meeting new moef norms: presentation title ( arial,...
TRANSCRIPT
International Seminar
On
Environmental compliances in TPPs– Issues and challenges30th January 2017
�Message Box ( Arial, Font size 18 Bold)
Presentation Title ( Arial, Font size 28 )
Date, Venue, etc..( Arial, Font size 18 )
Meeting New MOEF Norms:
Technological & Implementation Challenges for Utilities
Ramkrishna Gadre
CP Tiwari
Content
� About Tata Power Company
� Leader in Technology adoption
� MoEF Norms: Present and Revised
� Challenges in Compliance to Specific water consumption Norm and Conversion of OTC to RTC
System
� Challenges in Implementation of ZLD
� SPM abatement technologies and Implementation challenges
�Message Box ( Arial, Font size 18 Bold)
� SPM abatement technologies and Implementation challenges
� FGD Technologies and Implementation challenges
� De- NOx Technologies and Implementation challenges
� Estimated Capital Expenditure and Time Required
� Impact on O&M Cost
� Summary – Technological & Implementation Challenges
India’s largest integrated Power Company 2
About Tata Power Company
� India’s largest integrated power company with presence across the entire value chain - fuel, fuel
logistics, generation, transmission, distribution and power trading
� Founded in 1906 to supply power to Mumbai
» First hydro plant commissioned in 1915
» Set up thermal power plants in Mumbai in 1960s
� Current installed generation capacity is in excess of 10,500 MW including Thermal (Coal, Gas,
WHRSG) , hydro, wind, solar etc.
�Message Box ( Arial, Font size 18 Bold)
� Out of the above coal based thermal generation capacity is about 6300 MW (Using Imported and
domestic coal)
India’s largest integrated Power Company 3
First Flue Gas
First 800 MW
supercitical thermal unit
Largest Wind Turbine
Generator 2 MW (Visapur)
Largest single location
photovoltaic installation
3 MW (Mulshi)
First 25 MW
solar power
plant in India
5 y
ea
rs
Leader in technology adoption
First UMPP (4000MW) using super
critical technology
�Message Box ( Arial, Font size 18 Bold)
First
150 MW
thermal
unit
First
500 MW
thermal
unit
First
gas
insulated
switch
gear
Computerized
grid control &
energy
management
system
220 kV transmission
lines in four circuit
towers
220 kV
Cable
Transmission
Network
First Flue Gas
De-sulphurization
plant in India using
Seawater
First to Introduce SCADA
and Fibre Optic ground wire
communication
First pump storage unit
in the country of 150 MW
Capacity
45
ye
ars
4
MoEF Norms: Present and Revised
Plant / Unit Year of
Commissioning
Parameters Present Norms
(mg/Nm3)
Revised Norms
(mg/Nm3)
CGPL (Coastal Gujarat
Power Limited) – 5x 800
MW
2012 and 2013 SPM 50 50
NOX Not Specified 300
SOX Not Specified 200
Trombay Unit 5 – 500 MW 1984 SPM 150 100
NOX Not Specified 600
SOX * 200
�Message Box ( Arial, Font size 18 Bold)
SOX * 200
Trombay Unit 8 – 250 MW 2009 SPM 100 50
NOX Not Specified 300
SOX * 600
Maithon Power Limited –
2 x 525 MW
U1-2011
U2-2012
SPM 100 50
NOX Not Specified 300
SOX Not Specified 200
* Trombay station has a limit of 24 TPD of SO2.
5
Plant / Unit Year of
Commissioning
Parameters Present Norms
(mg/Nm3)
Revised Norms
(mg/Nm3)
Jojobera Unit 1 to 3 –
1x 67.5 and 2x 120 MW
U1-1996
U2-2000
U3- 2001
SPM 75 100
NOX Not Specified 600
SOX Not Specified 600
Jojobera Unit 4 and 5-
2 x 120 MW
U4-2005
U5- 2011
SPM 50 50
NOX Not Specified 300
MoEF Norms: Present and Revised for TPTCL units (Contd.)
�Message Box ( Arial, Font size 18 Bold)
2 x 120 MW U5- 2011NOX Not Specified 300
SOX Not Specified 600
All Operating Units All units
commissioned
before Dec 2016
Sp. Water
(m3/MWh)
Not Specified 3.5
Cooling Tower Not Specified Mandatory
6
Impacts of new MoEF Norms
Compliance to Specific water consumption
Implementation of Cooling tower
(Conversion from Once through cooling (OTC) to Recirculation Type Cooling (RTC))
Zero Liquid Discharge (ZLD) compliance
�Message Box ( Arial, Font size 18 Bold)
SPM abatement technology
Implementation of Flue Gas De-sulphurisation unit
(De- SOx technology)
De- NOx technology
(Implementation of SCR/ SNCR)
7
Challenges in Compliance to
Specific water consumption Norm and
�Message Box ( Arial, Font size 18 Bold)
Specific water consumption Norm and
Conversion of OTC to RTC System
8
� New MoEF norm doesn’t differentiate between raw and seawater while indicating norm restricting
the specific water consumption of the TPP
� Compliance to water consumption norm would be possible only for raw water based inland power
plants
� In coastal power plant based on seawater once through cooling (OTC) system and SWFGD, the
water requirement would be very high compared to latest norm of 3.5 and 2.5 cum / MWh
� In a typical 500 MW unit employing seawater based OTCS and SWFGD, estimated specific water
consumption will be as below:
Challenges - Compliance to Sp. Water Consumption Norm
�Message Box ( Arial, Font size 18 Bold)
Sr.
No
Consumers (m3/h)
1 Circulating water system 66000
2 Service water 200
3 Potable water 10
4 De-mineralized water 60
5 Total 66270
6 Intake quantity per MW (m3/ MWh) Approx. 132
9
� The typical water consumption for coastal thermal power plant using seawater for once through
cooling and SW FGD would range between 130 cum/MWh and 145 cum/MWh as against the norms
of 3.5 cum/MWh
� The probable options for these plants to reduce the water consumption up to normative levels can
be as follows:
� Option-1: Conversion of existing OTC system to sea water based RTC system for condenser
cooling + sea water FGD [OTC to Sea Water RTC + Sea Water FGD]
� Option-2: Conversion of existing OTC system to sea water based RTC system for condenser
Challenges - Compliance to Sp. Water Consumption Norm (Contd.)
�Message Box ( Arial, Font size 18 Bold)
� Option-2: Conversion of existing OTC system to sea water based RTC system for condenser
cooling + lime / limestone based fresh water FGD [OTC to Sea Water RTC + Lime / Lime Stone
FGD]
� Option-3: Conversion of existing OTC system to fresh water based RTC system for condenser
cooling + lime/limestone based fresh water FGD [OTC to Fresh Water RTC + Lime / Lime Stone
FGD]
10
� Post conversion to cooling tower based RCT system, seawater will be required CT Make-Up
� Seawater will be required for FGD System for scrubber and dilution requirement
� Cycle of Concentration (COC) of Seawater based RCT System will be 1.3 to 1.5 due to seawater
quality limitations (High TDS and TSS/Turbidity).
� As a result, specific water consumption remains above 50 cum/MWh (including Seawater
requirement for CT Make up and SW FGD)
� Due to make up water requirement of seawater based RCT System & FGD system, specific water
Option-1: OTC to Sea Water RTC + Sea Water FGD
�Message Box ( Arial, Font size 18 Bold)
� Due to make up water requirement of seawater based RCT System & FGD system, specific water
consumption is much above the stipulated figure of 3.5 m3/MWh
11
In option-1, it is not possible to restrict the specific Water consumption up to
3.5 m3/ MWh
Option-2: OTC to Sea Water RTC + Lime / Lime Stone FGD
� In case OTC system is converted to RTC system, seawater for FGD will have to be sourced separately
(almost 60% to 65% of current cooling water requirement)
� Due to large seawater requirement for seawater based FGD, it may be explored to replace existing
SWFGD with limestone based FGD system that requires comparatively less water
� Conversion of SW FGD into the lime based FGD would need additional space which would be difficult
in brownfield project
� Lime based FGD would need higher O&M costs towards sourcing of feedstock (limestone) and
operational costs for Limestone/gypsum handling system, limestone sizing, slurry preparation,
�Message Box ( Arial, Font size 18 Bold)
operational costs for Limestone/gypsum handling system, limestone sizing, slurry preparation,
gypsum dewatering/disposal, waste water treatment etc.
� Due to seawater based cooling tower (RTC system), the specific water consumption shall still be
much higher than specific water norms.
12
In option-2 also, it is not possible to restrict the specific Water consumption
up to 3.5 m3/ MWh
Option-3: OTC to Fresh Water RTC + Lime / Lime Stone FGD
� Fresh water requirement for typical 500 MW unit for Option-3 will be as under:
Sr No Consumers Consumption for 500 MW unit (m3/h)
1 Cooling tower make up 1395
2 Limestone FGD Cooling tower blow-down
3 Service water 200
4 Potable water 10
�Message Box ( Arial, Font size 18 Bold)
� As hypothetical scenario, With fresh water based cooling towers and limestone based FGD,
the specific water consumption for typical 500 MW unit may be restricted to 3.5 m3/MWh.
� However there are several technical challenges /constraints which needs consideration for
this option
5 De-mineralized water 60
6 Total 1665
7 Intake specific water quantity 3.33(m3/MWh)
13
� Conversion of Seawater based CW system into fresh water based RTC system would require
additional fresh water to be sourced
� In case of coastal plants with water scarcity, fresh water for CW requirement would have to be
generated through seawater desalination plant
� Desalination plant and lime/limestone based FGD shall also require additional land, infrastructure,
increased aux. power consumption and additional CAPEX+OPEX.
� Layout constraints: Layout study in existing plants has revealed that installation of desalination plant
+ Cooling tower + Limestone FGD installation in brownfield projects would be highly unfeasible.
Option-3: OTC to Fresh Water RTC + Lime / Lime Stone FGD (Contd.)
�Message Box ( Arial, Font size 18 Bold)
+ Cooling tower + Limestone FGD installation in brownfield projects would be highly unfeasible.
14
In view of all the above limitations, option-3 seems to be challenging
implementation especially in brownfield plants
� Conversion of existing OCT to RCT shall need major
modifications like:
• CW piping modifications/ replacement
• Condenser modifications/ replacement
• CW pumps modification/ replacement
• Augmentation of electrical power supply due to
increased Aux. power consumption
Difficulties in Conversion of OTC to RCT system
�Message Box ( Arial, Font size 18 Bold)
� Layout and Space constraints in installing Cooling tower &
associated system
� Cooling tower implementation feasibility study at one of
our coastal plant revealed that the current space is
insufficient for locating cooling tower. Cooling tower
installation shall need reclamation of marshy land covered
with mangroves which would not be environment friendly
15
Conversion of OTC to RCT System in existing Coastal Plant is not viable due to above
reasons
Challenges in Implementation of ZLD
(Zero Liquid Discharge)
�Message Box ( Arial, Font size 18 Bold)
(Zero Liquid Discharge)
16
� Plant uses raw water for various purpose such as cooling water, service water, potable water etc
� Plant generates different types of effluent water having different types / concentration of
contaminants, variations in flow rates, different frequency of generation of effluents etc.
� The zero liquid discharge condition (ZLD) for thermal power plant would need to recycle and
reutilize these different effluents on continuous basis.
� It is necessary to consider the different scenarios of operating conditions such as:
• Monsoon/ non-monsoon condition,
• Wet/ dry mode of ash disposal,
Challenges in implementing ZLD in TPP
�Message Box ( Arial, Font size 18 Bold)
• Wet/ dry mode of ash disposal,
• Variations in water requirement for coal handling,
• Water requirement for horticulture
• Effluent utilization opportunities
� Depending on the effluent water balance, the treatment scheme will have to be designed for
treating of high TDS complex waste priority wise
� The high recovery treatment plant is one such good option (>95% recovery plant)
17
SPM abatement technologies and Implementation Challenges
�Message Box ( Arial, Font size 18 Bold)18
Suspended Particulate Matter and its Challenges
� Options available for retrofitting of ESP to meet new norms
� Installing additional fields in the upstream/ downstream of ESP
� Increasing the height of ESP.
� Addition of pass parallel to existing ESP
� Challenges includes
� Layout constrain in addition of new field in the upstream/downstream of existing ESP.
� Replacement of ID fan may be required to suit the higher pressure drop across New ESP.
�Message Box ( Arial, Font size 18 Bold)
� Increase in height of ESP may require re-design of existing structure and foundation. The
existing foundation details may not be available.
� Space constraint for addition of New Pass.
19
FGD Technologies and implementation Challenges
�Message Box ( Arial, Font size 18 Bold)
FGD Technologies and implementation Challenges
20
Overview of all different FGD technologies
� Wet FGD
Uses Aqeous Limestone (Ca(OH)2) in slurry form
Dominantly used in Non- coastal power plants
� Dry FGD
Uses Quick Lime (CaO) in dry powdered form
Due to dry waste handling issues not much in use nowadays
� Sea water based FGD
Makes use of Sea water, Best suited for coastal power plants
�Message Box ( Arial, Font size 18 Bold)
Makes use of Sea water, Best suited for coastal power plants
� FBC Boiler
Lime is mixed with bed material and helps to absorb sulphur in furnace
21
Wet Limestone based Flue gas Desulphurization
�Message Box ( Arial, Font size 18 Bold)22
Difficulties in Installation of Wet Limestone FGD:
� Area within existing & Layout Constraints: Substantial footprint required for facilities like
limestone handling/storage, gypsum handling/storage, slurry preparation system, gypsum
dewatering system, waste water treatment plant etc. Absorber tower and GGH need space close
to chimney which becomes difficult if no sufficient space is provided in original layout.
� Sourcing and Logistics of Limestone: The plant would need access to the limestone on continuous
basis for the operation of FGD. The same may be constrained in many areas due to logistical issues
/ availability issues (For 1000 MW limestone requirement would be approx. 300 TPD)
� Disposal of gypsum: Huge quantity of Gypsum will be generated on a daily basis that would need
large storage pond and evacuation facility (For 1000 MW Gypsum generated daily would be
�Message Box ( Arial, Font size 18 Bold)
large storage pond and evacuation facility (For 1000 MW Gypsum generated daily would be
approx. 550-600 TPD)
� Waste water treatment: The waste water from limestone FGD would require the treatment
system to effectively treat the effluent and maintain ZLD for plant.
� Increase in Aux. power requirement (approx. 1.5%) and may need major augmentation in
electrical power supply system to meet this Aux power requirement
� Increased OPEX: The plant OPEX will increase substantially due to increased costs towards
limestone sourcing etc. (Approx. 40 crs. per annum. for 1000 MW plant).
23
Dry Lime based Flue gas Desulphurization
�Message Box ( Arial, Font size 18 Bold)24
Difficulties in installation of Dry Lime based FGD
� Area within existing layout: Dry Lime FGD faces similar issue of space availability in existing plant
layout especially older plants where sufficient space not provided in original layout.
� Based on the recent reports, Generation capacity of around 90 GW (430 units) is facing problem
due to non-availability of space for FGD.
� Sourcing and logistics of lime: The sourcing of lime will be issue in many areas.
� Byproduct utilization will be challenge
�Message Box ( Arial, Font size 18 Bold)
� High cost of reagent: Lime is costlier than Limestone, hence usage may be limited to smaller plant
capacities only.
� Increase in Aux. power requirement (approx. 0.5 to 1%) and may need major augmentation in
electrical power supply system to meet this Aux power requirement
25
Seawater based Flue gas Desulphurization (SWFGD)
�Message Box ( Arial, Font size 18 Bold)26
� Sea water by nature is alkaline with pH around 8.0 to 8.3. It contains an excess of calcium & sodium carbonates in solution. Theses components gives seawater a substantial capacity to absorb and neutralize SO2from flue gases.
� Only Seawater and air is used in the process, no chemicals/ special materials required
� No secondary waste products generation and hence no disposal issues
� The FGD outlet seawater is treated (dilution/ aeration) before discharge so as to meet the general effluent discharge norms.
Sea Water based FGD Technology
�Message Box ( Arial, Font size 18 Bold)
� The absorbed SO2 is transferred into sulphate ions, which is natural constituent of sea water for marine environment.
� The acidic nature of the scrubber water is mainly because of absorption of CO2 and SO2. On aeration the dissolved CO2 escapes out. This together with oxidation of S03 and HC03 brings back the pH & O2 of the scrubber water very close to its original value.
27
Challenges in installation of new SWFGD
� Area within existing layout: The installation of seawater FGD needs substantial footprint for
scrubber tower and auxiliary systems, seawater supply and seawater treatment scheme etc.
� Sourcing of seawater: Seawater for FGD requirement is usually about 20-25% of total CW flow
rate of the unit. In case of OTC system based on seawater it would be possible to tap it from CW
outlet by suitable means.
� It will be furthermore difficult to source seawater in case plant switches to seawater based RTC
system. The same may require separate FGD seawater pumping scheme.
� Treatment of FGD outlet seawater: The seawater treatment needs elaborate system for dilution
and aeration. Construction of the dilution and aeration basin alongside the existing outfall
�Message Box ( Arial, Font size 18 Bold)
and aeration. Construction of the dilution and aeration basin alongside the existing outfall
channel/ seal well and its connection would be challenging task.
� In case of seawater based RTC system, the seawater for dilution will not be available and the
process may need chemical dosing for pH correction.
� Variations in requirement of scrubbing water, Dilution and Aeration scheme depending on the
technology provider makes it difficult to plan the scheme/layout/costing in advance prior to
order finalisation
28
� Flue gas duct design:
• Difficulty in duct modifications in older plants including GGH inlet / outlet ducting
� Design of dilution basin/aeration basin and it’s interconnection with existing CW channel/ seal
well in SWFGD:
• It may require the temporary diversion of the CW outfall channel
• CFD modelling/ physical modelling study would be required for hydraulic design
� Outage requirement: Implementation of FGD would require approx. 1 to 4 months outage
Other technological challenges in implementing FGD
�Message Box ( Arial, Font size 18 Bold)
� Outage requirement: Implementation of FGD would require approx. 1 to 4 months outage
� Chimney lining of stack post FGD-
• To avoid the corrosion at lower flue gas temperature chimney shall require the acid proof
lining
• Lining activity may need longer outage (> 3 to 4 months)
� Vendor specific changes in the seawater requirement for scrubbing and dilution makes it
difficult to plan the scheme/layout/ Overall Project Cost estimate prior to bidding
29
De- NOx Technologies and Implementation Challenges
�Message Box ( Arial, Font size 18 Bold)
De- NOx Technologies and Implementation Challenges
30
NOx Generation & Available De-NOx Technologies
NOx Type Fuel NOx Thermax NOx
Source: NOx formed from Nitrogen in
the Fuel.
NOx formed from N2 in the
Combustion Air.
Formation Sensitive to: • Oxygen Availability
• Fuel Nitrogen Content
• Kinetics
• Furnace Temperature
• Oxygen Availability
�Message Box ( Arial, Font size 18 Bold)
Proportion 60% - 80 % 20% – 40 %
Technologies available for NOx abatement:
• Combustion Technology
• SNCR (Selective Non Catalytic Reduction)
• SCR (Selective Catalytic Reduction)
Combustion Technology
� Type of Combustion technologies:
� Low-NOx Burners (LNB):
� Better air and fuel mixture
� Improves staged combustion process.
� Optimize air requirement during primary combustion of coal.
�Message Box ( Arial, Font size 18 Bold)
Optimize air requirement during primary combustion of coal.
� Over Fire Air (OFA) / Seperated Over Fire Air (SOFA):
� Better air staging.
� Approx. 70% through LNB and 30% through OFA / SOFA.
� Expected reduction in NOx level < 20%.
Combustion Technology (Contd.)
�Message Box ( Arial, Font size 18 Bold)
Typical Scheme of Windbox Arrangement for Low NOx
Challenges in Combustion Technology
� Challenges:
� Modification to existing windbox/ burner arrangement.
� Modification to the existing air duct / structure to accomodate SOFA arrangement.
� Shut down of approx. 6 to 14 weeks depending on extent of work involved.
� Impact on boiler efficiency.
�Message Box ( Arial, Font size 18 Bold)
Selective Non Catalytic Reduction (SNCR)
� Selective Non Catalytic Reduction:
� Introducing reagent at appropriate section of furnace where flue gas temperature is
the range of 850 to 11000C.
� Injection ports provided either by multiple injectors or by using retractable lances
with multiple nozzles.
� Injection rate is controlled through each nozzle w.r.t boiler load to minimize reagent
�Message Box ( Arial, Font size 18 Bold)
� Injection rate is controlled through each nozzle w.r.t boiler load to minimize reagent
slip.
� Mixing of reagent either with water or compressed air.
� Expected reduction in NOx level < 50% max.
Selective Non Catalytic Reduction (Contd.)
�Message Box ( Arial, Font size 18 Bold)
Typical Scheme of Selective Non-Catalytic Reduction
Challenges in SNCR Technology
� Challenges:
� Approx. 4 to 8 weeks of shut down.
� Ammonia slip to be kept minimum (less than 10 ppm).
� Ammonia storage and handling and space requirement.
� Provenness of OEMs in Indian context and for bigger units
�Message Box ( Arial, Font size 18 Bold)
� Selective Catalytic Reduction (SCR):
� Uses catalyst and hence installed at low temperature zone of furnace
� Temperature required is in the range of 250 to 4000C.
� Located between economizer and air pre heater.
� Injection of Aqueous ammonia / Anhydrous ammonia / Urea into hot flue gas through
injection grid.
Selective Catalytic Reduction (SCR)
�Message Box ( Arial, Font size 18 Bold)
� Mixture passes through a catalyst surface where the NOx is converted into nitrogen
and water.
� NOx reduction efficiency shall be from 50% to 95%.
Selective Catalytic Reduction (SCR) (Contd.)
�Message Box ( Arial, Font size 18 Bold)
Typical Scheme of Selective Catalytic Reduction System
Challenges in SCR Technology (Contd.)
� Challenges:
� Catalyst:
� Use of metals such as Molybdenum, Vanadium, Tungsten etc. in catalyst. Hence
this is costly alternative.
� Catalyst designs for low ash coal used in countries abroad are well established.
Use of these catalyst for high ash containing Indian coal are to be proven.
�Message Box ( Arial, Font size 18 Bold)
� Cyclone technology proposed by OEMs needs validation.
� Expected life of catalyst is max 3 years. Availability and regeneration facility of
catalyst on long term after first instillation is concern.
� Disposal of catalyst is a challenge. Presently there is no guideline for disposal.
� Auxiliary Power:
� Introduction of catalyst increases pressure drop in fuel gas path.
� Increase ID fan loading and auxiliary power consumption of unit. In some cases
replacement of ID fans may be required.
� Increase in auxiliary power shall be 0.5 to 0.7%.
� Layout Requirement:
Challenges in SCR Technology (Contd.)
�Message Box ( Arial, Font size 18 Bold)
� Space requirement to accommodate reactor in the existing layout.
� Modification in the existing duct.
� Support and strengthening of existing boiler structures.
� Non availability of data for existing plant for layout, foundation details etc.
� Effect on Performance:
� Ammonia bisulphate formation lead to air preheater fouling which may reduce the
air preheater effectiveness.
� Cost and Schedule:
� Structural design cost due to catalyst weight and reactor span is considerable.
� The cost and schedule of implementation shall be reconfirmed.
� Provenness:
� Provenness of OEMs in Indian context.
Challenges in SCR Technology (Contd.)
�Message Box ( Arial, Font size 18 Bold)
� Challenges for use of reagents:
� Anhydrous Ammonia: Harmful for biological life and difficult to handle.
� Ammonia solution (19 to 25% in water): Handling cost due to dilution.
� Urea:
� Available in India is a challenge and needs to be imported.
� Requires elaborate heating arrangements for tank, pipe lines etc. for handling
Challenges in SCR Technology (Contd.)
�Message Box ( Arial, Font size 18 Bold)
� Requires elaborate heating arrangements for tank, pipe lines etc. for handling
urea solution.
� Handling of Ammonia, Storage within existing layout needs detailed analysis
�Message Box ( Arial, Font size 18 Bold)
Estimated Capital Expenditure and Time Required
Installation of pollution control equipment is expected to have an avg impact
of 20-40 paise per unit of electricity
Additional Fixed
Cost (e) (Rs./kWh)
0.455 yrs
Pollutant Technology Analyst Cost
Estimates (Rs
lakh/MW)
Impact on
Levelised
Tariff
(Rs / unit)
Construc
tion Time
(Months)
Downt
ime
(Days)
Particulate
Matter
ESP
Upgradation
10 – 15 0.02 – 0.03 3 – 6 20 –
30
SOx FGD 50 – 60 0.11 – 0.13 18 – 24 30 –
�Message Box ( Arial, Font size 18 Bold)
0.00 0.50
25 yrs
15 yrs
10 yrs
Bala
nce
Life
Source: Ministry of Environment and Forests, CSE (Proceedings of
Stakeholder Workshop, Sep 2016)10
0.28
0.23
0.20
SOx
Emission
FGD 50 – 60 0.11 – 0.13 18 – 24 30 –
90
NOx
Emission
SCR/SNCR 10 – 25 0.02 – 0.05 4 – 5 7 – 30
Water Cooling Tower
(Cap Ex for
Coastal Plants)
25 - 35 0.05 – 0.07
Total Inland Plants 70 – 100 0.15 – 0.22
Coastal Plants 95 – 135 0.20 – 0.30
�Message Box ( Arial, Font size 18 Bold)
Impact on the O&M Costs*
Parameter Plant A Plant B
Annual OPEX
(Rs. Crs)
Cost per unit
(Rs./kWh)
Annual OPEX
(Rs. Crs)
Cost per unit
(Rs./kWh)
CT & CW System 200 0.07 0 0.00
ESP 0 0.00 0 0.00
FGD 200 0.07 18.6 0.02
SCR / SNCR 800 0.27 190 0.16
�Message Box ( Arial, Font size 18 Bold)
*at 85% PLF
Typical Opex cost is expected between 25-33% (including Aux) to meet
the new environmental norm. (Based on analyst reports)
11
SCR / SNCR 800 0.27 190 0.16
� Total expenditure expected to implement environment norms will be over Rs 150,000 Cr.
� Fund Availability to fund capital expenditure at such a large scale is a issue
� In existing plants, it may not be possible to implement some of these new MoEF requirements like
RCT System for coastal plants, SCR & FGD System in smaller old units
� Implementation of new Norms will have impact of CAPEX & OPEX on consumer tariff
� Ability of vendors to execute projects nationally at such a large scale may be a challenge
� Short timeframe (Only 1 year left) to implement norms is a major challenge
Summary – Technological & Implementation Challenges
�Message Box ( Arial, Font size 18 Bold)
� Short timeframe (Only 1 year left) to implement norms is a major challenge
� Cost of equipments where demand could be more than supply and Indian manufacture content
is yet to be ascertained.
� Challenges of outages timings and management of grid.
Policy of incentive & penalty for complying & non complying Generator with
option of phasing out non complying plant after pre-defined time frame need to
be firmed-up
�Message Box ( Arial, Font size 18 Bold)
Website: www.tatapower.com
Email ID:[email protected]
Contact No: 022 67173809
47