McKellar Park Information Session
Ottawa LRT Stage 2
![Page 2: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/2.jpg)
2
Stage 2 Background
• $3-billion Stage 2 plan approved unanimously by Ottawa City Council in July 2015
• East to Place d’Orléans, west to Bayshore and Baseline, and south to Bowesville
• 30 kms of new rail and 19 new stations• 70% of Ottawa residents will live within five
kilometres of rail
![Page 3: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/3.jpg)
3 3
Ottawa’s O-Train
![Page 4: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/4.jpg)
4
Why Stage 2?
Ottawa’s population growth • 1.14 million people by 2031 Increased Ridership• 13.5 million more trips/year by 2031Decreased Congestion • 14,000 less vehicles during rush hour
![Page 5: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/5.jpg)
5
Environmental Benefits
![Page 6: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/6.jpg)
6
Less Cars and Buses
![Page 7: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/7.jpg)
7 7
Confederation Line West - Tunnel
Western extension also includes a 4-km tunnel running under a relocated Sir John A. Macdonald Parkway:• Starts just west of Dominion Station• Ends just south of Richmond Road overpass
over the Parkway (Pinecrest Creek Corridor)
![Page 8: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/8.jpg)
8 8
Cleary Station
![Page 9: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/9.jpg)
13 9
Cleary Station Concept
![Page 10: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/10.jpg)
10
Dominion Station
![Page 11: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/11.jpg)
11
Dominion Station Concept
![Page 12: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/12.jpg)
12
Richmond Rd. Streetscape
• “Complete street” west of Cleary to Pinecrest Creek Corridor – Budgeted as part of Stage 2• East of Cleary to Golden Avenue –
Unbudgeted as part of Stage 2• Seeking input from community
![Page 13: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/13.jpg)
13
Station Connectivity
• Improved unimpeded access to waterfront from station and community
• New multi-use pathway bridge over LRT• Reduced impact on existing landscape• Better passenger pickup and drop-off points• Improved pathway and sidewalk
neighbourhood connections
![Page 14: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/14.jpg)
10 14
Construction Oversight
• “Cut and cover” technique for tunnel construction• Only pre-2018 work is borehole
drilling happening right now
![Page 15: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/15.jpg)
16 15
Construction Impacts
• Once underway, construction activities will impact the area for up to two years
• Limits on noise and vibration during construction and operation
• All City of Ottawa Noise By-laws will be respected
• Regular construction hours in City of Ottawa: Monday – Saturday: 7:00am -10:00pm
Sunday: 9:00am-10:00pm
![Page 16: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/16.jpg)
16
Impacts on Richmond Rd.
• ??
![Page 17: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/17.jpg)
17 17
Common Mitigation Measures
• Communicating scheduled and anticipated works• Noise and vibration monitoring• Design of track• Dust mitigation strategies• Compliance with contract and City Bylaw for
work hours• Activities scheduled to create minimal impacts to
traffic
![Page 18: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/18.jpg)
18 18
LRT Service
• Core part of network (between Blair and Lincoln Fields Stations), trains will run:–Approximately every 4 minutes in each
direction during morning and afternoon peak periods–5 to 15 minutes in off-peaks and on
weekends • Run an average of 35 km/h
![Page 19: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/19.jpg)
19 19
Light Rail Vehicle
• Ottawa vehicle amongst quietest in the world• Noise levels less than background traffic• Wide access doors for improved passenger
flow• Low floor for 100% accessibility• Vehicles have regenerative breaking system,
low consumption LED interior lighting, and almost 100% efficient electric drive system
![Page 20: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/20.jpg)
20 20
Next Steps
November 2015 – Preliminary Engineering work begins
End of 2015 – “Environmental Project Report” issued
Spring 2016 – EA Notice of Completion issued
2017 – Request for Proposals goes out
2018 – Project awarded to winning consortium
2018/19 – Construction begins
2023 – Revenue service begins
![Page 21: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/21.jpg)
21 21
Community liaison throughout project
The City is committed to providing up to date information during LRT planning and construction. Our Stakeholder
Relations team is available to answer and respond to any issues/questions from stakeholders.
Rosemary Pitfield, Stakeholder Relations & Communications
Light Rail Planning & Implementation, City of Ottawa
Email: [email protected]
![Page 22: McKellar Park Information Session Ottawa LRT Stage 2 1](https://reader036.vdocuments.net/reader036/viewer/2022062309/5697c0021a28abf838cc341c/html5/thumbnails/22.jpg)
22 22
For project updates and more information on Stage 2 visit: