Marine Creek Middle School
Area D Competition Gym
tall irrigation plan south and west of ding, install sub floor in both gyms,
ckers scheduled for install next Monday.
Courtyard Canopy
Area F Backpack Storage
nstalling asework
Area F Workroom
Area A 1st & 2nd floor
Sheetrocking 1st floor & 2nd floor, finishing painting Administration area on 1st floor, and installing stone and installing glass at curtain wall.
Area A Media Center
Area A Front Entrance
Area C 1st Floor
Area C 2nd Floor
ating ductwork, texturing walls, and g sheetrock to 2nd floor
Field Events
Tennis Courts
g to pour tennis courts. roof is on storage building
idewalks poured on southside.
Copper Creek Elementary School
• TNP is working with developer for electrical service.
• The Board will consider naming a general contractor this evening.
• Notice to proceed on Friday, March 1, 2019.
Highland Middle School, Creekview Middle School, and Gililland Elementary School Renovation Progress
Projects are tracking on time. Demolition of existing space complete.
Drywall is near completion.
Security Upgrades
• The Board will consider a general contractor recommendation this evening.
Bryson ES, Eagle Mountain ES, Elkins ES and Boswell HS Renovations
• The Board will consider a general contractor recommendation this evening.
• Additional Serving Lines added to Highland MS and Creekview MS.
Shade Structures
• Obtained four quotes from approved BuyBoard vendors to consider needs at Chisholm Ridge ES, Eagle Mountain ESRemington Point ES, and Gililland ES.