memorandum for the super charters inc
TRANSCRIPT
15TH INTERNATIONAL MARITIME LAW ARBITRATION MOOT JULY 2014
Team no. 13
ERASMUS UNIVERSITY ROTTERDAM
MEMORANDUM FOR THE SUPER CHARTERS INC.
IN THE MATTERS OF ARBITRATION BETWEEN:
Claimant Reliable Tankers Inc.
v.
Respondent Super Charters Inc.
Claimant
Super Charters Inc.
v. Respondent Reliable Tankers Inc.
COUNSEL
ALEXANDER J. BARENDREGT ♦ EVANGELIA PATRIKALAKI ♦
MARTA K. KOŁACZ ♦ NEDYALKO MINKOV ♦ SONJA VAN WIJK
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | ii
TABLE OF CONTENTS:
TABLE OF CONTENTS: .......................................................................................................... ii
LIST OF ABBREVIATIONS ...................................................................................................... iv
TABLE OF AUTHORITIES ....................................................................................................... vi
TABLE OF CASES .................................................................................................................. viii
INDEX OF LEGAL ACTS ......................................................................................................... xi
INDEX OF DOCUMENTS INVOKED ..................................................................................... xi
STATEMENT OF FACTS ......................................................................................................... 1
INTRODUCTORY REMARKS ON LEGAL ARGUMENTS AND APPLICABLE LAW .... 4
I. THE TRIBUNAL SHOULD FIND NO GENUINE MISNOMER IN COMMENCING
THE ARBITRATION PROCEEDINGS IN THE NAME OF THE RELIABLE TANKERS
INC. ............................................................................................................................................ 6
1. Bad faith should not be honored. .................................................................................... 6
II. THE TRIBUNAL SHOULD CONSIDER THE OWNER’S CLAIMS AS TIME
BARRED .................................................................................................................................... 6
1. Parties have the autonomy to agree about the time for commencement of the
arbitration. ............................................................................................................................... 6
III. THE TRIBUNAL SHOULD FIND A BREACH OF CONTRACTUAL
OBLIGATIONS COMMITED BY THE RELIABLE TANKERS INC. WHICH LED TO
THE SUBSEQUENT CANCELLATION OF THE CHARTER PARTY BY THE
CHARTERERS. ......................................................................................................................... 9
1. The Tribunal should find a breach of contractual obligations committed by the Reliable
Tankers Inc. which lead to the cancellation of the Charter Party by the Charterers. ............. 9
2. The Reliable Tankers Inc. were in breach of contractual obligations. ............................ 10
3. The cancellation of the Charter Party. ............................................................................ 11
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | iii
1. The Tribunal should regard the arrest of the Vessel as an unavoidable hindrance to the
fulfillment of the Charter Party for which the fault is to be borne by the Owners as a legal
successor of the Reliable Tankers Inc. ................................................................................. 13
IV. THE TRIBUNAL SHOULD FIND THAT THE FREIGHT STIPULATED IN THE
CONTRACT WAS NOT DUE AND PAYABLE AND THAT THE RELIABLE TANKERS
INC. ACTIONS LEAD TO SUBSEQUENT DAMAGES FOR THE CHARTERERS. ........ 14
1. Freight is not due and payable. ...................................................................................... 14
2. The claim for damages. ................................................................................................... 17
3.. Further claim for the set-off damages. ............................................................................. 18
V. REQUEST FOR RELIEF ................................................................................................. 18
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | iv
LIST OF ABBREVIATIONS
& And
§ Section
¶/¶¶ Paragraph/Paragraphs
Ad hoc For this
ASBATANKVOY
Charter Party
Association of Ship Brokers & Agents Tanker Voyage Charter
Party
C.A. Court of Appeal
Charterers The Super Charters Inc.
ed./eds. Editor/Editors
ETA Estimated Time of Arrival
Ibid. Ibidem (in the same place)
Laycan Laydays Cancelling
Memorandum Memorandum for the Super Charters Inc. submitted by the
Team of Erasmus School of Law, Rotterdam participating in
15th
International Maritime Law Arbitration Moot.
MT Metric ton
No. Number
Owners The Reliable Holdings Inc. acting as a legal successor of the
Reliable Tankers Inc.
p./pp. Page/ Pages
Recap The summary of the Charter Party
Vessel The Reliable Butterfly
Voyage The transport of crude oil at each of two terminals from the
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | v
loading port BlueLand, to Redland for bunkers and thereafter to
the discharge port IndigoLand.
Tribunal Panel consisting of the Chairperson (presiding arbitrator) and
Ms. Arbitrator 1 and Mr. Arbitrator 2
USD United States dollars
v. Versus; against
Vol. Volume
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | vi
TABLE OF AUTHORITIES
Books: Audley Sheppard,
English Arbitration Act (Chapter 23),
Part I, The Arbitral Proceedings, Section
34 [Procedural and evidential matters],
in: L. Mistelis (ed.),
Concise International Arbitration
[Kluwer Law International, 2010].
Referred to in: ¶ 21 of the
Memorandum
Clare Ambrose, Karen Maxwell,
The Arbitration Act 1996 - London Maritime
Arbitration,
[1st., LLP, 1996].
Referred to in: ¶ 25 of the
Memorandum
David St John Sutton, Judith Gill, Matthew
Gearing,
Russell on Arbitration,
[23rd., Sweet & Maxwell, 2007].
Referred to in: ¶ 27 of the
Memorandum
John F. Wilson,
Carriage of Goods by Sea,
[7th., Pearson, 2010].
Referred to in: ¶ 40 of the
Memorandum
Michael Mustill,
Commercial arbitration,
[2nd., Butterworths, 2001].
Referred to in: ¶19 of the
Memorandum
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | vii
Robert Merkin,
Arbitration Law,
[3rd., Informa Law, 2004].
Referred to in: ¶ 24, 28 of the
Memorandum
Stephen Girvin,
Carriage of Goods by Sea,
[2nd., Oxford University Press, 2011].
Referred to in: ¶ 40 of the
Memorandum
Articles
and
Rapports:
Andrew Tweeddale, Karen Tweeddale,
'Commencement of Arbitration and Time-
Bar Clauses',
[Arbitration, Vol. 75, No. 4, 2009].
Referred to in: ¶ 25 of the
Memorandum
Cavinder Bull,
‘Commencing Arbitration’,
in: Albert Jan van den Berg (ed),
‘International Arbitration: The Coming of a
New Age?’,
ICCA Congress Series, Volume 17 ,Kluwer
Law International, 2013.
Referred to in: ¶ 25 of the
Memorandum
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | viii
TABLE OF CASES
A Antaios Compania Naviera S.A. v. Salen
Rederierna A.B. (‘The Antaios’),
[1985] A.C. 191.
Referred to in: ¶ 40 of the
Memorandum
B
B. Richards, Devisee of John Richards, Deceased
v. Bluck,
136 E.R. 1319.
Referred to in: ¶ 40 of the
Memorandum
Blackgold Trading of Monrovia v. Almare S.p.A
Navigazione of Genoa, (‘The Almare Seconda’),
[1981] 2 Lloyd's Rep. 433.
Referred to in: ¶ 36 of the
Memorandum
C
Cholmondeley v. Clinton,
[1937] E.R. 527.
Referred to in: ¶ 39 of the
Memorandum
Colonial Bank (now bank of Boston Connecticut)
v. European Grain & Shipping Ltd.,
(‘The Dominique’),
[1989] 1 Lloyds Rep. 436.
Referred to in: ¶ 48 of the
Memorandum
D De Silvale v. Kendall,
[1815] 4 M & S 37.
Referred to in: ¶ 41 of the
Memorandum
G
Geogas S.A. v. Tranumo Gas Ltd.,
(‘The Baleares’),
[1993] 1 Lloyd's Rep. 215.
Referred to in: ¶ 34 of the
Memorandum
H
Harbour & General Works Ltd. v. Environment
Agency,
[1999] Adj.L.R. 02/19.
Referred to in: ¶ 23 of the
Memorandum
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | ix
Hume v. Rundell,
[1824] E.R. 311.
Referred to in: ¶ 40 of the
Memorandum
I
Investors Compensation Scheme Ltd. v. West
Bromwich Building Society,
[1998] 1 W.L.R. 896.
Referred to in: ¶ 39 of the
Memorandum
J James Reid and James Stewart v. William
Blackedon Fairbanks, Jonathan Crane Allison,
and David Allison,
138 E.R. 1371.
Referred to in: ¶ 40 of the
Memorandum
L Law Debenture Trust Corp. plc v. Elektrim
Finance B.V.,
[2005] EWHC 1412 (Ch), 2 All ER (Comm) 476.
Referred to in: ¶ 24 of the
Memorandum
Lazard Brothers & Company v. Midland
Bank Ltd.,
[1993] AC 289 [HL].
Referred to in: ¶ 27 of the
Memorandum
Lorna I Compania Naviera General S.A
v. Keramental Ltd.,
[1983] 1 Lloyds Rep. 373.
Referred to in: ¶ 41 of the
Memorandum
M
Mannai Investment Co Ltd. v. Eagle Star Life
Assurance Co. Ltd.,
[1997] A.C. 749.
Referred to in: ¶ 39 of the
Memorandum
Marbienes Compania Naviera S.A. v. Fervostaal
A.G., (‘The Democritos’),
[1976] 2 Lloyd's Rep. 149 (C.A.).
Referred to in: ¶ 30 of the
Memorandum
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | x
Maredelanto Compania Naviera S.A. v. Bergbau-
Handel G.m.b.H.,
[1970] 2 Lloyd's Rep. 43 (C.A.).
Referred to in: ¶ 33, 35 of the
Memorandum
Metalfer Corp. v. Pan Ocean Shipping Co. Ltd.,
[1998] 2 Lloyd’s Rep 632.
Referred to in: ¶ 26, 27 of the
Memorandum
Monroe Brothers, Ltd. v. Ryan,
[1935] 2 K.B. 28.
Referred to in: ¶ 36, 37 of the
Memorandum
P Pittalis v. Sherefettin,
[1986] 1 QB 868.
Referred to in: ¶ 24 of the
Memorandum
R Robertson v. French,
[1803] 102 ER 779.
Referred to in: ¶ 41 of the
Memorandum
S
SEB Trygg Holding A.B. v. Manches,
[2005] EWHC 35 Lloyd’s Rep 129 (Com).
Referred to in: ¶ 27 of the
Memorandum
Smith v. Lucas,
[1880-81] L.R. 18 Ch. D. 531.
Referred to in: ¶ 39 of the
Memorandum
Southland Frozen Meat & Produce Export Co.
Ltd. v. Nelson Bros Ltd.,
[1898] A.C. 442.
Referred to in: ¶ 40 of the
Memorandum
Strand Music Hall Co. Ltd.,
(1865) 55 ER 853.
Referred to in: ¶ 40 of the
Memorandum
W WJ Alan and Co Ltd. v. El Nasr Export and
Import Co.,
[1971] 1 Lloyd’s Rep 401.
Referred to in: ¶ 24 of the
Memorandum
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | xi
INDEX OF LEGAL ACTS
Arbitration Act
English Arbitration Act 1996 c. 23
Referred to in: ¶¶19,
23 of the
Memorandum
INDEX OF DOCUMENTS INVOKED
ASBATANKVOY form [the Charter Party] Referred to in: ¶¶ 18, 21, 23, 28, 29, 30,
32,33,34, 38, 39, 40, 42, 43, 44, 45, 46,
47, 49 of the Memorandum
Claim submission
of the Reliable Holdings Inc.
Referred to in:¶ 14 of the Memorandum
Combined claim submission
of the Super Charters Inc.
Referred to in:¶ 14 of the Memorandum
Correspondence
from the Super Charters Inc. to the Reliable
Tankers Inc. From 10 October 2011
Referred to in:¶ 21 of the Memorandum
Correspondence
from the Super Charters Inc. to the Reliable
Tankers Inc. from 19 November 2011
Referred to in:¶ 5 of the Memorandum
Correspondence
from the Reliable Tankers Inc. to the Super
Charters Inc. from 19 November 2011
Referred to in:¶ 6 of the Memorandum
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | xii
Correspondence
from the Reliable Tankers Inc. to the Super
Charters Inc. from 23 November 2011
Referred to in:¶ 9 of the Memorandum
Correspondence
from the Reliable Tankers Inc. to the Super
Charters Inc. from 25 November 2011
Referred to in:¶¶ 10, 29 of the
Memorandum
Correspondence
from the Reliable Tankers Inc. to the Super
Charters Inc. from 28 November 2011
Referred to in: ¶¶ 12, 13, 31 of the
Memorandum
Moot Problem Referred to in: ¶ 19 of the Memorandum
Newspaper Article concerning the merger of
the Reliable Tankers Inc. and Reliable
Holdings Inc. from 3 January 2012
Referred to in: ¶ 22 of the Memorandum
Notice of Appointment and Arbitration of the
Reliable Holdings Inc. from 28 January 2012
Referred to in: ¶¶ 14, 22, 27, of the
Memorandum
Notice of Appointment and Arbitration
of the Reliable Holdings Inc. from 24
February 2012
Referred to in:¶ 16 of the Memorandum
Notice of Appointment and Arbitration of the
Super Charters from 12 February 2012
Referred to in: ¶¶ 15, 28 of the
Memorandum
Notice of Cancellation of the Super Charters
from 27 November 2012
Referred to in:¶¶ 11, 31 of the
Memorandum
Reliable Tankers Inc. Internal Note from 23
November 2011
Referred to in:¶ 46 of the Memorandum
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | xiii
Spot Tanker Market Report Referred to in:¶ 35 of the Memorandum
Standard Terms of the Super Charters Inc. Referred to in:¶¶23, 24, 25, 28 of the
Memorandum
Standard Terms of the Reliable Tankers Inc. Referred to in:¶¶ 39, 40, 41, 44, 45 of
the Memorandum
The Super Charters Company Single Voyage
Charter Party Rider Clauses
Referred to in:¶ 29 of the Memorandum
Erasmus University Rotterdam Memorandum for the Charters Inc.
Page | 1
STATEMENT OF FACTS
1. Please note the following statements as a description of the course of the contractual
relationship between the Super Charters Inc. (hereafter: the Charterers) and the Reliable
Holdings Inc. (hereafter: the Owners) acting as a legal successor of the Reliable Tankers Inc.
The Charterers ask the Tribunal to see there are two referrals, where in the first one, wrongly
commenced on 28 January 2012, the Charterers are the Respondent, but in the second
commenced on 12 February 2012 the Charterers are acting as the Claimant. Regarding the
fact of the similarity of the claims in both disputes, in the following document the Charterers
will present combined submissions which are to be construed as appropriate in each referral.
2. On 1 October 2011, 22nd Century Broking (Intermediary) offered an agency in business
relation between the Charterers and the Reliable Tankers Inc.
3. Nonetheless, the Charterers and the Reliable Tankers Inc., due to the clear position and good
reputation of the latter, resigned from the agency offer on 10 October 2011. The Charterers
sent an invitation for tender concerning a ship able to load and transport bulk of crude oil
on two terminals in BlueLand going to IndigoLand (hereafter: the Voyage).
4. After the ongoing scrupulous negotiations, which lasted till middle of November, parties were
ready to enter the Charter Party. The Reliable Tankers Inc., after accepting the detailed
ETA provisions on 17 November 2011, sent a firm offer. There was also an exchange of
standard terms, although the Owners led to a common mistake by not correcting Clause 2.
The Charterers, from that point, did not accept the shape of the Clause 2 and based on parties
intention proved by the Owners’ message from that day.
5. On 19 November 2011, the Charterers made an amendment to the Charter Party, and asked
the Reliable Tankers Inc. for confirmation and circulation of the Charter Party for signatures
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 2
in due course. At the same time the Charterers asked about a certain captioned ship - Reliable
Butterfly (hereafter: the Vessel), which was the only one available.
6. The same day (19 November 2011) the Reliable Tankers Inc. recap the fixture of the Vessel.
In a separate message the Reliable Tankers Inc. confirmed and ensured the conditions of
the ETA and the laycan (5-6 December2011) and that the Vessel should sail by 8 December
2011 and finish the discharge by 10 January 2012 - so before shutting down the refinery
planned on 15 January 2012. The laycan was narrowed to 5 December 2011.
7. The Reliable Tankers Inc., did not inform the Charterers about the faith of the Vessel. News
about the arrest reached the Charterers on 22 November 2011 through back channels, and not
directly from the Reliable Tankers Inc. As a consequence this would mean that the Vessel
would not meet the laycan of 5 December 2011.
8. The Reliable Tankers Inc., despite the knowledge that not promising financial condition of
the company would be a reason of not releasing the Vessel from the arrest and not meeting
the laycan, wrongly assured on 23 November 2011 that the Vessel would be on time,
however, did not ensure the proper progress of the Voyage.
9. On 25 November 2011 it became clear that the Reliable Tankers Inc. are incapable of dealing
with the problem. The Reliable Tankers Inc. informed the Charterers that the Vessel was not
able to meet the laycan and that there was no possibility to point out new dates. Thereafter, far
from informing immediately, the Reliable Tankers Inc. also declared a revised ETA and a
new laycan for undetermined dates.
10. On 27 November 2011 the Charterers sent the Notice of Cancellation including clear refusal
of the revised ETA and the laycan. The Charterers filed a claim for damages, since the
Charter Party was breached.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 3
11. On 28 November 2011 the Reliable Tankers Inc. accepted cancellation of the Charter
Party but wrongly denied the fact of its breach. Furthermore, the Reliable Tankers Inc.
groundlessly invoked the clause concerning the relief from liability.
12. Due to negligence in appointing revised ETA and the laycan the Reliable Tankers Inc.
exposed the Charterers for financial loss regarding such market realities as higher prices of
ship charter. The Reliable Tankers Inc. claimed also outstanding freight, which was not due
at the moment of the breach. This because the Vessel never arrived in the port of loading.
13. On 28 November 2011 the Reliable Tankers Inc. placed also a new offer for replacing the
Vessel with a sister vessel. Unfortunately, the sister vessel would arrive a few days later than
the stated laycan. Therefore, Charterers were unable to accept this offer and were forced to fix
another vessel from another company.
14. On 28 January 2012 the Reliable Tankers Inc. sent the Notice of Appointment and
Arbitration concerning a breach of the Charter Party by the Charterers and referring the
current and future cases to arbitration in London. Mr. Smith was appointed as an arbitrator.
As it turned out later Reliable Tankers Inc. merged with the Owners in December 2011. The
merger was kept in secret and mislead a lot of investors.
15. Therefore, on 12 Febuary the Charterers considered commencing the arbitration as
invalid because of appointing a non-existent party. Mr. John was appointed as an
arbitrator to this referral. On the same date, the Charterers addressed their Notice of
Appointment and Arbitration to the Owners as a legal successor of the Reliable Tankers
Inc. which included referral to arbitration in London as a result of breach of Charter Party.
Mr. John was again appointed as an arbitrator. The Owners were also informed about the
time-barred claims.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 4
16. Nevertheless, the Owners in the mail from 24 February 2012 clumsily rebutted arguments
about invalidly commenced arbitration by invoking results of an universal succession or
alternatively a clear misnomer in their Notice of Appointment and Arbitration. Mr. Smith
was again appointed as an arbitrator. However, their action broke the time bar in Clause 4 of
the Super Charters’ standard terms and in any case was burden with the bad faith.
17. On 14 March 2012’ the Owners filed the Claim Submissions for second referral because of
which the Charterers submit combined submissions.
INTRODUCTORY REMARKS ON LEGAL ARGUMENTS AND APPLICABLE LAW
18. The Charterers and the Reliable Tankers Inc. entered into a Charter Party concerning the
Vessel able to load and transport bulk of crude oil on 19 November 2011, on an amended
ASBATANKVOY form (hereinafter: the Charter Party) subject of it was the Vessel owned by
Reliable Tankers Inc., flying a Bahamas’ flag and registered at the Port of Nassau, carrying
out the transportation of 260,000 MT of crude oil from BlueLand to IndigoLand, with the
stipulated freight respective to the cargo transported. The prearranged laycan was stipulated
for 5/6 December with the precondition for further specification of the exact date.
19. The parties have agreed in the Charter Party that any dispute of whatsoever nature, arising out
of or relating to their Charter Party, shall be put to ad hoc arbitration in London, United
Kingdom, thus agreeing to the law of England as the lex arbitri.1 Furthermore, the parties
agreed on the applicability of the English Arbitration Act 1996 (hereinafter: the Arbitration
Act) as far as procedure before the Tribunal is concerned. For that reason, when discussing
the conduct of the Parties, a reference to general principles of the Arbitration Act itself and to
general principles of the law is made, bearing in mind the international context of arbitration.2
1 ASBATANKVOY, Part II - clause 24.
2 Michael Mustill, Commercial arbitration, [2nd., Butterworths, 2001] pp. 66-82.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 5
20. The Charterers submit the following claims and arguments in their support, to be considered
by the present Tribunal:
Commencing the arbitration proceedings in the name of Reliable Tankers Inc. was a
fundamental error,
The Reliable Tankers Inc. are liable for the breach of contractual relation which led to
the cancellation of the Charter Party,
The Owners’ claims are time-barred,
The Owner bears the responsibility of the arrest of the Vessel,
The freight stipulated in the Charter Party was not due and payable,
The Owners’ actions lead to subsequent damages for the Charterers.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 6
I. THE TRIBUNAL SHOULD FIND NO GENUINE MISNOMER IN
COMMENCING THE ARBITRATION PROCEEDINGS IN THE NAME OF
THE RELIABLE TANKERS INC.
1. Bad faith should not be honored.
21. It should be held that the Owners as a legal successors of the Reliable Tankers Inc. acted to
the Charterers detriment and, accordingly, also to the detriment of the arbitration proceedings.
The Charterers represent a position that the conduct of the Owners falls within the meaning of
the term ‘bad faith’. It has been prescribed as malice in the context of personal spite or desire
to injure for improper reason.3 Moreover, the Charterers want to underline that, they relied on
the Reliable Tankers Inc. good reputation in their contractual relationships which was proven
by signing the Charter Party without the intermediary.4
22. The Owners’ had a duty to appoint a real counter party to the proceedings which was on
contrary not fulfilled. The Charterers were not aware, and had no obligation to be, of the
newspaper article at the time of its publication (3 January 2012), thus, the Notice of
Arbitration and Appointment from 28 January 2012 in the name of Reliable Tankers Inc. was
misleading and as a consequence caused delay of the proceedings.
II. THE TRIBUNAL SHOULD CONSIDER THE OWNER’S CLAIMS AS TIME
BARRED
1. Parties have the autonomy to agree about the time for commencement of the
arbitration.
23. The Tribunal should find that the parties voluntarily agreed on unilateral conditions regarding
commencing the arbitration which do not preclude a fully bilateral agreement constituting a
3
Audley Sheppard, English Arbitration Act (Chapter 23), Part I, The Arbitral Proceedings, Section 34
[Procedural and evidential matters], in: L. Mistelis (ed.), Concise International Arbitration [Kluwer Law
International, 2010], pp. 835-836. 4 Correspondence from the Super Charters Inc. to the Reliable Tankers Inc. from 10 October 2011.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 7
contract to refer. Parties are free to do so according to the § 14 (1) of the Arbitration Act.
Consequently, in the conclusion of the Charter Party, the Reliable Tankers Inc. accepted, inter
alia, the time bar provision included as Clause 4 in the Charterers’ Standard Terms. As stated
by the ‘Waller L.J. in Harbour & General Works v Environment Agency’ case the application
of the principle of party autonomy means that the choice of the parties has to be respected.5
24. A time bar clause in the Charterers’ Standard Terms is unilateral6 and this fact does not
preclude its enforceability.7 Under English law, the lack of specific mutual consent to arbitrate
or litigate likewise does not invalidate unilateral option clauses. The Court of Appeal in the
‘Pittalis v. Sherefettinheld’ case held that the clause did constitute an arbitration agreement
supporting the unilateral options to arbitrate.8 Thus, the fact that the option is exercisable by
one of the parties is irrelevant. Parties have accepted the arrangement and there is no question
of any lack of mutuality because the arrangement suits both parties.9
25. The fulfillment of a condition is a jurisdictional barrier that must be crossed before the
Tribunal can hear the dispute.10
With respect to that the notification of a claim must be treated
as such a condition to commence the arbitration proceedings.11
The parties agreed that, certain
steps should be taken by certain dates, and, therefore, they would be held to their bargain.12
Accordingly, it should be held by the Tribunal that the Owners did not follow the contracted
5 See: Harbour & General Works Ltd. v. Environment Agency, [1999] Adj.L.R. 02/19.
6 WJ Alan and Co Ltd. v. El Nasr Export and Import Co., [1971] 1 Lloyd’s Rep 401. & Pittalis v.
Sherefettin,[1986] 1 QB 868. 7 Robert Merkin, Arbitration Law, [3rd., Informa Law, 2004], p. 482.
8 Also: Law Debenture Trust Corp. plc v. Elektrim Finance B.V., [2005] EWHC 1412 (Ch), 2 All ER
(Comm) 476. 9 Pittalis v. Sherefettin,[1986] 1 QB 868.
10 Cavinder Bull, ‘Commencing Arbitration’, in: Albert Jan van den Berg (ed), ‘International Arbitration: The
Coming of a New Age?’, ICCA Congress Series, Volume 17 ,Kluwer Law International, 2013, p. 149. 11
Clare Ambrose, Karen Maxwell, The Arbitration Act 1996 - London Maritime Arbitration, [1st., LLP, 1996],
p. 83. 12
Andrew Tweeddale, Karen Tweeddale, 'Commencement of Arbitration and Time-Bar Clauses', [Arbitration,
Vol. 75, No. 4, 2009], p. 485.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 8
procedure for the commencement of arbitration, meaning that the Owners did not respect the
contractual condition precedent for commencing the arbitration. With regard to the
aforementioned Clause 4, the Owners had to notify a claim to the Charterers within 10 days of
the discharge or when discharge would have taken place and after that start the proceedings
within the next few days. This Clause clearly states two conditions for the commencement of
arbitration proceedings. The Charterers didn’t receive any notification of a claim before 28
January 2012.
26. Furthermore, there was even no offer for an amicable settlement which was possible at the
time and could suggest a notification of a claim. This comportment was based on the Owners’
bad faith of not acting according to the agreed standard terms. With regard to aforementioned,
the Charterers invoke the decision in the ‘Metafer Corp v. Pan Ocean Shipping Co.’ case
where the limitation of time by contract was held to bar the claims.13
Similarly to the current
dispute there was a fixture agreement according to which, the claims had to be referred to
arbitration within 30 days of completion of the voyage. The interpretation of this clause
requiring notice to be given within a certain number of days was that, if it was not given, the
claims were barred.
27. Even if the Tribunal finds that the condition for commencement is met, it is submitted that
there was a fundamental error in beginning the proceedings in the name of a non-existent
party. It was certified in the ‘Lazard Brothers & Company v. Midland Bank Ltd.’ that the
defect could not be amended to substitute different legal entity.14
Accordingly, the Notice of
Appointment and Arbitration from 28 January 2012 should be considered as null and void15
and hence, the arbitration as not commenced by the Owners properly precluding at the same
13
Metalfer Corp. v. Pan Ocean Shipping Co. Ltd., [1998] 2 Lloyd’s Rep 632. 14
Lazard Brothers & Company v. Midland Bank Ltd., [1993] AC 289 [HL], see also:
SEB Trygg Holding A.B. v. Manches, [2005] EWHC 35 Lloyd’s Rep 129 (Com). 15
David St John Sutton, Judith Gill, Matthew Gearing, Russell on Arbitration, [23rd., Sweet & Maxwell, 2007],
p. 191.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 9
time mere misnomer.16
If the Tribunal accepted on the contrary, this could easily be corrected
by simple amendment as to the name of the party.17
However, the Tribunal should find that
the Owners intentionally started the proceedings on behalf of the Reliable Tankers Inc. and
because of that the error cannot be regarded as mere misnomer, thus cannot be corrected and
proceeding must be deemed as null and void.
28. Last but not least, the Charterers wants to underline that by considering a breach by the
Reliable Tankers Inc. [point III], it should be found that parties by the Charter Party could not
have intended limitations of Clause 4 to apply to breach of contract.18
Accordingly, the fact of
the breach diminished the importance of time-bar pre-condition and preclude benefiting from
it by the party being in the breach of contractual relation. As a consequence, commencing the
arbitration by the Charterers without fulfilling the procedure does not influence validity of the
referral from 12 February 2012.
III. THE TRIBUNAL SHOULD FIND A BREACH OF CONTRACTUAL
OBLIGATIONS COMMITED BY THE RELIABLE TANKERS INC. WHICH
LED TO THE SUBSEQUENT CANCELLATION OF THE CHARTER PARTY
BY THE CHARTERERS.
1. The Tribunal should find a breach of contractual obligations committed by the
Reliable Tankers Inc. which lead to the cancellation of the Charter Party by the
Charterers.
29. The Charter Party should be considered cancelled. As mentioned in the Statement of Facts,
submitted within the present Memorandum, the Voyage, subject to the presently regarded
Charter Party, was interrupted abruptly by an arrest imposed on the Vessel, upon its arrival at
16
Metalfer Corp. v. Pan Ocean Shipping Co. Ltd., [1998] 2 Lloyd’s Rep 632. 17
AMB Generali Holding A.G. v. SEB Trygg Liv Holding A.B., [2005] EWCA Civ 1237; [2006] 1 WLR 2276. 18
Robert Merkin, Arbitration Law, [3rd., Informa Law, 2004], p. 483.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 10
the Bunker Port in Redland. The Reliable Tankers Inc. did not inform the Charterers about the
arrest of the Vessel, an act which should be regarded by the Tribunal as a breach in Reliable
Tankers’ obligation of disclosure implied in the Charter Party.19
After an enquiry was made
by the Charterers, the Reliable Tankers Inc., at first, reassured the Charterers that the arrest
would not affect the stipulated voyage. However, in later correspondence it became clear that
the former are incapable of dealing with the pending problem.20
Furthermore, the Reliable
Tankers Inc. proved to be unable to provide a renewed cancellation date and expected time of
arrival of the Vessel for the purposes of the Charter Party. In the light of the aforementioned
situation, the Charterers rejected the revision of the proposed laycan.
2. The Reliable Tankers Inc. were in breach of contractual obligations.
30. The arrest of the Vessel carrying out the Voyage under the present Charter Party is to be
regarded as an evident disturbance in the stipulated schedule of the Voyage, and furthermore,
a major impediment to her meeting the stipulated laycan of 5-6 December 2011. It is
important to note that, had the Reliable Tankers Inc. provided reasonable security, the arrest
could have been avoided. Following the decision, along with its respective reasoning, in
respect of the ‘Marbienes Compania Naviera S.A. v. Fervostaal A.G.’ case, 21
English courts
established the existence of an implied obligation upon the owner to exercise reasonable
diligence in ensuring the arrival of the vessel within the cancelling date. The latter has been
accepted despite the belief that cancelling clauses in general do not impose an absolute
obligation for the vessel to arrive by the cancelling date. Consequently, by not securing the
19
The Super Charters Company Single Voyage Charter Party Rider Clauses, ¶ 27: ETA, “Any changes which
affect Vessel’s ETA by 6 hours or more (3 hours if Vessel is within 24 hours of port) shall be advised to
Charterer immediately, with brief explanation.” 20
Correspondence from the Reliable Tankers Inc. to the Super Charters Inc. from 25 November 2011. 21
Marbienes Compania Naviera S.A. v. Fervostaal A.G., (‘The Democritos’), [1976] 2 Lloyd's Rep. 149 (C.A.).
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 11
undertaken voyage, subject to the Charter Party, the Reliable Tankers Inc. committed a breach
in their contractual obligation to exert reasonable diligence on their part of the contract.
31. The Charterers consider that the offer to dispatch the sister-ship of the Vessel to carry out the
stipulated Voyage, once it was established the latter was arrested, cannot be regarded as a
valid action by the Reliable Tankers Inc. to redeem their fault for not ensuring the unimpeded
fulfillment of their contractual obligations. The Tribunal should note that the arrest of the
Vessel will irreversibly hinder the completion of the stipulated Voyage. The reason for such
contention is the lack of persuasion that the offered substitution would possibly provide the
timely conduct of the stipulated Voyage. Next, the fact that the offer in question was made
after the cancellation of the Charter Party was announced by the Charterers is to serve as
evidence of its ineptitude.22
Furthermore, the offer of the another ship, which had to begin its
approach voyage from that moment on, should be regarded by the Tribunal as evidence of the
Reliable Tankers Inc. inability to meet their obligations derived from the Charter Party.
3. The cancellation of the Charter Party.
32. In addition to the aforementioned breach of contractual obligation by the Reliable Tankers
Inc., the Tribunal should consider the noncompliance of the actions performed by Reliable
Tankers Inc. in regard of ETA clause included in the Charter Party. Thus, the Charterers look
forward to the present Tribunal to find their actions in regard of the delicate and unfortunate
situation which has arisen in the present case as correct and reasonable. The Charterers,
furthermore, consider that the inability of the Reliable Tankers Inc. to provide the necessary
securities to ensure the fulfillment of the Voyage, as well as to provide a revised laycan, was a
breach of their contractual obligations.
22
Correspondence from the Reliable Tankers Inc. to the Super Charters Inc. from 28 November 2011; where the
Notice of Cancellation was from 27 November 2011.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 12
33. The Charterers rejected the revision of the cancelling date and expected time arrival dates
proposed by the Reliable Tankers Inc, as the latter failed to provide specific dates, making it
practically impossible for a revision to be negotiated. Furthermore, by weighing the situation
in which the stipulated Vessel, and therefore the Charter Party in its entirety were, the
Charterers became aware of the improbability of the Voyage to be fulfilled by the Reliable
Tankers Inc. and had right to cancel the Charter Party. The decision of the Charterers is
supported by the decision of the Court of Appeal in ‘The Mihalis Angelos’ case where the
court held that the expected Ready to Load provision (which is considered the same as ETA
clause) is to be regarded as a condition of the contract, which allows the charterer to terminate
the charter party in case of the clause being breached by the owner. It is widely accepted in
English law that parties to a charter party, such as the present, are to stipulate for an ETA (and
also Estimated Ready to Load) clause to be included in the charter party. It has also been
agreed that should an ETA clause be included in the charter party, it creates for the charterer
the right to terminate the charter party and claim damages if the vessel fails to arrive by the
stipulated date.23
34. Furthermore, it should be noticed by the Tribunal that the cancellation of the Charter Party is
justified immediately when it became obvious that the Voyage could not meet conditions of
the Charter Party. In ‘The Baleares’24
case, the Court of Appeal stated that the owners are in
breach when it becomes clear that there is no reasonable prospect of the vessel being able to
perform the contemplated voyage.25
23
Maredelanto Compania Naviera S.A. v. Bergbau-Handel G.m.b.H., [1970] 2 Lloyd's Rep. 43 (C.A.).
Later, the assertion of the Court found in the Mihalis Angelos Case, stating that the charterer is entitled to the
right of anticipatory cancellation should it be found that the conduct of the voyage is in discordance with the
contractual stipulations, is confirmed by the Court of Appeal (Civil Division) in Georgian Maritime Corp v Sea
Land Industries (Bermuda) Ltd. [1998] C.L.C. 1395 24
Geogas S.A. v. Tranumo Gas Ltd., (‘The Baleares’), [1993] 1 Lloyd's Rep. 215. 25
Ibid.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 13
35. In addition, a brief analysis of the price rates of crude oil,26
the cargo stipulated to be
transported by the Vessel, served as a further reason for the Charterers to terminate the halted
Charter Party in order to consider alternative options. The latter was based on the arising
possibility of serious financial losses to be suffered due to the occurred delay. It is important
to note that such measures taken by the Charterers are not at all uncommon in the legal
practice, and have even been defended by the courts. Again in the ‘The Mihalis Angelos’ case,
Lord Denning stated that: ‘The charterers have the option of cancelling the contract as soon
as it becomes plain that the vessel cannot possibly be ready to load on or before [the
cancelling date]. This is a sensible interpretation: because, as a matter of commercial
convenience, it is better for both sides that, when it is obvious that the vessel will not arrive in
time, the charterer should be able to cancel. The charterer can then engage another vessel:
and the shipowner can use his ship elsewhere’.27
1. The Tribunal should regard the arrest of the Vessel as an unavoidable hindrance to
the fulfillment of the Charter Party for which the fault is to be borne by the Owners
as a legal successor of the Reliable Tankers Inc.
36. The Charterers believe that the Tribunal should find that the arrest is a consequence of
previous undertakings of the Reliable Tankers Inc. that created an unavoidable hindrance to
the completion of the present contract. The Charterers invoke the ‘Monroe Bros. v Ryan’
case28
and although the circumstances in the current dispute do not correspond to the ones
considered in mentioned case, the conclusion made by the Court of Appeal is relevant to the
matter of the arrest of the Vessel.
26
Spot Tanker Market Report. 27
Maredelanto Compania Naviera S.A. v. Bergbau-Handel G.m.b.H., [1970] 2 Lloyd's Rep. 43 (C.A.). 28
Monroe Brothers, Ltd. v. Ryan,[1935] 2 K.B. 28; See also: Blackgold Trading of Monrovia v. Almare S.p.A
Navigazione of Genoa, (‘The Almare Seconda’), [1981] 2 Lloyd's Rep. 433.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 14
37. In the ‘Monroe Bros v Ryan’ case29
it has been established by the Court that in case of a
charter party as the one in the present case, where the preliminary voyage was undertaken
upon the completion of a previous adventure, the party (the owners) ‘run the risk of the
engagements clashing with one another so as to prevent the performance of one or other of
their contracts, and they have to take the consequences by paying damages to the party whose
contract they, in the result, have failed to perform.’30
The assertion of the Court is with regard
to a situation in the cited case where due to delays in the prior voyage the vessel failed to meet
her stipulated ready-to-load date. For those reasons, the court adjudged a compensation to be
paid by the owners.
38. Consequently, the Charterers believe that the Tribunal should find that the arrest of the Vessel
which prevented the fulfillment of the Charter Party in question is in fact a failure on part of
the Reliable Tankers Inc. to perform their obligations of the Charter Party towards the
Charterers. Furthermore, based on the latter fault on part of the Reliable Tankers Inc., the
Tribunal should adjudge a compensation for damages to be paid by the Owners to the
Charterers.
IV. THE TRIBUNAL SHOULD FIND THAT THE FREIGHT STIPULATED IN
THE CONTRACT WAS NOT DUE AND PAYABLE AND THAT THE
RELIABLE TANKERS INC. ACTIONS LEAD TO SUBSEQUENT DAMAGES
FOR THE CHARTERERS.
1. Freight is not due and payable.
39. The freight clause in the Standard Terms of the Reliable Tankers Inc.31
is not binding upon
the Charterers, thus the Charterers ask the Tribunal to rule that the freight was deemed
29
Monroe Brothers, Ltd. v. Ryan,[1935] 2 K.B. 28. 30
Ibid., p. 38 31
Standard Terms of the Reliable Tankers Inc.; Clause 4.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 15
payable at the delivery of the cargo and, therefore not due and payable at the moment of the
cancellation. A contract needs to be construed in accordance with the intention of the parties
as determined objectively from the nature of the terms used and any other relevant evidence.32
The Charter Party states that freight is due at the delivery of the cargo. Taking this in
consideration, the Charter Party itself prevails over the Standard Terms of the Reliable
Tankers Inc.33
40. Even if the Tribunal finds that the Standard Terms are part of the Charter Party, the Charter
Party needs to be looked at as a whole in its context in construing individual provisions.34
Where the context of a contract is particular commercial field, the commercial realities and
usages will be considered in determining the natural meaning of the terms.35
At common law
there is a presumption that freight is payable only on the delivery of the goods to the owner.36
Therefore, the natural meaning of the terms of the contract would be that freight is payable at
the delivery of the cargo to the Charterers.
41. Furthermore, The Clause 4 of the Standard Terms of the Reliable Tankers Inc. is not an
express stipulation and is not drawn sufficient and clear. In the ‘De Silvale v. Kendall’ case
Lord Ellenborough stated that: ‘Under English law freight and wages do not become due until the
voyage has been performed. This can otherwise be agreed by a provision in the Charter Party by
express stipulation in such manner as to control the general operation of law’. 37
In this case there is
32
Cholmondeley v. Clinton, [1937] E.R. 527. & Mannai Investment Co Ltd. v. Eagle Star Life Assurance Co.
Ltd., [1997] A.C. 749. & Investors Compensation Scheme Ltd. v. West Bromwich Building Society, [1998] 1
W.L.R. 896. 33
Smith v. Lucas, [1880-81] L.R. 18 Ch. D. 531. 34
See: Hume v. Rundell, [1824] E.R. 311. & B. Richards, Devisee of John Richards, Deceased v. Bluck, 136 E.R.
1319. & James Reid and James Stewart v. William Blackedon Fairbanks, Jonathan Crane Allison, and David
Allison, 138 E.R. 1371.; ; In re: Strand Music Hall Co. Ltd., (1865) 55 ER 853. 35
Southland Frozen Meat & Produce Export Co. Ltd. v. Nelson Bros Ltd., [1898] A.C. 442.; see also: Antaios
Compania Naviera S.A. v. Salen Rederierna A.B. (‘The Antaios’), [1985] A.C. 191. 36
John F. Wilson, Carriage of Goods by Sea, [7th., Pearson, 2010], p. 289, see also: Stephen Girvin, Carriage of
Goods by Sea,[2nd., Oxford University Press, 2011], p. 337. 37
De Silvale v. Kendall, [1815] 4 M & S 37.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 16
no express stipulation. Referring to the ‘Lorna I’ case38
advanced freight provisions should be
drawn sufficient and clear. In ‘Robertsen v. French’ case the Court stated that in the absence
of a reason for ascribing a technical or other special meaning to a word, it is to be given the
meaning that it would naturally have in the ordinary English usage.39
42. With regard to the aforementioned, the sentence “lifting subjects” could be interpreted in
different ways. If it comes to the interpretation at the conclusion of the Charter Party,
Charterers argue that “lifting subjects” must be interpreted against the background of its
industry. Common practice is that this provision is used when actually lifting something from
the quayside into the vessel before the commencement of the voyage. In the current dispute
the Charter Party is for the transport of crude oil and it is, therefore, unusual to pay for freight
in advance.
43. However, in case the Tribunal finds that the freight must be seen as advanced freight, and that
the interpretation of ‘lifting subjects’ is the conclusion of the contract, the freight is still not
due and payable. When there is advanced freight, the sums are payable in the loading port.
Here, the Vessel never arrived at the loading port. The Vessel was on her way to the Redland
when the Charter Party was fixed. As a result, the Charterers interpreted the provision as if
freight was payable in the port of loading, since the Vessel never commenced the approach
Voyage.
44. The Clause 2 of the Standard Terms of the Reliable Tankers Inc. is misinterpreted by the
Owners.40
It provides cancellation of the Charter Party without either party being required to
act any further. It does not release either Party from liability as stated by the Owners.
38
Lorna I Compania Naviera General S.A v. Keramental Ltd.,[1983] 1 Lloyds Rep. 373. 39
Robertson v. French, [1803] 102 ER 779. 40
Standard Terms of the Reliable Tankers Inc.; Clause 2.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 17
However, if Clause 2 is a mutual relieve of obligations and liabilities, the Charterers were,
thereby released from any obligation to pay freight.
45. To the extent that the Tribunal finds that the Owners are released from liability, the Charter
Party should be rectified by reason of a common or unilateral mistake. There was no intention
on the side of the Charterers to accept the provision in which either Party would be released
from liability. The terms of Clause 2 must have been amended so as to displace the Owners’
usual regime of releasing them from liability.
2. The claim for damages.
46. The Charter Party is terminated by the Charterers because of negligence by the Reliable
Tankers Inc. The arrest could easily be avoided by granting a guarantee. However, as stated in
the Internal Note of the Reliable Tankers Inc.41
, they were unwilling to pay the bunker
supplier. They had no haste what so ever and no intention in providing a guarantee. If they
had done so, the Vessel would be released from the arrest, and would have proceeded to the
loading port on time. If the Vessel arrived on time the Charterers would not have been forced
to cancel the Charter Party.
47. The Reliable Tankers Inc. did not proceed to the port of loading with utmost dispatch and
therefore the Vessel could not meet its laycan. Since the Vessel’s laycan was not met, the
Charterers were allowed to cancel the Charter Party. The Charters ask the Tribunal to hold the
Owners as a legal successors of the Reliable Tankers Inc. liable for the damages occurred of
fixing another vessel.
41
Reliable Tankers Inc. Internal Note from 23 November 2011.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 18
3.. Further claim for the set-off damages.
48. The Charterers are entitled to and do set-off the damages that occurred.42
By the breach of the
Reliable Tankers Inc., the Charterers have suffered a loss. For reasons set out before the
Charterers had to fix another vessel. This resulted in an increase of the freight price of $US
824,000. The offered option of waiting for the sister vessel, was not a suitable one. As the
sister vessel would not meet the laycan of 5 December 2012, which would result in a delayed
arrival at the terminal. Since the terminal would be shut down due to maintenance, the risk
was too high to wait for a new laycan of the sistership. As a consequence, Charterers fixed
two other vessels. Because of the minor delay, the Charterers had to pay damages to the
Terminal of $US 100,000 for the late arrival and $US 300,000 for the loss.
49. In the light of the facts and arguments listed above the Charterers look forward to the Tribunal
to find their actions for the freight claim in the present case as correct and reasonable. The
Charterers reject the arguments of the Owners and state that they are not obliged to pay
freight under the Charter Party. The Charterers counterclaim $US 824,000 being the
difference between the charter freight and the amount payable under replacement fixtures by
the Charterers and the sums due and payable at the load port for the delayed arrival $US
100,000 and sums due and payable at the port of discharge $US 300,000.
V. REQUEST FOR RELIEF
On the basis of the foregoing arguments and the Charterers’ prior written submissions, the
Charterers’ respectfully requests the Tribunal
42
Colonial Bank (now bank of Boston Connecticut) v. European Grain & Shipping Ltd., (‘The Dominique’),
[1989] 1 Lloyds Rep. 436.
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 19
TO ADJUDGE AND DECLARE that:
a) there was no genuine misnomer in commencing the arbitration proceeding in the name of
the Reliable Tankers Inc.;
b) the stipulated fright is not due and payable;
c) the Owner’s claims are time barred and not meeting the conditions to commence the
arbitration;
d) the Owners as a legal successor of the Reliable Tankers Inc. are liable for the breach of
contractual relation which led to the cancellation of the Charter Party;
e) the Owners as a legal successor of the Reliable Tankers Inc. are liable for the arrest of the
Vessel which was an obstacle to fulfill the obligations concluded in the Charter Party;
f) the Owners as a legal successor of the Reliable Tankers Inc. are liable for the subsequent
damages for the Charterers.
And to ORDER the Owners to:
1. Pay the total amount of USD 6159368 consisting of:
a) USD 4,935,368,75 for the loss resulting in obligation (which is denied) to pay freight;
Erasmus University Rotterdam Memorandum for the Super Charters Inc.
Page | 20
b) USD 824,000 for the increase in freight for fixing another vessel;
c) USD 300,000 for sums due and payable at the port of discharge;
d) USD 100,000 for the sums due and payable at the load port for the delayed.
2. Pay the costs of arbitration, including the Charterers’ expenses for the legal representation;
3. Pay the Charterers’ simple or compound interest on any sum found owing to them at such a
rate and with such rests and for such a period as the Tribunal sees fit.
Rotterdam, 2 May 2014.
On behalf of the Super Charters Inc.:
ALEXANDER J. BARENDREGT ♦ EVANGELIA PATRIKALAKI
MARTA K. KOŁACZ ♦ NEDYALKO MINKOV ♦ SONJA VAN WIJK