Confirmed Process Order Without TECO through COOISPI
Procedure:
i) Put T-Code (COOISPI) in the user menu screen and then press ENTER.
ii) After pressing ENTER you will get below screen where few parameters should be selected to see plant wise Process Order.
Prepared By: Md. Rashidul Haque
iii) Selected Parameters are given below:
By default: List – Order HeadersLayout - /SQUARE (Standard Layout)Tick Marked on Process Orders
Manual: Production Plant - 1002, 1003, 1004 etc)Syst. Status – CNF and TECO (excluded)
iv) After selecting all above parameter then click execute button ( ).
Prepared By: Md. Rashidul Haque
Click EXECUTE button after selecting all below marked parameters
v) Then you will get your desired report of Open / Incomplete PO.