Meeting Utility Step Voltage Change Requirements by Providing Precise Voltage Control for a PV Plant on a

Distribution Feeder

2014 IEEE PES Transmission & Distribution Conference & Exposition

Chicago, IL April 16, 2014 - 14TD0512

1

Page 2: Meeting Utility Step Voltage Change Requirements by

US Photovoltaic Solar Resources

2

Bagdad

Solar Plant

Page 3: Meeting Utility Step Voltage Change Requirements by

Area One-Line Diagram

3

Transmission System Serving Bagdad, Arizona

115 kV Bagdad

Copper

Mine

12.47 kV

Town of

Bagdad

Capacitor Banks

Bagdad

Substation

Radial 115 kV

Line Back to

APS Grid

Page 4: Meeting Utility Step Voltage Change Requirements by

Area One-Line Diagram

4

Addition of PV Solar Plant – 15 MW / 0 MVAR

Solar

Plant

15 MW

115 kV Bagdad

Copper

Mine

12.47 kV

Town of

Bagdad

Capacitor Banks

Bagdad

Substation

Radial 115 kV

Line Back to

APS Grid

Page 5: Meeting Utility Step Voltage Change Requirements by

Variations in Solar PV Plant Output

5

Actual Field Measurements - PV Solar Generation (MW)

Page 6: Meeting Utility Step Voltage Change Requirements by

Loadflow: The Voltage Problems

6

Voltage and Step Voltage Change vs. PV Generation

Page 7: Meeting Utility Step Voltage Change Requirements by

Voltage and

Current

Monitoring

Area One-Line Diagram

7

PV Solar Plant with the D-VAR® STATCOM Addition

2 MVA 4 MVA

CT

PT

D-VAR

System

Control

SGI

Smart Grid

Interface

PF Control

D-VAR

STATCOM

Line Flow –

Constant PF

2 MVAR

Reactor

Solar

Plant

15 MW

115 kV Bagdad

Copper

Mine

12.47 kV

Town of

Bagdad

Capacitor Banks

Bagdad

Substation

Radial 115 kV

Line Back to

APS Grid

Page 8: Meeting Utility Step Voltage Change Requirements by

Voltage and

Current

Monitoring

Area One-Line Diagram

8

PV Solar Plant with the D-VAR® STATCOM Addition

2 MVA 4 MVA

CT

PT

D-VAR

System

Control

SGI

Smart Grid

Interface

PF Control

D-VAR

STATCOM

Line Flow –

Constant PF

2 MVAR

Reactor

Solar

Plant

15 MW

115 kV Bagdad

Copper

Mine

12.47 kV

Town of

Bagdad

Capacitor Banks

Bagdad

Substation

Radial 115 kV

Line Back to

APS Grid

Page 9: Meeting Utility Step Voltage Change Requirements by

Area One-Line Diagram

9

PV Solar Plant with the D-VAR® STATCOM Addition

Page 10: Meeting Utility Step Voltage Change Requirements by

The STATCOM System Solution

10

D-VAR® MVAR Output and Feeder PF vs. PV Generation

Page 11: Meeting Utility Step Voltage Change Requirements by

Loadflow: The STATCOM System Solution

11

Voltage and Step Voltage Change vs. PV Generation

Page 12: Meeting Utility Step Voltage Change Requirements by

Stability: The Problem

12

Voltage and PV Generation vs. Time

Page 13: Meeting Utility Step Voltage Change Requirements by

Stability: The STATCOM System Solution

13

Voltage, PV Generation, and D-VAR® Output vs. Time

Page 14: Meeting Utility Step Voltage Change Requirements by

Variations in Solar PV Plant Output

14

Actual Field Measurements

Page 15: Meeting Utility Step Voltage Change Requirements by

Variations in Solar PV Plant Output

15

Actual Field Measurements

Page 16: Meeting Utility Step Voltage Change Requirements by

Satellite View – Google Maps

16

Mine Site Near Bagdad, Arizona

Town

Airport Bluff

& Solar

Farm Mine Tailings Pond

Page 17: Meeting Utility Step Voltage Change Requirements by

Satellite View – Google Maps

17

Bagdad PV Plant - Under Construction

• 135 acres, farm total

• 107 acres, PV arrays (behind the fence)

• Construction started Feb 2011

• Commercial Operation Date (COD): Dec 2011

Page 18: Meeting Utility Step Voltage Change Requirements by

Panoramic View

18

Bagdad PV Plant - Completed

Page 19: Meeting Utility Step Voltage Change Requirements by

Questions?

19

John A. Diaz de Leon II Senior Consulting Engineer

• 608-828-9179

• j

• w

[email protected]