Sufaida, Kikar and fruit plants 50, 50 & 10 110
4 Along Haveli Canal Cono, Kikar 60 & 30 90
5 Chinese Camp Sufaida, Kikar 50 & 50 80
6 Police Barracks Sufaida, Kikar 50 & 50 90
Grand Total: 490
3.6. Oil Spill Management
Diesel and Petrol products are being used for the operation of machinery and generator operations.
Diesel and petrol drums are placed in warehouse, whereas concrete pads have been provided. On
the other hand, the diesel operated generates are placed at various locations of the Project such
as Coffer Dams, Additional Bays Area, Batching Plants, Main Office & Labor Camp. These
generators are being maintained by the concerned staff so that no leakage occurs. However, minor
leakage was observed and the Contractor was informed to scrap the contaminated soil for proper
disposal. However, no major oil leakage was reported during the reporting period. In the Batching
Plant Area generators are placed on concrete pad and oil leakage bund constructed. But for the
generators working at additional bay areas and coffer dams, no concrete pad or oil collection trays
are provided beneath. So minor oil leakage was identified.
Figure 3-6: Concrete Pad Beneath Generators & Director E&S Monitoring Generator
3.7. Fuel Station Area
According EMP requirements, the fuel storage area was constructed by M/s. Sinohydro. Fuel
storage site is provided with impervious floor (concrete) in underground tanks only. Initially, no
fence, warning sign, no fire extinguishers were available. After ADB Environmental Specialist’s
instructions, the Contractor has constructed a pad in fuelling area and further improvement is in
progress. Until now, no serious oil/fuels spillage is recorded at site.
Director E & S PMO and TPBC Senior Environmentalist have advised the Contractor to make
stringent efforts like the area should be placed under restricted access with provisions of firefighting
equipment, sand heap should be arranged in fuelling site to combat with fire hazard. Furthermore,
the firefighting equipment drill must be arranged for working staff. Latest photographs of fuel station
are provided in Figure 3-7.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 37
Figure 3-7: Before & After Fuel Station
3.8. Environmental Management and Monitoring Plan (EMMP)
Environmental Management and Monitoring Plan is prepared at design phase of the project and
then made part of the Environmental Management Plan. EMMP is aimed at mitigation of the
possible adverse impact(s) of a development project and ensuring to maintain the existing quality
of environment. Environmental Management and Monitoring Plan addresses all aspects, pre-
construction, construction and operational phase of the project which are relevant to the
Environment. Main objective of EMMP is to identify the project’s specific activities which may cause
negative impact and proposes mitigation measures thereof.
The framework of Environmental Management and Monitoring Plan includes identifying and
evaluating the risk, organizing, managing environmental responsibilities, evaluating quality of air,
drinking water, surface water and determining how it is affected by the project activities and
achieving adequate level of environmental performance.
Scope of EMMP encompasses following pertinent activities:
• Civil works for the proposed Project
• Operational Activities
• Occupational Health & Safety
• Discharges Effluents & Emissions
• PPEs
• Waste Management
• Hazardous Waste Management
• Biological Hazard(s)
• Emergency Response Plan (ERP)
• Oil spillage/Leakage
• Noise Control
• Surface Water Monitoring
• Litter & Solid Waste
• Flora & Fauna
• Traffic Management
• Campsite Management
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 38
• Environmental Monitoring
• Environmental Audit
• Trainings
• Deployment of HSE/Environment Staff
• Compliance status of the Project
3.9. Campsite Management & Labor Accommodation
Necessary guideline for campsite management were prepared by the Senior Environmentalist
under the light of EMMP recommendations. Initially learnt the project scope of work, then advised
the Contractor accordingly for adequate arrangements for safe and sound execution of the Project.
The Contractor was advised to hire experienced Health Safety and Environment Team to supervise
various project activities. Consultant and Contractor staff mutually prepared the Environment Health
and Safety Checklist to identify the issues at project site. All the provisions were added in
comprehensive checklist so that no activities were left unattended.
Furthermore, the Contractor was intimidated that to establish a First Aid Center and hire the services
of MBBS doctor and paramedic staff. Moreover, standby ambulance was also needed in case of
emergency observing the wearing of PPEs are also vital part of the Project and Contractor was
advised to show maximum emphasize for the labor for wearing PPE’s.
• Arrangements regarding waste management were also streamlined by proposing waste pit
and instructed to adopt the 3Rs technique for effective management of solid waste.
• All the Sub-Contractor(s) shall follow main Contractor’s HSE policy and to provide satisfactory residences arrangements for their labor.
The Contractor was advised not to hire child labor and equal employment opportunity shall be
provided to everybody. Preference will be given to Project Affected Persons (PAPs) and local
residents for hiring.
For labor and staff accommodation, prior to mobilization of the Contactor, PMO and TPBC
conducted numerous visits of site to facilitate the Contractor for site selection and construction of
the camp facilities. After detailed site visit, the Contractor was advised to construct the main camp
near the Irrigation Canal Colony located on left side of the Barrage, as there were no trees, land
was compacted and no private land was needed. The Contractor submitted detailed staff
accommodation plan, in which messing facilities, sewerage system, waste collection plan,
firefighting arrangements, walkways, recreational management were described. Presently, the
management camp is imparting an excellent view due to proper walkways, jogging tracks,
plantation, grassy lawns etc. Detailed drawing of the Management Camp is attached as Annex-X.
M/s. Sinohydro has constructed two barracks for labor accommodations for its 600 strong labor
force. Other pertinent facilities are provided such as kitchen, washroom, toilets, recreational
facilities, mosque etc. Initially, there was poor housekeeping, now the same has improved.
Construction of walkways is under consideration, although the Contractor was instructed many time.
Before Labor Barracks have been regularly monitored by the Engineer’s Senior Environmentalist.
During the monitoring of housekeeping, solid waste collection segregation and disposal, food quality
and hygienic condition of toilets and kitchen were checked.
There is only one mess due to low labor strength. The provision of good quality food is inspected
by the Engineer staff and PMO on regular basis. As desired by the laborers Mess Menu has been
prepared and the food is now hygienic and satisfactory. The Contractor has provided cooling and
heating facilities in the Labor Barracks, and the Mosque. Overall the Contractor seems to be
continuously working for the improvement of the Labour Barracks, under the supervision and
guidance of the Engineer but pace work is slow. Labor Barracks Plan is attached as Annex-XI.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 39
Following shops have been working in labor camp:
• Barber Shop/Hair Dresser
• Juice/Cold Drinks Shop
• General Super Store
• Laundry Shop
Figure 3-8: Labor Camp Mosque & Accommodation Block
3.10. Field Visits by PMO Director E & S Malik Pervaiz
Several field visits have been carried out by the Director Environment & Social PMO along with
Monitoring & Evaluation Expert Mr. Nazim Hussain Shah and Chief Sociologist Mr. Rana Abdul
Rahman during reported period to check the project activities. Environmental issues were raised
with the Contractor and corrective and preventive actions discussed for amicable solution. The
purpose of the field visit is to sensitize the Contractor regarding EMP provisions such as excavation
of borrow area, traffic management, safety arrangements, health facilities, labor employment
opportunities, proper disposal of solid and liquid waste, provision of PPEs HSE, compliance
checklist and Consultant’s monitoring and evaluation.
Figure 3-9: PMO Monitoring the Site & First Aid Center
3.11. Grievance Redressal Committee
Project Management Office (PMO) issued a notification vide letter No. 791/HPMO/PMO dated
October 07, 2016 for establishment of Grievances Redressal Cell (GRC-I) of Trimmu Barrage
Rehabilitation and Upgrading Project to address the outstanding/unsettled issues by the following
nominees:
• Deputy Director Social (ESU), PMO Conveyer
• Resident Engineer (Civil), TPBC Member
• Senior Environmentalist, TPBC Member
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 40
• Administrative Office, M/s. Sinohydro Member
• Incharge HSE, M/s. Sinohydro Member
• DPC Male/Female Representative Member
Figure 3-10 shows a GRC Board Meeting in progress.
Figure 3-10: GRC Board Meeting in Progress
3.12. Complaint Register
As per ADB’s Environment & Social Safeguard Policy, EMP requirements, the Contractor was
advised to maintain two exclusive registers, one in the Main Camp and the other in Labor Camp to
record the complaints of labor and local community. The Contractor and Consultant concerned staff
noted the complaint registered by the labor and local community regarding job requirements.
Furthermore, PMO staff Director E & S also monitor the complaint register on his visit and advise
his opinions about complaints. During the reported period, various complaints were lodged and
matter resolved amicably. Photographs and complaints are depicted in below Figure 3-11.
Figure 3-11: Complaint Register
3.13. Employment Status
According to EIA requirements, the Contractor will ensure the employment for local labor upto 60%
or more. In this regard PMO and TPBC vividly conveyed that the Contractor shall hire more than
60% of local labor. PMO & TPBC prepared a format to know the monthly status of labor at Trimmu
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 41
Barrage Project and Contractor share this status with Consultant and PMO for record keeping. The
record of labor is provided in Table 3-2.
Table 3-2: Employment Status of Labor
SINOHYDRO CORPORATION LIMITED
Trimmu Barrage
District Wise Skilled/Unskilled Labour for the Month of May ,2017
Sr. No.
Districts SINOHYDRO
Total Sub-Contractor
Total Skilled Unskilled Skilled Unskilled
1 Jhang 132 157 289 69 45 114
2 Toba Tek Singh 8 0 8 0 0 0
3 Muzaffargarh 97 14 111 11 0 11 Total 237 171 408 80 45 125
%age 58% 42% 100% 64% 36% 100%
4 Other Districts 219 34 253 29 14 43
%age 87% 13% 100% 67% 33% 100%
Total Districts 456 205 661 109 59 168
Total %age 69% 31% 100% 65% 35% 100%
Note: 21 PAPs are employed at Project so far.
3.14. Social Framework Agreement
Social Framework Agreement has been completed with representative of local villages. The
agreement has been attached as Annex-XII.
3.15. Waste Management
3.15.1. Waste Water Collection & Disposal
Waste water generated at all camps is being collected and disposed off properly. In all camps waste
water is mixture of grey and black water which is disposed off into septic tank through sewer lines
as per layout plan. After primary treatment in three compartments of septic tank, the black water is
collected into soakage pit. When soakage pit gets filled, then the waste water is pumped out and
sprinkled away from Project Area. We have noted that, sometime, the Contactor do not pump out
waste water on time which over flows into nearby fields. No compliant has so for been noted by
residents or farmers in this regard so far. However, the Engineer has instructed the Contactor for
timely collection of waste water and proper disposal. Photographs for over flow of waste water
provided in Figure 3-12.
Figure 3-12: Over Flow of Waste Water
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 42
3.15.2. Solid Waste Collection
All the solid wastes generated in both camps is being collected into waste bins. In both the camps,
separate bins have been placed to segregate the waste at source. However, the Contractor has
also placed empty drums in construction yards for collection of solid waste i.e. warehouse, steel
yard, workshop area, batching plant etc. Waste bins in use are shown in Figure 3-13.
Figure 3-13: Waste Bins in Labor Camp
Regarding disposal of solid waste, the Contractor was advised that organic waste should be handed
over to the local municipal services or dispose it off into waste pit. The Contractor agreed to
construct the waste pit at agreed location, but until now no action has been taken in this regard.
Presently, waste is being disposed off outside the boundary wall of the camps which may cause
nuisance at a later stage. However, the Contractor has agreed to develop a waste pit soon.
3.15.3. Segregated Waste Management
Following the recommendation of the Engineer’s team, the Contractor has started to maintain the
waste management data sheet so that actual amount of waste could be estimated properly
On volumetric basis, the waste generated during this quarter was primarily associated with
workshop area, steel yard, remnants of concrete at additional bays areas and existing Barrage.
Other waste generated from the Main & Labor Camps and Medical Center are categorized and
segregated.
REDUCE, REUSE AND RECYCLING
• This quarter rebar end cuttings and scrap tension cables were delivered to recycling yard.
• Ply board sizes (from 0.4-1.2 m x 2.4 m) was re-used by other contractor? subcontractors.
Whereas small sizes which cannot be re-used were disposed off as waste.
• Chemical drums of Sikamen, diesel and petrol drums provided to vendor.
• Used oil filters, scraps from work shop area handed over to vendor.
• Continuous housekeeping and waste segregation at all works sites increases the general
and construction waste production. More mesh wires, timber pieces, iron bars were
collected by the Contractor with the massive housekeeping activities.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 43
Table 3-3 indicates the Non-Hazardous Waste Tons.
Table 3-3: Non-Hazardous Waste (Tons)
Waste Type Jan-17 17-Feb 17-Mar 17-Apr 17-May 17-Jun
General Domestic Waste 4 7 11 5 8 3
Mixed Construction Waste 1 3 5 2 1.5 2
Concrete 2 4 7 1.5 3 5
Wood 150 100 105 170 115 80
Metal 0 0 0 0 0 0
Tires 0.5 0.2 0 0.7 0.6 0.1
Drums/tins/containers 2 3 4 1 1.5 2
Graph 3-1 presents the Non-Hazardous Waste in graphical form.
Graph 3-1: Non-Hazardous Waste
Table 3-4: Hazardous Waste (Tons)
Waste Type Jan-17 17-Feb 17-Mar 17-Apr 17-May 17-Jun
Oil Filters/Air Filters (tons)
0.009 0.007 0.005 0.006 0.004 0.007
Oily Rags/Absorbents (tons)
0.002 0.001 0.001 0.003 0.005 0.006
Used Oil / Grease / Lubricants (Liters)
65 71 79 27 31 17
Medical Waste (kg) 1.5 2 1.9 0.9 1 0.7
Contaminated Soil (tons) 0.002 0.001 0.002 0.003 0.002 0.001
Batteries (tons) 0.02 0.04 0.07 0.01 0.3 0.5
Drums/tins/containers (tons)
0.1 0.2 0.07 0.1 0.03 0.05
0
50
100
150
200
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17
Non-Hazardous Waste (Tons)
General Domestic Waste Mixed Construction Waste Concrete Wood Tires Drums/tins/containers
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 44
Graph 3-2: Hazardous Waste
Graph 3-3: Recycled Waste
0
20
40
60
80
Jan-17 F b 17 M 17 A 17 M 17 Jun-17
Hazardous Waste (Tons)
Oil Filters/Air Filters (tonnes) Oily Rags/Absorbents (tonnes)
Used Oil / Grease / Lubricants (Liters) Medical Waste (kg)
Contaminated Soil (tonnes) Batteries (tonnes)
Drums/tins/containers (tonnes)
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17
Recycled Waste (Tons)
Concrete Paper Plastic Metal Glass Asphalt Wood
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 45
Graph 3-4: Recycled Waste
Graph 3-5: Recycled Waste
10
30
50
70
90
110
130
150
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17
125132
138
117123
131
39
61
73
55 5262
31.10% 46.20% 52.80% 47% 42% 47.32%
Disposed vs Recycled Waste (Tons)
Disposed to waste pit Disposed to Recycling/Reuse Percent Recycled/Reused
12%
17%
20%
17%
16%
18%
34%
Percent Recycled/Reused
Jan-17
17-Feb
17-Mar
17-Apr
17-May
17-Jun
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 46
4. OCCUPATIONAL HEALTH & SAFETY
4.1. Health, Safety & Construction Works Management
The following objectives are identified to create a positive approach to health and safety during all
activities of the Project:
• To avoid minimize all personal injuries during the execution of the Project
• To ensure that all personnel employed on the Project are competent to carry out their
designated tasks safely
• To create positive health and safety attitudes and perceptions at all levels of the project
organization and to raise health and safety awareness in general
• To implement a training programme that supports the achievement of personnel
competency in relation to Health and Safety
• To complete the Project without incurring any significant property damage to permanent
equipment or temporary facilities
• To introduce a method of motivating good safety which shall include the use of
commendation, as well as correction techniques
• To continually monitor and improve HS performance
Regular supervision and monitoring of the construction phase is being carried out in compliance
with the Health and Safety requirements as per standard specifications outlined in EMP and the
Contract. The practices are not fully compliant with the health and safety requirements; however,
the Contractor is overall demonstrating positive response to the contractual obligations and
instructions by the Engineer about employees’ health and safety matters. Some of the issues highlighted to the Contractor are partially resolved or in progress.
4.1.1. First Aid Center & First Aid Box
The Contractor established First Aid Center for the labor and staff for Emergency Medical
Treatment. According to EMP requirement, the Contractor has appointed MBBS doctor and two
paramedic staff to work on day and night basis. Sufficient quantities of medicines are available in
first aid center. Furthermore, first aid has been provided in batching plant and material engineering
laboratory. Paramedic staff and MBBS doctor conduct trainings with laborers on HIV/AIDs on
regular basis. Kitchen checklist is attached as Annex-XIII.
An exclusive ambulance has been arranged by the Contractor at site so that in case of any
emergency, the victims could be shifted into first aid center. However, in the ambulance, gas
cylinder has not been fixed and the Contractor agreed to fix but work is still pending since long.
Photographs of trainings and ambulance are shown in Figure 4-1.
Figure 4-1: Ambulance and Training on HIV/AIDs
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 47
4.1.2. Zero Accident Campaigns
In order to create awareness among the labor and staff regarding safety hazards and protection,
TPBC and SCL jointly started a zero-accident campaign at site. The purpose of this campaign is to
get the zero-target injury. Photographs are attached in Figure 4-2.
Figure 4-2: Zero Accident Campaign
4.1.3. Housekeeping
Poor housekeeping is one of the basic cause of accident and its improvement requires continued
efforts. The followings arrangements are in progress to maintain good housekeeping at site:
• The Contactor is regularly delivering tool box talk to create awareness to prevent slip trip and
fall by improving housekeeping
• To examine electric wires are buried or hanged
• Regular cleaning of workplace and maintain different items in an appropriate way
• Lumber with protruding nails is segregated at site.
• Steel bars are collected separately
4.1.4. Firefighting Arrangements Vis-à-Vis Welding
Fire Extinguishers are inspected on regular basis and kept in good condition. “Smoking is
prohibited” signs are displayed where there is potential of fire such as petrol pump area and ware
house. The Contractor has provided four types of the fire extinguishers at site according to potential
fire protection classification i.e. water types, Dry Chemical Powder (DCP), Aqueous Film Forming
Foam (AFFF) and Carbon Dioxide. Furthermore, the trainings and TBTs are delivered at site to the
concerned workers how to use the fire extinguishers at the time of any fire hazards. Since the project
started at site, not major fire accident occurred at site except one incident. One moderate fire
accident happened at site during welding, the flames pulled back into a hose which caught fire.
However, the site Safety Officer handled the fire by using fire extinguisher and using sand. The
Contractor was advised to provide the flashback arrestors with welding torch and acetylene
cylinders. Few flashback arrestors have been provided with the cylinders and procurement of
flashback arrestors is in progress as informed by the Contractor. Fire extinguisher and inspection
tag are shown in Figure 4-3.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 48
Figure 4-3: Fire Extinguisher and Flashback Arrestors with Cylinder
During site inspections, it has been noted with grave concern that, the Contractor has not provided
trollies to secure and keep the gas welding cylinders in upright position. The Contractor has been
informed in this regard many time, but no rectification has been done so far.
4.1.5. Safety Air Compressor Tanks
The air compressor tanks are meant to run the hilty under high air pressure. During site inspection
by the Consultant’s Senior Environmentalist, it was noted with great concern that, the air hose was
fixed with simple clamp which is not sufficient to properly connect the hose with the tank. The
Engineer immediately instructed to the Contractor’s staff M/s. Jiajang to fix the hose with Chicago
Coupling, otherwise it could cause a colossal damage to the working staff and the project. The
Engineer’s letter is attached as Annex-XIV. The Contractor however didn’t pay heed and kept using the air compressor. Photo of air compressor tanks is shown in Figure 4-4.
Figure 4-4: Chicago Coupling Missing with Air Compressor
4.1.6. Provision of PPEs
Use of mandatory PPEs at site is compulsory. Compliance about the PPEs is less than satisfactory,
the Engineer has raised this matter with the Contractor on various platforms, the Civil Contractor
issued PPEs at initial stage of the project but the Sub-Contractor M/s. Jiajang has not followed the
instructions and labor were forced to work without proper safety shoes at site. The Engineer has
written reports and letter regarding importance of PPEs and their utilization but all efforts were
squandered due to Contractors’ non-seriousness. However, the Chinese labor and Civil
Contractor’s labor expressed their reservations during site inspection but satisfactory arrangement
has not been made by the Contractor. Photographs placed in Figure 4-5 show the non-compliance
with PPEs at site.
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 49
Figure 4-5: Non-Compliance of PPEs at Site
4.1.7. Safety Sign Boards
Safety sign posters are considered one of the tools of creating awareness among the workers. The
Civil Contractor has arranged satisfactory work in this regard.
4.1.8. Safety Trainings
Site based daily tool box talks (TBT) are arranged by the site safety supervisor for safe about
execution of the work. The laborers are encouraged to participate in TBT and have been advised
them to tell any unsafe work at site so that safety should be ensured before time. TBTs were
delivered on following topics:
• Usage of PPEs
• Work at height
• Slip, trip and fall hazards
• Access paths
• Safety of scaffolding
• Oil spillage
• Electric wires hazard
• Noise hazard
• Welding, cutting and grinding
• Excavations
• Defensive driving
• Heat stress
Figure 4-6: TBT in Progress at Site
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 50
4.1.9. Swimmer & Boating Arrangements
The Contractor was instructed to arrange at least two swimmers and one boat to combat with any
hazard due to flood. The Contractor hired the services of two swimmers and kept ones boat as
standby as shown in Figure 4-7.
Figure 4-7: Standby Boat and Swimmer
4.1.10. Unsafe Acts & Unsafe Conditions (UA/UC System)
It is a usual practice on mega projects, that UA/UC system is introduced to get the workers informed
about safety hazards at site. the Contractor agreed to develop such system at site to make robust
safety arrangements at site.
4.1.11. Electrical Components
As a continuous activity, electrical generators are covered with proper shed to prevent the direct
rain over the generators. The transformers are covered with proper fence and door to minimize the
probability of entrance of unauthorized persons in the area. Electric shock hazard signs are placed
there to warn the workers from the hazard. The same warning signs are placed along the electric
poles located near the workplace.
Suitable lighting arrangement exist at power house to make the Project Area highly visible and
illuminated at night. Adequate guard rails are provided to avoid fall.
4.1.12. Accident/Incident Statistics
Table 4-1 shows the HSE Score Board in May 2017.
Table 4-1: HSE Score – May 2017
Category Till Last Month Project to Date
Safe Man Hours 2,092,596 2,043,356
Common Sickness 13 1,326
First Aid Cases 13 15
Medical Treatment Cases (MTC) 1 0
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 51
Category Till Last Month Project to Date
Restricted Work Injury (RWI) 0 0
Lost Time Injury (LTI) 0 0
Near Miss 21 22
Trainings 43 47
HSE Orientation 644 656
Total Recordable Injury Rate (TRIR) 0.143 0.143
Note: Based on the above statistics no major accident/incident took place at site during this
month.
Graph 4-1 presents the Incident Analysis upto June 2017.
Graph 4-1: HSE Statistics
4.1.13. Status of Non-Compliances (NC)
Non-compliances have been categorized according to likelihood and impact/significance of hazard
at workplace. Non-Compliances been divided into four extent of degrees with their impact. The
timeline and priority of has been described in Table 4-2.
Table 4-2: Type of Non-Compliance & Its Priority
Type of NC & Priority Description
Critical Required immediate attention (the work to be stopped)
High Required immediate attention (to be resolved within 20 days)
Medium To be resolved within 40 days
Low To be resolved when possible
1
MTC 1
RWI 0
FAC 2
NM 1
TRIR 0.143
Training 4
1
0
2
1
0.143
00.5
11.5
22.5
33.5
44.5
v
a
l
u
e
s
Incident catagories
Incident Analysis Project to date, June-2017
MTC RWI FAC NM TRIR Training
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 52
Figures 4-8 & 4-9 present the percentages of Resolved & Unresolved Issues and Overall Priority
of HSE issues respectively.
Percentage (%) of HSE issues resolved and unresolved.
Figure 4-8: %age of Resolved and Pending Issues
Figure 4-9: Overall Priority of HSE Issues
19%
81%
Overall status of Non-Compliance
Resolved Unresolved
25%
37%
19%
19%
Overall HSE issues and level of priority
Critical
High
Medium
Low
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 53
Figure 4-10: Overall Pending and NC Issues
0
1
2
3
4
5
6
7
Critical High Medium Low
Overall status of pending non-complaince issus
Resolved Unresolved
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 54
Table 4-3 T presents the status of outstanding issues.
Table 4-3: Out-Standing Issues
Sr.
No. Date
Raised
By Location Description Category* Corrective Action Obligations
Original
Target
Date
Current
Status
1 01-02-17 TPBC Project area Ambient air quality
Critical
In compliance to EMP requirement, the Contractor shall conduct third party ambient air quality on quarterly basis, after first round, 2nd of monitoring is still in pending since February 22, 2017.
Contractor 28-02-17 Non-
Compliance
2 01-03-17 TPBC Both camps
Drinking
water
facilities
Critical
Since March, after testing from PCSIR
that drinking water is arsenic
contaminated and alternate sources
was advised to the Contractor but no
cognizable action has been taken so
far.
Contractor 31-3-17 Non-
Compliance
3 01-03-17 TPBC Both
Camps
Waste
water
testing
High the Contractor has not performed the
waste water testing Contractor 31-03-17
Non-
Compliance
4 01-5-17 TPBC
At
construction
work
PPEs High
According to the Contractor’s HSE
Plan, Contractor requirements, no
fully PPEs have been provided
Contractor 30-05-17 Compliance
5 01-11-16 TPBC
T.S Link
Canal and
Haveli
Canal
borrow area
Deep
Excavation High
Common bank borrow area has been
reinstated witnessed by the PMO Contractor 31-01-17 Compliance
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 55
Sr.
No. Date
Raised
By Location Description Category* Corrective Action Obligations
Original
Target
Date
Current
Status
6 01-12-16 TPBC First aid
center
AC, Fridge,
structure,
bedding
Critical
Despite consistent perusal by the Engineer, the Contractor has not provided AC, Bedding, structure, fridge in first aid center
Contractor 31-12-16 Non-
Compliance
7 01-5-17 TPBC Project area Water sprinkling
Medium
The Contractor has deputed one water bowser for water sprinkling in project area, which is insufficient. The is advised to arranged at least two more bowsers
Contractor 30-5-17 Compliance
8 01-05-17 TPBC Material
Lab Sulphur Hood
High
For safe dispersion of sulphur fume, separate hood should be constructed and furthermore, R-95 must be provided
Contractor 31-05-17
Non-
Compliance
9 01-06-17 TPBC Project area Waste pit Low
Waste pit should be constructed as per direction of the Engineer. The Contractor promised to do needful in this regard.
Contractor 30-06-17
Non-
Compliance
10 01-05-17 TPBC additional
bay area Deep
excavation High
The Contractor is required to stop steep excavation in additional bay area
Contractor 31-05-17 Non-
Compliance
111 01-02-17 TPBC Disposal
area
Irregular dumping of
bela excavated
area
High
The Contractor has informed many time that, the bela removal material should be dumped in designated area and it should be spread out.
Contractor 28-02-17 Non-
Compliance
12 01-03-17 TPBC Project
Area
Cranes third party
certificates
Critical
Cranes are heavy equipment and quite dangerous, per international stipulations, the third party of cranes must be carried out at earliest.
Contractor 30-03-17 Non-
Compliance
13 01-05-17 TPBC Fuel station Lean concrete
Medium The Contractor completed work in fuel station area Contractor 30-05-17
Non-
Compliance
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 56
Sr.
No. Date
Raised
By Location Description Category* Corrective Action Obligations
Original
Target
Date
Current
Status
14 01-06-17 TPBC
Panaflex of
Safety
campaign Project area Low
The Contractor resolved the matter
Contractor 30-06-17 Compliance
15 01-05-17 TPBC
Super
structure of
M & E work Gangways Medium
No proper access gangway prepared by the Jiajang Chinese firm in spite of dangerous access towards mechanical work
Contractor 30-05-17 Non-
Compliance
16 01-06-17 TPBC Batching
plant Disposal of waste water
Low The has advised that to construct waste pit for collection of waste water. Contractor 30-06-17
Non-
Compliance
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 57
Annex-I: Approval of SSEMP
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 58
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 59
Annex-II Filled Checklists
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 60
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 61
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 62
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 63
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 64
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 65
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 66
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 67
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 68
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 69
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 70
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 71
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 72
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 73
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 74
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 75
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 76
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 77
Annex-III: EPRM
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 78
Annex-IV: Detail of Irrigation Trees
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 79
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 80
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 81
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 82
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 83
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 84
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 85
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 86
Annex-V: Detail of Forest Trees
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 87
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 88
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 89
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 90
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 91
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 92
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 93
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 94
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 95
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 96
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 97
Annex-VI: Surface Water Results
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 98
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 99
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 100
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 101
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 102
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 103
Annex-VII: TPBC letter regarding unsuitability of water
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 104
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 105
Annex-VIII: PCSIR Drinking Water Reports
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 106
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 107
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 108
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 109
Annex-IX: Stability of Coffer Dams for Traffic
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 110
Annex-X: Layout Plan of Main Camp
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 111
Annex-XI: Layout Plan of Labor Camp
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 112
Annex-XII: Social Framework Agreement
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 113
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 114
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 115
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 116
Annex-XIII: Kitchen hygiene checklist
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 117
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 118
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 119
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 120
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 121
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 122
Annex-XIV: TPBC letter on HSE
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 123
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 124
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 125
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 126
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 127
Annex-XV: Vehicular Inspection Checklist
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 128
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 129
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 130
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 131
Rehabilitation and Upgrading of Trimmu Barrage Bi-Annual Environmental Monitoring Report
NESPAK – SMEC – EGC (TPBC) 132