martijn blansjaar laura rock kopczak april 08, 2011
DESCRIPTION
WASH Cluster Stockpile project 5, phase 3 Supply Chain and Operating Concept Design and Implementation . WASH Stockpile April 2011 update and key issues. Martijn Blansjaar Laura Rock Kopczak April 08, 2011. This session. Recap of previous phase outcomes. Current work. - PowerPoint PPT PresentationTRANSCRIPT
WASH Cluster Stockpile project 5, phase 3 Supply Chain and Operating Concept Design and Implementation
Martijn BlansjaarLaura Rock Kopczak
April 08, 2011
WASH StockpileApril 2011 update and key issues
This session
1) Recap of previous phase outcomes.2) Current work.3) Key design issues and decision
Phase 2 Objective
Design the best feasible supply chain and operating concept for a proposed WASH Cluster emergency materials stockpile and prepare the implementation of a 2 year pilot.
Design principles
• WASH cluster agreed-upon standard items and modules to meet full set of WASH needs
• Pre-funded interagency stockpile and transport and replenishment costs
• Trigger and allocation done by the WASH cluster• Fast decision-making and execution result in
early response• Leverage of existing proven logistics processes of
WASH agencies to support this new approach
WASH Stockpile Processes
Trigger Deploy Use
Replenish
FOCUS OF PHASE 2
Donor
Funding
Technical
Specification and
Input to Sourcing
Materials: Six ModulesReference
s Hygiene Sanitation
Water treatment
Water trucking
Water storage & distribution
There are six modules. Each module is composed of several items. The entire kit of six modules will be deployed.
The global stockpile consists often units of each module. Each unit supports 5,000 beneficiaries. The Global stockpile supports 50,000Beneficiaries.
The minimum deployment quantity Is two units of each of the six modules – enough to support 10,000 beneficiaries.
Annual Demand Scenario
• 1 big emergency (50K)– 50% chance in Africa and 50% in Asia– May hit anytime throughout the year
• 3-4 small/medium emergencies totaling 45,000– 2 in Africa– 1 in Asia– 1.5 in Latin America
The stockpile inventory is expected to turn over approximately twice a year.
Recommended Oxfam – IFRC supply chain.
Procurement Storage &dispatch
Local receipt &dispatch
UPSTREAMSUPPLY CHAIN
DOWNSTREAMSUPPLY CHAIN
IN-COUNTRYSUPPLY CHAIN
Engineering
IFRC LRMD Strengths:Regional locations,Storage and dispatch on behalf of NS’s,Innovative supply chain
IFRC LRMDStrengths:In-country presence through Nat. Societies. .
Oxfam Strengths:Supplier relationships, Procurement,Engineering support,Field knowledge,Sells WASH items to other agencies.
Key issues under discussion at end of Phase 2
1. Stock ownership2. In-country receipt3. Contracts and funds flows4. Reporting
Project Organization (Phase III) WASH Steering Committee (Oversight)
Jean Lapegue, Action Contre la Faim Paul Shanahan , CareMark Buttle, Save the ChildrenLuke Dokter, NCAWilliam Fellows, UNICEF
Paul Molinaro, UNICEF Supply Division (advisor)
Project Manager
Martijn Blansjaar/Oxfam [email protected]
Consultants Laura Rock Kopczak/ MIT-ZaragozaSander de Leeuw/ Vrije Universiteit Amsterdam
[email protected]@feweb.vu.nl
Current Status
• IFRC agreed to collaborate with Oxfam on the supply chain.
• A mini-pilot project was funded in December 2009, as a practical continuation of detailed preparations and ‘road-test’ of the scheme so that it will be “ready to go” and “proven”.
• It was envisioned that the mini-pilot would be done in parallel with donor consultations.
• ‘On hold’ during 2010
Mini-Pilot Activities Objectives • To ensure all systems developed (upstream
&downstream) for the Global WASH Cluster Stockpile - complete the detailed design of an agreed interagency Global WASH Cluster stockpile procurement and delivery mechanism and complete a full trial run (‘mini-pilot’). This includes provision of a limited amount of WASH material to an implementing agency through the WASH Cluster coordination in an actual emergency response.
Three Sets of Activities to Realize the WASH Stockpile
Develop andPilot
Program Processes
DevelopAnd Pilot Supply Chain
Processes
Obtain Funding To Run theStockpile
For 2-3 Years
Mini-pilot Project
Activities Required
• Complete demand & transport analysis
• Definite design & physical location choice
• Agreed stock ownership and transfer
• Contract and fund-flows between participants established
• Information flow and management agreement
• Limited amount of material bought, stored and delivered
• Trigger process• Allocation process• Reporting process /
measuring success
• Donor consultations• Funds flow and
financial reporting worked out
• Donor proposal for main 3-year pilot completed (and agreed…)
Program LogisticsEngagement Of Donors
Design choices
Regional WASH Stockpile
Dispatch Receipt
Customs
Use
Three Options to Consider
Start: one consolidated shipment made by air.
OPTION 1 Direct Shipment (Multiple Consignees)Allocation Before Dispatch
Shipment Through an Intermediate Agency (Single Consignee)
OPTION 2 Single ConsigneeAllocation Before Dispatch
OPTION 3 Single ConsigneeAllocation After Receipt
OPTION 1 – Direct ShipmentMultiple Consignees, Allocation Before Dispatch
Requirements: Each consignee = agency to whom WASH has allocated…• Is registered in-country• Will use the goods in their own program; may decide themselves to
transfer some goods to their own partners• Formally & practically is able to take ownership, receive, import,
store & move goods• Can get tax exemption• Will not charge a fee to the scheme• Will guarantee and report on use to donors and host government
Limitation: Import and tax exemption paperwork must be done by each consignee before dispatch. If one agency is late with paperwork, shipment/receipt/use of the whole cargo may be delayed.
OPTION 2/3 – Shipment Through An Intermediate Agency
Requirements – the single consignee:• Is registered in-country• Formally & practically is able to take ownership, receive, import, store & move
goods and hand them over to other agencies• Can get tax exemption• Will charge a reasonable fee• Will guarantee and report on use to donors and host government
Requirements – the “allocated” agencies:• Are registered in-country• Will use the goods in their own program• Will not charge a fee to the scheme• Will guarantee and report on use to the single consignee
Limitation: Documentation of ownership transfer, liability, unproven concept
Three Options: Legal Differences
START: One consolidated shipment will be made by air.
OPTION 1 Direct Shipment (Multiple Consignees)Allocation Before Dispatch
Shipment Through an Intermediate Agency (Single Consignee)
OPTION 2 Single ConsigneeAllocation Before Dispatch
OPTION 3 Single ConsigneeAllocation After Receipt
The consigneesguarantee and reporton proper use.
The single consignee guarantees and reportson proper use. ??
The single consignee guarantees and reportson proper use. ??
Three Options: Logistical Differences
START: One consolidated shipment will be made by air.
OPTION 1 Direct Shipment (Multiple Consignees)Allocation Before Dispatch
Shipment Through an Intermediate Agency (Single Consignee)
OPTION 2 Single ConsigneeAllocation Before Dispatch
OPTION 3 Single ConsigneeAllocation After Receipt
The single consignee stages and delivers/hands over goods
Consignee stores and delivers/ hands over goods as theyare allocated, in effect, running a warehouse.
Goods flow directly toconsignees.
Comparison of the Three OptionsDirect Shipment(ABD)
Single Consignee(ABD)
Single Consignee(AAR)
Early dispatch (no delays in dispatch due to agencies not creating their paperwork on time)
- - - +
Guarantee of proper use and reporting lie with using agencies
+ + - - - -
Consignee(s) are willing to guarantee proper use
+ + ? ?UNICEF unwilling
? ?UNICEFunwilling
Likely management/donation fee charged by consignee(s) for assuming that role
0% 10% UNICEF 10% UNICEF
Quick handover to using agencies, once goods clear customs
+ + + + +
Goods can be allocated bit by bit - - - - + +
Goods will all be allocated + + + + - -
Recommended Next Steps for Mini-Pilot
Proceed with the mini-pilot using the “Direct to Consignees” approach with allocation before dispatch.
Next steps
Mini-pilot TOR covers logistics activities Program Logistics Engagement of Donors
Feb-March
Define trigger criteria and process.Define allocation criteria and process.Define in-country receipt process.
Finalize specs, markingSolicit quotes for non- Oxfam partsSet up process for receipt and pre-positioning.
April-May
Define reporting process.
Order and receive items.Define dispatch and transport process.
Develop donor proposal presentation and have first meetings with potential donors.
July-Aug
Dispatch, use, evaluate, report.
Dispatch, evaluate, report.
Sept-Oct
Develop follow-up presentation and have second meetings with donors.
Covered by Minipilot TOR