 for Inur Sakato Power Plant in Timor Leste PT WIJ Y K RY REK Y S K ONSTRUKSI Mechanical & Electrical Construction - Operation & Maintenance METHOD STATEMENT FOR CABLE GROUNDING INSTALLATION Erection and Installation of Civil, Mechanical and Electrical Works Workshop: Komplek Industri Kembang Kuning. Jl. Raya Narogong, KM 26,5. Cileungsi - Bogor - Jawa Barat HEAD OFFICE : Menara MTH, 17th Floor, Jl. M. T. Haryono, Kav 23, Jakarta Selatan 12820, Indonesia Telephone : +62 (021) 83782491-93; Fax. : +62 (021) 83782494 Website : www. Wikarekon.co.id

Upload: timothy-white

Post on 04-Nov-2015

72 views

Category:

Documents


3 download

DESCRIPTION

Method

TRANSCRIPT

  • for Inur Sakato Power Plant in Timor Leste

    PT WIJAYA KARYA

    REKAYASA KONSTRUKSI

    Mechanical & Electrical Construction - Operation & Maintenance

    METHOD STATEMENT FOR CABLE GROUNDING INSTALLATION

    Erection and Installation of Civil, Mechanical and Electrical Works

    Workshop: Komplek Industri Kembang Kuning. Jl. Raya Narogong, KM 26,5. Cileungsi - Bogor - Jawa Barat

    HEAD OFFICE :Menara MTH, 17th Floor, Jl. M. T. Haryono, Kav 23, Jakarta Selatan 12820, Indonesia

    Telephone : +62 (021) 83782491-93; Fax. : +62 (021) 83782494

    Website : www. Wikarekon.co.id

  • Owner:

    INUR SAKATO 4 X W9L34 POWER PLANT - PROJECT

    Contractor:

    PT WIKA REKAYASA KONSTRUKSI

    Contract No

    METHOD STATEMENT FOR CABLE

    GROUNDING INSTALLATION.

    Document No :

    Page 1 of 8

    1 of 8

    METHOD STATEMENT FOR CABLE GROUNDING INSTALLATION

    Revision Name Kind of Change Date Signature

    Action Name Title Date Signature

    Prepared By Bayu dwi p

    Reviewed By

    Reviewed By

    Reviewed By

    Reviewed By

    Reviewed By

  • Owner:

    INUR SAKATO 4 X W9L34 POWER PLANT - PROJECT

    Contractor:

    PT WIKA REKAYASA KONSTRUKSI

    Contract No

    METHOD STATEMENT FOR CABLE

    GROUNDING INSTALLATION.

    Document No :

    Page 2 of 8

    2 of 8

    CONTENTS

    Page

    1. TITLE 3 of 8

    2. SCOPE . 3 of 8

    3. OBJECTIVE 3 of 8

    4. REFERENCE .. 3 of 8

    5. RESPONSIBILITY .. 3 of 8

    6. WORK PROSEDURE 4 of 8

  • Owner:

    INUR SAKATO 4 X W9L34 POWER PLANT - PROJECT

    Contractor:

    PT WIKA REKAYASA KONSTRUKSI

    Contract No

    METHOD STATEMENT FOR CABLE

    GROUNDING INSTALLATION.

    Document No :

    Page 3 of 8

    3 of 8

    1.0 TITLE

    Underground Earthing Works

    2.0 SCOPE

    This method is to describe the minimum requirements for earthing conductor installation in materials receiving, storing, and installation.

    3.0 OBJECTIVE

    This is to assure that the requirements of underground earthing installation works are meets the codes requirements and contract specifications. To make sure, the works are carried out in acceptable workmanship and follow the requirements of project.

    4.0 REFERENCE

    4.1 Applicable Manufacturers Recommendation 4.2 Contract Specifications and approved Construction Drawing 4.3 Standards, codes and recommended practices

    5.0 RESPONSIBILITY

    5.1 The Site Engineer at site shall be responsible for the planning scheduling and coordination, record and monitor progress of Underground earthing works. To guide the supervisors in the field in terms of engineering and technical problems.

  • Owner:

    INUR SAKATO 4 X W9L34 POWER PLANT - PROJECT

    Contractor:

    PT WIKA REKAYASA KONSTRUKSI

    Contract No

    METHOD STATEMENT FOR CABLE

    GROUNDING INSTALLATION.

    Document No :

    Page 4 of 8

    4 of 8

    6.0 WORK

    6.1 GENERAL

    1. The field installation, inspection and test of underground earthing shall be executed under the responsibility of contractor according to the relevant drawings and documents.

    2. The work shall be done according to good workmanship and by using the

    suitable tools and material as stated in the construction drawings, approve documents, and procedures and it shall be studied before carry out any electrical works.

    3. Safety and Sanitation.

    Full care and pre-caution shall be given by the field management for the safety and sanitation of workman in the field to prevent accidents during execution of the works.

  • Owner:

    INUR SAKATO 4 X W9L34 POWER PLANT - PROJECT

    Contractor:

    PT WIKA REKAYASA KONSTRUKSI

    Contract No

    METHOD STATEMENT FOR CABLE

    GROUNDING INSTALLATION.

    Document No :

    Page 5 of 8

    5 of 8

    6.2 GENERAL STEP OF CABLE GROUNDING INSTALLATION

    1. Prepare the clamping tool :

    To know C clamp already installed corectly, we must measure the difference end

    of the C clamp before and after clamping proses.

  • Owner:

    INUR SAKATO 4 X W9L34 POWER PLANT - PROJECT

    Contractor:

    PT WIKA REKAYASA KONSTRUKSI

    Contract No

    METHOD STATEMENT FOR CABLE

    GROUNDING INSTALLATION.

    Document No :

    Page 6 of 8

    6 of 8

    2. Ensure excavation work in every building foundation already finish, and the

    elevation of excavation appropriate with the design level

    3. .Install Grounding cable in every building foundation, Installation start from

    base excavation, and cable grounding must be touch with the soil.

  • Owner:

    INUR SAKATO 4 X W9L34 POWER PLANT - PROJECT

    Contractor:

    PT WIKA REKAYASA KONSTRUKSI

    Contract No

    METHOD STATEMENT FOR CABLE

    GROUNDING INSTALLATION.

    Document No :

    Page 7 of 8

    7 of 8

    4. Ensure every conection of grounding cable installed correctly.

  • Owner:

    INUR SAKATO 4 X W9L34 POWER PLANT - PROJECT

    Contractor:

    PT WIKA REKAYASA KONSTRUKSI

    Contract No

    METHOD STATEMENT FOR CABLE

    GROUNDING INSTALLATION.

    Document No :

    Page 8 of 8

    8 of 8

    5. For grounding cable rise up the installation must be installed correctly.