memorymap_4thed

Upload: marcelo-melo

Post on 03-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 MemoryMap_4thED

    1/2

    Initiating &

    Planning

    Processes GroupsCollect RequirementsRequirements

    Documentation

    Define Scope

    Scope Baseline

    Estimate

    Costs

    Determine

    BudgetPlan

    Procurements

    Plan Risk

    Management

    Define

    Activities

    Activity

    Cost

    Estimates

    Cost Performance

    Baseline

    Risk Management

    Plan

    ActivityList

    Sequence

    Activities

    Estimate

    Activity

    Durations

    Network Diagrams ActivityDuration

    Estimates

    Develop Project Management Plan

    Estimate

    Activity

    Resources

    Develop

    Schedule

    ActivityResource

    Requirements

    ProjectSchedule

    Procurement

    Management Plan

    Identify

    Risks

    Perform

    Qualitative Risk

    Analysis

    Perform

    Quantitative RiskAnalysis

    Plan Risk

    Responses

    Scope Statement

    Create WBS

    Plan Communications

    Plan Quality

    Develop HR Plan

    Comm. Management Plan

    HR Plan

    Quality metrics/checklists

    Process improvement plan

    Risk Register

    NOTE: All boxed

    rectangles are

    PROCESSES.

    Plain text is an

    output/inputfrom one process

    to the other. Not

    all inputs and

    outputs are

    represented

    here.

    Initiating Process Group

    Develop Project Charter

    Project Charter

    Identify Stakeholders

    Stakeholder Register

    Planning Process Group

    Scope Baseline

    PMBOKGuideFourth Editionv10.08

    PM Plan (Ready for Kick-o

  • 7/28/2019 MemoryMap_4thED

    2/2

    EARNED VALUE ANALYSIS

    Planned Value = Budgeted Cost of Work Scheduled PV = BCWS

    Earned Value = Budgeted Cost of Work Performed EV = BCWP

    Actual Cost = Actual Cost of Work Performed AC = ACWP

    BAC is original budget

    Planned Value-what we planned to spend at a particular pt. in tim

    Earned Value EV = BAC * %Co

    Cost Variance CV = EV - AC

    Schedule Variance SV = EV - PV

    Cost Performance Index CPI = EV / AC

    Schedule Performance Index SPI = EV / PV

    Estimate At Completion EAC = AC / %Co

    Estimate To Complete ETC = EAC - AC

    Variance At Completion VAC = BAC - EAC

    Close Project or Phase Close Procurements

    Final product, service or result

    transition

    Org. Process Assets updates

    Accepted DeliverablesProcurement

    Documentation

    Closed procurements

    Org. Process Assets

    updates

    Closing Process Group

    Break at 50

    Breathe & Stretch

    Read ?? Carefully

    Read all 4 answers

    Track answers

    Present Value

    FV

    (1+r)nr = int. rate, n = # of periods

    Comm ChannelsN(N-1)

    2

    Project Std. Dev.

    = square root

    of the sum of the

    task variances

    PERT

    (P+4M+O)

    6

    Std. Dev.

    (P-O)

    6

    Task Variance

    (P-O) 2

    6

    Control Scope

    Report Performance

    Monitor & Control Risks

    Perform Quality Control

    Monitoring & Controlling Process Group

    Monitor and Control

    Project Work

    Control Costs

    Change Requests

    Administer Procurements

    Control Schedule

    Work Performance

    Information

    Verify ScopeValidated Deliverables

    NOTE: Items in boxes

    are processes. Items as

    standalone text are input

    or outputs.

    Perform Integrated

    Change Control

    Change requests

    status updates

    Normal Distribution1 Sigma = 68.26%

    2 Sigma = 95.46%

    3 Sigma = 99.73%6 Sigma = 99.99%

    Executing Process Group

    Direct and Manage Project Execution

    DeliverablesWork pkgs

    Work Performance Info

    Change requests

    Perform Quality Assurance

    Develop Project Team

    Manage Project Team

    Org. Process Assets updates

    Team Performance assessments

    Manage Stakeholder Expectations

    Conduct Procurements

    Selected sellers

    Contract award

    Acquire Project Team

    Staff assignments

    Resource calendars

    Executing, Monitoring and Controlling, & Closing Processes Groups

    Expected Monetary

    Value (EMV)

    probability x impact

    Distribute Information

    Org. Process Assets updates

    Org. Process Assets updates

    Org. Process Assets updatesChange requests

    Performance Reports

    PMBOKGuideFourth Editionv10.08