logistic plan
DESCRIPTION
demuTRANSCRIPT
LOGISTIC PLAN
1. Fabrication shall follow construction sequence i.e. first in first out basis
2. An fabricated components to be delivered from fabrication yard to laydown area via lorry
3. For delivery of pipe racks components ,where possible, to be delivered to point of erection
4. Operating platform/access platform will be assembled at laydown area and to be
5. Transported to point of erection by forklift and lorry