market performance and planning forum - california review key market performance topics • share...
TRANSCRIPT
Market Performance and
Planning Forum
May 16, 2017
Objective: Enable dialogue on implementation
planning and market performance issues
• Review key market performance topics
• Share updates to 2017 release plans, resulting from
stakeholders inputs
• Provide information on specific initiatives
–to support Market Participants in budget and
resource planning
• Focus on implementation planning; not on policy
• Clarify implementation timelines
• Discuss external impacts of implementation plans
• Launch joint implementation planning process
Slide 2
Market Performance and Planning ForumAgenda – May 16, 2017
Time: Topic: Presenter:
10:00 – 10:05 Introduction, Agenda Kristina Osborne
10:05 – 10:20 May 3 CAISO Stage 1 System Emergency Tim Beach
10:20 – 12:00 Market Performance and Quality Update Guillermo Bautista Alderete
Amber Motley
James Lynn
12:00 – 1:00 Lunch
1:00 – 1:30 Policy Update Brad Cooper
1:30 – 2:00 Flexible Capacity Update Amelia Blanke
David Robinson
2:00 – 3:00 Release Update Adrian Chiosea
Janet Morris
Slide 3
May 3 CAISO Stage 1 System Emergency
Tim Beach
Shift Manager, Operations
Slide 4
May 3, 2017 Stage 1 Emergency Summary
• Peak load at 17:45 with sufficient capacity and operating
reserves
• Actual Net Scheduled Interchange (including dynamics) was
~1,150 MW below Day Ahead schedules
• ~600 MW of forced generation outages
• The HA market awarded 1,230 MW of supplemental energy
on the interties for HE20 (19:00 to 20:00) but 830 MW of that
was declined
• At 19:01 a Stage 1 Emergency was declared and all DR
verbally dispatched (PDR & RDRR)
– Two Contingency dispatches issued, RDRR enabled in the
market in the second dispatch (and actually dispatched
during manual implementation of DR.)
• Operating reserves recovered at 19:56
• 21:00 Stage 1 Emergency terminatedSlide 5
Market Performance and Quality Update
James Lynn
Senior Advisor, Market Settlements Design
Amber Motley
Manager, Short Term Forecasting
Guillermo Bautista Alderete, Ph.D.
Director, Market Analysis and Forecasting
Congestion Revenue Right Analysis Effort
CRR Auction Effort
• Initiative is split in two phases
– Analysis phase
– Policy phase
• CRR Working group session held on April 18 to discuss
the Analysis scope
• Analysis phase needed to have in-depth analysis of the
auction efficiency, and identify drivers and guide the
policy phase
Slide 8
Market Analysis done in three phases along the
following areas
• Auction results
• Participation
• Transparency
• Modeling
– Accuracy
– ISO practices/procedures
– Market events
– Systemic differences
• Constraint by constraint analysis
– Analyze constraints that did not bind in the auction but had
payouts in the DAM
– Analyze constraints with large payouts
• Impact of changes over timeSlide 9
Over Supply Update
Frequency of negative system prices has steadily
increased year over year
Slide 11
0%
5%
10%
15%
20%
25%
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Freq
uen
cy
2014 2015 2016 2017
Distribution of negative prices have shifted from early
morning hours to midday hours*
Slide 12* Metric of 2017 may be over-estimated since it includes only January through April.
0%
5%
10%
15%
20%
25%
30%
35%
40%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Freq
uen
cy
2014 2015 2016 2017
Slide 13
ISO total monthly VERS schedules and forecasts
Slide 14
IFM under-scheduling of wind generation
Monthly wind (VERS) downward flexibility in FMM
Slide 15
Monthly solar (VERS) downward flexibility in FMM from
11 AM to 5 PM
Slide 16
Slide 17
Hydro production higher than recent historical production
Slide 18
RTD renewable (VERS) curtailment continued to increase
in March and April
The trend of curtailments is accelerating
Slide 19
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
May Jun
Jul
Au
g
Sep
Oct
No
v
Dec Jan
Feb
Mar
Ap
r
May Jun
Jul
Au
g
Sep
Oct
No
v
Dec Jan
Feb
Mar
Ap
r
May Jun
Jul
Au
g
Sep
Oct
No
v
Dec Jan
Feb
Mar
AP
R
2014 2015 2016 2017
ENER
GY
CU
RTA
ILM
ENTS
(M
WH
)
Local Economical System Economical Local ED System ED Self Sch System Self Sch Local
Solar production and net load records have been
observed this Spring
Slide 20
. Saturday May 13 Sunday May 14
Maximum load 26,120 MW at 20:36 25,644 MW at 20:36
Minimum load 20,342 MW at 03:44 19,428 MW at 03:58
Minimum net load 8,804 MW at 14:44 8,493 MW at 13:03
How are curtailments determined?
• All curtailments are driven by prices, either economical bids or
penalty prices.
• Effective April 11, 2017 the step-size of the power balance constraint
relaxation for over-supply conditions was reduced to 30 MW.
• Only April 30 and May 8 have observed self schedule curtailments
and by less than 100MW
Slide 21
TOR/ETC
IFM self schedule
RMT
Price taker
PBC violation
Economical bids
Slide 22
Hydro production is trending upward for Spring but still
lower than historical high hydro year of 2006
0
1,000
2,000
3,000
4,000
5,000
6,000
Ja
n
Feb
Mar
Ap
r
May
Ju
n
Ju
l
Au
g
Se
p
Oct
No
v
De
c
Ja
n
Feb
Mar
Ap
r
May
Ju
n
Ju
l
Au
g
Se
p
Oct
No
v
De
c
Ja
n
Feb
Mar
Ap
r
May
Ju
n
Ju
l
Au
g
Se
p
Oct
No
v
De
c
Ja
n
Feb
Mar
Ap
r
May
Ju
n
Ju
l
Au
g
Se
p
Oct
No
v
De
c
Ja
n
Feb
Mar
Ap
r
2006 2014 2015 2016 2017
GW
h
Hydro vs. Solar Monthly Production
Hydro Solar
Slide 23
Self scheduled interties in the real-time market remain high
Flexible Ramp Update
Flexible Ramp Product Up Requirement
Slide 25
Flexible Ramp Product Down Requirement
Slide 26
Flexible Ramp Product Up Awards
Slide 27
Flexible Ramp Product Down Awards
Slide 28
How is FRP settled?
Slide 29
Forecasted
Upper limit
Lower limit
Net system demand at t
t+1 (advisory interval)t (binding interval) Time
Net system demand
Minimum
requirement
Demand curve
Demand curve
Forecasted movement known with certainty - e.g. self-schedule supply expected to ramp (up) from t to t+1; or load forecast that’s known to increase
from time t to t+1, requires an equivalent ramp up.
Uncertainty movement (forecast error)- the requirements for this is derived from demand curve modeling based on historical forecast errors
Demand Curve to Meet FRD Uncertainty
Slide 30
t (binding interval) t+1 (advisory interval)
Forecast net demand
FRU forecasted net load change
FRD uncertainty FRD max expected forecast error
t (binding interval) t+1 (advisory interval)
Forecast net demand
FRU forecasted net load change
FRD max expected forecast error
No FRD procured
First figure – need to procure FRD uncertainty; second figure – no need to procure
Forecasted Movement has a direct settlement,
uncertainty is awarded and allocated as an uplift
Binding Advisory …
B A …
Forecasted Movement (Market)
Uncertainty
A ARTD1
RTD2
Slide 31
• Supply and Interties resources (CC 7070)
– Separate FMM and Incremental RTD forecasted
movement qty
– (-1) * Forecasted Movement Qty * (FRU price - FRD
price)
– Rescind portion of forecasted movement in case of
deviation (UIE/OA)
• Load resources (CC 7076)
– Allocate to SCs based on SC’s metered EIM Demand
or metered CAISO Demand
Forecasted movement settlement
Slide 32
• Dispatchable Resources (CC 7071: FRU & CC 7081: FRD)
– Uncertainty award for FRU/FRD in FMM is settled at FMM FRU/FRD price
– Uncertainty award for FRU/FRD in RTD which is incremental to FMM uncertainty award is settled at the RTD FRU/FRD price
– Price has breakdown, which differentiates BAA constraint from EIM Area constraint contribution
– Rescind portion of Uncertainty Capacity where resource deviation (UIE/OA) overlaps
Uncertainty Award Settlement
Slide 33
FRP Uncertainty Cost Allocation
Slide 34
I
E
Flexible ramping up Flexible ramping down
E
I
I
E E
I
Total
Uncertainty
MW by FRP
Constraint
Category’s
Uncertainty
MW
Allocate to
individual resource
Uncertainty
Forecasted Movement Settlement ISO – From
November 1 to February 28, 2017
Scheduled Settlement
Correction
Slide 35
Uncertainty Up Settlement – From Jan 2015 – April
2017
Slide 36
Once normalized for capacity procured, FRP uncertainty
settlements in the same range as in prior months
Slide 37
FRP Up Uncertainty Payment Amount in EIM areas
Slide 38
FRP Down Uncertainty Payment Amount in EIM areas
Slide 39
FRP Up Payment – Hourly Distribution correlated to
hourly profile
Slide 40
FRP Down Payment – Hourly Distribution correlated to
hourly profile
Slide 41
Persistency Model Enhancement
Current Data Transfer Time Needed for External
Forecast Service Provider (FSP)
Slide 43
CAISO is working on an enhancement based on
persistency
• For Wind
– Recommendation is to use the simple lag
persistence model.
• For Solar
– Recommendation is to use a persistence contour
model.
Slide 44
Accounting of Market Dispatches/Curtailments of
Renewables is also considered
• Market software will also handle cases of market
dispatches or curtailments of renewables
– As soon as the market dispatches an EIR resource,
logic will be included to take into consideration the
supplemental dispatch of resource to be the EIR
Resource Forecast.
Slide 45
Mean Average Percent Error for January 2017
Slide 46
PCM and Lag methods reduced External FSP MAPE by 50% for
RTD
Wind Solar
External FSP 6.5% 8.5%
Lag 3.2% 5.9%
PCM 3.5% 4.9%
Forecast Type
RTD
Total Mae Value for RTD SOLAR Forecast
Slide 47
0%
1%
2%
3%
4%
5%
6%0
:00
1:1
0
2:2
0
3:3
0
4:4
0
5:5
0
7:0
0
8:1
0
9:2
0
10
:30
11
:40
12
:50
14
:00
15
:10
16
:20
17
:30
18
:40
19
:50
21
:00
22
:10
23
:20
MA
E
Unit A
lag pcm
0%
2%
4%
6%
8%
10%
12%
0:0
0
1:1
0
2:2
0
3:3
0
4:4
0
5:5
0
7:0
0
8:1
0
9:2
0
10
:30
11
:40
12
:50
14
:00
15
:10
16
:20
17
:30
18
:40
19
:50
21
:00
22
:10
23
:20
MA
E
Unit B
lag pcm
0%
2%
4%
6%
8%
10%
12%
0:00
1:25
2:50
4:15
5:40
7:05
8:30
9:55
11:2
012
:45
14:1
015
:35
17:0
018
:25
19:5
021
:15
22:4
0
MAE
Unit C
lag pcm
0%
2%
4%
6%
8%
10%
12%
14%
0:00
1:25
2:50
4:15
5:40
7:05
8:30
9:55
11:2
012
:45
14:1
015
:35
17:0
018
:25
19:5
021
:15
22:4
0
MAE
Unit D
lag pcm
APPENDIX
Slide 48
Simple Lag Persistence Model
• Name Convention:
A (actual),
F (forecast),
E (Error) = F – A
• FH = Forecast Horizon (RTD)
• Lag Model
– F(t) = A(t-FH) (Forecast for time t = Actuals from time t-FH)
Slide 49
Recommendation for Solar Resources
Persistence Counter Market Model
• Let F(t) be forecast, A(t) be actual, and FPI(t) be
estimate of full power output taking into consideration
sun angle.
• The persistent forecast is then:
– F(t) = A(t-lag) / FPI(t-lag)* FPI(t)
– Where A(t-lag) / FPI (t-lag) is the estimate “cloud”
factor to A(t)/FPI(T)
The premise is the lag forecast A(t-lag) should adjust
according the track of performance under different
cloudiness condition at lag time point
Slide 50
Example
• Sunny Day:
– A(t-lag) / FPI(t-lag) = 1
• Cloudy Day:
– A(t-lag) / FPI(t-lag) = .3
Slide 51
Market Update
Slide 53
Good price convergence in April based.
Note: Metric Based on System Marginal Energy Component (SMEC)
Slide 54
RT prices higher than DA prices for both NP15 and SP15 in
April.
Slide 55
Insufficient upward ramping capacity in ISO continued to be
at low levels since last November.
Slide 56
Insufficient downward ramping capacity declined since
February.
Slide 57
Congestion revenue rights market revenue inadequacy
without auction revenues.
Slide 58
Congestion revenue rights market revenue sufficiency
including auction revenues.
Slide 59
Exceptional dispatch volume in the ISO area decreased
since February.
Slide 60
Real-time Bid cost recovery dropped in April
Slide 61
Bid cost recovery (BCR) by Local Capacity Requirement area
Slide 62
Minimum online commitment (MOC)
MOC San Onofre Bus
Slide 63
Pmax of MOC Cleared Units
Slide 64
Enforcement of minimum online commitments in March
and April
MOC NameNumber (frequency) of hours in
January and February
Humboldt 7110 SVC In 1196
MOC Pease 994
Orange County 7630 801
Humboldt 7110 215
MOC East Nicolaus 96
MOC SAN ONOFRE BUS 90
MOC Devers Bus 41
SDGE 7820 CFEIMP_BG 34
MOC Placer 4551087 26
MOC Moss 4575683 15
SDGE 7820 9
SCIT MOC 8
MOC NP15 7
Orange county outage 7630 2
Slide 65
Renewable (VERS) schedules including net virtual supply
and aligns with VER forecast in March and April
http://www.caiso.com/Pages/documentsbygroup.aspx?GroupID=EFF75C
2E-F28E-4087-B88B-8DFFAED828F8
Slide 66
Hourly distribution of maximum RTD renewable (VERS)
curtailment in April
Slide 67
ISO area RTIEO increased since February.
2016 2017 (YTD)
RTCO $50,398,946 $9,701,084
RTIEO -$3,706,211 $18,633,447
Total Offset $46,692,735 $28,334,531
Slide 68
CAISO Price correction events increased in March and April
0
1
2
3
4
5
6
7
8
9
10
Jan
-16
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Feb
-17
Mar
-17
Ap
r-1
7
Co
un
t o
f Ev
ents
Process Events Software Events Data Error Events Tariff Inconsistency
Slide 69
EIM-Related Price correction events decreased in March and
April
0
2
4
6
8
10
12
14
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2016 2017
Co
un
t o
f Ev
ents
Process Events Software Events Data Error Events Tariff Inconsistency
EIM Price trends
Slide 70
Robust Energy transfers observed in in 1st
quarter, 2017
Average – 259MW
Maximum – 1196MW
Average – 186MW
Maximum – 739MW
Average – 108MW
Maximum – 300MW
Average – 173MW
Maximum – 506MW
Average – 0MW
Maximum – 0MW
Average – 84MW
Maximum – 150MW
Average – 80MW
Maximum – 300MW
Average – 118MW
Maximum – 300MW
Average – 231MW
Maximum – 871MW
Average – 222MW
Maximum – 791MW
Average – 141MW
Maximum – 330MW
Average – 136MW
Maximum – 360MW
Average – 165MW
Maximum – 909MW
Average – 184MW
Maximum – 945MW
Average – 144MW
Maximum – 857MW
Average – 0MW
Maximum – 0MW
PACE
CAISO
PACW
NEVP
AZPS
PSEI
Slide 71
Slide 72
EIM BCR observed a modest increased in April
Slide 73
EIM Manual Dispatch increased in April and is mostly
concentrated in APS area
Day-ahead load forecast
0.0%
0.5%
1.0%
1.5%
2.0%
2.5%
3.0%Jan
Feb
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
PE
Slide 74
Day-ahead peak to peak forecast accuracy
0.0%
0.5%
1.0%
1.5%
2.0%
2.5%
3.0%
3.5%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
PE
Slide 75
Day-ahead wind forecast
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
E
**In 2015-2016, Economic dispatches are not added back in to the generation data.
**The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
Slide 76
Day-ahead solar forecast
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
E
**In 2015-2016, Economic dispatches are not added back in to the generation data.
**The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
Slide 77
Real-time wind forecast
0.0%
0.5%
1.0%
1.5%
2.0%
2.5%
3.0%
3.5%
4.0%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
E
**2015-2016 represent the accuracy of the forecast made each hour at xx:55 for the following hour, i.e. the 5-65
minute ahead forecast. Economic dispatches are not added back in to the generation data.
**2017 has been changed to track the RTD accuracy, i.e. the forecast made 7.5 minutes before the binding
interval. The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
**This forecast accuracy is pulled directly from the CAISO Forecasting System.
Slide 78
Real-time solar forecast
0%
1%
2%
3%
4%
5%
6%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
E
**2015-2016 represent the accuracy of the forecast made each hour at xx:55 for the following hour, i.e. the 5-65
minute ahead forecast. Economic dispatches are not added back in to the generation data.
**2017 has been changed to track the RTD accuracy, i.e. the forecast made 7.5 minutes before the binding
interval. The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
**This forecast accuracy is pulled directly from the CAISO Forecasting System.
Slide 79
Market Performance and Planning ForumMay 16, 2017
We are on lunch break, returning at 1:00 p.m. If you have
questions, send to Kristina Osborne at [email protected]
or call on cell at 916-802-7631.
Policy Update
Brad Cooper
Manager, Market Design and Regulatory Policy
Ongoing policy stakeholder initiatives
• Energy storage and distributed energy resources (ESDER)
Phase 2
– Publish draft final proposal in June
– July EIM Governing Body and CAISO Board meetings
• Contingency modeling enhancements
- Fourth revised straw proposal including prototype results in late
June
- September CAISO Board meeting
• Generator contingency and remedial action scheme
modeling
– Draft final proposal in June
– Sept EIM Governing Body and CAISO Board meetings
Slide 82
Ongoing policy stakeholder initiatives (continued)
• Commitment costs and default energy bid enhancements
– Recent stakeholder working groups
– Straw proposal in June
– November 2017 EIM Governing Body and CAISO board
meetings
• Temporary suspension of resource operations
– Recently posted issue paper
– Nov CAISO Board meeting
• Capacity Procurement Mechanism risk-of-retirement
process enhancements
– Recently posted issue paper
– Nov CAISO Board meeting
Slide 83
Ongoing policy stakeholder initiatives (continued)
• EIM Greenhouse Gas Enhancements
– Draft final proposal in late May
– July 2017 EIM Governing Board and ISO Board meetings
(briefing)
– Report evaluating two-pass solution in late Q4 2017
– Early 2018 EIM Governing Body and ISO Board meetings for
approval
• Flexible resource adequacy criteria and must-offer
obligation – phase 2
– Second revised straw proposal in July
– Q2 2018 ISO Board meeting
• Congestion revenue right auction efficiency
– Stakeholder working group on analysis in April
– Analysis phase in progress
– Policy development phase starting after analysis complete in Q4Slide 84
Ongoing policy stakeholder initiatives (continued)
• Frequency response – phase 2
– Developing new schedule
– Early 2018 CAISO board meeting
• Bid cost recovery enhancements
– Suspended due to FERC uplift allocation NOPR
Slide 85
Upcoming policy stakeholder initiatives
• Aliso Canyon mitigation measures extension
– Straw and draft final proposals in June
– July EIM Governing Body and ISO Board meetings
• Management of EIM Imbalance settlement for bilateral
schedule changes
– Issue paper in June
– Oct EIM Governing Body and Nov ISO Board meetings
• Donation by third party of transmission capacity available
for EIM transfers
– Issue paper in June
– Oct EIM Governing Body and Nov ISO Board meetings
Slide 86
Upcoming policy stakeholder initiatives (continued)
• Planned to start in Q3 2017
– EIM net wheeling charge
– Review Transmission Access Charge Structure
– Resource adequacy reform
– Real-time market enhancements
Slide 87
2016 Annual Report
Amelia Blanke
Manager, Monitoring & Reporting
Department of Market Monitoring
Total market costs were down by about 4 percent after
accounting for natural gas and greenhouse gas price
changes.
Slide 89
$0
$1
$2
$3
$4
$5
$6
$7
$0
$10
$20
$30
$40
$50
$60
$70
2012 2013 2014 2015 2016
Ave
rage
an
nu
al g
as p
rice
($
/MM
Btu
)
Ave
rage
an
nu
al c
ost
($
/MW
h)
Average cost (nominal)
Average cost normalized to gas price, including greenhouse gas adjustment
Average daily gas price, including greenhouse gas adjustments ($/MMBtu)
Estimated average wholesale energy costs per MWh
(2012 – 2016)
Slide 90
2012 2013 2014 2015 2016
Change
'15-'16
Day-ahead energy costs 32.57$ 44.14$ 48.57$ 34.54$ 30.70$ (3.84)$
Real-time energy costs (incl. flex ramp) 0.99$ 0.57$ 1.98$ 0.69$ 1.02$ 0.33$
Grid management charge 0.80$ 0.80$ 0.80$ 0.80$ 0.81$ 0.01$
Bid cost recovery costs 0.45$ 0.47$ 0.40$ 0.39$ 0.33$ (0.06)$
Reliability costs (RMR and CPM) 0.14$ 0.10$ 0.14$ 0.12$ 0.11$ (0.01)$
Average total energy costs 34.96$ 46.08$ 51.89$ 36.54$ 32.97$ (3.58)$
Reserve costs (AS and RUC) 0.37$ 0.26$ 0.30$ 0.27$ 0.54$ 0.26$
Average total costs of energy and reserve 35.33$ 46.34$ 52.19$ 36.81$ 33.50$ (3.31)$
Markets continued to perform close to competitive
benchmarks.
Slide 91
$0
$10
$20
$30
$40
$50
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Ave
rag
e p
ric
e (
$/M
Wh
)
Competitive baseline ($/MWh) Average load-weighted day-ahead price
Average load-weighted 15-minute price Average load-weighted 5-minute price
Estimated net revenue of a hypothetical new unit 2012 - 2015
$0
$20
$40
$60
$80
$100
$120
$140
$160
$180
$200
$220
2012 2013 2014 2015
$/k
W-y
ear
Net revenues (NP15)
Net revenues (SP15)
Levelized fixed cost target
$0
$20
$40
$60
$80
$100
$120
$140
$160
$180
$200
$220
2012 2013 2014 2015
$/k
W-y
ear
Net revenues (NP15)
Net revenues (SP15)
Levelized fixed cost target
Combined Cycle Combustion Turbine
Slide 92
DMM updated net revenue analysis assumptions in 2016
• Not directly comparable to prior analysis
• Optimized dispatch of hypothetical resource
– Objective: maximize profit subject to resource
constraints
– 2016 NP15 and SP15 prices
• Combined cycle: day-ahead and five minute prices
• Combustion turbine: 15 and 5 minute prices
– Incremental energy cost = default energy bid
– Commitment cost = proxy start up and minimum load
http://www.caiso.com/Documents/2016AnnualReportonMarketIssuesandPerformance.pdf
Slide 93
Financial analysis of new combined cycle unit (2016)
Slide 94
Zone Scenario Capacity factorTotal energy
revenues ($/kW-yr)
Operating costs
($/kW-yr)
Net revenue
($/kW-yr)
Day-ahead prices and default energy bids 21% $75.88 $64.65 $11.23
Day-ahead prices and default energy bids without adder 23% $83.12 $70.45 $12.67
Day-ahead commitment with dispatch to day-ahead and
5-minute prices using default energy bids22% $79.73 $66.82 $12.91
Day-ahead prices and default energy bids 29% $104.92 $84.40 $20.52
Day-ahead prices and default energy bids without adder 32% $111.20 $88.83 $22.37
Day-ahead commitment with dispatch to day-ahead and
5-minute prices using default energy bids30% $108.51 $86.38 $22.13
NP15
SP15
Significantly below California Energy Commission’s estimate of annualized fixed costs for a hypothetical combined cycle is $166/kW-yr
Financial analysis of new combustion turbine (2016)
Slide 95
Zone Scenario Capacity factorReal-time energy
revenues ($/kW-yr)
Operating costs
($/kW-yr)
Net revenue
($/kW-yr)
15-minute prices and default energy bids 4.5% $23.46 $18.67 $4.80
15-minute prices and default energy bids without
adder5.6% $27.85 $22.17 $5.68
15-minute commitment with dispatch to 15-minute
and 5-minute prices using default energy bids5% $31.41 $21.03 $10.38
15-minute prices and default energy bids 7% $41.37 $28.87 $12.50
15-minute prices and default energy bids without
adder9% $48.20 $34.33 $13.87
15-minute commitment with dispatch to 15-minute
and 5-minute prices using default energy bids8% $50.07 $32.79 $17.29
NP15
SP15
Significantly below California Energy Commission’s estimate of annualized fixed costs for a hypothetical combustion turbine is $177/kW-yr
Flexible ramping payments
Slide 96
$0.00
$0.02
$0.04
$0.06
$0.08
$0.10
$0.0
$0.5
$1.0
$1.5
$2.0
$2.5Ja
n
Fe
b
Ma
r
Apr
Ma
y
Ju
n
Ju
l
Aug
Sep
Oct
No
v
De
c
Ja
n
Fe
b
Ma
r
Apr
Ma
y
Ju
n
Ju
l
Aug
Sep
Oct
No
v
De
c
2015 2016
Pa
ym
en
ts p
er
MW
h lo
ad
($
/MW
h)
To
tal p
aym
en
ts (
$ m
illi
on
)
California ISO PacifiCorp East
PacifiCorp West NV Energy
Puget Sound Energy Arizona Public Service
Payments per MWh of load
Flexible ramping product implementation
Release Plan Update
Janet Morris
Director, Program Office
Adrian Chiosea
Manager, Strategic Initiative Management
Release Plan 2017
Slide 98
Independent 2017
• MRI-S ACL Groups + CPG Enhancements (formerly OMAR Replacement)
• RIMS Functional Enhancements
• Black Start and System Restoration Phase 2
• Forecasting & Data Transparency Improvements (PIRP System Decommissioning)
• Aliso Canyon mitigation measures extension
Fall 2017 (11/1/17)
• EIM Portland General Electric (PGE) – 10/1/17
• Bidding Rules Enhancements – Part B
• Commitment Cost Enhancement Phase 3
• RM & EIM 2017 Enhancements
• Gas Burn Report
• SIBR UI Upgrade
Release Plan – 2018 and subject to further planning
Slide 99
Spring 2018
• Reliability Services Initiative 2017
• EIM 2018 Idaho Power Company
Fall 2018 – tentative, subject to impact assessment
• Contingency Modeling Enhancements
• Flexible Resource Adequacy Criteria and Must-offer Obligation Phase 2
• Commitment Costs and Default Energy Bid Enhancements
• Energy Storage and DER Phase 2
• Temporary Suspension of Resource Operations
• Capacity Procurement Mechanism – risk-of-retirement process enhancements
• Management of EIM imbalance settlement for bilateral schedule changes
• ADS User Interface Replacement
• CIRA Technology Upgrade
Spring 2019
• EIM 2019 Seattle City Light
• EIM 2019 Balancing Authority of Northern California (BANC)
Fall 2019 – tentative, subject to impact assessment
• Regional Integration and EIM Greenhouse Gas Compliance
• Generation Contingency and Remedial Action Scheme
• Frequency Response Phase 2
• Congestion Revenue Right auction efficiency
Spring 2020
• EIM 2020 Salt River Project
Subject to further release planning:
• DRS Replacement
2017 - MRI-S ACL Groups+ CPG Enhancements
Project Info Details/Date
Application Software Changes
The MRI-S metering (MRI-S) application cannot currently support ACL (Access Control
List) groups functionality for defining a subset of resources belonging to an SCID.
Enhancements to the Application Identity Management (AIM) application will enable the
use of ACL groups for SCID-level read-only access for MRI-S.
A customer partnership group is scheduled for May 11, 2017 to address issues
encountered during market sim, and to discuss the steps necessary for cut-over from
OMAR Online to MRI-S Metering.
OMAR Online will be decommissioned four months after the May 2nd re-opening of the
MRI-S Metering: September 1, 2017.
BPM Changes None
Business Process ChangesPotential Level-II business process changes under –
• Manage Market & Reliability Data & Modeling
• Manage Operations Support & Settlements
Slide 100
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A
BPMs BPMs N/A
External BRS Post External BRS Nov 14, 2016
Tariff Tariff N/A
Config Guides Config Guide N/A
Tech Spec Publish Tech Specs Nov 02, 2016
Market Simulation Phase 2 - MRI-S Metering Enhancements Mar 13, 2017 – June 9, 2017
Production Activation Phase 1 - ACL Groups Mar 10, 2017
Phase 2 - MRI-S Metering CPG Enhancements Jun 13, 2017
2017 – RIMS Functional Enhancements
Project Info Details/Date Status
Application Software ChangesFunctional enhancements resulting from the Customer Partnership Group CPG.
More details to be provided in the future.
BPM Changes
Generator Interconnection and Deliverability Allocation Procedures
Generator Interconnection Procedures
Managing Full Network Model
Metering
Generator Management
Transmission Planning Process
Customer Partnership Group 10/16/15
Application and Study Webinar 3/31/16
Slide 101
Milestone Type Milestone Name Dates Status
Board Approval Board approval not required N/A
BPMs Generator Interconnection and Delivery Allocation Apr 29, 2016
External BRS External BRS not Required N/A
Tariff No Tariff Required N/A
Tech Spec No Tech Specifications Required N/A
Production Activation Ph1 RIMS5 App & Study Mar 21, 2016
Production Activation Ph2 RIMS5 Queue Management, Transmission and Generation Dec 14, 2017
2017- Black Start and System Restoration Phase 2
Project Info Details/Date
Application Software Changes
Settlements:
• Modifications to existing charge codes for Black Start capacity and
Black Start allocations will need to occur.
MPP (Market Participant Portal):
• Possibility to use current functionality for receiving RMR invoices
for Black Start units.
BPM Changes
Definitions & Acronyms:
• Revision of the following definitions to match the Tariff language:
• Ancillary Services (AS)
• Black Start Generator
• Black Start Generating Unit
• Interim Black Start Agreement
• Reliability Services Costs
Settlements & Billing:
• Pending Settlements review. Revisions will be directly based on
Tariff changes.
Business Process Changes N/A
Slide 102
Milestone Type Milestone Name Dates Status
Board Approval Board approval May 1, 2017
BPMs BPM Changes Required TBD
External BRS External BRS not Required N/A
TariffDraft tariff
Web Conference to finalize tariff
May 1, 2017
May 15, 2017
Tech Spec No Tech Specifications Required N/A
2017 – Forecasting and Data Transparency Improvements
(PIRP System Decommissioning)
Project Info Details/Date
Application Software Changes:
PIRP/CMRI
• Forecast Data Reporting (resource-level) that was performed in PIRP will be done in
CMRI. Rolling Hour Ahead, Locked Hour Ahead, and Rolling Day-Ahead forecasts.
• PIRP Decommissioning to occur in 2017
• CMRI to receive the Electricity Price Index for each resource and publish it to the
Market Participants.
• 60 Day PIRP / CMRI parallel production to start when AIM/ACL becomes available.
BPM Changes CMRI Technical Specification; New APIs will be described.
Data Transparency
• Independent changes, won’t
impact existing services
• Will be made available in
Production and cutover
schedule is discretionary
Atlas Reference:
1. Price Correction Messages (ATL_PRC_CORR_MSG)
2. Scheduling Point Definition (ATL_SP)
3. BAA and Tie Definition (ATL_BAA_TIE)
4. Scheduling Point and Tie Definition (ATL_SP_TIE)
5. Intertie Constraint and Scheduling Point Mapping (ATL_ITC_SP)
6. Intertie Scheduling Limit and Tie Mapping (ATL_ISL_TIE)
Energy
• EIM Transfer Limits By Tie (ENE_EIM_TRANSFER_LIMITS_TIE)
• Wind and Solar Summary (ENE_WIND_SOLAR_SUMMARY)
Prices
• MPM Default Competitive Path Assessment List (PRC_MPM_DEFAULT_CMP)
Business Process Changes MPs will receive the VER reports from CMRI rather than PIRP.
Slide 103
2017 – Forecasting and Data Transparency Improvements
(PIRP System Decommissioning)
Project Info Details/Date
User-Provisioning process for
CMRI in preparation of Market
Simulation and subsequently for
production
• Client Services will reach out to the User Access Administrator (UAA)
• Updated AIM User Guide, detailing how to create new ACL groups, was posted on
February 21, 2017 - The market notice was posted on February 23, 2017
• If a user is at the SC level, there is no need to provision ACL access
• Exceptions - (Non-SC Level Users) – provisioning via AIM will be required
• Provisioning will be required to be done prior to Market Simulation
• Provisioning for PIRP via AARF will discontinue on Feb 16, 2017 for Map Stage and
Mar 20, 2017 for Production.
• Participants should begin to download their PIRP data (all reports) as soon as possible
as the data will not be available after June 20, 2017
• PIRP application including all the UI and API reports will be decommissioned June 20,
2017
• If you have any questions please contact your client services representative
Slide 104
2017 – Forecasting and Data Transparency Improvements
(PIRP System Decommissioning)
Slide 105
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A
BPMsPublish Draft Business Practice Manuals (Market
Instruments; PRR 936)Sep 06, 2016
External BRS External Business Requirements Jun 29, 2015
Tariff Tariff Filing Activities N/A
Config Guides Settlements Configuration N/A
Tech Spec Publish Technical Specifications (CMRI; Wind and Solar) Apr 15, 2016
Publish Technical Specifications (CMRI: PIRP
Decommissioning)Feb 05, 2016
Market Sim CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Aug 23, 2016 - Sep 23, 2016
New Renewables CMRI reports and APIs Market
SimulationApr 04, 2017 - Apr 18, 2017
Production Activation CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Oct 01, 2016
OASIS API Enhancements; 9 Reports Dec 20, 2016
New Renewables CMRI reports and APIs Production
DeploymentApr 20, 2017
PIRP Decommission PIRP Decommissioning Jun 20, 2017
Fall 2017 Release – Overview
Slide 106
Board Approval
BPMs External BRS Tariff Config Guide Tech Spec Market SimProduction Activation
Fall 2017 Release
EIM Portland General Electric N/A N/A N/A 8/31/17 N/A N/A6/6/17 -7/6/17
10/1/17
Bidding Rules Enhancements - Part B 3/25/16
6/15/17
1/13/17 6/1/17
6/27/17
• 4/3/17 (MF)
• 4/3/17 (OASIS)
• 4/17/17 (CMRI)
• 4/25/17(CMRI)
• 5/2/17 (OASIS)
8/8/17 -9/8/17
11/1/17
Commitment Cost Enhancement Phase 3 3/25/161/6/17
4/10/176/15/17
RM & EIM 2017 Enhancements N/A N/A1/23/172/17/174/10/17
N/A
Gas Burn Reports N/A N/A 7/29/16 N/A N/A N/A
SIBR UI Upgrade N/A N/A N/A N/A N/A N/A N/A
COMPLETE
N/A
Fall 2017 – EIM Portland General Electric
Project Info Details/Date
Application Software Changes Implementation of Portland General Electric as an EIM Entity.
BPM ChangesEIM BPM will be updated to reflect new modeling scenarios identified
during PGE implementation and feedback from PGE.
Market SimulationPGE continues Day in the Life and unstructured scenario testing in a non-
production environment in preparation for Market Simulation.
Parallel Operations August 1 – September 30, 2017
Slide 107
Milestone Type Milestone Name Dates Status
Tariff File Readiness Certification Aug 31, 2017
Market Sim Market Sim Window Jun 6, 2017 – Jul 6, 2017
Parallel Operations Parallel Operations Window Aug 1, 2017 – Sep 30, 2017
Production Activation EIM - Portland General Electric Oct 01, 2017
Fall 2017 - Bidding Rules Enhancements – Part B
Slide 108
Project Info Details/Date
Application Software Changes
• MasterFile:
• Electric Region added to GRDT as non-modifiable
• CMRI:
• Resource-level monthly EPI (calculated on daily basis) based on wholesale or reatil
electric region type.
• CAISO.COM:
• Only publish total monthly fuel region GPI (existing) and eliminate publishing the
monthly fuel region GPI components as PDF file. (public information)
Business Process Change• Manage Transmission & Resource Implementation
• Manage Entity & Resource Maintenance Updates
• Manage Full Network Model Maintenance
BPMs Market Instruments
Milestone Type Milestone Name Dates Status
BPMs Post Draft BPM changes June 15, 2017
Board Approval BOG Approval Mar 25, 2016
External BRS Post External BRS Jan 13, 2017
Config Guides Prepare Draft Configuration Guides Jun 27, 2017
Tech Spec Publish CMRI Tech Specs Apr 17, 2017
Publish MF Tech Specs Apr 03, 2017
Market Sim Market Sim Window Aug 08, 2017 - Sep 08, 2017
Production Activation Bidding Rules Part B Nov 01, 2017
Project Info Details/Date
Application Software
Changes
Scope:1. Clarify use-limited registration process and documentation to determine opportunity costs2. Determine if the ISO can calculate opportunity costs
• ISO calculated; Modeled limitation Start/run hour/energy output• Market Participant calculated; Negotiated limitation
3. Clarify definition of “use-limited” 4. Change Nature of Work attributes (Outage cards)
• Modify use-limited reached for RAAIM Treatment• Allow PDR to submit use-limit outage card for fatigue break.
5. Market Characteristics• Maximum Daily Starts• Maximum MSG transitions• Ramp rates
Impacted Systems:1. Master File: Set use-limited resource types and limits; Set market-based values2. ECIC: Process use limited resource input values for and Receive opportunity cost adders from
opportunity cost tool3. CIRA: RAAIM exempt rule for “use-limited reached”4. CMRI: Publish opportunity cost5. IFM/RTN: Use market-based values MDS, MDMT and RR6. SIBR: Add Opportunity cost adders on bid caps, remove daily bid RR7. MasterFile: Set use-limited resource types and limits; Set market-based values8. OMS: “Use-Limited Reached” nature of work attribute for Generation Outage Card9. Settlements: Publish the actual start up, run hour and energy output for the use-limited
resources10. Opportunity cost calculator (OCC): Calculate and publish opportunity costs for start-up, MLC and
DEB
BPM Changes Market Instruments, Outage Management, Reliability Requirement, Market Operations
Business Process Changes• Manage Market & Reliability Data & Modeling• Manage Markets & Grid
Slide 109
Fall 2017 - Commitment Cost Enhancements Phase 3
Slide 110
Fall 2017 - Commitment Cost Enhancements Phase 3 (cont.)
Milestone Type Milestone Name Dates Status
Board Approval Board of Governors (BOG) Approval Mar 25, 2016
BPMs Post Draft BPM changes Jun 15, 2017
External BRS Post External BRS Jan 06, 2016
Tariff File Tariff Jun 15, 2017
Config Guides Config Guide Jun 27, 2017
Tech Spec
Publish ISO Interface Spec (Tech spec) – MF
Publish ISO Interface Spec (Tech spec) – CMRI
Apr 03, 2017
Apr 17, 2017
Market Sim Market Sim Window Aug 08, 2017 – Sep 8, 2017
Production Activation Commitment Costs Phase 3 Nov 01, 2017
Fall 2017 – RM & EIM Enhancements 2017Project Info Details/Date
Application Software Changes
Address enhancements identified by policy, operations, technology, business
and market participants.
Scope:
1. Access & Integration Enhancements: EIM Entity Access in ALFS, MF,
OASIS, WebOMS, and CMRI.
2. EIM data report enhancements to support market participant and EIM entity
settlements
3. EIM software enhancements
4. Change to ETSR formulation to separate base energy transfer to distinct
non-optimizable ETSRs.
Out of Scope:
1. BAAOP provisioning in AIM
2. Joint Owned Unit/Shared BAA Resource Modeling
BPM Changes
Energy Imbalance Market: Access & Integration, Data Report
Outage Management: Access & Integration
Market Instruments: Access & Integration, Data Reports
Market Operations: Data Report
Settlements & Billing: Data Report
Business Process Changes N/A
Slide 111
Fall 2017 – RM & EIM Enhancements 2017
Slide 112
Milestone Type Milestone Name Dates Status
External BRS Post External BRS Jan 23, 2017
Post Updated External BRS Feb 17, 2017
Post Updated (v1.2) External BRS to public site Apr 10, 2017
Config Guides Config Guide Jun 27, 2017
Tech Spec Publish Technical Specifications (CMRI) Apr 17, 2017
Publish Technical Specifications (OASIS) Apr 03, 2017
Publish Technical Specifications (MF) Apr 03, 2017
Market Sim Market Simulation Aug 08 – Sept 08, 2017
Production Activation RM & EIM Enhancements 2017 Nov 01, 2017
Fall 2017 – Gas Burn Report
Slide 113
Project Info Details/Date
Application Software Changes
CMRI - implement ISO Market software functionality to calculate and present gas burn
estimates to gas companies serving electric generation located within the CAISO BAA
OASIS - Control Area Generating Capability List report
Business Process Change• Develop Infrastructure
• Manage Market & Reliability Data & Modeling
Milestone Type Milestone Name Dates Status
Board Approval BOG Approval N/A
BPMs Post Draft BPM changes N/A
External BRS External Business Requirements Jul 29, 2016
Tariff Receive FERC order N/A
Config Guides Configuration Guides N/A
Tech Spec Publish Technical Specifications - CMRI Apr 25, 2017
Publish Technical Specifications - OASIS May 02, 2017
Market Sim Market Sim Window N/A
Production Activation GenDB MF Consol and Gas Burn Report Nov 01, 2017
Fall 2017 – SIBR UI Upgrade
Slide 114
Project Info Details/Date
Application Software Changes
SIBR – The CASIO will be upgrading the underlying SDK platform utilized for displaying the
user interface. This latest SDK version will strengthen the security of the SIBR application
and will improve compatibility with the latest version of Internet Explorer.
It is anticipated no functional changes or API will be impacted by this upgrade.
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A
BPMs Publish Final Business Practice Manuals N/A
External BRS Post Draft BRS N/A
Tariff Receive FERC order N/A
Tech Spec Publish Tech Specs N/A
Market Sim Market Sim Window N/A
Production Activation SIBR UI Upgrade Nov 01, 2017
Spring 2018 - Reliability Services Initiative 2017
Project Info Details/Date
Application Software Changes
Developments under consideration include:
Scope:Redesign of Replacement Rule for System RA and Monthly RA Process.
• RA Process and Outage Rules for implementation for 2017 RA year.
• CSP Offer Publication (RSI 1A scope)
• Local and system RA capacity designation
• RA showing requirements for small load serving entities (LSEs)
• RA showing tracking and notification
Impacted Systems:
• OASIS
• Settlements
• CIRA
CIRA:• Modifications to the RA and Supply Plan to show breakdown of local and system. Validation
rules need to be updated.
• Update planned/forced outage substitution rules
• Allow market participants to select how much system/local MWs to substitute.
• Modification of UI screens to accommodate system/local MW split.
• Enhance system to allow exemption from submission of RA Plans for LSE that have a RA
obligation < 1 MW for a given capacity product.
Settlements:• Splitting local from system in upstream RA system could potentially impact the RAAIM
calculation.
BPM Changes• Reliability Requirements: Changes to the monthly RA process
• Settlements and Billing
Business Process Changes
Manage Market & Reliability Data & Modeling- Manage Monthly & Intra-Monthly Reliability Requirements
- Manage Yearly Reliability Requirements
Slide 115
Spring 2018 - Reliability Services Initiative 2017
Slide 116
Milestone Type Milestone Name Dates Status
Board Approval Board Approval May 12, 2015
BPMs Post Draft BPM changes Jun 15, 2017
External BRS Post Updated External BRS v1.1 (RSI 2) Apr 07, 2017
Post Updated External BRS v1.3 (RSI 1B) Mar 03, 2017
Post RSI 2017 External BRS v2.0 Apr 19, 2017
Tariff File Tariff Q3 2017
Config Guides Config Guide Jun 27, 2017
Tech Spec Publish Technical Specifications Apr 03, 2017
Market Sim Market Sim Window Oct 30, 2017 - Dec 08, 2017
Production Activation RSI 2017 Feb 13, 2018
Spring 2018 – EIM Idaho Power Company
Project Info Details/Date
Application Software Changes Implementation of Idaho Power Company as an EIM Entity.
BPM Changes
EIM BPM will be updated if needed to reflect new modeling scenarios
identified during Idaho Power implementation and feedback from Idaho
Power.
Market Simulation
The ISO approved the Idaho Power network model and continues to make
progress integrating the Idaho model into the ISO non-production
environment in preparation for integration testing.
Parallel Operations February 1, 2018 – March 30, 2018
Slide 117
Milestone Type Milestone Name Dates Status
Tariff File Readiness Certification Feb 28, 2018
Market Sim Market Sim Window Dec 01, 2017 - Jan 31, 2018
Parallel Operations Parallel Operations Window Feb 01, 2018 - Mar 30, 2018
Production Activation EIM - Idaho Power Apr 04, 2018
The ISO offers comprehensive training programs
Slide 118
All classes are offered at our Folsom, CA location unless noted otherwise.
Training calendar - http://www.caiso.com/participate/Pages/Training/default.aspx
Contact us - [email protected]
Date Training
May 24-25 Get to Know the ISO
Jul 6 Welcome to the ISO - webinar
Aug 16 Settlements 101
Aug 17 Settlements 201
ISO Daily Briefing
• A digest version of ISO market notices
• Distributed daily, Mon-Fri around 1:30 p.m. (PST)
• NEW: Upcoming Events - Every Thursday the briefing
will include stakeholder activities for the following week
• To subscribe to the Daily Briefing:
Go to www.caiso.com
Under “Stay Informed” tab
Select “Notifications”
Click under Market notices heading
Select Daily Briefing from the list of categories
Note: If you currently receive ISO market notices and you re-subscribe, the system will override your previous
category selections. If you still want to receive market notices in other categories, you’ll need to reselect those
categories of interest.
Slide 119
Market Performance and Planning Forum
2017 Schedule
• July 18
• October 5 – Rescheduled from September 19
• November 14
Questions or meeting topic suggestions:
Submit through CIDI - select the “Market Performance and
Planning Forum” category
Slide 120