    DIVISION: NH Division, PWD, BAREILLY

    KM - 268

    1 2 3 5 6 7 8 9 10 11 12

    up to 50 KM

    268 Lal Kuan 500 64 494.50 449.55 949.55 949.55 949.55 51 to 64 KM

    268 Lal Kuan 510 64 494.50 449.55 959.55 959.55 959.55 Total

    Less Loadin

    268 Lal Kuan 540 64 494.50 449.55 989.55 989.55 989.55 Rs

    268 Lal Kuan 600 64 494.50 449.55 1049.55 1049.55 1049.55

    268 Lal Kuan 600 64 494.50 449.55 1049.55 1049.55 1049.55Quarry to KM

    KM

    268 Lal Kuan 600 64 494.50 449.55 1049.55 1049.55 1049.55

    268 Lal Kuan 470 64 494.50 449.55 919.55 919.55 919.55

    268 Lal Kuan 550 64 494.50 449.55 999.55 999.55 999.55

    268 Lal Kuan 500 64 494.50 449.55 949.55 949.55 949.55

    300 Local 380 380.00

    1) Distances from quarry have been taken from the shortest route.

    2) Quarry rates have been taken of the respective circle applicable.

    3) Cartage rates has been taken approved by SE Lko. Circle in the RMR.

    4) Quarry rates are for approved quarry and RMR rates are minimum .

    N.H. Construction DivisionN.H. Construction Division 28th Circle N.H.

    P.W.D. Bareilly P.W.D. Bareilly P.W.D. Bareilly

    Stone Dust

    stone boulder 25-60 Kgs

    Coarse Sand

    Fine Sand

    JUNIOR ENGINEER EXECUTIVE ENGINEER SUPERINTENDING ENGI

    Stone grit 5.6 mm and below

    Total

    (3+7)

    (Rs)

    I.S.

    Transit

    Tax

    (Rs)

    Total of

    col.

    (8+9)

    (Rs)

    Trade

    Tax on

    col. 11

    (Rs)

    G.Total of

    col

    11+12

    (Rs)

    Stone Ballast ( 45-90 mm)

    Stone Ballast ( 45-63 mm)

    Stone Ballast ( 22.4-53 mm)

    16mm-22.4mm/ 11.2mm/13.2mm/ 10-16mm

    11.2-2.8 mm / 2.3-9.5 (6.7mm)

    R

    ROAD METAL RATES part-B

    CIRCLE : 28th .Circle, N.H. P.W.D. , B

    NH-74 ( New N H No -30 ) BAREILLYKm.

    No.

    Quarry Quarry

    Rate

    ( Rs)

    Distence

    from

    Quarry to

    Site (KM)

    Cost of

    cartage

    without

    loading

    Cost of

    cartage

    excluding

    C.P. (Rs)

  • 8/13/2019 Maintenance & Estimate

    2/40

    DIVISION: NH Division, PWD, BAREILLY

    KM - 300

    1 2 3 5 6 7 8 9 10 11 12

    up to 50 KM

    300 Lal Kuan 500 85 594.50 540.45 1040.45 1040.45 1040.45 51 to 75 KM

    76 to 85KM

    300 Lal Kuan 510 85 594.50 540.45 1050.45 1050.45 1050.45 Total

    Less Loadin

    300 Lal Kuan 540 85 594.50 540.45 1080.45 1080.45 1080.45 Rs

    mean km

    300 Lal Kuan 600 85 594.50 540.45 1140.45 1140.45 1140.45 to km 304

    300 Lal Kuan 600 85 594.50 540.45 1140.45 1140.45 1140.45Quarry to KM

    KM

    300 Lal Kuan 600 85 594.50 540.45 1140.45 1140.45 1140.45

    300 Lal Kuan 470 85 594.50 540.45 1010.45 1010.45 1010.45

    300 Lal Kuan 550 85 594.50 540.45 1090.45 1090.45 1090.45

    300 Lal Kuan 500 85 594.50 540.45 1040.45 1040.45 1040.45

    300 Local 380 380.00

    1) Distances from quarry have been taken from the shortest route.

    2) Quarry rates have been taken of the respective circle applicable.

    3) Cartage rates has been taken approved by SE Lko. Circle in the RMR.

    4) Quarry rates are for approved quarry and RMR rates are minimum .

    N.H. Construction Division

    ROAD METAL RATES

    CIRCLE : 28th .Circle, N.H. P.W.D. ,

    NH-74 ( New N H No -30 ) BAREILLYKm.

    No.

    Quarry Quarry

    Rate

    Distence

    from

    Cost of

    cartage

    Cost of

    cartage

    Total

    (3+7)

    I.S.

    Transit

    Total of

    col.

    Trade

    Tax on

    G.Total of

    col

    Stone Ballast ( 45-90 mm)

    Stone Ballast ( 45-63 mm)

    Stone Ballast ( 22.4-53 mm)

    16mm-22.4mm/ 11.2mm/13.2mm/ 10-16mm

    11.2-2.8 mm / 2.3-9.5 (6.7mm)

    Stone grit 5.6 mm and below

    Stone Dust

    stone boulder 25-60 Kgs

    Coarse Sand

    Fine Sand

    P.W.D. Bareilly P.W.D. Bareilly P.W.D. Bareilly

    JUNIOR ENGINEER EXECUTIVE ENGINEER SUPERINTENDING ENG

    N.H. Construction Division 28th Circle N.H.

  • 8/13/2019 Maintenance & Estimate

    3/40

    513 Seal Coat

    (ii) Case - II :Type BProviding and laying of premix sand seal coat with HMP of appropriate

    capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7

    mm size and penetration bitumen of suitable grade.

    Unit = sqm

    Taking output = 7858 sqm (47.16 cum)

    a) Labour

    Mate day 0.160 125.00 20.00

    Mazdoor day 4.000 125.00 500.00

    b) Machinery

    HMP of 75 tonnes/hour. hour 2.000 11167.00 22334.00

    Electric Generator Set 250 KVA hour 2.000 450.00 900.00

    Front end loader 1 cum bucket capacity hour 2.000 520.00 1040.00

    Tipper 10 tonne capacity tonne.km 104 x 5' 14.50 75400.00

    Add 10 per cent of cost of carriage to cover cost of loading and unloading 7540.00

    Paver finisher hydrostatic with sensor attachment hour 2.000 629.00 1258.00

    Smooth wheeled 8-10 tonnes capacity hour 2.000 297.00 594.00

    add : escaslation @ 35 % on machinery 30041.20

    c) Material

    Bitumen@ 6.80 kg per 10 sqm tonne 5.340 41682.80 222586.15

    Crushed stone chipping of 6.7 mm size defined as passing 11.2 mm sieve

    and retained on 2.36 mm sieve applied @ 0.06 cum per 10 sqm

    cum 47.160 1049.55 49496.56

    d) Overhead charges @10% input on (a+b+c) 41170.99

    e) Contractor's profit @10% input on (a+b+c+d) 45288.09

    Cost for 7858 sqm = a+b+c+d+e 498168.99

    Rate per sqm = (a+b+c+d+e)/7858 63.40

    say 63.40

    Assistant Engineer Executive Engineer

    Analysis of Rate for PART-B

    Junior Engineer

  • 8/13/2019 Maintenance & Estimate

    4/40

    506 Built-up-Spray Grout

    Providing, laying and rolling of built-up-spray grout layer over prepared

    base consisting of a two layer composite construction of compacted

    crushed coarse aggregates using motor grader for aggregates. key

    stone chips spreader may be used with applicat ion of bi tuminous

    binder after each layer, and with key aggregates placed on top of the

    second layer to serve as a Base conforming to the line, grades and

    cross-section specified, the compacted layer thickness being 75 mm

    Unit = sqm

    Taking output = 3000 sqm (225 cum)a) Labour

    Mate day 0.400 125.00 50.00

    Mazdoor including for brooming of key aggregates day 8.000 125.00 1000.00

    Mazdoor skilled day 2.000 130.00 260.00

    b) Machinery

    Hydraulic self propelled chip spreader both for aggregates and key

    aggregates@ 1500 sqm per hour for 3000 x 3 sqm

    hour 6.000 1700.00 10200.00

    Bitumen pressure distributor for 3000 x 2 sqm @ 1750 sqm per hour hour 3.430 516.00 1769.88

    Tipper 5.5 cum capacity hour 10.000 200.00 2000.00

    smooth wheel roller 8 tonnes hour 6.000 297.00 1782.00

    Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00

    add : escaslation @ 35 % on machinery 6605.16c) Material

    Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for each layer tonne 9.000 41682.80 375145.20

    Crushed stone coarse aggregate passing 53 mm and retained on 2.8

    mm sieve @ 0.5 cum per 10 sqm for each layer

    cum 300.000 989.55 296863.64

    Key aggregates passing 22.4 mm and retained on 2.8 mm sieve @

    0.13 cum per 10 sqm

    cum 39.000 989.55 38592.27

    d) Overhead charges @10% input on (a+b+c) 73738.81

    e) Contractor's profit @10% input on (a+b+c+d) 81112.70

    Cost for 3000 sqm = a+b+c+d+e 892239.66

    Rate per sqm = (a+b+c+d+e)/3000 297.41

    say 297.41

    Assistant Engineer Executive Engineer

    Analysis of Rate for PART-B

    Junior Engineer

  • 8/13/2019 Maintenance & Estimate

    5/40

    3004.2 Filling Pot-holes and Patch Repairs with open-Graded Premix

    surfacing, 20mm.

    Removal of all failed material, trimming of completed excavation to

    provide firm vertical faces, cleaning of surface, painting of tack coat on

    the sides and base of excavation as per clause 503, back f il ling the

    pot holes with hot bituminous material as per clause 504, compacting,

    trimming and finishing the surface to form a smooth continuous

    surface, all as per clause 3004.2

    Unit = Sqm

    Taking out put = 10250 sqm (205 cum)(450 Tonnes)

    a) LabourMate Day 3.760 125.00 470.00

    Mazdoor Day 90.000 120.00 10800.00

    Mazdoor skilled Day 4.000 130.00 520.00

    b) Machinery

    Air compressor 250 cfm hour 6.000 206.00 1236.00

    HMP 100-110 TPH Capacity hour 6.000 11167.00 67002.00

    Tipper 10 tonnes capacity hour 45.000 200.00 9000.00

    Smooth wheeled roller 8-10 tonnes hour 12.000 297.00 3564.00

    add : escaslation @ 35 % on machinery 28280.70

    c) Material

    I) Bitumen tonne 14.970 41682.80 623991.52

    ii) Bitumen emulsion for tack coat . tonne 2.460 36075.43 88745.55

    iii) AggregatesCrushed stone aggregates nominal size 13.2mm cum 184.500 1049.55 193641.14

    Crushed stone aggregates nominal size 11.2 mm cum 92.250 1049.55 96820.57

    d) Overhead charges @10% input on (a+b+c) 112407.15

    e) Contractor's profit @10% input on (a+b+c+d) 123647.86

    Cost for 4900 cum = a+b+c+d+e 1360126.48

    Rate per cum = (a+b+c+d+e)/10250 132.70

    say 132.70

    Assistant Engineer Executive Engineer

    Analysis of Rate for PART-B

    Junior Engineer

  • 8/13/2019 Maintenance & Estimate

    6/40

  • 8/13/2019 Maintenance & Estimate

    7/40

    503 Tack Coat

    Providing and applying tack coat with bitumen emulsion usingemulsion pressure distributor at the rate of 0.25 kg per sqm on the

    prepared bituminous/granular surface cleaned with mechanical broom.

    Unit = sqm

    Taking output = 3500 sqm

    a) Labour

    Mate day 0.080 125.00 10.00

    Mazdoor day 2.000 125.00 250.00

    sub total 260.00

    b) Machinery

    Mechanical broom @ 1250 sqm per hour hour 2.800 230.00 644.00

    Air compressor 250 cfm hour 2.800 206.00 576.80

    Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 516.00 1032.00add : escaslation @ 35 % on machinery 788.48

    sub total 3041.28

    c) Material

    Bitumen @ 0.25 kg per sqm tonne 0.875 41682.80 36472.45

    sub total 36472.45

    a+b+c 39773.73

    d) Overhead charges @10% input on (a+b+c) 3977.37

    e) Contractor's profit @10% input on (a+b+c+d) 4375.11

    Cost for 3500 sqm = a+b+c+d+e 48126.21

    Rate per sqm = (a+b+c+d+e)/3500 13.75

    Say 13.75

    Assistant Engineer Executive EngineerJunior Engineer

    Analysis of Rate for PART-B

  • 8/13/2019 Maintenance & Estimate

    8/40

    Sr No

    Ref. to

    MoRTH

    Spec.

    Description Unit Quantity Rate Rs

    5.21 (ii) Stress absorbing membrane (SAM) with crack width 6

    mm to 9 mm

    Providing and laying of a stress absorbing membrane over a

    cracked road surface, with crack width 6 to 9 mm after

    cleaning with a mechanical broom, using modif ied binder

    complying with clause 521, sprayed at the rate of 11 kg per

    10 sqm and spreading 11.2 mm crushed stone aggregates @

    0.12 cum per 10 sqm, sweeping the surface for uniform

    spread of aggregates and surface finished to conform to

    Unit = sqm

    Taking output = 10500 sqm

    a) Labour

    Mate day 0.240 125.00

    Mazdoor day 6.000 120.00

    SUB TOTALb) Machinery

    Mechanical broom @ 1250 sqm per hour hour 6.000 230.00

    Air compressor 250 cfm capacity hour 6.000 206.00

    Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 516.00

    Hydraulic Chip spreader hour 6.000 1700.00

    Smooth wheeled road roller 8-10 tonne hour 6.000 297.00

    ADD 35 % ESCALATION ON MACHINARY

    SUB TOTAL

    c) Material

    Modified binder tonne 11.550 41682.80

    Crushed stone chipping 11.2 mm size cum 105.000 1049.55

    SUB TOTAL

    A+B+C

    d) Overhead charges @ input on (a+b+c)

    e) Contractor's profit @ input on (a+b+c+d)

    Cost for 10500 sqm = a+b+c+d+e

    Rate per sqm = (a+b+c+d+e)/10500

    say

    Junior Engineer Assistant Engineer Executive Engineer

    Analysis of Rate for PART-B

  • 8/13/2019 Maintenance & Estimate

    9/40

    Cost Rs

    30.00

    720.00

    750.00

    1380.00

    1236.00

    3096.00

    10200.00

    1782.00

    17694.00

    6192.90

    23886.90

    481436.33

    110202.27

    591638.60

    616275.50

    61627.55

    67790.31

    745693.36

    71.02

    71.00

  • 8/13/2019 Maintenance & Estimate

    10/40

    BITUMRN RATE FOR ( PART-B )

    NH-74 268

    Distance from Mathura Refinery 248

    Distance from Panipat Refinery 458

    MATERIAL Bitumen VG-

    30(Bulk) From

    Mathura Refinery

    ( Rs )

    Emulsion M/S (PackedReconditioned Drums from

    Panipat Refinery)

    ( Rs )

    CRMB-55(Bulk) from

    Mathura Refinery

    ( Rs )

    Basic Rates

    01-05-2012

    A 35740.00 32160.00 35890.00

    Excise

    Duty@14%

    on 'A'

    B 5003.60 4502.40 5024.60

    Education

    Cess@

    3% on 'B'

    C 150.11 135.07 150.74

    Cartage(1.75/km

    ) excluding 10%

    O.H.

    2792

    km

    D 789.09 - 789.09

    Cartage(1.75/km) excluding 10%

    O.H.

    489X1.75

    E - 777.95

    EMPTY DRUMS (-)1500

    Total

    '(A+B+C+D+

    E)'

    F 41682.80 36075.43 41854.43

    SAY G 41683 36075 41854

    JUNIOR ENGINEER ASSISTANT ENGINEER EXECUTIVE ENGINEER

    Rate w.e.f. 01- 05 - 2012

    CIRCLE : 28th Circle, NH , PWD, BAREILLY

    DIVISION : N H Construction Division, PWD ,Bareilly

    IN KM

  • 8/13/2019 Maintenance & Estimate

    11/40

    1 Date of Calling Tender

    2 Date of Receiving Tender

    3 Date of Openning Technical bid

    4 Bid Security

    5 Time of Completion

    6 Validity Period

    7 Cost of Tender Form

    S. No. Item of work Unit Qty. Rate Per Amount

    1 Built-up-Spray GroutProviding, laying and rolling of built-up-

    spray grout layer over prepared base

    consisting of a two layer composite

    construction of compacted crushed coarse

    aggregates using motor grader for

    aggregates. key stone chips spreader may

    be used with application of bituminousbinder after each layer, and with key

    aggregates placed on top of the second

    layer to serve as a Base conforming to the

    line, grades and cross-section specified,

    the compacted layer thickness being 75

    km-265 sqm 100.00

    km-266 sqm 80.00

    km-267 sqm 80.00

    km-269 sqm 110.00

    km-271 sqm 90.00

    km-273 sqm 105.00

    Total sqm 565.00 297.41 168036.652 Tack Coat

    Providing and applying tack coat with bitumen

    emulsion using emulsion pressure distributor at the

    rate of 0.25 kg per sqm on the prepared

    bituminous/granular surface cleaned with

    mechanical broom.

    qty same as above item no-1 sqm 565.00 13.75 7768.75

    3 Filling Pot-holes and Patch Repairs with open-

    Graded Premix surfacing, 20mm.

    Removal of all failed material, trimming of completed

    excavation to provide firm vertical faces, cleaning of

    surface, painting of tack coat on the sides and baseof excavation as per clause 503, back filling the pot

    holes with hot bituminous material as per clause

    511, compacting, trimming and finishing the surface

    to form a smooth continuous surface, all as per

    clause 3004.2

    km-265 sqm 280.00

    km-266 sqm 245.00

    km-267 sqm 310.00

    km-269 sqm 295.00

    BILL OF QUANTITY

    Name of work : Filling Pot-holes with B.U.S.G.& Patch-repair with open graded

    surfacing From km 264.00 to 275.00 of NH-74 Premix (New NH-30 )

  • 8/13/2019 Maintenance & Estimate

    12/40

    S. No. Item of work Unit Qty. Rate Per Amount

    km-271 sqm 250.00

    km-273 sqm 265.00

    Total sqm 1645.00 132.70 218283.71

    4 Seal Coat

    Providing and laying seal coat sealing the voids in a

    bituminous surface laid to the specified levels, grade

    and cross fall using Type B seal coats

    Qty same as above item no-3sqm 1645.00 63.40 104287.09

    Total 498376.21

    Signature of Contractor

    Complete Adress of Contractor

  • 8/13/2019 Maintenance & Estimate

    13/40

    1 Date of Calling Tender

    2 Date of Receiving Tender3 Date of Openning Technical bid

    4 Bid Security

    5 Time of Completion

    6 Validity Period

    7 Cost of Tender Form

    S. No. Item of work Unit Qty. Rate

    1 Built-up-Spray Grout In Figure In Words

    Providing, laying and rolling of built-up-

    spray grout layer over prepared base

    consisting of a two layer composite

    construction of compacted crushed coarseaggregates using motor grader for

    aggregates. key stone chips spreader may

    be used with application of bituminous

    binder after each layer, and with key

    aggregates placed on top of the second

    layer to serve as a Base conforming to the

    line, grades and cross-section specified,

    the compacted layer thickness being 75

    mm

    km-265 sqm 100.00

    km-266 sqm 80.00 km-267 sqm 80.00

    km-269 sqm 110.00

    km-271 sqm 90.00

    km-273 sqm 105.00

    Total sqm 565.00 295.00

    2 Tack Coat

    Providing and applying tack coat with bitumen

    emulsion using emulsion pressure distributor at the

    rate of 0.25 kg per sqm on the prepared

    bituminous/granular surface cleaned with

    mechanical broom.qty same as above item no-1 sqm 565.00 11.30

    3 Filling Pot-holes and Patch Repairs with open-

    Graded Premix surfacing, 20mm.

    Rate

    BILL OF QUANTITY

    Name of work : Filling Pot-holes with B.U.S.G.& Patch-repair with open graded

    surfacing From km 264.00 to 275.00 of NH-74 Premix (New NH-30 )

  • 8/13/2019 Maintenance & Estimate

    14/40

    Removal of all failed material, trimming of

    completed excavation to provide firm vertical faces,

    cleaning of surface, painting of tack coat on the

    sides and base of excavation as per clause 503,

    back filling the pot holes with hot bituminous

    material as per clause 511, compacting, trimming

    and finishing the surface to form a smooth

    continuous surface, all as per clause 3004.2

    km-265 sqm 280.00

    km-266 sqm 245.00

    km-267 sqm 310.00

    km-269 sqm 295.00

    km-271 sqm 250.00

    km-273 sqm 265.00

    Total sqm 1645.00 130.00

    4 Seal Coat

    Providing and laying seal coat sealing the voids in a

    bituminous surface laid to the specified levels,grade and cross fall using Type B seal coats

    Qty same as above item no-3 sqm 1645.00 63.00

    Total

    Signature of Contractor Officer Calling Tender Officer Openning Tender

    Complete Adress of Contractor Officer Accepting Tender

  • 8/13/2019 Maintenance & Estimate

    15/40

    1 Date of Calling Tender

    2 Date of Receiving Tender

    3 Date of Openning Tender

    4 Security E/M

    5 Time of Completion

    6 Validity Period

    7 Cost of Tender Form

    S. No. Item of work Unit Qty.

    1 Stress absorbing membrane (SAM) with

    crack width 6 mm to 9 mm In Figure In Words

    Providing and laying of a stress absorbing

    membrane over a cracked road surface, with

    crack width 6 to 9 mm after cleaning with a

    mechanical broom, using modified binder

    complying with clause 521, sprayed at the rate of

    11 kg per 10 sqm and spreading 11.2 mm

    crushed stone aggregates @ 0.12 cum per 10

    sqm, sweeping the surface for uniform spread of

    aggregates and surface finished to conform to

    km-265 sqm 800.00

    km-266 & 267 sqm 1050.00

    km-268 & 269 sqm 1250.00

    km-270 sqm 850.00

    km-271 & 272 sqm 1400.00

    km-273 & 274 sqm 1200.00

    Total sqm 6550.00 71.00 Rs Seventy One only

    I/We here by tender my / our rates ...% above/below/atpar the departmental rates.

    Signature of Contractor Officer calling Tender Officer openning Tender

    Complete Adress of Contractor

    Officer Accepting Tender

    One Month

    Three Months

    150+500+88 = 738/-

    Rate

    BILL OF QUANTITY

    Name of work : Crack Sealing with Stress absorbing membrane (SAM) with crack width 6

    mm to 9 mm repair over a crack road surface From km 264.00 to 274.00 of NH-74 (New NH-

    30 )

    25th April 2012

    11th May 2012

    14 th May 2012

    Rs. 50000/-

  • 8/13/2019 Maintenance & Estimate

    16/40

    Analysis Of Rate For PART-A

    Tack Coat

    Providing and applying tack coat with bitumen emulsion using

    emulsion pressure distributor at the rate of 0.25 kg per sqm

    on the prepared bituminous/granular surface cleaned with

    mechanical broom.

    Unit = sqmTaking output = 3500 sqm

    a) Labour

    day 0.080 125.00 10.00

    Mazdoor day 2.000 125.00 250.00

    sub total 260.00

    b) Machinery

    Mechanical broom @ 1250 sqm per hour hour 2.800 230.00 644.00

    Air compressor 250 cfm hour 2.800 206.00 576.80

    Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 516.00 1032.00

    add : escaslation @ 35 % on machinery

    788.48

    sub total 3041.28

    c) Material

    Bitumen @ 0.25 kg per sqm tonne 0.875 41781.44 36558.76

    sub total 36558.76

    a+b+c 39860.04

    d) Overhead charges @10% input on (a+b+c) 3986.00

    e) Contractor's profit @10% input on (a+b+c+d) 4384.60

    Cost for 3500 sqm = a+b+c+d+e 48230.64

    Rate per sqm = (a+b+c+d+e)/3500 13.78

    Say 13.78

    J.E. A.E. Executive Engineer J.E.(T) Superindenting EngineerNH C.D.P.W.D.Bareilly NH28th Circle p. w.d.Bareilly

    Analysis Of Rate For PART-A

  • 8/13/2019 Maintenance & Estimate

    17/40

    10.4 3004.2 Filling Pot-holes and Patch Repairs with open-Graded

    Premix surfacing, 20mm.

    Removal of all failed material, trimming of completed

    excavation to provide firm vertical faces, cleaning of surface,

    painting of tack coat on the sides and base of excavation as

    per clause 503, back fil ling the pot holes with hot bituminous

    material as per clause 511, compacting, trimming and

    finishing the surface to form a smooth continuous surface, all

    as per clause 3004.2

    Unit = SqmTaking out put = 10250 sqm (205 cum)(405 tonne)

    a) Labour

    Mate Day 3.760 125.00 470.00

    Mazdoor Day 90.000 120.00 10800.00

    Mazdoor skilled Day 4.000 130.00 520.00

    b) Machinery

    Air compressor 250 cfm hour 6.000 206.00 1236.00

    HMP 100-110 TPH Capacity hour 6.000 11167.00 67002.00

    Tipper 5.5 tonnes capacity hour 45.000 200.00 9000.00

    Smooth wheeled roller 8-10 tonnes hour 12.000 297.00 3564.00

    add : escaslation @ 35 % on machinery 28280.70

    c) Material

    Crushed stone aggregates nominal size 13.2mm cum 184.500 1140.45 210413.03

    Crushed stone aggregates nominal size 11.2mm cum 92.250 1140.45 105206.51

    Bitumen 60/70 tonne 14.970 41781.44 625468.09

    Bitumen emulsion for tack coat including vertical sides of pot

    hole.

    tonne 2.460 36075.43 88745.55

    d) Overhead charges @10% input on (a+b+c) 115070.59

    e) Contractor's profit @10% input on (a+b+c+d) 126577.65

    Cost for 10250 sqm = a+b+c+d+e 1392354.11

    Rate per sqm = (a+b+c+d+e)/10250 135.84

    say 135.84

    J.E. A.E. Executive Engineer J.E.(T) Superindenting Engineer

    NH C.D.P.W.D.Bareilly NH28th Circle p. w.d.Bareilly

    Analysis Of Rate For PART-A513 Seal Coat

  • 8/13/2019 Maintenance & Estimate

    18/40

    (ii) Case - II :Type B

    Providing and laying of premix sand seal coat with HMP of

    appropriate capacity not less than 75 tonnes/ hours using

    crushed stone chipping 6.7 mm size and penetration bitumen

    of suitable grade.

    Unit = sqm

    Taking output = 7858 sqm (47.16 cum)

    a) Labour

    Mate day 0.160 125.00 20.00

    Mazdoor day 4.000 125.00 500.00

    b) Machinery

    HMP of 75 tonnes/hour. hour 2.000 11167.00 22334.00

    Electric Generator Set 250 KVA hour 2.000 450.00 900.00

    Front end loader 1 cum bucket capacity hour 2.000 520.00 1040.00

    Tipper 10 tonne capacity tonne.km 104 x 5' 14.50 75400.00

    Add 10 per cent of cost of carriage to cover cost of loading 7540.00Paver finisher hydrostatic with sensor attachment hour 2.000 629.00 1258.00

    Smooth wheeled 8-10 tonnes capacity hour 2.000 297.00 594.00

    add : escaslation @ 35 % on machinery 30041.20

    c) Material

    Bitumen@ 6.80 kg per 10 sqm tonne 5.340 41781.44 223112.86

    Crushed stone chipping of 6.7 mm size defined as passing

    11.2 mm sieve and retained on 2.36 mm sieve applied @

    cum 47.160 1140.45 53783.62

    d) Overhead charges @10% input on (a+b+c) 41652.37

    e) Contractor's profit @10% input on (a+b+c+d) 45817.61

    Cost for 7858 sqm = a+b+c+d+e 503993.66

    Rate per sqm = (a+b+c+d+e)/7858 64.14

    say 64.14

    J.E. A.E. Executive Engineer J.E.(T) Superindenting Engineer

    NH C.D.P.W.D.Bareilly NH28th Circle p. w.d.Bareilly

    Analysis Of Rate For PART-A

    506 Built-up-Spray Grout

  • 8/13/2019 Maintenance & Estimate

    19/40

    Providing, laying and rolling of built-up-spray grout layer over

    prepared base consisting of a two layer composite

    construction of compacted crushed coarse aggregates using

    motor grader for aggregates. key stone chips spreader may

    be used with application of bituminous binder after each layer,

    and with key aggregates placed on top of the second layer to

    serve as a Base conforming to the line, grades and cross-

    section specified, the compacted layer thickness being 75

    mm

    Unit = sqmTaking output = 3000 sqm (225 cum)

    a) Labour

    Mate day 0.400 125.00 50.00

    Mazdoor including for brooming of key aggregates day 8.000 125.00 1000.00

    Mazdoor skilled day 2.000 130.00 260.00

    b) Machinery

    Hydraulic self propelled chip spreader both for aggregates

    and key aggregates@ 1500 sqm per hour for 3000 x 3 sqm

    hour 6.000 1700.00 10200.00

    Bitumen pressure distributor for 3000 x 2 sqm @ 1750 sqm

    per hour

    hour 3.430 516.00 1769.88

    Tipper 5.5 cum capacity hour 10.000 200.00 2000.00

    smooth wheel roller 8 tonnes hour 6.000 297.00 1782.00

    Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00

    add : escaslation @ 35 % on machinery 6605.16

    c) Material

    Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for each layer tonne 9.000 41781.44 376032.92

    Crushed stone coarse aggregate passing 53 mm and cum 300.000 1080.45 324136.36

    Key aggregates passing 22.4 mm and retained on 2.8 mm cum 39.000 1140.45 44477.73

    d) Overhead charges @10% input on (a+b+c) 77143.40e) Contractor's profit @10% input on (a+b+c+d) 84857.75Cost for 3000 sqm = a+b+c+d+e 933435.20

    Rate per sqm = (a+b+c+d+e)/3000 311.15

    say 311.00

    J.E. A.E. Executive Engineer J.E.(T) Superindenting Engineer

    NH C.D.P.W.D.Bareilly NH28th Circle p. w.d.Bareilly

    Analysis of Rate( PART-A )

    Sr No

    .

    MoRTH Description Unit Quantity Rate Rs Cost Rs

  • 8/13/2019 Maintenance & Estimate

    20/40

    5.21 (ii) Stress absorbing membrane (SAM) with crack width 6 mm to 9 mm

    Providing and laying of a stress absorbing membrane over a cracked road

    surface, wi th crack width 6 to 9 mm after c leaning wi th a mechanical

    broom, using modified binder complying with clause 521, sprayed at the

    Unit = sqm

    Taking output = 10500 sqm

    a) Labour

    Mate day 0.240 125.00 30.00

    Mazdoor day 6.000 120.00 720.00

    SUB TOTAL 750.00

    b) Machinery

    Mechanical broom @ 1250 sqm per hour hour 6.000 230.00 1380.00

    Air compressor 250 cfm capacity hour 6.000 206.00 1236.00

    Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 516.00 3096.00

    Hydraulic Chip spreader hour 6.000 1700.00 10200.00Smooth wheeled road roller 8-10 tonne hour 6.000 297.00 1782.00

    17694.00

    ADD 35 % ESCALATION ON MACHINARY 6192.90

    SUB TOTAL 23886.90

    c) Material

    Modified binder tonne 11.550 41781.44 482575.58

    Crushed stone chipping 11.2 mm size cum 105.000 1140.45 119747.73

    SUB TOTAL 602323.30

    A+B+C 626960.20

    d) Overhead charges @ input on (a+b+c) 62696.02

    e) Contractor's profit @ input on (a+b+c+d) 68965.62Cost for 10500 sqm = a+b+c+d+e 758621.85

    Rate per sqm = (a+b+c+d+e)/10500 72.25

    say 72.25

    J.E. A.E. Executive Engineer J.E.(T) Superindenting Engineer

    NH C.D.P.W.D.Bareilly NH28th Circle p. w.d.Bareilly

    Analysis Of Rate For PART-A

    10.5 3004.2 Filling Pot-holes and Patch Repairs with Bituminous

    Removal of all failed material, trimming of completed

    excavation to provide firm vertical faces, cleaning of surface,

    painting of tack coat on the sides and base of excavation as

  • 8/13/2019 Maintenance & Estimate

    21/40

    Unit = Sqm

    Taking out put = 4900 sqm (196 cum)(450 Tonnes)

    a) Labour

    Mate Day 2.920 125.00 365.00

    Mazdoor Day 70.000 120.00 8400.00

    Mazdoor skilled Day 3.000 130.00 390.00

    b) Machinery

    Air compressor 250 cfm hour 6.000 206.00 1236.00

    HMP 100-110 TPH Capacity hour 6.000 11167.00 67002.00

    Tipper 10 tonnes capacity hour 45.000 200.00 9000.00

    Smooth wheeled roller 8-10 tonnes hour 12.000 297.00 3564.00add : escaslation @ 35 % on machinery 28280.70

    c) Material

    I) Bitumen tonne 22.500 41781.44 940082.29

    ii) Bitumen emulsion for tack coat . tonne 1.180 36075.43 42569.00

    iii) Aggregates

    Grading I - 19mm(Nominal size)

    20-10mm 35 per cent cum 99.750 1140.45 113759.89

    10-5 mm 23 per cent cum 65.550 1140.45 74756.50

    5mm and below40 per cent cum 114.000 1140.45 130011.30

    Add 5 per cent for wastage 15926.38

    orGrading-II 13mm (Nominal size)

    13.2-10 mm 30 per cent cum 85.500 1140.45 97508.48

    10-5 mm 25 per cent cum 71.250 1140.45 81257.06

    5 mm and Below43 per cent cum 122.550 1140.45 139762.15

    5 mm and Below43 per cent cum 122.550 1140.45 139762.15

    Filler 2 per cent tonne 9.000 1010.45 9094.05

    Add 5 per cent for wastage 18493.77

    Any one of the above alternatives of aggregate i.e. 19mm or

    13mm nominal size may be adopted as per approved design.

    10.5 (i) for grading I Material

    d) Overhead charges @10% input on (a+b+c) 143497.81e) Contractor's profit @10% input on (a+b+c+d) 157847.59

    Cost for 4900 cum = a+b+c+d+e 1736323.46

    Rate per cum = (a+b+c+d+e)/4900 354.35

    say 354.00

    10.5 (ii) for grading II Material

    d) Overhead charges @ input on (a+b+c) 148889.32

    e) Contractor's profit @ input on (a+b+c+d) 163778.25

    Cost for 4900 cum = a+b+c+d+e 1801560.74

    Rate per cum = (a+b+c+d+e)/4900 367.67

    say 368.00

    J.E. A.E. Executive Engineer J.E.(T) Superindenting Engineer

    NH C.D.P.W.D.Bareilly NH28th Circle p. w.d.Bareilly

  • 8/13/2019 Maintenance & Estimate

    22/40

    Analysis Of Rate For PART-A

    3004.2 Filling Pot-holes and Patch Repairs with open-Graded

    Premix surfacing, 20mm.

    Removal of all failed material, trimming of completed

    excavation to provide firm vertical faces, cleaning of surface,

    painting of tack coat on the sides and base of excavation as

    per clause 503, back fil ling the pot holes with hot bituminous

    material as per clause 511, compacting, trimming andfinishing the surface to form a smooth continuous surface, all

    as per clause 3004.2

    Unit = Sqm

    Taking out put = 10250 sqm (205 cum)(405 tonne)

    a) Labour

    Mate Day 3.760 125.00

    Mazdoor Day 90.000 120.00

    Mazdoor skilled Day 4.000 130.00

    b) Machinery

    Air compressor 250 cfm hour 6.000 206.00

    HMP 100-110 TPH Capacity hour 6.000 11167.00

    Tipper 5.5 tonnes capacity hour 45.000 200.00

    Smooth wheeled roller 8-10 tonnes hour 12.000 297.00

    add : escaslation @ 35 % on machinery

  • 8/13/2019 Maintenance & Estimate

    23/40

    c) Material

    Crushed stone aggregates nominal size 13.2mm cum 184.500 1140.45

    Crushed stone aggregates nominal size 11.2mm cum 92.250 1140.45

    Bitumen 60/70 tonne 14.970 41781.44

    Bitumen emulsion for tack coat including vertical sides of pot

    hole.

    tonne 2.460 36075.43

    d) Overhead charges @10% input on (a+b+c)

    e) Contractor's profit @10% input on (a+b+c+d)

    Cost for 10250 sqm = a+b+c+d+e

    Rate per sqm = (a+b+c+d+e)/10250

    say

    A.E. Executive Engineer J.E.(T) Superindenting

    NH C.D.P.W.D.Bareilly NH28th Circle p.

  • 8/13/2019 Maintenance & Estimate

    24/40

    470.00

    10800.00

    520.00

    1236.00

    67002.00

    9000.00

    3564.00

    28280.70

  • 8/13/2019 Maintenance & Estimate

    25/40

    210413.03

    105206.51

    625468.09

    88745.55

    115070.59

    126577.65

    1392354.11

    135.84

    135.84

    Engineer

    w.d.Bareilly

  • 8/13/2019 Maintenance & Estimate

    26/40

    surfacing From km 295.00 to 304.00 &km264.oo to 274.00of NH-74 (New NH-30 )

    S. No. Item of work no. L B H/D Qty

    1 Built-up-Spray Grout

    Providing, laying and rolling of built-up-

    spray grout layer over prepared base

    consisting of a two layer composite

    construction of compacted crushed

    coarse aggregates using motor graderfor aggregates. key stone chips

    spreader may be used with application

    of bituminous binder after each layer,

    and with key aggregates placed on top

    of the second layer to serve as a Base

    conforming to the line, grades and cross-

    section specified, the compacted layer

    thickness being 75 mm

    km-295 1 6.70 4.00 26.80

    1 12.40 5.80 71.921 24.70 3.70 91.39

    1 21.60 4.80 103.68

    1 18.70 4.20 78.54

    1 6.80 3.90 26.52

    1 26.00 4.60 119.60

    518.45

    km-296 1 10.40 3.40 35.36

    1 22.40 6.40 143.36

    1 27.20 4.80 130.56

    1 12.90 3.80 49.02

    1 20.80 4.60 95.68

    1 12.80 3.60 46.081 8.60 4.20 36.12

    1 20.40 3.80 77.52

    1 10.90 4.70 51.23

    664.93

    km-297 1 9.60 5.70 54.72

    1 14.20 5.80 82.36

    1 7.40 5.40 39.96

    2 16.50 4.00 132.00

    1 3.90 2.70 10.53

    1 6.70 3.30 22.11

    341.68

    DETAILS OF MEASURMENTSName of work : Filling Pot-holes with B.U.S.G.& Patch-repair with open graded Premix

  • 8/13/2019 Maintenance & Estimate

    27/40

    km-298 1 9.80 4.20 41.16

    1 16.80 5.80 97.44

    1 20.85 3.90 81.32

    2 12.00 4.00 96.00

    1 11.20 4.60 51.52

    2 6.00 3.60 43.20

    410.64

    km-299 1 6.40 3.70 23.68

    1 7.70 3.90 30.03

    1 17.60 3.55 62.48

    1 3.40 2.20 7.48

    1 16.50 2.90 47.85

    1 5.40 3.80 20.52

    1 18.90 4.10 77.49

    1 10.40 3.90 40.56

    310.09

    km-300 1 20.40 2.70 55.08

    1 9.90 4.00 39.60

    1 11.80 3.20 37.76

    1 22.20 2.90 64.38

    1 16.00 3.75 60.00

    1 17.90 3.80 68.02

    1 7.40 3.50 25.90

    1 16.40 3.70 60.68

    411.42

    km-301 1 6.70 3.30 22.11

    1 11.20 3.50 39.20

    1 3.80 2.40 9.12

    1 22.20 3.00 66.60

    1 6.90 3.20 22.08

    1 9.80 4.20 41.16

    1 33.30 2.80 93.24

    293.51

    km-302 1 15.40 2.70 41.58

    1 8.40 3.00 25.201 12.00 3.30 39.60

    1 4.80 1.80 8.64

    1 15.80 4.20 66.36

    2 5.60 2.20 24.64

    1 6.80 3.20 21.76

    1 12.30 3.50 43.05

    270.83

    km-303 1 4.70 2.50 11.75

    1 23.40 3.70 86.58

    1 9.10 2.60 23.66

    1 28.00 4.80 134.40

    1 21.50 3.15 67.731 5.50 2.65 14.58

    1 16.25 3.90 63.38

    1 26.40 4.30 113.52

    1 7.50 3.55 26.63

    542.21

  • 8/13/2019 Maintenance & Estimate

    28/40

    km-304 1 11.20 2.90 32.48

    1 6.40 4.80 30.72

    1 9.40 3.20 30.08

    1 22.00 4.80 105.60

    1 7.80 3.05 23.79

    1 4.20 2.10 8.82

    1 2.40 1.90 4.56

    1 3.80 2.10 7.98

    244.03

    Total (A) 4007.79

    km-265 1 6.40 3.10 19.84

    1 8.60 2.60 22.36

    1 10.80 4.10 44.28

    1 5.60 3.20 17.92

    1 17.60 4.40 77.44

    1 12.60 3.80 47.88

    1 9.70 4.00 38.80

    268.52

    km-266 1 6.40 3.70 23.68

    1 11.30 4.20 47.46

    1 21.50 4.80 103.20

    1 8.80 3.30 29.041 11.80 4.60 54.28

    257.66

    km-267 1 9.40 3.90 36.66

    1 9.00 3.40 30.60

    1 12.80 4.00 51.20

    1 6.60 3.60 23.76

    142.22

    km-268 1 11.70 3.25 38.03

    2 9.50 3.00 57.00

    1 6.50 4.50 29.25

    1 16.20 4.10 66.42

    190.70

    km-269 1 6.90 3.75 25.88

    1 11.70 4.50 52.65

    1 18.60 3.90 72.54

    1 12.00 3.30 39.60

    190.67

  • 8/13/2019 Maintenance & Estimate

    29/40

    km-270 1 10.60 3.20 33.92

    1 14.40 2.80 40.32

    1 5.80 2.40 13.92

    1 11.90 3.70 44.03

    132.19

    km-271 1 21.50 3.65 78.48

    1 3.00 1.60 4.80

    1 11.50 4.40 50.60

    1 7.90 3.90 30.81

    1 13.55 4.30 58.27

    222.95

    km-272 1 8.80 3.60 31.68

    1 24.60 3.90 95.94

    1 6.90 3.40 23.46

    1 28.50 3.05 86.93

    1 4.80 3.00 14.40

    1 11.80 3.80 44.84

    1 9.60 3.40 32.64

    1 12.80 3.70 47.36

    377.25

    km-273 1 10.50 2.60 27.30

    1 7.50 2.20 16.50

    1 8.20 4.00 32.80

    1 8.40 3.20 26.88

    1 10.50 2.80 29.40

    1 4.40 2.70 11.88

    1 14.40 3.30 47.52

    192.28

    km-274 1 12.20 2.85 34.77

    1 4.20 1.95 8.19

    1 6.20 2.70 16.74

    1 9.80 2.40 23.52

    1 7.20 3.30 23.76

    106.98

    Total (B) 2081.41

  • 8/13/2019 Maintenance & Estimate

    30/40

    2 Filling Pot-holes and Patch Repairs

    with open-Graded Premix surfacing,

    20mm.

    Removal of all failed material, trimming

    of completed excavation to provide firm

    vertical faces, cleaning of surface,

    painting of tack coat on the sides and

    base of excavation as per clause 503,

    back filling the pot holes with hot

    bituminous material as per clause 511,compacting, trimming and finishing the

    surface to form a smooth continuous

    surface, all as per clause 3004.2

    km-295 1 7.00 4.20 29.40

    1 12.80 5.80 74.24

    1 18.60 3.90 72.54

    1 9.40 4.40 41.36

    1 10.60 3.45 36.571 32.80 4.85 159.08

    1 7.90 4.00 31.60

    1 27.90 4.80 133.92

    578.71

    km-296 1 12.40 3.60 44.64

    1 32.40 6.40 207.36

    1 9.60 4.75 45.60

    2 28.50 3.85 219.45

    1 19.45 3.30 64.19

    1 12.90 4.85 62.57

    1 36.00 3.30 118.80

    1 22.40 4.80 107.521 14.90 4.80 71.52

    941.64

    km-297 1 10.60 6.30 66.78

    1 6.40 3.80 24.32

    1 19.40 5.40 104.76

    1 5.90 3.50 20.65

    1 18.40 5.00 92.00

    1 9.70 3.80 36.86

    345.37

  • 8/13/2019 Maintenance & Estimate

    31/40

  • 8/13/2019 Maintenance & Estimate

    32/40

    km-303 1 14.70 4.20 61.74

    1 25.40 3.90 99.06

    1 12.85 3.85 49.47

    1 38.20 3.45 131.79

    1 24.00 4.50 108.00

    1 6.80 3.65 24.82

    1 20.80 3.90 81.12

    1 28.80 4.80 138.24

    1 9.85 4.00 39.40

    733.64

    km-304 1 16.60 4.80 79.68

    1 9.20 4.80 44.16

    1 16.60 4.65 77.19

    1 10.80 3.75 40.50

    1 7.20 2.90 20.88

    1 24.40 3.90 95.16

    1 7.30 2.85 20.81

    378.38

    Total (A) 5581.66

    km-265 1 16.80 3.50 58.80

    1 8.70 2.80 24.36

    1 13.80 4.10 56.581 25.90 3.90 101.01

    1 19.60 4.90 96.04

    1 14.65 4.80 70.32

    1 10.70 4.60 49.22

    456.33

    km-266 1 6.90 3.75 25.88

    1 21.30 4.20 89.46

    2 18.00 3.80 136.80

    1 26.80 5.40 144.72

    1 20.75 3.80 78.85

    1 16.80 4.60 77.28

    552.99

    km-267 1 9.90 4.50 44.55

    1 29.80 3.60 107.28

    1 28.80 4.80 138.24

    1 22.80 4.10 93.48

    1 6.80 4.60 31.28

    414.83

    km-268 1 21.70 3.95 85.72

    2 12.50 3.80 95.00

    1 38.50 4.50 173.25

    1 19.65 4.70 92.36

    446.32

  • 8/13/2019 Maintenance & Estimate

    33/40

    km-269 1 11.90 3.75 44.63

    1 18.85 4.80 90.48

    1 22.00 3.50 77.00

    1 18.00 4.20 75.60

    1 20.20 4.25 85.85

    1 12.80 3.85 49.28

    422.84

    km-270 1 18.60 3.60 66.96

    1 34.80 3.40 118.32

    1 9.80 2.90 28.42

    1 33.30 4.10 136.53

    350.23

    km-271 1 21.90 3.80 83.22

    1 7.70 3.60 27.72

    1 21.50 4.40 94.60

    2 16.00 4.50 144.00

    1 29.90 4.10 122.59

    1 16.60 4.60 76.36

    548.49

    km-272 1 10.80 3.75 40.50

    1 27.60 4.25 117.30

    1 7.90 3.40 26.86

    1 37.20 3.70 137.64

    1 25.80 2.75 70.95

    1 13.60 4.80 65.28

    1 19.90 3.85 76.62

    1 14.10 3.80 53.58

    588.73

    km-273 1 12.20 2.60 31.72

    1 7.50 2.20 16.50

    1 28.20 4.00 112.80

    1 8.40 3.20 26.88

    1 30.50 2.80 85.40

    1 4.40 2.70 11.88

    1 14.40 3.30 47.52332.70

    km-274 1 12.20 3.30 40.26

    1 5.20 3.00 15.60

    2 15.50 3.50 108.50

    1 26.90 3.70 99.53

    1 11.80 3.30 38.94

    1 8.75 3.60 31.50

    334.33

    Total (B) 4447.78

  • 8/13/2019 Maintenance & Estimate

    34/40

    surfacing From km 295.00 to 304.00& km 264.00 to 274.00 of NH-74 (New NH-30 )

    S. No. Item of work Unit Qty. Rate Per Amount

    3 Seal Coat

    Providing and laying seal coat sealing

    the voids in a bituminous surface laid to

    the specified levels, grade and cross fall

    using Type B seal coats

    qty same as above item no-3 (A)5581.66

    qty same as above item no-3 (B)

    4447.78

    4 Stress absorbing membrane (SAM) withcrack width 6 mm to 9 mm

    Providing and laying of a stress absorbing

    membrane over a cracked road surface, with

    crack width 6 to 9 mm after cleaning with a

    mechanical broom, using modified binder

    complying with clause 521, sprayed at the rateof 11 kg per 10 sqm and spreading 11.2 mm

    crushed stone aggregates @ 0.12 cum per 10

    sqm, sweeping the surface for uniform spread of

    aggregates and surface finished to conform to

    km-295 1 17.00 2.50 42.50

    1 45.80 2.80 128.24

    1 22.80 3.70 84.36

    1 38.80 2.45 95.06

    1 49.50 2.80 138.60

    1 42.00 2.75 115.50

    1 18.95 3.00 56.85

    1 62.00 3.45 213.901 59.40 3.40 201.96

    1 7.90 2.60 20.54

    1 27.90 2.80 78.12

    1175.63

    km-296 1 32.40 2.90 93.96

    1 18.60 3.10 57.66

    1 38.60 4.40 169.84

    1 114.80 2.80 321.44

    1 21.40 2.85 60.99

    1 42.80 3.00 128.40

    1 29.45 3.65 107.49

    1 28.60 2.90 82.941 19.60 3.75 73.50

    1 38.40 3.80 145.92

    1 31.50 3.10 97.65

    1339.79

    DETAILS OF MEASURMENTSName of work : Filling Pot-holes with B.U.S.G.& Patch-repair with open graded Premix

  • 8/13/2019 Maintenance & Estimate

    35/40

    km-297 1 20.60 3.30 67.98

    1 16.40 3.80 62.32

    1 32.50 3.15 102.38

    1 66.60 4.60 306.36

    1 27.55 3.90 107.45

    1 46.10 2.90 133.69

    1 49.40 3.75 185.25

    1 14.90 3.50 52.15

    1 29.70 3.40 100.98

    1118.55

    km-298 1 19.80 3.20 63.36

    1 54.20 4.45 241.19

    1 26.40 3.10 81.84

    1 16.70 2.95 49.27

    1 24.40 3.75 91.50

    1 32.80 4.80 157.44

    1 44.60 3.80 169.48

    2 38.80 4.10 318.16

    1108.88

    km-299 1 8.40 2.70 22.68

    1 27.90 3.40 94.86

    1 76.40 4.80 366.72

    1 43.80 3.65 159.87

    1 30.50 2.90 88.45

    1 58.70 3.65 214.26

    1 48.60 3.80 184.68

    1 12.90 2.90 37.41

    1 35.40 3.50 123.90

    1292.83

    km-300 1 22.80 3.25 74.10

    1 112.60 3.80 427.88

    1 54.70 3.35 183.25

    1 40.80 3.25 132.60

    1 62.80 3.80 238.64

    2 9.40 2.90 54.52

    1 22.60 3.40 76.84

    1187.83

    km-301 1 18.40 3.60 66.24

    1 48.20 3.90 187.98

    1 6.80 2.80 19.04

    1 67.20 3.60 241.92

    1 30.00 4.00 120.00

    1 79.00 3.75 296.25

    1 11.40 4.40 50.16

    1 36.30 3.30 119.79

    1101.38

  • 8/13/2019 Maintenance & Estimate

    36/40

    km-302 1 17.25 3.90 67.28

    1 9.40 3.60 33.84

    1 66.60 4.50 299.70

    1 9.00 3.20 28.80

    1 11.80 4.40 51.92

    1 20.50 3.30 67.65

    1 77.80 3.20 248.96

    1 33.50 4.20 140.70

    1 9.80 4.75 46.55

    1 48.80 3.90 190.32

    1175.72

    km-303 1 36.80 4.20 154.56

    1 105.40 3.90 411.06

    1 22.50 6.60 148.50

    1 78.00 4.10 319.80

    1 6.80 3.65 24.82

    1 49.80 3.90 194.22

    1 58.00 4.80 278.40

    1 9.85 3.00 29.55

    1560.91

    km-304 1 16.60 3.80 63.08

    1 90.00 2.80 252.00

    1 36.60 4.30 157.38

    1 42.50 3.70 157.25

    1 10.80 3.75 40.50

    1 7.20 2.90 20.88

    1 40.00 2.90 116.00

    1 7.30 2.85 20.81

    827.90

    Total (A) 11889.40

    km-265 1 16.80 3.50 58.80

    1 28.70 2.80 80.36

    1 42.80 3.55 151.94

    1 25.90 3.90 101.011 29.60 4.20 124.32

    1 44.00 4.60 202.40

    1 10.70 4.60 49.22

    768.05

    km-266 1 6.90 3.75 25.88

    1 31.60 4.70 148.52

    1 19.50 3.30 64.35

    1 26.80 4.40 117.92

    1 30.75 3.80 116.85

    1 16.80 4.60 77.28

    550.80

  • 8/13/2019 Maintenance & Estimate

    37/40

    km-267 1 9.90 4.50 44.55

    1 39.80 3.60 143.28

    1 52.80 3.70 195.36

    1 22.80 4.10 93.48

    1 6.80 4.60 31.28

    507.95

    km-268 1 21.70 3.95 85.72

    2 22.00 3.80 167.20

    1 45.00 3.30 148.50

    1 35.60 4.40 156.641 8.50 4.50 38.25

    1 19.65 4.70 92.36

    688.66

    km-269 1 38.90 3.75 145.88

    1 18.85 4.80 90.48

    2 36.50 4.30 313.90

    1 34.00 3.00 102.00

    1 70.20 3.25 228.15

    1 12.80 3.85 49.28

    929.69

    km-270 1 18.60 3.60 66.96

    1 45.50 3.40 154.701 9.80 2.90 28.42

    1 48.50 4.00 194.00

    444.08

    km-271 1 21.90 3.80 83.22

    1 120.00 4.00 480.00

    1 37.70 4.40 165.88

    1 55.50 4.00 222.00

    1 9.90 4.10 40.59

    1 26.80 4.60 123.28

    1114.97

    km-272 1 10.80 3.75 40.50

    1 27.60 4.25 117.301 47.90 3.40 162.86

    1 52.90 3.50 185.15

    1 107.20 3.70 396.64

    1 43.60 4.80 209.28

    1 9.90 3.85 38.12

    1 34.80 3.80 132.24

    1282.09

  • 8/13/2019 Maintenance & Estimate

    38/40

    km-273 1 12.20 2.60 31.72

    1 7.50 2.20 16.50

    1 48.20 4.10 197.62

    1 8.40 3.20 26.88

    1 42.00 5.20 218.40

    1 30.50 2.80 85.40

    1 24.40 2.70 65.88

    1 14.40 3.30 47.52

    689.92

    km-274 1 12.20 3.30 40.26

    1 35.20 3.00 105.601 6.90 3.70 25.53

    1 31.80 3.80 120.84

    1 60.80 3.60 218.88

    511.11

    Total (B) 7487.31

    Junior Engineer Assistant Engineer

    NH, PWD, Bareilly

  • 8/13/2019 Maintenance & Estimate

    39/40

    surfacing From km 295.00 to 304.00 & km 264.00 to 274.00 of NH-74 (New NH-30 )

    S. No. Item of work Unit Qty. Rate Per Amount

    1 Built-up-Spray Grout

    Providing, laying and rolling of built-up-spray grout

    layer over prepared base consisting of a two layer

    composite construction of compacted crushed coarse

    aggregates using motor grader for aggregates. key

    stone chips spreader may be used with application of

    bituminous binder after each layer, and with keyaggregates placed on top of the second layer to serve

    as a Base conforming to the l ine, grades and cross-

    section specif ied, the compacted layer thickness

    being 75 mm ( from km 294.00 to 304.00 ) A

    sqm 4007.79 311.15 sqm 1247022.30

    ( from km 264.00 to 274.00 ) B sqm 2081.41 297.41 sqm 619038.85

    2 Filling Pot-holes and Patch Repairs with open-

    Graded Premix surfacing, 20mm.

    Removal of all failed material, trimming of completed

    excavation to provide firm vertical faces, cleaning of

    surface, paint ing of tack coat on the sides and base

    of excavation as per clause 503, back f il ling the pot

    holes with hot bituminous material as per clause 511,compacting, trimming and finishing the surface to

    form a smooth continuous surface, all as per clause

    3004.2 (from km 294.00 to 304.00) A

    sqm 5581.66 135.84 sqm 758212.69

    ( from km 264.00 to 274.00 ) B sqm 4447.78 132.70 sqm 590199.35

    3 Providing and laying seal coat sealing the voids in a

    bituminous surface laid to the specified levels, grade

    and cross fall using Type B seal coats (from km

    294.00 to 304.00 ) A sqm 5581.66

    #

    #

    #

    # sqm 358007.67

    ( from km 264.00 to 274.00 ) B sqm 4447.78 63.40 sqm 281972.97

    4 Stress absorbing membrane (SAM) with crack width 6 mmto 9 mm

    Providing and laying of a stress absorbing membrane over a

    cracked road surface, with crack width 6 to 9 mm after cleaning

    with a mechanical broom, using modified binder complying with

    clause 521, sprayed at the rate of 11 kg per 10 sqm and

    spreading 11.2 mm crushed stone aggregates @ 0.12 cum per

    10 sqm, sweeping the surface for uniform spread of aggregates

    and surface finished to conform to clause 902. ( from km

    294.00 to 304.00 ) Asqm 11889.40 72.25 sqm 859005.58

    ( from km 264.00 to 274.00 ) B sqm 7487.31 71.00 sqm 531598.66

    Total 5245058.07

    J.E. A.E. Executive Engineer Superinding Engineer

    NHCD PWD Bareilly NH 28th Circle PWD Bareilly

    Name of work : Filling Pot-holes with B.U.S.G.& Patch-repair with open graded Premix

    BILL OF QUANTITY

  • 8/13/2019 Maintenance & Estimate

    40/40

    S.No. Item of Work Amount .

    1 Filling Pot-holes with B.U.S.G.& Patch-

    repair with open graded Premix

    surfacing From km 295.00 to 304.00 &

    km 264.00 to 274.00 of NH-74(NewNH-30) 5245058.07

    Total 'A' 5245058.07

    2 Contingency 2.8% 146861.63

    3 Quality Control 1% on A 52450.584 W.C. Establishment 1.5% on A 78675.87

    5 Centage Charges 9% on A 472055.23

    6 Labour cess 1% on A 52450.58

    Total 6047551.96

    Say 60.48 Lacs

    Junior Engineer Assistant Engineer Executive Engineer

    NH, PWD, Bareilly NH, PWD, Bareilly NH, PWD, Bareilly

    SUMMARY OF COST

    Name of work : Filling Pot-holes with B.U.S.G.& Patch-repair with open Graded Premix

    surfacing From km 295.00 to 304.00 &km264.oo to 274.00of NH-74 (New NH-30 )

    .