measures of performance ch-3

Upload: anjali

Post on 07-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/4/2019 Measures of Performance Ch-3

    1/54

    Designing the Management

    Control System

  • 8/4/2019 Measures of Performance Ch-3

    2/54

    An important component of Management Controls

    Assigning responsibility for executing strategy

    Implementing strategies is not

    adequate if individuals whomust execute them fall short.

    3-2

  • 8/4/2019 Measures of Performance Ch-3

    3/54

    Therefore, management controls

    must include

    How responsibility is assigned and measured

    How tasks are measured (not necessarily tasks done

    by humans but also by machines; e.g. units

    produced)

    Task controls such as when to order inventory, why

    the actual differ from budgeted (the causes)

    And, not easy to measure or quantify items such asimpact on behaviors, intangible assets, and so on.

    3-3

  • 8/4/2019 Measures of Performance Ch-3

    4/54

    Factors influencing Design

    Size of organization

    Organizational philosophy of delegation anddecentralization

    Types of responsibility centers

    Perception of people

    3-4

  • 8/4/2019 Measures of Performance Ch-3

    5/54

    Process of designing control system

    and required constraints

    3-5

  • 8/4/2019 Measures of Performance Ch-3

    6/54

    RESPONSIBILITY CENTERS

    3-6

  • 8/4/2019 Measures of Performance Ch-3

    7/54

    What is a responsibility center?

    In simple words: an organizational unit for which a

    manager is made responsible.

    Examples: A specific store in a chain of grocery

    stores.

    A work-station in a production line manufacturing

    automobile batteries.

    The payroll data processing center within a firm.

  • 8/4/2019 Measures of Performance Ch-3

    8/54

    Attributes of a responsibility center

    It is like a small business, and its manager is

    Asked to run that small business and preserve the

    interests of the larger organization.

    Goals for the center should be specific and

    measurable, and

    Should promote the long terms interests of the

    organization and should be compatible with otherresponsibility center activities.

  • 8/4/2019 Measures of Performance Ch-3

    9/54

    Example: A courier service (DHL)

    Courier operations dispatch trucks to pick up or deliver

    shipments from local terminals.

    It could be sent to one or more central terminals and then

    sorted and redirected. Success of this service would depend on:

    Service commitment to customers (on time, without damage) and

    Controlling costs

    Let us suppose that each terminal is treated as a responsibilitycenter.

    How should the company measure the performance of each

    terminal, its mangers, and its employees?

  • 8/4/2019 Measures of Performance Ch-3

    10/54

    Measuring the performance of the

    courier-terminal responsibility center

    To focus on efficiency: we could measure no. of parcels picked

    up, sorted or delivered, per route, per employee, per vehicle,

    per hour or per shift.

    To focus on customer service, we could measure each groupscontribution to customers: proportion of the time the terminal

    met its deadlines, when terminals are required to sort

    shipments, what the sorting error rate was.

    We could also measure customer service by: no. of complaints

    operations group receives, average time taken by the

    operation group to respond to complaints, and no. of

    complaints of poor, or impolite service.

  • 8/4/2019 Measures of Performance Ch-3

    11/54

    Measuring inputs and outputs

    In the courier example, the inputs are causal and

    direct: e.g. no. of packets received to time taken to

    deliver them.

    But, such causal and direct relationships are not

    always possible. For example, how does

    advertising contribute to increase in revenues?

    Or, how would you measure the contribution of R &D to product innovation, revenue generation, or cost

    reduction?

  • 8/4/2019 Measures of Performance Ch-3

    12/54

    Converting the inputs into monetary units

    Most organizations would convert the physical inputs

    into monetary units when evaluating a responsibility

    center.

    No. of units x cost of production, labor hours x per

    hour rate, etc.

  • 8/4/2019 Measures of Performance Ch-3

    13/54

    Measuring outputs

    Measuring outputs is more difficult. This is because:

    Input may be extended this year but outputs

    (benefits) may be received over several years (e.g.

    employee training).

    It would be difficult to make the causal relationship

    e.g. marketing expenses, IT investments,

    accountants and generation of revenue and profits.

  • 8/4/2019 Measures of Performance Ch-3

    14/54

    The input-output attributes

    Most organizations use financial controls cost,

    revenue, and profits, etc.

    However, such measures are not applicable to all

    units within an organization.

    For example, how would you measure the

    contribution of a production department? It can

    only be done on a cost measurement basis. How would you measure the contribution of a sales

    department only by revenue generated.

  • 8/4/2019 Measures of Performance Ch-3

    15/54

    Why does an organization

    relate input to outputs?

    Because they inherently measure efficiency and effectiveness.

    Efficiency: ratio of output to inputs;

    Caution: Do not use ratio of output to input in an absolute

    sense; but, only in a comparative sense. If Dept. A is more efficient than Dept. B, do not rush to

    conclusions; examine why Dept. B is less efficient and what can

    be done about it.

    Also, comparisons are possible only if Dept. B and Dept. A usecomparable outputs and comparable inputs. You cannot

    compare advertising to accounting.

  • 8/4/2019 Measures of Performance Ch-3

    16/54

    Efficiency

    Efficiency is generally measured by comparing

    actual costs to standard costs.

    Issues:

    Standard costs do not remain stationery.

    Recorded costs are often different from actual

    resources (costs) consumption.

    Lesson: Establishing a responsibility center is easy;

    Measuring its efficiency in a reasonable manner is

    difficult.

  • 8/4/2019 Measures of Performance Ch-3

    17/54

    Effectiveness

    Relationship between a responsibility centers output

    and its objectives (what it was intended to do or

    perform or deliver).

    If the output contributes to satisfying the objectives,

    the more effective it is.

    The new advertising and marketing efforts has

    increased awareness and recognition of ourproduct. Advertising and marketing has been

    effective.

  • 8/4/2019 Measures of Performance Ch-3

    18/54

    Efficiency-Effectiveness

    Not a compromise

    A responsibility center must both be efficient and

    effective.

    It must use the least amount of inputs to get the

    maximum amount of output and yet deliver on the

    goals.

    A sales department was efficient in growing the

    sales by 10% without adding additional salespeople or marketing expenses (efficient); however,

    many of the credit sales could not be collected (bad

    debts). It is ineffective.

  • 8/4/2019 Measures of Performance Ch-3

    19/54

    Role of Profit

    The goal of every for-profit organization is earn profits

    (effectiveness).

    If the organization could use the least input to get the

    maximum earnings, profits will be high (efficiency). Therefore, profit is an indicator of both efficiency and

    effectiveness.

    However, not every unit within an organization earns profit

    and therefore, this measure cannot be used for allresponsibility centers.

    Therefore, an organization must establish various types of

    responsibility centers.

  • 8/4/2019 Measures of Performance Ch-3

    20/54

    Types of Responsibility Centers

    Revenue Centers

    Cost Centers or Expense Centers

    Profit Centers and Investment Centers

    Financial performance center

    Strategic business unit (SBU)

  • 8/4/2019 Measures of Performance Ch-3

    21/54

    Revenue Centers

    Responsibility Centers whose members control

    revenues but,

    Not the manufacturing or acquisition cost of the

    products or service they sell, or

    The level of investment in the responsibility center.

    In other words, you cannot link the input to the

    output.

  • 8/4/2019 Measures of Performance Ch-3

    22/54

    Revenue Centers (continued)

    Most revenue centers may not set selling prices

    They definitely have no control over the costs ofinput acquired (service manager of an automobile

    workshop does not control gasoline costs) These centers are generally not allocated costs of

    the goods that they market (there are exceptions).Manager is responsible only for costs directly

    incurred by his/her unit. They are evaluated on the basis of actual sales or

    orders booked against budgets or quotas and

    Example: a unit of a chain store in a mall.

  • 8/4/2019 Measures of Performance Ch-3

    23/54

    Expense/Cost Centers

    Responsibility centers whose employees control costs, but

    Do not control their revenues or investment level.

    Examples: Production department in a manufacturing unit, a

    dry cleaning business Two types of costs:

    Engineered: those costs that can be reasonably associated with a cost

    center direct labor, direct materials, telephone/electricity consumed,

    office supplies.

    Discretionary: where a direct relationship between a cost unit and

    expenses cannot be reasonably made; Management allocates them on

    a discretionary basis (e.g. depreciation expenses for machines utilized).

  • 8/4/2019 Measures of Performance Ch-3

    24/54

    Engineered costs

    Should be measurable in monetary terms, outputs inphysical quantities.

    Works well in units such as production, distribution,

    accounting receivables, payables where repetitivetasks are performed.

    Developing standard costs for such activities is morereliable than in other cases.

    Multiply standard cost per unit x no. of unitsproduced or processed = this is the ideal cost.

    Compare it to actual costs and the difference isindicative of efficiency or lack thereof.

  • 8/4/2019 Measures of Performance Ch-3

    25/54

    Engineered costs

    Important to remember

    The fundamental purpose of all responsibility

    centers is accountability; evaluating performance.

    And a engineered cost center,

    Does not merely compare costs but also

    Holds the managers accountable for

    obtaining/producing right quality of product

    Volume of production, speed of processing.

  • 8/4/2019 Measures of Performance Ch-3

    26/54

    Discretionary costs

    Mostly administrative and support service costs

    More difficult to measure in physical quantities or precisely onmonetary terms (e.g. customer relations or even R & D).

    Discretionary means, management allocates them based on

    established polices (not arbitrarily). More caution is required while using discretion cost numbers.

    Difference between budgeted expenses and actual expensesdoes not indicate efficiency.

    Suppose if the actual cost is less than budget, does it mean

    good or bad? Suppose if the actual cost is higher than budget, does it mean

    good or bad?

  • 8/4/2019 Measures of Performance Ch-3

    27/54

    Expense centers (continued)

    Comparing Budgeted and Actual Costs

    Budgeted costs are target estimates.

    It points to a goal to be achieved.

    But, it is not written in concrete.

    Actual costs are that were incurred during a given period.

    The difference between the two could be either positive or

    negative variances.

    However, making conclusions on the basis of positive or

    negative variances must be done carefully. See the next set slides and the example.

  • 8/4/2019 Measures of Performance Ch-3

    28/54

    Morton Carpets Master Budget (Fixed)

    Prod. 1 Prod. 2 Prod. 3 Prod. 4 Total

    Units made 245,000 385,000 636,000 1,250,000

    Units per batch 500 2,500 1,500 5,000

    No. of batches 490 154 424 250

    Cost per unit $ 5.40 $3.20 $4.25 $1.45

    Cost per batch $325.00 $680.00 $400.00 $135.00

    Unit-related costs

    (245,000x$5.40)

    $1,323,000 $1,232,000 $2,703,000 $1,812,500 $7,070,500

    Batch-related costs

    (490x$325)

    159,250 104,720 169,600 33,750 467,320

    Prod.-sustaining costs 125,000 168,000 256,000 355,000 904,000

    Facility costs 1,450,000

    Total cost center costs $9,891,820

  • 8/4/2019 Measures of Performance Ch-3

    29/54

    Morton Carpets Actual Costs

    Prod. 1 Prod. 2 Prod. 3 Prod. 4 Total

    Units made 2,945,000 345,000 675,000 950,000

    Units per batch 600 2,300 1,800 6,000

    No. of batches 492 150 375 159

    Cost per unit $ 5.43 $3.18 $4.33 $1.40

    Cost per batch $335.00 $670.00 $387 $144.00

    Unit-related costs $1061,850 $1,097,100 $2,922,750 $1,330,000 $6,951,700

    Batch-related costs 164,820 100,500 145,125 22,896 433,341

    Prod.-sustaining costs 133,000 163,000 259,000 362,000 917,,000

    Facility costs 1,650,000

    Total cost center costs $9,952,041

  • 8/4/2019 Measures of Performance Ch-3

    30/54

    Budget Actual VarianceUnrelate d costs

    Product 1 1,323,000.00 1,601,850.00 278,850.00

    Product 2 1,232,000.00 1,097,100.00 -134,900.00Product 3 2,703,000.00 2,922,750.00 219,750.00Product 4 1,812,500.00 1,330,000.00 -482,500.00

    Total 7,070,500.00 6,951,700.00 -118,800.00Batch related costs

    Product 1 159,250.00 164,820.00 5,570.00

    Product 2 104,720.00 100,500.00 -4,220.00Product 3 169,600.00 145,125.00 -24,475.00Product 4 33,750.00 22,896.00 -10,854.00

    Total 467,320.00 433,341.00 -33,979.00Prod. sus. Costs

    Product 1 125,000.00 133,000.00 8,000.00

    Product 2 168,000.00 163,000.00 -5,000.00Product 3 256,000.00 259,000.00 3,000.00Product 4 355,000.00 362,000.00 7,000.00

    Total 904,000.00 917,000.00 13,000.00Fac. Sus. Costs 1,450,000.00 1,650,000.00 200,000.00

    Total 9,891,820.00 9,952,041.00 60,221.00

    Variance Analysis

  • 8/4/2019 Measures of Performance Ch-3

    31/54

    What do we learn from the variance analysis of

    Morton Carpets?

    The variance analysis presents a mix of positive and

    negative variances.

    Example: Product 1 and 3, unit-related costs were

    higher than planned, and

    For products 2 and 4 they were lower than planned.

    In total, the unit-related costs and batch-related

    costs were lower than planned and the product-sustaining and facility-sustaining costs were higher

    than planned.

  • 8/4/2019 Measures of Performance Ch-3

    32/54

    What can we conclude about

    Morton Carpets?

    Based on initial analysis, manufacturing is able to control unit-related and batch-related costs, but

    Did not do so well controlling product-sustaining and facility-sustaining costs.

    A closer examination, however, casts doubts on theseconclusions.

    If you look at slides 24 and 25, you will notice that the no. ofunits actually made differed from budgeted for all fourproducts.

    Similarly, no. of units per batch actually produced differedfrom budgeted units per batch.

    Because of these volume differences, it is inappropriate tocompare the cost targets in the master budget with actual costresults.

  • 8/4/2019 Measures of Performance Ch-3

    33/54

    What can managers do to make the numbers

    comparable and meaningful?

    Use a flexible budget (the text does not use this

    term but discusses the same concepts within cost

    variability and incremental budgeting sections). The

    objectives are the same. Flexible budget recasts cost targets in the planned

    or budget to reflect the achieved level of

    production.

    The flexible budget develops cost target levels

    based on actual level of activity.

    See the next set of slides.

  • 8/4/2019 Measures of Performance Ch-3

    34/54

    Morton Carpets Flexible Master Budget

    Prod. 1 Prod. 2 Prod. 3 Prod. 4 Total

    Units made 295,000 345,000 675,000 950,000

    Units per batch 500 2,500 1,500 5,000

    No. of batches 590 138 450 190

    Cost per unit $ 5.40 $3.20 $4.25 $1.45

    Cost per batch $325.00 $680.00 $400.00 $135.00

    Unit-related costs $1,593,000 $1104,000 $2,868,750 $1,337,500 $6,943,250

    Batch-related costs 191,750 93,840 180,000 25,650 491,240

    Prod.-sustaining costs 125,000 168,000 256,000 355,000 904,000

    Facility costs 1,450,000

    Total cost center costs $9,788,490

  • 8/4/2019 Measures of Performance Ch-3

    35/54

    Budget Fl. Budget Actual

    Planning

    variance

    Fl. Bud.

    Variance

    Unrelated costs (slide) (B-Fl.B) (Act.-F.B)

    Product 1 1,323,000.00 1,593,000.00 1,601,850.00 270,000.00 8,850.00

    Product 2 1,232,000.00 1,104,000.00 1,097,100.00 -128,000.00 -6,900.00

    Product 3 2,703,000.00 2,868,750.00 2,922,750.00 165,750.00 54,000.00

    Product 4 1,812,500.00 1,377,500.00 1,330,000.00 -435,000.00 -47,500.00

    Total 7,070,500.00 6,943,250.00 6,951,700.00 -127,250.00 8,450.00Batch related costs

    Product 1 159,250.00 191,750.00 164,820.00 32,500.00 -26,930.00

    Product 2 104,720.00 93,840.00 100,500.00 -10,880.00 6,660.00

    Product 3 169,600.00 180,000.00 145,125.00 10,400.00 -34,875.00

    Product 4 33,750.00 25,650.00 22,896.00 -8,100.00 -2,754.00

    Total 467,320.00 491,240.00 433,341.00 23,920.00 -57,899.00

    Prod. sus. Costs

    Product 1 125,000.00 125,000.00 133,000.00 0.00 8,000.00

    Product 2 168,000.00 168,000.00 163,000.00 0.00 -5,000.00

    Product 3 256,000.00 256,000.00 259,000.00 0.00 3,000.00

    Product 4 355,000.00 355,000.00 362,000.00 0.00 7,000.00

    Total 904,000.00 904,000.00 917,000.00 0.00 13,000.00

    Fac. Sus. C 1,450,000.00 1,450,000.00 1,650,000.00 200,000.00 200,000.00Total 9,891,820.00 9,788,490.00 9,952,041.00 -103,330.00 163,551.00

    Variance Analysis

    Flexible Budget Cost Analysis

  • 8/4/2019 Measures of Performance Ch-3

    36/54

    What did we infer from the

    flexible budget slides?

    Cost standards are the same as in the case of the fixed budget.Why?

    Difference: volume levels are adjusted to reflect achieved level ofactivity (e.g. Product 2 was 345,000 and std. batch size of 2,500

    or 345/2.5 = 138 batches). Using std. unit cost of $3.20 and std. batch cost of $680, unit-

    related and batch-related costs for Prod. 2 should have been$1,104,000 (345,000 x $3.20) and $93,840 ($680 x 138).

    Planned variance reflect cost adjustment needed to show the

    differences in production volume between master budget andflexible budget. Negative variance means a cost reduction due to lower volume and

    a positive variance means a cost increase because of a highervolume.

    Flexible budget variances are the focus of cost control in a costcenter.

  • 8/4/2019 Measures of Performance Ch-3

    37/54

    Cost/Expense center variances

    A few pointers

    Dont rush to conclusions based on positive or

    negative variances.

    Find the cause behind the variances.

    Decompose the flexible budget variances for unit-

    related costs into price and quantity components.

    Since analysis of variances for batch-related,

    product-sustaining, and facility-sustaining costs is notformalized and proceeds on an ad hoc basis,

    Use your common sense and rationale as a neutral

    evaluator.

  • 8/4/2019 Measures of Performance Ch-3

    38/54

    Profit Centers

    Managers of profit centers control both the

    revenues and costs of the product or service they

    deliver.

    It is like an independent business except it is part ofa larger organization (e.g. departmental stores of

    larger chains Wal Mart, restaurants, corporate

    hotels such as Hilton, Holiday Inn).

    The store manager would have responsibility for

    pricing, product selection, and promotion.

  • 8/4/2019 Measures of Performance Ch-3

    39/54

    Profit Centers (continued)

    Cost for these units vary depending on ability to

    control labor, waste, and hours.

    Revenues also will vary depending on the units

    service level, location, etc.

    In other words, local discretion would affect

    revenues and costs.

    Investments and some costs (e.g. centralizedpurchasing).

    Therefore, profits represent a broader index of

    both corporate and local decisions.

  • 8/4/2019 Measures of Performance Ch-3

    40/54

    Profit Centers (continued)

    If performance is poor, it may reflect poor

    conditions that no one in the organization could

    control as well as poor local conditions.

    For this reason, organizations should not evaluateperformance only based on costs and profits, but

    Perform detailed evaluations that include quality,

    material use, labor use, and service measures thatthe local unit can control.

  • 8/4/2019 Measures of Performance Ch-3

    41/54

    Investment Centers

    Responsibility centers whose managers and

    employees control revenues, costs, and the level of

    investment.

    It is also like an independent business (commonwhen an organization acquires another organization

    e.g. Sears financial centers).

  • 8/4/2019 Measures of Performance Ch-3

    42/54

    Administrative Centers (support centers)

    One of the most difficult to evaluate because

    neither the input nor the output is easy to measure

    (e.g. accounting services, marketing), and

    Linking units input and output to organizationalobjectives.

    But, with a little careful approach, the costs of such

    centers can be reasonably computed.

    Since most of these centers are treated somewhat

    like cost centers, an approach based on costs would

    be helpful.

  • 8/4/2019 Measures of Performance Ch-3

    43/54

    A simple summary of the

    responsibility centers

    Revenue CenterOutput measured in

    monetary terms

    Input measured inmonetary terms

    Output measured in

    monetary terms

    Output measured in

    monetary terms

    Expense/Cost Centers

    Profit Centers

    Investment Centers

  • 8/4/2019 Measures of Performance Ch-3

    44/54

    What did we learn from these

    control system illustrations?

    All responsibility centers evolve from the concept of

    controllability.

    Controllability principle states a manager should be assigned

    responsibility for the revenue, costs, or investment that he/shecould control.

    Revenues, costs, or investments that do not fall under a managers

    control must be excluded when evaluating the manager or his/her

    center.

    Problem with this concept: In most organizations, many revenues

    and costs are jointly earned or incurred and differentiation the

    controllable from the uncontrollable is difficult.

  • 8/4/2019 Measures of Performance Ch-3

    45/54

    An alternative to Controllability

    Some argue that performance measures should be

    chosen to influence decision-making behavior.

    For example, if market prices for raw material is

    increasing, what can a manager do?

    Perhaps, enter into long term contract for fixed

    prices for raw materials.

    If electricity consumption cost is going up, find outhow consumption can be economized (better

    machines, lighting, reduce waste).

  • 8/4/2019 Measures of Performance Ch-3

    46/54

    MEASURES OF PERFORMANCE

  • 8/4/2019 Measures of Performance Ch-3

    47/54

    Measures of performance

    Financial measures

    Expenses incurred

    Revenuesearned

    profit

    ROI/ROCE

    EVA

    other

    Nonfinancial measures

    customers

    operations

    suppliers

    HR & safety

    Environment

  • 8/4/2019 Measures of Performance Ch-3

    48/54

    Financial measures of performance

    1 Expenses center measure the actual cost with standard cost

    2

    Revenues cannot measure effectively so performance of organization

    can be analyzed on the basis of regional performance

    3 Organizations established for only profit making

    4 Rate on capital employed=EBIT/cost of investment

    5 Economic value added =net operating after tax-economicvalue of

    assetsin place * weighted cost of capital

  • 8/4/2019 Measures of Performance Ch-3

    49/54

    Nonfinancial measures of performance

    Measures ofperformance

    Environment

    HR&safty

    OperationsCustomers

    Suppliers

  • 8/4/2019 Measures of Performance Ch-3

    50/54

    Monitoring and reporting results

    Monitoring is needed to analyse or review the

    progress of project or task of organisation

    Helps in getting information about techanical

    progress ,manpower deployment,financial

    expenditures,constraints,remedial actions,task

    completion,etc

  • 8/4/2019 Measures of Performance Ch-3

    51/54

    Need .?

    Helps in identifying the ,decision,actions for

    avoiding damages and losses

    Helps to find what actualy goes wrong,for better

    prevention

    Helps in determining the accountability for where

    goes wrong

  • 8/4/2019 Measures of Performance Ch-3

    52/54

    Requisites of good management system

    Long term and short term objectives

    Compilences to the all levels of mgt and user friendly

    Facts and figures

    Operations and accounting oriented

    Behavioral aspects

    Detail report

    Constant review of plans and schedules

    Review of reports yearly

  • 8/4/2019 Measures of Performance Ch-3

    53/54

    Management control &reporting system

    for Commertial banks

    Long run plan&stratagic

    control

    Operational

    controlsystem

    Performancebudgeting &

    controlsystem

  • 8/4/2019 Measures of Performance Ch-3

    54/54

    Is Anything in your brain..?