maintenance procedure-slurry stripper trays removal

11
MAINTENANCE PROCEDURE MUHAMMAD REHAN KHAN MAINTENANCE ENGINEER Slurry Stripping Column’s trays removal CL-1G

Upload: muhammad-rehan-pmp

Post on 25-May-2015

215 views

Category:

Engineering


4 download

DESCRIPTION

this is the training on removing trays' bundle of Slurry stripping column

TRANSCRIPT

Page 1: Maintenance procedure-Slurry stripper trays removal

   

 

MAINTENANCE PROCEDURE

MUHAMMAD REHAN KHANMAINTENANCE ENGINEER

Slurry Stripping Column’s trays

removalCL-1G

Page 2: Maintenance procedure-Slurry stripper trays removal

WASTE WATER STRIPPER (CL-1G)

0 0 0

Top Shell

Tray Bundle

6728

• It contains 34 trays

• Column height is 19.5 m & diameter is 1.5 m

• Slurry enters from top at 90C & leaves from bottom at 110C

• About 10000 to 15000 PPM VCM is recovered from stripping column

• Total Column weight: 11,865kg 

• Trays’ bundle weight: 2,690kg

• Top shell weight: 1,823kg 

• Trays’ Material: 0Cr18Ni9

Page 3: Maintenance procedure-Slurry stripper trays removal

MAINTENANCE ACTIVITY

1. Scaffolding is constructed on top and mid platform2. Insulation cladding is removed from head cover and mid platform manway

JOB METHOD STATEMENT

3. Open manway on mid platform, remove associated piping and perform required blinding

Mid platform manway

Page 4: Maintenance procedure-Slurry stripper trays removal

MAINTENANCE ACTIVITY

4. Remove bolts of shell on mid platform 

JOB METHOD STATEMENT

5. Park crane on the east side road of the equipment

Page 5: Maintenance procedure-Slurry stripper trays removal

MAINTENANCE ACTIVITY

6. Install slings on the lifting eyes at the top dome

JOB METHOD STATEMENT

7. Remove the top shell and placed it on ground

Page 6: Maintenance procedure-Slurry stripper trays removal

MAINTENANCE ACTIVITYJOB METHOD STATEMENT

Page 7: Maintenance procedure-Slurry stripper trays removal

MAINTENANCE ACTIVITY

8. Install a fabricated lifting jig on the top plate with the help of stud bolts 

JOB METHOD STATEMENT

9. Attach Chain block to crane’s slings for slow lifting of the trays’ bundle 

13 Stud Rods (0Cr18Ni9 and 52 Bolts of SS304)

Page 8: Maintenance procedure-Slurry stripper trays removal

MAINTENANCE ACTIVITY

10. Slowly lift the trays bundle until they will be free from the shell

JOB METHOD STATEMENT

11. Remove the complete trays’ bundle and placed it on ground

Clearance between shell and trays’ bundle is 2mm

Page 9: Maintenance procedure-Slurry stripper trays removal

MAINTENANCE ACTIVITY

12. Support the trays’ bundle with the help of scaffolding structure as shown

JOB METHOD STATEMENT

Page 10: Maintenance procedure-Slurry stripper trays removal

MAINTENANCE ACTIVITY

13. Cleaning and inspection of trays and shell is done

14. Both trays bundle and top shell are installed back

15. Associated piping and manway are boxed up

JOB METHOD STATEMENT

Page 11: Maintenance procedure-Slurry stripper trays removal

THANK YOU

MUHAMMAD REHAN KHANMAINTENANCE ENGINEER