memo - edgeedge.rit.edu/edge/p10008/public/concept design review.docx · web viewalter assembly...
TRANSCRIPT
KGCOE MSDI Concept Design ReviewP10008: ArcWorks Fill Vent Closure Line Improvement
Meeting Purpose:
Initial overview of project.
Validate customer needs and specifications
Review sonic weld test fixture concepts and confirm functionality
Review rubber cap assembly station fixture design and confirm functionality
Generate further ideas through review of materials
Materials Reviewed:
• Assembly Line Layout
Customer Needs Table
Engineering Specification Table
Pugh Concept Selection Process and Selected Concept
High Level System Diagram
Risk Analysis
Meeting Date: January 15, 2010 from 10:30AM to 12:00PM room 09-1515
Meeting Timeline
Start Time Discussion Topics
10:30 Project introduction
10:35 Overview of Layout
10:40 Initial Observations
10:45 Customer Needs Table
10:50 Engineering Specification Table
11:00 Preliminary Concepts for Leak Test Station
11:05 Pugh Concept Selection for Leak Test Station
11:10 Air Flow Diagrams for Finalists
11:15 Risk Assessment of Finalists
11:20 Discussion of Finalists
KGCOE MSD Page 1 of 15 Technical Review
Meeting Timeline
Start Time Discussion Topics
11:30 Pugh Concept Selection for Rubber Cap Assembly
11:35 Hand Tool Concept and Risks
11:40 Discussion of Concept
11:50 Project Risks
11:55 Project Gantt Chart
Senior Design Project Data Sheet
Project # Project Name Project Track Project Family10008 ArcWorks Cap Tube
AssemblyAssistive Devices Biomedical Systems and
Technology
Start Term Team Guide Faculty Consultant Doc. Revision20101 Dr. Marshall Sanjay Palit Orig.
Project Description:
Project Background:The Fill Vent Closure line is located at
ArcWorks of Monroe County. Currently, the assembly line has room for major improvement, primarily in the current testing of the integrity of the ultrasonic weld performed on site. The weld connects the threaded portion of the cap to the actual tube assembly. The current test utilizes a container filled with water and compressed air, this process is very time consuming and labor intensive. In addition, there are secondary assembly and packaging steps.
Problem Statement:The primary goal of this project is to
design a fixture that can consistently and accurately test the integrity of the weld on the cap assembly. This fixture will utilize the current resources available at ArcWorks, but will use a
simpler indicator for leaks than the current water set up. In addition, a device for applying rubber caps to the tube assembly that is easier to handle and more ergonomic is to be designed. Any other modifications to the assembly line process that increases efficiency and daily output will be implemented.
Objectives/ Scope:• Improve system that tests integrity of weld.• Ensure accurate and consistent testing.• Improve method of attaching rubber caps.• Expedite product assembly and packaging.• Alter assembly line process to improve
functionality.
Deliverables:• Design fixture to test weld integrity.• Design device to attach rubber caps.
KGCOE MSD Page 2 of 15 Technical Review
• Test fixture for reliability and troubleshooting.
• Documentation for improvements to process.
Expected Project Benefits:The primary goals of the deliverables are
to expedite the assembly line process of the cap tube assembly.
Core Team Members:• Adam Janicki• Andrew Lawlor• Chris Somers• John Zeffer
Strategy & Approach
Assumptions & Constraints
The team must construct a robust system to test the integrity of the weld, utilizing the current resources available at ArcWorks and remain within budget limits. The test system must be intuitive enough to use so that current operators need little or no training. In addition, team must maintain current space constraints.
Issues & Risks
• Design system to allow current operators to use fixture with little training
• System must have simple indications for pass/failure
Work Breakdown Structure
Current Layout
KGCOE MSD Page 3 of 15 Technical Review
Customer Needs
Customer Specifications Table
KGCOE MSD Page 4 of 15 Technical Review
KGCOE MSD Page 5 of 15 Technical Review
KGCOE MSDI Concept Design ReviewP10008: ArcWorks Fill Vent Closure Line ImprovementConcepts for Leak Test Station
KGCOE MSD Page 6 of 15 Technical Review
Single Fixture VacuumPress Tester
Lever Pressurizer
Double Fixture Vacuum
Threaded Pressure Fixture
Table Air Pressure Tester
KGCOE MSDI Concept Design ReviewP10008: ArcWorks Fill Vent Closure Line ImprovementRound 1
Round 2
KGCOE MSD Page 7 of 15 Technical Review
ConceptsA B
Lever PressurizerSelection Criteria
Water Pressure Test
Air Flow Diagrams
Press Tester Diagram
Single Fixture Vacuum Diagram
KGCOE MSD Page 8 of 15 Technical Review
3D Representation of the Press Tester and Single Fixture Vacuum
Press Tester Risks
ID Risk Item Effect Cause
Likelihood
Severity
Importance Action to Minimize Risk Owner
1Operator fails to place cap on fixture correctly
Air escapes from under cap, test would fail.
Deformation of top or improper instruction.
2 3 6 Grooves on fixture make improper placement difficult
Drew
2
Operator fails to keep cap on fixture for whole duration of test
The test may fail with gap between fixture and cap.
The force to hold cap on fixture is too strong.
2
3 6Test turns off since plate is no longer initiating the test and pressing button. John
3
Pressure of air is stronger than operator is able to press on fixture.
Possibility of cap coming off of fixture.
Air pressure is set to high or settings were changed. 1 3 3
Keep maximum air pressure limited with a dial on fixture. Adam
4
Leak is detected from operator pulling cap off prematurely. Test turns off.
Initiation is no longer achieved since the plate is not down. 3 1 3
Test will turn off since plate is no longer initiating the test and pressing button. Chris
5
Manufacturer changes pressure required to test cap.
Current air pressure is no longer adequate.
System was set to only one pressure. 2 3 6
Have dial on side of fixture to change test pressure. Drew
Single Fixture Vacuum Risk
KGCOE MSD Page 9 of 15 Technical Review
i Risk Item Effect Cause
Pugh Concept Selection for Rubber Cap Assembly
Round 1
Round 2
KGCOE MSD Page 10 of 15 Technical Review
ConceptsA B C
Selection Criteria
Hand Assembly
Vacuum Suction Assembly
Use of Hammer in assembly
DDrill Press Cap
Assembly
Hand Tool Concept and Risks
i Risk Item Effect Cause
Like
lihoo
d
Seve
rity
Impo
rtan
ce
Action to Minimize Risk
1
The handtool doesn't work
The output does not change
The rubber stoppers aren't going on the tubes
2 3 6
Make the design so that the handtool puts the rubber stoppers on each time
2
The collar pinches the operator
Injury to the operator
When collar is depressed on the handtool the operator's finger is pinched in the collar
2 2 4
Make the tool long enough for the operator's hand to fit properly on the tool and away from the moving piece
3
The rubber stopper doesn't fit in the designed collar
The stoppers cannot be placed on the tubes by the handtool
The rubber stoppers are different sizes 2 3 6
Make adaptable parts for each size rubber stopper
4
The handtool does not make the process faster than the previous method
The output does not improve
It is a slower process than manually placing each cap
1 3 3
Make sure the tool is a quicker solution to the capping process
KGCOE MSD Page 11 of 15 Technical Review
KGCOE MSDI Concept Design ReviewP10008: ArcWorks Fill Vent Closure Line Improvement
ID Risk Item Effect Cause
Like
lihoo
d
Seve
rity
Impo
rtan
ce Action to Minimize Risk Owner
1
Sensors fail to indicate leak in ultrasonic weld.
A bad part gets to customer.
Sensor is not accurate enough for scope of job. 2 2 4
Purchase sensors that are accurate and precise enough to catch any leaks that may occur in the ultrasonic welding process.
Chris
2
Parts for design do not come on time or are incorrect.
Causes delays in project time line subsequently causing tardiness of the project.
Supplier company making an error.
2 3 6
Call company and double check the order and status of the parts.
Drew
3
Customer changes specifications.
Project gets delayed due to new specifications.
Customers customer changes specifications. 2 2 4
Keep close connections with customer and create design that is flexible to many scenarios.
Drew
4
Design fails to complete customer specifications.
Project not implemented and project failed.
No close understanding of customer specifications of needs.
2 3 6
Keep contact with customer on all changes and design possibilities.
Drew
5
Gantt chart for project plan is incorrect.
Project gets behind and team fails to deliver project on time.
Team does not take time to make a detailed Gantt chart.
1 1 1
Meet as a team and spend time together ensuring a complete and thorough Gantt chart.
Team
6
Customer changes project timeline.
Project gets behind and team fails to deliver project on time.
Unknown customer changes
1 2 2
Stay in contact at all times with customer to ensure any changes will be known immediately.
Drew
7
Budget is cut. Design must be changed to accommodate a different set of parts.
Funding is unavailable at a certain time. 1 2 2
Keep in contact with guide to ensure budget stays steady.
Team
8
Team does not order items with a long lead-time at appropriate time.
Project gets behind. Not being detailed when ordering parts. 2 2 4
Have one team member be in charge and responsible for ordering parts to ensure the long lead-time parts are ordered on time.
John
9
Design does not work as originally intended.
Must re-design a fixture and still be under budget.
Tightens budget and can cause lateness in the project.
2 2 4
Team must do research and meet with company to thoroughly understand design concept.
Adam
10
Operators do not find design easy to
Failure on deliverables
Team not communicating 2 2 4
Meet with operators and supervisors to ensure
Team
KGCOE MSD Page 12 of 15 Technical Review
use. with operators to ensure good design.
they are involved in the design process.
12
Cup isn’t always secured while test is being conducted
Not a sufficient test could send a defective part to customer.
Design does not create a singular method to test product
2 2 4
Effectively design so that test can only be performed with a secure hold in place.
Chris
13
Pressure standards change
Design may become obsolete
Pressure needs to change due to testing standards
1 2 2Design the ability to change the pressure of the testing device
Chris
14
Product changes Design may become obsolete
Product needs to change due to industry standards
2 2 4Design the ability to change the interface of the testing device
Chris
15
Lots of custom parts General maintenance becomes too expensive
Design is over complicated 1 2 2
Make the design with common parts
Adam
16
The pass/fail indication is not simple enough
Operator is not sure what the device is telling them
Pass/fail indication is more complex than it needs to be 1 2 2
Keep the design a Boolean level of complexity
Adam
17
The total operation of test has too many steps
The total run time of the capping system increases
Operation adds more steps to the process
3 2 6Operation of system should be limited to 4 total steps
Team
18
The group’s ability to meet together
The team may fall behind deadlines
Group member’s schedules do not coincide appropriately
1 2 2
Make a set time beforehand to meet so that the team will not schedule something during that set time.
Drew
19
The device does not meet requirements
Customer cannot use device in process
Design/Build fails to meet requirements 2 2 4
Make sure design falls within requirements and build to match the design inside of the tolerance
John
20
Team falls behind schedule
Device is not finished before end of the spring quarter
The team does not meet and schedule well enough to complete job
1 2 2
Project manager makes sure schedules are set and deliverables are completed on, or ahead, of schedule
Drew
21
Device does not speed up overall process
The device acts more of a hindrance than a benefit for the customer
Device may have too many steps, be too complicated or just runs slowly
3 2 6
Make sure design of device will increase the production of the end product
Chris
22
Space is not utilized Device gets in the way of other steps in production
Device is oversized and takes more space than originally given
1 2 2
Design a device that is small enough to fit in an area predetermined by the customer
Adam
23
Need outside help to finish
Spend money for another company to finish device
Team is too far behind schedule
2 2 4 Plan accordingly so the team stays on track to complete the device by the 5th week of spring quarter
Drew
KGCOE MSD Page 13 of 15 Technical Review
KGCOE MSD Page 14 of 15 Technical Review
KGCOE MSDI Concept Design ReviewP10008: ArcWorks Fill Vent Closure Line Improvement
Project Gantt Chart for MSDI
KGCOE MSD Page 15 of 15 Technical Review