metecno wall vertical manual

Upload: blutch0

Post on 15-Oct-2015

43 views

Category:

Documents


0 download

TRANSCRIPT

  • 5/25/2018 Metecno Wall Vertical Manual

    1/37

    20067 TRIBIANO, Milan

    Phone +39 02 906951 - Fax +39 02 90634238

    METECNO INDUSTRIES.p.A.

    Phone +39 02 906951 - Fax +39 02 90634238

    www.metecno.com - [email protected]

    WALL-PANELS

    POLYURETHANE OR ROCK WOOL

    SELF-SUPPORTING INSULATING

    METAL PANEL

    T E C H N I C A L H A N D B O O K

    ENG

    VERTICAL ASSEMBLING

  • 5/25/2018 Metecno Wall Vertical Manual

    2/37

    WALL-PANELS

    1

    TECHNICAL MANUAL

    This document has been drawn up to help you in using the following

    panels.

    time to carefully read the present manual to refresh your technical

    and operative knowledge.

    This manual is divided into several sections, which are identified by

    a number. Each section is subdivided into numbered chapters.

    METECNO GROUP sales conditions apply to all aspects that are not covered by

    the present technical manual.

    For any information or suggestion, please send your mail to:

    Before using the products, we suggest to take some of your

    MONOWALL

    SUPERWALL

    SUPERWALL (ML)

    SUPERWALL (HF)

    HIPERTEC WALL

    HIPERTEC WAND SOUND

    ROCKSTEEL WALL

    H-WALL 8P / 8M / 10P / 10M

    FRIMET TP-SMFIREMET WALL

    (vertical assembling)

  • 5/25/2018 Metecno Wall Vertical Manual

    3/37

    2

    1. GENERALS

    1.1 COMPOSITION AND USE

    All the wall panels from Metecno are composite panels, formed by two metal sheets linked by a layer of insulating material,which can be manufactured upon request:

    with polyurethane foam with mineralwool

    The shape of the panels longitudinal joint is such as to hide the fastening screw, making thepanel more pleasant and elegant looking. In addition to the economic benefits for the structure costs, this solution is an

    innovative architectural alternative.

    1.2 STANDARD SIZE

    Panels are manufactured in 1000 mm wide modules (except the FRIMET TP-SM is 1130mm) ; their length depends

    on the specific design requirements and the feasibility of the manufacturing factory. Please request for that.

    WALL-PANELS(vertical assembling)

    MonowallSuperwallSuperwall MLH-Wall 8P

    H-Wall 10P

    Hipertec WallRocksteel WallSuperwall HF

    H-Wall 8MH-Wall 10M

    HIDDEN FIXING

    Only for panel type: Superwall ML / HF ; H-Wall 8P / 8M

    1000

    Gasket(polyurethane version only)

    Monowall A-B

    250 250 250 250

    S

    62,562,5

    with combined insulation

    FIREMET Wall

    S

    62,5

    Monowall B-B

    1000

  • 5/25/2018 Metecno Wall Vertical Manual

    4/37

    Gasket(polyurethane version only)

    WALL-PANELS(vertical assembling)

    H-Wall8P / 8M

    HIPERTECWALL / HIPERTECWALLSOUND/ ROCKSTEELWALL / FIREMETWALL

    S

    62,5

    1000

    62,562,562,5

    s

    12562,5

    1000

    20

    Gasket

    (polyurethane version only)

    H-Wall10P / 10M

    s

    1000

    100 62,5

    18

    1000

    S

    Gasket(polyurethane version only)

    25

    62,5

    SUPERWALLML / HF

    3

  • 5/25/2018 Metecno Wall Vertical Manual

    5/37

    4

    1.3 REACTION AND RESISTANCE TO FIRE

    Contact METECNO for detailed information.

    1.4 FASTENERS

    When panels are laid vertically, they require the following type of fastening.

    WALL-PANELS(vertical assembling)

    p a n e l ty p e t h i c k n e s s t h i c k n e s s s t e e l c o n s t r u c t io n w o o d e n c o n s t r u c t io n

    p a n e l a t t h e p o in t > 1 , 5 m m > 5 0 m m

    w e r e t h e s c r e w s c r e w w i t h s c r e w w i t h

    i s lo c a t e d f in e t h r e a d c o a r s e t h r e a d

    [ m m ] [ m m ] [ m m ] [ m m ]

    M o n o w a l l A - B 2 5 2 0 4 5 8 5

    3 0 2 5 5 0 9 0

    3 5 3 0 4 5 9 5

    4 0 3 5 6 0 1 0 05 0 4 5 7 0 1 1 0

    6 0 5 5 8 0 1 2 0

    8 0 7 5 1 0 0 1 4 0

    1 0 0 9 5 1 2 0 1 6 0

    1 2 0 1 1 5 1 4 0 1 8 0

    1 4 0 1 3 5 1 6 0 2 0 0

    1 5 0 1 4 5 1 7 0 2 1 0

    M o n o w a l l B - B 2 5 2 5 5 0 9 0

    F ir e m e t W a l l 3 0 3 0 5 5 9 5

    H ip e r t e c W a l l 3 5 3 5 5 0 1 0 0

    4 0 4 0 6 5 1 0 5

    5 0 5 0 7 5 1 1 5

    6 0 6 0 8 5 1 2 5

    8 0 8 0 1 0 5 1 4 5

    1 0 0 1 0 0 1 2 5 1 6 5

    1 2 0 1 2 0 1 4 5 1 8 51 4 0 1 4 0 1 6 5 2 0 5

    1 5 0 1 5 0 1 7 5 2 1 5

    S u p e r w a l l 6 0 6 0 8 0 1 2 0

    8 0 8 0 1 0 0 1 4 0

    1 0 0 1 0 0 1 2 0 1 6 0

    1 2 0 1 2 0 1 4 0 1 8 0

    H - W a l l 8 5 0 / 7 0 5 0 7 0 1 1 0

    8 0 / 1 0 0 8 0 1 0 0 1 4 0

    p a n e l ty p e t h i c k n e s s t h i c k n e s s s t e e l c o n s t r u c t io n w o o d e n c o n s t r u c t io n

    p a n e l a t t h e p o in t > 1 , 5 m m > 5 0 m m

    w e r e t h e s c r e w s c r e w w i t h s c r e w w i t hi s lo c a t e d f in e t h r e a d c o a r s e t h r e a d

    [ m m ] [ m m ] [ m m ] [ m m ]

    S u p e r w a l l 6 0 4 6 6 0 1 0 5

    8 0 6 6 8 0 1 2 5

    1 0 0 8 6 1 0 0 1 4 5

    1 2 0 1 0 6 1 2 0 1 6 5

    H - W a l l 8 5 0 / 7 0 4 0 6 0 1 0 0

    8 0 / 1 0 0 7 0 9 0 1 3 0

    w a s h e r w ith d ia m e te r o f 1 6 o r 1 9 m m

    * re c o m m e n d e d m in im a l le n g th o f t h e s c re w

    T h e a d v e rt is e d le n g th o f t h e s c re w d e p e n d s o n th e s te e l th ic k n e s s o f

    th e s u p p o rt c o n s tru c t io n a n d d iffe re n s e b e tw e e n th e v a rio s s c re w s u p p l ie rsIf y o u u s e s e lf d r i l l in g s c re w s , p le a s e c o n ta c t u s b e fo re .

    l e n g t h o f t h e s c r e w *

    h id d e n fix in g

    l e n g t h o f t h e s c r e w *

    v is ib le F ix in g

  • 5/25/2018 Metecno Wall Vertical Manual

    6/37

    5

    WARNING !Carefully follow these

    handling and storage instructions

    Sling the package by using a rocker arm and min. 200 mm-wide nylonbelts. Insert min. 200 mm-wide wooden boards between the package

    and the belts. The wooden boards will have to be approximately 2 cm

    longer than the package width.

    Do not store more than three packages one on top of another, and placespacers or boards between them.

    Place the package on a flat and rigid surface, and position 50 mm-thickand 200 mm- wide polystyrene spacers or wooden boards at max. 1 m

    intervals. Panels will have to be stored slightly sloping in order to help

    possible condensation flow and to prevent backwater.

    Store packages under cover; if this is impossible, protect them withrainproof membranes. Make sure that the goods are appropriately

    aerated. Any protective film should be not exposed to direct sunbeams

    and, in any case, should be removed within 45 days after the date when

    the panels are prepared.

    Slightslope-

    min.5%

    3

    2

    1

    1/5L

    1/5L

    L

    200min

    .

    Slightslope-min.5%

    1 m 1 m 1 mRemoveprotection

    Donotexpose

    tosunbeams-

    Keepunderco

    ver

    NOTE: The extendable polyethylene forming the external wrap

    of this package is not suitable for a long exposition outdoor,

    since sunbeams change its properties.

    When panels have to be moved one by one due tobuilding yard needs, they should be always carried

    as shown in the illustration.

    2.3 HANDLINGAND STORAGE

    Package handling and storage is a very delicate phase, in which panels can get damaged. For this reason, a label with the

    following instructions is applied to each package:

    WALL-PANELS(vertical assembling)

  • 5/25/2018 Metecno Wall Vertical Manual

    7/37

    3. ASSEMBLY TOOLS

    PORTABLE DRILLING MACHINE

    Portable drilling machine

    with max. 8-mm diameter spindle

    and relevant helical drills.

    ELECTRIC SCREW-DRIVER

    Reversible electric screw-driver

    with relevant bushes.

    HACK SAWING MACHINE

    RIVETING MACHINE

    Riveting machine for 2.5-5 mm diameterrivets and relevant rivets.

    VACUUM CLEANER RELEASE PINCERS

    PLIERS HAND LEVER SHEARS (right and left)

    SCRAPER OR SPATULE PLUMB LINE SPIRIT LEVEL

    SLEDGE HAMMER

    WALL-PANELS(vertical assembling)

    6

  • 5/25/2018 Metecno Wall Vertical Manual

    8/37

    7

    4. ASSEMBLY INSTRUCTIONS

    4.1 PRELIMINARIES

    a) Check that the storage has been carried out according to the directions in chapter 2.b) Check that the panel support structures are level.

    c) Position the packages of panels near the points of use.

    d) Prepare a fixed or cradle scaffold, according to the working height, 30/40 cm far from the external edge of the main

    columns and comply with the rules on safety in the workplace.

    e) Control that all workers are equipped with individual safety equipment according to current regulations.

    f) Prepare all the power supply lines for tools according to current regulations.

    g) Prepare the panel lifting vehicles.

    4.2 PREPARING PANELS

    4.2.1 Before the assembly, the polyethylene protecting film must be taken away from the entire panel. Thoroughly check that no

    traces of residual glue of the protecting film are left on the surface. In such case, remove them using a detergent in a water-

    based solution.

    4.2.2 If the panel surface shows clear damages on the sheet, set the panel aside and use it when undersizes are required.

    4.3 WALL WITH VERTICAL PANELS IN GENERAL

    4.3.1 The base-connection must be perfectly stationed horizontally. Attachment with rivets at the sub-construction before

    positioning the panels (s. Fig. 5). After the deposition of the panels, the base -connection will be fastened, thus the

    panels connected with the sub-construction.

    Figure 5

    Maincolumn

    Maincolumn

    Maincolumn

    Drip

    rivet

    angle steel basementsheet steel

    WALL-PANELS(vertical assembling)

    gasket

  • 5/25/2018 Metecno Wall Vertical Manual

    9/37

    4.3.3 Place the panel on a basis with a plumpline, examine

    whether it is exactly vertical, afterwards block it with

    pliers. (fig. 6)

    Fig. 6

    4.3.4 Go on with the installation of the screws. Please see

    Fig. 7

    4.3.5 It is of advantage, to insert a seal between the

    basis-connection and the panel, in order to prevent the

    air-penetration. It should not touch under no

    Fig. 8

    plumpline

    current of wall

    current of wall

    basis-connection

    direction of assembly

    seal

    pliers to release

    pliers to release

    panel

    current of wall

    current of wall

    basis-connection

    direction of assembly

    seal

    panel

    screw connection

    screw connection

    Viti di fissaggio

    sheet metal basementangle steel

    screw

    seal

    panel

    8

    illustration point 1.6.2 (fig. 7)

    pliers to release

    circumstances the ground with the metal sheet.(fig. 8)

    support profilas gage

    WALL-PANELS(vertical assembling)

    (remove aftermounting)

    gasket

  • 5/25/2018 Metecno Wall Vertical Manual

    10/37

    4.3.6 Remove the pliers to release and check again with the plumpline the vertical position of the panel.

    4.3.7 When the panels are protected with a self-sticking transparent film, it is important

    to remove this from the panel for assembly.

    4.3.8 Before assembling the second panel, control that thejoints are clean and free from eventual resiudes of

    foam. For a correct and easy assembly, the second

    panel must be approached to that one already fixedand with a light inclination it must be pushed

    to contact, in such way its possible to obtain

    a perfect joint. (fig. 9)

    Verify the perfect realization of the joint, control the

    external sheet of the contiguous panel,

    so that the external surfaces of the panels next to each

    Fig. 9

    4.3.9 Splices of head on facade walls

    4.3.10 When the front of a building is higher than the maximum length of the panel (fig. 10), it must be proceeded

    with horizontal jointing of panels. The total height of the front will be subdivided in a number of bands ofpanels (fig. 11 and 12) that complete the total surface to be covered.

    Fig. 10 Fig. 11 Fig. 12

    current of wall

    current of wall

    basis-connection

    direction of assembly

    seal

    panel

    basement

    H>Lm

    axpanel

    basement

    1. wrap panels

    2. wrap panels

    basement

    2. wrap panels

    3. wrap panels

    1. wrap panels

    other are in contact. It is important to control every 3 or 4

    panels concerning their vertical direction.

    H>Lmaxpanel

    WALL-PANELS(vertical assembling)

    9

  • 5/25/2018 Metecno Wall Vertical Manual

    11/37

    Herewith to show you some joint-details (fig. 13 e 14).

    Fig. 13 Fig. 14

    4.5. Fastening and screw connection for the different panel types

    10

    WALL-PANELS(vertical assembling)

    4.5.1 Type Monowall

    gasket

    gasket

    insulation insulation

    It is important for the fixing of the panels to use stainless steel screws with washers. You can use self-cutting screws orself-drilling screws. For a constructive-fixing of the panels use 2 screws at the end-support resp. middle-support. A fixingof the longitudinal-joint is not necessary.

    1middle-fixing2screws in the joint

    direction of the weather

    r no m

    t

    diectio f

    ouning

    gasket 20/10

    support profile as gage

  • 5/25/2018 Metecno Wall Vertical Manual

    12/37

    11

    WALL-PANELS(vertical assembling)

    4.5.2 Type Superwall ML / HF

    directiono

    fweather

    i om un

    t g

    directon f

    o in

    direc ionof weathert

    d rec ion ofw ath ri t e e

    Fixing with a screw in the joint

    Fixing with a screw and a load distribution plate in the joint

    Superwall panels should be mounted against the direction of the wind. The panels can be fixed both, visibly andhidden. The number of screws is dependent on the statical calculation, especially taking into account the wind loads

    on the surface and the corners of the building. It is important for the fixing of the panels to use stainless steel screws.You can use self-cutting screws or self-drilling screws. Some cases of higher wind loads can make it necessary to fixwith a additional steel plate.

  • 5/25/2018 Metecno Wall Vertical Manual

    13/37

    12

    WALL-PANELS(vertical assembling)

    4.5.3 Type H-Wall 8P / 8M

    1 Fixing with a screw in the joint

    1a Fixing with a screw and aload distribution plate in the joint

    2 Visible fixing in the valley(if necessary)

    direction of weather

    support profile as gagegasket 20/10

    irec ono m

    ountig

    d ti f

    n

    The mounting of the H Wall 8 panels is against the direction of the weather. The panels can be fixed both, visibly andhidden. The number of screws is dependent on the statical calculation, especially taking into account the wind loads

    on the surface and the corners of the building. It is important for the fixing of the panels to use stainless steel screws.You can use self-cutting screws or self-drilling screws. Some cases of higher wind loads can make it necessary to fixwith a additional steel plate.

  • 5/25/2018 Metecno Wall Vertical Manual

    14/37

    13

    WALL-PANELS(vertical assembling)

    4.5.3 Type H-Wall 10P / 10M

    The mounting of the H Wall 10 panels has to be against the weather direction. The fixing of the panels is only possiblein a visible version. The number of screws is dependent on the statical calculation, especially taking into account thewind loads on the surface and the corners of the building. It is important for the fixing of the panels to use stainlesssteel screws with washers. You can use self-cutting screws or self-drilling screws.

    support profile as gagegasket 20/10

    re tio m

    u t

    di cnof

    o ning

    direction of mounting

    direction of weather

    1 Screw on the left and rightside from the joint.

    2 Fixing in the middle

  • 5/25/2018 Metecno Wall Vertical Manual

    15/37

    5. USEFUL CONSIDERATIONS FOR THE VERTICAL ASSEMBLY

    For Metecno wall panels posed in vertical position its necessary to follow these suggestions:

    The panels must be raised very carefully avoiding

    to damage the surface. The raising can beexecuted simply by hand or with

    the aid of one rope, like evidenced in

    fig.15 and the 16.

    Fig. 15

    Fig. 16

    14

    5-10m.

    WALL-PANELS(vertical assembling)

    (A better alternative is using a crane)

    2 screws (type M10)

    An easy support-solution to lift the panels by crane forthe vertical assembling is to use a U-profile fixed onthe end of the panel.

    When the panels must be lifted up to a height where you can not work from the ground, you are adviced to use special

    tools to lift the panels up, as shown on the sketch (fig17 and 18), or simply use a mobile or stationary crane.

    Fig.17

    Fig. 18

    cable of raising

    flowing stirrupwith detention

    detention

    carrying stirrup

    guide rope

    SUPERWALL

  • 5/25/2018 Metecno Wall Vertical Manual

    16/37

    Adhesive tape

    Cutting line marked with a felt-tip pen Panel cut made with a hack sawing machine

    Hole

    6. CUTTING PANELS

    6.1 If panels need to be cut to make openings or passages, proceed as follows:

    Protect the surface to be cut with adhesive tape. Draw the cut to be made on the tape using a felt-tip pen.

    for cutting use a hack sawing machine or a hand-held circular saw

    Clean the surface from the shavings formed during the cutting, because they can cause corrosion over time.

    Remove the adhesive tape.

    WALL-PANELS(vertical assembling)

    6.2 Cutting at the building site

    the use of a parting of grinder is not permitted

    CORRECT

    NEVER !

    15

  • 5/25/2018 Metecno Wall Vertical Manual

    17/37

    16

    7. CONSTRUCTION DETAILS

    Some construction details relevant to the individual points of a wall formed by Metecno wall

    panels are enclosed to the

    present document.

    NO. 12 DRAWINGS(annexed to the present manual)

    WALL-PANELS(vertical assembling)

  • 5/25/2018 Metecno Wall Vertical Manual

    18/37

  • 5/25/2018 Metecno Wall Vertical Manual

    19/37

  • 5/25/2018 Metecno Wall Vertical Manual

    20/37

  • 5/25/2018 Metecno Wall Vertical Manual

    21/37

  • 5/25/2018 Metecno Wall Vertical Manual

    22/37

  • 5/25/2018 Metecno Wall Vertical Manual

    23/37

  • 5/25/2018 Metecno Wall Vertical Manual

    24/37

  • 5/25/2018 Metecno Wall Vertical Manual

    25/37

  • 5/25/2018 Metecno Wall Vertical Manual

    26/37

  • 5/25/2018 Metecno Wall Vertical Manual

    27/37

  • 5/25/2018 Metecno Wall Vertical Manual

    28/37

  • 5/25/2018 Metecno Wall Vertical Manual

    29/37

  • 5/25/2018 Metecno Wall Vertical Manual

    30/37

  • 5/25/2018 Metecno Wall Vertical Manual

    31/37

  • 5/25/2018 Metecno Wall Vertical Manual

    32/37

  • 5/25/2018 Metecno Wall Vertical Manual

    33/37

  • 5/25/2018 Metecno Wall Vertical Manual

    34/37

  • 5/25/2018 Metecno Wall Vertical Manual

    35/37

    34

    9. PANEL MAINTENANCE

    9.1 For the good panel maintenance, two phases must be distinguished:

    First phase: regards the time necessary to assemble the panels. Second phase: regards the use of the building, to which the panels have been assembled.

    In the first phase, in order to maintain panels undamaged, you should take care of what follows:

    the handling during the unloading operations from vehicles must be carried out with suitable means and appropriate

    protections, in order to prevent panels from being indented or scratched.

    the handling during the removal of the protective film and the distribution near the works. In this stage, we always

    suggest that the panel and sections are controlled to remove any excess of the insulating material for the benefit of the

    perfect execution of the panel coupling joint.

    the lifting operations near walls, to be carried out with suitable means and safety systems for the staff.

    the assembly stages, taking particular care to the fastening operations, immediately removing all the shavings causedby drilling from the panel surface. In order to insert screws and avoid indentations to the panel, use screwdrivers that

    are equipped with a depth limiting device.

    when, during the distribution of panels, stains or deformations (indentations) that cannot be easily fixed are found,

    avoid to assemble such panels and set them aside for use as undersize elements, where possible.

    9.2 If the above-mentioned recommendations are truly complied with, they guarantee the product integrity and avoid the

    annoying building yard objections that very often translate into unpleasant financial costs. The second stage regards the

    panel maintenance, which is the final users task, in order for the panels of his building to maintain their original look and

    have the building look pleasant.

    9.3 The consequences of a slow degradation of the pre-painted external sides are mostly originated from the contact with

    aggressive substances contained in corrosive air and gaseous emissions from surrounding activities. Therefore, periodicalinspections to the panels should be planned in order to find possible corrosion; if it is found, action should be taken

    immediately, starting protective cycles to stop the process. In the long run, smog deposits on painted surfaces and may

    create a dirt film, and the walls will have to be cleaned with water jets.

    9.4 The existing seals will have to be controlled, verifying that they are still airtight and waterproof, which otherwise may

    cause deterioration. All the fastenings will have to be controlled to verify that they are still in good conditions. Any

    scratches of the paint that may have been caused accidentally will have to be protected by retouching: cleaning and

    painting. In case of large size dents caused by impacts, the panel will have to be replaced.

    9.5 DISPOSAL

    In case of yard working wastes and/or dismissal, the panel disposal shall only be entrusted with authorized

    companies and carried out in compliance with the current laws in each country.

    WALL-PANELS(vertical assembling)

  • 5/25/2018 Metecno Wall Vertical Manual

    36/37

    10. SAFETY INFORMATION

    Each user and/or worker must be aware of all the problems connected with the assembly of these panels, and should

    prepare a SAFETY PLAN in order to prevent dangerous situations.

    THEREFORE, WE REMIND YOU TO STRICTLY COMPLY WITH THE REGULATIONS ON SAFETY IN WORKPLACES,

    BUILDING YARDS AND EQUIPMENT SAFETY.

    WALL-PANELS(vertical assembling)

    35

  • 5/25/2018 Metecno Wall Vertical Manual

    37/37

    METECNOS.p.A.

    Via Per Cassino, 19

    20067 TRIBIANO, Milan

    Phone +39 02 906951 - Fax +39 02 90634238www.metecno.com

    METECNO INDUSTRIE S.p.A.

    Via Per Cassino, 19

    20067 TRIBIANO, Milan

    Phone +39 02 906951 - Fax +39 02 90634238

    www.metecno.com - [email protected]

    IMPORTANT

    The information contained in this manual has

    been prepared in connection with our

    customers needs. It has been processed

    based on our know-how at the time of

    publishing and, therefore, it is subject to

    changes without any prior notice.

    For the same reason, this is not a full guide

    to installation, use and maintenance of

    METECNO products. In case of doubt or

    difficulty, the user must seek for METECNOs

    advice before proceeding.

    METECNO does not accept any responsibility

    for damages to individuals or properties,

    caused by faults in assembly or installation,

    by improper use and wrong maintenance of

    Superwall ML

    sandwich panels.

    Metecno trademark

    Metecno copyright