Millennium Challenge Account Zambia
Reducing Poverty Through Economic Growth
LUSAKA WATER SUPPLY
SANITATION AND DRAINAGE
PROJECT
IMPROVEMENT OF MAZYOPA DRAINAGE
(CP10)
Presentation by Bismark Pule
Drainage Specialist MCA - ZAMBIA
31st March, 2015
9-Apr-15 www.mcaz.gov.zm 1200, Twikatane Road, off Addis Ababa Drive
1
The Presentation
1. Introduction
2. Objective 3. Outline
4. Safety Tip
5. The Project
6. Forms of Contract
7. Contract Packages
8. Mazyopa Drainage
9. New Drain Design 10. Construction Works
11. Construction Schedule
2 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Objective
To provide insight into the LWSSD project
areas with focus on the drainage Contract
Package 10 to enable interested bidders
submit responsive bids for construction
works
3 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Safety Tip
4
Caught-in Between
Some Causes of Caught-in-
Between Fatalities
• Trench/Excavation Collapse
• Rotating Equipment
• Unguarded Parts
• Equipment Rollovers
• Equipment Maintenance
• Rigging accidents
4/9/2015
www.mcaz.gov.zm 1200, Twikatane Road, off Addis Ababa Drive
9-Apr-15
Safety Tip
5
Accident Prevention
1. Guarding Moving Equipment/Parts
2. Barricades
3. Proper Materials Handling
4. Shielding/Trench Boxes
4/9/2015
www.mcaz.gov.zm 1200, Twikatane Road, off Addis Ababa Drive
9-Apr-15
The Project
6
The Lusaka Water Supply, Sanitation and
Drainage Project ( LWSSDP)
Water Supply
Sanitation Drainage
9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
The Project
• WTP rehabilitation
• Distribution Centres Rehabilitation
• New Pipeline Construction
• New Networks and Customer Connections
• Sewer Networks
• Ground and Elevated Concrete Water Towers
• NRW Water Reduction
• Drainage Works Construction
7 9-Apr-15
www.mcaz.gov.zm 1200, Twikatane Road, off Addis Ababa Drive
Contract Packages
8 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
CP1 Water Supply
CP2 Water Supply
CP3 Water Supply and Sanitation
CP4 Sanitation
CP5 Water Supply
CP6 Water Supply
CP7 Drainage
CP8 Drainage
CP10 Drainage
Forms Of Contract
FIDIC
• Red Book (1999)
• Yellow Book
• Green Book
• Gold Book
• Silver Book
9 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Mazyopa Drainage
10 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Improvement of Bombay Drainage
System
• Targeted the system stretching from the
southern part of the city (Kamwala,
Chilenje, Libala) through the CBD and
ending up just after the Kasangula
Road bridge at the Trash Trap
• Improvements to the drainage system
to result in serious flooding downstream
negatively affecting residents of
Mazyopa Compound.
Mazyopa Drainage
11 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
LOCATION AND DESCRIPTION OF THE
PROPOSED SYSTEM
• Mazyopa is a natural stream to which
storm water from the Bombay Drainage
System discharges
• Commences from the discharge point
of the proposed trash trap for the
Bombay, an open space with
vegetation on both sides.
• Approximate length of 2,600m
Mazyopa Drainage
12 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
LOCATION AND DESCRIPTION OF THE
PROPOSED SYSTEM
• At a distance of about 600m from
Trash Trap No. 1, the drain is joined
by inflow from the Luangwa and
City Airport catchments.
• The drain then meanders for about
740m along an area of informal
houses on the western bank where
the Mazyopa south settlement is
situated
Mazyopa Drainage
13 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
LOCATION AND DESCRIPTION OF THE
PROPOSED SYSTEM
• After meandering for 740m, there is a
walled private plot with a frontage
length of about 140m on the western
bank
• Immediately downstream of the
northern boundary wall, there is a
pipe bridge which is also used as a
pedestrian crossing
Mazyopa Drainage
14 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
LOCATION AND DESCRIPTION OF
THE PROPOSED SYSTEM
• At about 1,130m downstream of the
confluence there is an abandoned
weir and consequently a waterfall
immediately downstream of the
northern boundary wall
• At a distance of about 1,100m
downstream of the weir, the drain is
traversed by a recently constructed
suspension footbridge with a span of
27m
Mazyopa Drainage
15 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
LOCATION AND DESCRIPTION OF THE
PROPOSED SYSTEM
• The last section of the drain is
about 270m further downstream
with few housing units thins out
and mostly comprises farmed
vegetation.
• Downstream of the point where
the Chipata Drain enters the
Ngwerere is the proposed location
of Trash Trap No. 2 and the
energy dissipating structure
Mazyopa Drainage
16 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Location of Abandoned weir
Location of Suspension bridge
Approximate location of Trash Trap No. 2
Chipata Drain
Confluence
Ngwerere Stream Railway Line Mazyopa Settlement
Project Location
Map showing
some prominent
features of the
Mazyopa Drain
Location of Pipe Bridge
New Drain Design
17 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
A two stage drain has been designed, the first stage is based on a
1:5yr. event lined section that generally following the existing
meandering path of the stream, plus improved unlined channel
sections on either side
New Drain Design
18 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
• Original full natural channel (app.
1:2 yr)
• Stage1 channel concrete lined.
Flow 1:5 (improved + Other
current)
• Stage 1 compacted fill (as req’d)
with stabilized surface
• Stage 1 channel, banks part
stabilized. Flow 1:20yr (improved
Bombay +Other )
• Future Stage 2 channel part
stabilized.
New Drain Design
19 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Safety Fencing Safety concrete post and
rail fencing with child
deterrent spiked topping
will be provided in a few
areas due either to the
depth of the drains
and/or where high
velocities of flood water
may be encountered.
New Drain Design
21 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Trash Trap
Trash trap no. 2 and energy
dissipating structure will be
constructed at the end of the
improved section near the
Chipata Drain Inflow (Similar design as the one shown in the picture)
Construction
Works
22 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Construction works are likely to proceed in the following manner:
• Clearance of vegetation from the stream;
• Removal of accumulated solid waste from the stream;
• Dewatering and diversion of dry-weather flow variously with cofferdams, flumes, gravity pipes or by pumping;
• Earthworks including excavation of rock where encountered, reshaping and improvement of the gradients where required;
• Relocation of utility services crossing the drainage (e.g. water supply and sewers) ;
Construction
Works
23 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
• Erection of the base of drains which will include: – blinding layer to the base
– Laying pre-cast sections of the central cunette or constructing in-situ as preferred by the contractor
– Blinding layer to the base
– Casting the base slab
• Erection of drain sides which will include: – side trimming
– polythene sheeting for in situ concreting of drain side walls
– free-draining material for drain side walls
– In-situ concreting or laying of pre-cast side slabs according to the contractor’s preference
Construction
Works
24 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
• Erection of the base of drains which will include: – blinding layer to the base
– Laying pre-cast sections of the central cunette or constructing in-situ as preferred by the contractor
– Blinding layer to the base
– Casting the base slab
• Erection of drain sides which will include: – side trimming
– polythene sheeting for in situ concreting of drain side walls
– free-draining material for drain side walls
– In-situ concreting or laying of pre-cast side slabs according to the contractor’s preference
• Construction of access road
Construction
Works
25 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
• Erection of the base of drains which will include: – blinding layer to the base
– Laying pre-cast sections of the central cunette or constructing in-situ as preferred by the contractor
– Blinding layer to the base
– Casting the base slab
• Erection of drain sides which will include: – side trimming
– polythene sheeting for in situ concreting of drain side walls
– free-draining material for drain side walls
– In-situ concreting or laying of pre-cast side slabs according to the contractor’s preference
• Construction of access road
Construction
Works
26 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
• Diversion works
• Demolition of the abandoned weir
• Erection of the trash trap
• Transportation of other materials required for construction to site and offloading
• Erection of permanent safety fencing along the drainage
• Rehabilitation of the 27m span suspension bridge will be carried out by the replacement of the following items:
Wooden decking
Safety netting
• Besides the above, at crossing point for the pipe bridge situated some 330 metres upstream of the weir, a pedestrian footbridge constructed alongside it.
Construction Works
(Cont’d)
27 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Corridor of Construction
• The will be confined within the total width of the proposed
two stage drain, which will have a width of 24.9 m (max)
• The width will however vary between 9.0 m and 24.9 m
Construction Works
(Cont’d)
28 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
Corridor of Construction
Construction Works
(Cont’d)
Construction Work Challenges
Location of Existing Utilities
Access to Working Areas
Weather Disruption (rains)
Dewatering and flow diversion
Undefined geotechnical risk
Known rock occurrence (2 -3m)
Groundwater in excavations
Traffic Accommodation
Public Road Traffic
Public Access Disruption
A summary of construction challenges
likely to be encountered is presented in the
following table where: KEY
Works largely
unaffected by issue
Works moderately
affected by issue
Works significantly
impacted by issue
Construction
Schedule
30 9-Apr-15 www.mcaz.gov.zm 1200, Twikatane
Road, off Addis Ababa Drive
The Contract is proposed to start by August, 2015 and
the period of construction is 27 months
The installation of the trash trap has to done in parallel
with the other works
pre-casting works can be carried on during each rainy
season.
Construction
Schedule
31
IFB Release
Pre-Site Visit
Pre-Bid Meeting
Bid Submission
03/2015
03/2015
03/2015
05/2015
Bid Evaluation
Letter of Acceptance
Negotiations
Commencement of Work
05/2015
06/2015
07/2015
08/2015
Contract Completion 01/2018 Project
Closure 11/2018