![Page 1: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/1.jpg)
Metrics BasedMetrics BasedProjectProject
GovernanceGovernance
“Without objective data you are justanother person with an opinion”
Presented by : Pam MorrisTOTAL METRICS
ACOSM 2003
![Page 2: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/2.jpg)
Department of Innovation, Industry and Regional Development Victoria Online
“harnessing the“harnessing thecapabilities of yourcapabilities of your
metrics team tometrics team tominimise project risk”minimise project risk”
![Page 3: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/3.jpg)
3
Victoria Online
Summary SlideStandish Group Chaos Report : 1994 -2002
![Page 4: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/4.jpg)
4
Victoria Online
Standish Group Chaos Report : 1994 - 2002
0%10%20%30%40%50%60%70%80%90%
100%
1994 1996 1998 2002
ChallengedFailedSucceeded
•Successful - on timeand on budget with allfeatures and functions•Challenged - overbudget, over time, not allfunctions and features•Failed - cancelled
Only 34 % achieved Business Intent
Governance – “balancing risk against opportunity”
![Page 5: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/5.jpg)
5
Victoria Online
Consequences of Failure� Private / public embarrassment
� Missed business opportunities
� Disenchanted clients
� Legal repercussions
� De-moralised staff
![Page 6: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/6.jpg)
6
Victoria Online
August 1999 - INCIS - New ZealandPolice System “NZ Finance Minister confirmed that INCIS' cost to thetaxpayer so far was $106 million. Others have estimated thecost at up to $130 million, but in any case, costs have run wellbeyond the $98 million police budgeted for the entire project in1995”.Computerworld - 10th August 1999
“the New Zealand police said to have made more than 900variations to the original 10,000-page contract and IBM saying ithad already lost $40 million on the ill-fated application”The Age 24 June 2003
![Page 7: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/7.jpg)
7
Victoria Online
Feb 2001 - Citylink – Melbourne’s Tolling andTunnel System- “Trouble is, it's been plagued with problems from
the first sod - delays technical problems withcomputer tolling systems” 7:30 Report 22nd Feb 2001
- “Transurban claimed liquidated damages of$251.5 million from TOJV for the late completionof the Melbourne CityLink”. Citylink Media Release - 27th November 2001
![Page 8: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/8.jpg)
8
Victoria Online
Feb 2003 - Victorian Public TransportTicketing System
- “In February, the Victorian Governmentcompleted payment of a $65 million settlementto ERG subsidiary OneLink after changes madeto the project design at a late stage blew out thebudget of OneLink's Melbourne public transportticketing system rollout. ” The Age June 24th 2003
-
![Page 9: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/9.jpg)
9
Victoria Online
August 2003 - RMIT - Academic ManagementSystem
- “The AMS project displayed a lack of essentialrigour and a lack of effective risk management ”Victorian Auditor Generals Report 2003
- “Original estimate was $12.6 million it is nowanticipated to cost $47.3 million by the end of thisYear” The Australian – August 5th 2003
![Page 10: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/10.jpg)
Department of Innovation, Industry and Regional Development Victoria Online
Attributes ofAttributes of“Scope Manager”“Scope Manager”
Excellent skills in:Business analysisMetrics and Function pointsCommunicationManagement Reporting
Report to:Project Board / Project Sponsor
Paid by:Project Budget/client/supplier
Independence
![Page 11: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/11.jpg)
11
Victoria Online
Governance
Board of Directors
CFO CEO CIO
Project Board
IT Project Director
Business ProjectManager
DevelopmentProject Manager
Project Team
“ScopeManager”
Project Governance
IT Governance
Project Sponsor
Corporate Governance
![Page 12: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/12.jpg)
Project Activities – Metrics Based Governance
Business CaseFPA Size “Estimate”
Effort, Costand DurationEstimate
ISBSGIndustryProductivityData
Approval
©Total Metrics
BENEFIT - Independent project estimatesbased Industry data from ‘best practice’
experience or reality check on clientbudget.
Feasibility Study
Budget allocation
![Page 13: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/13.jpg)
13
Victoria Online
Will the software be delivered in time and beworth the Business Value?
300 ~ 500 function points
Delivery ~ 7 to 9 months
Cost ~ $390k to $580k
Develop Requirements / RFT
Budget Approval
![Page 14: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/14.jpg)
Project Activities – Metrics Based GovernanceRequirementsSpecification
Functional Analysis
RequirementsFunctionalSize
RequirementsAssessment &Refinement
BENEFIT – Independently reviewed,auditable, quantified, traceable list of
requirementsRFT
©Total Metrics
RequirementsFunction &DataCataloguedList + Profiles
![Page 15: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/15.jpg)
15
Victoria Online
Baseline List of Individual Requirements
![Page 16: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/16.jpg)
16
Victoria Online
Profile and Quantify Requirements
Core Functions selectivelyidentified and selectively sized= 300fps of total of 450 fps
![Page 17: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/17.jpg)
17
Victoria Online
Re-Estimate – Java , J2EE
Minimum MaximumFunction Points 400 550PDR hrs/fp 17 21Effort hours 5,442 7,197Duration months 9.0 11.4Cost $642,108 $849,255Cost $/fp $1,167 $2,123
![Page 18: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/18.jpg)
Project Activities– Metrics Based GovernanceTenderResponseEvaluation
SuppliersFunctionalSolution
BENEFIT – Independent evaluationsuppliers price and schedule
estimates. Quantitative match ofsupplier functional proposal
Select Supplier
©Total Metrics
Compare againstInitial Effort, Cost andDuration Estimate
Suppliers totalcost andschedule
SuppliersPrice Dollarsper FP
Estimates Reality Check
%Match against RFTFunction & DataCatalogue Lists
![Page 19: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/19.jpg)
19
Victoria Online
Suppliers Solution Mapped to Requirements
Quantify % Match = 205out of core 300 functionpoints can be deliveredwithout change by theSuppliers PackageSolution
![Page 20: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/20.jpg)
20
Victoria Online
Evaluate Suppliers Responses forReasonableness
Estimates Minimum MaximumDuration months 9.0 11.4Cost $/fp $1,167 $2,123Supplies Bids Cost $/fp DurationSupplier A $1,892 12Supplier B $1,563 10Supplier C $987 6⌧
![Page 21: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/21.jpg)
Project Activities– Metrics Based Governance
FunctionalSpecification
BENEFIT – Independent assessment ofcompleteness of Functional Requirements.Quantify different functional solutions to fitbudget / schedule. Expert advice on Pricing &Change Control Model and Project Metrics.
Build
©Total Metrics
SpecificationAssessment &Refinement
FunctionalAnalysis
Refine BaselineFunctional Sizeand Catalogue
Quantify FRS matchto RequirementsRFT
EstimatesReality Check
Budget andscheduleconstraints
Advice on Cost & Change Control Model and Metrics
![Page 22: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/22.jpg)
Project Activities– Metrics Based GovernanceFunctionalChanges
Implement Change
©Total Metrics
SpecificationAssessment &Refinement
FunctionalAnalysis
Update BaselineFunctional Size
Quantify sizeof Change forPricing
EstimatesReality Check
Budget andscheduleconstraints
BENEFIT – Independent objective assessmentof the extent of change and assistance with
pricing. Quantify impact on plannedschedules and budgets.
![Page 23: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/23.jpg)
23
Victoria Online
Quantified Traceable Changes AgainstRequirements
![Page 24: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/24.jpg)
Project Activities– Metrics Based GovernanceProjectProgressReporting
BENEFIT – Independent assessment ofproject status by quantifying percent
delivered.
ReviseStrategy
©Total Metrics
Earned Value -FPs deliveredversus plannedschedule.
Map User AcceptanceTesting Test Cases againstFunctional Catalogue
ISBSGIndustryProjectActivityProfile
Identify and quantify Test Casecoverage, hot spots for defects
![Page 25: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/25.jpg)
25
Victoria Online
Independent ProgressRecording Project Team
record Actualtime againstfunction
Completed %Status ofFunctionpredicts EffortConsumed
TodaysD 25-Apr-02Week # 8
BFCs
1.1Create Assignment 2.4 Specified 26% 6 14.4 3.0 3.7 11.4
1.2 Modify Assignment 2.4 Specified 26% 6 14.4 5.0 3.7 9.4
1.3View / Print Assignment Detail 2.4 Specified 26% 3 7.2 5.0 1.9 2.2
1.4.1Assign Contractor to Assignmnt 2.4 Specified 26% 4 9.6 4.0 2.5 5.6
1.4.2Remove Contractor Assignmnt 2.4 Specified 26% 3 7.2 7.0 1.9 0.2
1.4.3List Assignment Contractors 2.4 Specified 26% 4 9.6 4.0 2.5 5.6
1.5 Quotation Success 2.4 Built 74% 4 9.6 6.0 7.1 3.6
1.6List Assignments Date Range 2.4 Built 74% 3 7.2 1.5 5.3 5.7
2.1Create Assignment Type 2.4 Built 74% 4 9.6 6.5 7.1 3.1
2.2Modify Assignment Type 2.4 Built 74% 4 9.6 5.5 7.1 4.1
2.3Delete Assignment Type 2.4 Specified 26% 3 7.2 1.5 1.9 5.7
2.4View Assignment Type 2.4 Specified 26% 3 7.2 1.5 1.9 5.7
2.5List /Print Assignment Type 2.4 Tested 91% 3 7.2 4.7 6.6 2.5etc…………… etc……
TOTAL 119 285.6 105.9 139.5 178.2
Completed Stage
Current Completion %
Function Points
Predicted PDR
(hrs/fp)Actual Hours Remaining
Predicted Total Hours
FP Predicted
Hours Consumed
Actual Hours Consumed
![Page 26: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/26.jpg)
26
Victoria Online
Progress Reporting
start 01-Mar-02 Week Number 8today 25-Apr-02 Actual Original Plan
1.8 2.4
58.1 46.5
105.9 132.8
178.2 161.8
10.5 9.607-Jul-02 01-Jul-02
PDR
Actual Value Calculation based on:
Hours consumed for FPs delivered
Function Points Delivered
Effort Hours ConsumedRecorded by team for work against a function
FPs by Percentage completion
Effort Hours Remaining
Predicted by Remaining hours
Relationship between Effort and Duration
Total hours predicted minus hours consumed
Weeks RemainingDue Completion Date
![Page 27: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/27.jpg)
27
Victoria Online
Progress Reportingstart 01-Mar-02 Week Number 8today 25-Apr-02 Actual Original Plan
48.9% 39.1%
40.2% 48.9%
45.1% 36.0%
% Effort Consumed
%Effort Consumed of total compared to Effort predicted to be consumed for FPs delivered
%Schedule Consumed
%Schedule Consumed of total compared to predicted to be consumed for the effort expended
% Product Delivered
%FPs Delivered of total compared to that predicted to be delivered for effort consumed
Calculation based on:
![Page 28: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/28.jpg)
Project Activities– Metrics Based GovernanceProjectImplementation
BENEFIT – Independent assessmentproject productivity and process. Expert to
assist in the collation of data forsubmission to the ISBSG Repository and
interpretation of results.
Contract Signoff
©Total Metrics
Validation,collation,analysis andsubmission ofProject Metrics.
Project Productivity andQuality AssessmentReport
ISBSGIndustryProjectDataRepository
![Page 29: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/29.jpg)
Department of Innovation, Industry and Regional Development Victoria Online
Case StudiesCase Studies
Case 1- Win / Win
Complete functional requirementsSuccessful implementation, on
time, on budget and all requirementsGood Productivity ratesOngoing good relationship
![Page 30: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/30.jpg)
Department of Innovation, Industry and Regional Development Victoria Online
Case StudiesCase StudiesCase 2 – Conflictive
Supplier estimates unrealisticEarly warning of potential over
runs
Supplier status reporting notreflective true situation
Quantitative assessment offunctionality delivered to UAT
Requirements not all implemented Quantitative assessment of
functionality omitted for pricenegotiations
![Page 31: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/31.jpg)
Department of Innovation, Industry and Regional Development Victoria Online
Which ProjectsWhich ProjectsNeedNeed
Governance?Governance?High risk
New / inexperienced projectmanagement
High profile
![Page 32: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/32.jpg)
Cost / BenefitCost / BenefitAnalysisAnalysis
Cost ? = 1 – 3 % of software cost•depending on :
•level of activities•Size of project•Internal or external consultant
Cost of not having it ?•0 – >100% of project cost
![Page 33: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/33.jpg)
Key SuccessKey SuccessFactors?Factors?
FPA is a standardised, structuredmethod to identify, classify andquantify functionality to be deliveredIndependence of Scope ManagerCertification of Scope ManagerReporting at Project Board LevelCommitment both Client and SupplierCustomisation of method to suitProjectTransparency of the processAvailability of relevant ISBSG data
![Page 34: Metrics Based Project Governance · 2009-04-01 · 7 Victoria Online Feb 2001 - Citylink – Melbourne’s Tolling and Tunnel System - “Trouble is, it's been plagued with problems](https://reader033.vdocuments.net/reader033/viewer/2022042206/5ea8cbf480de1656d460cebd/html5/thumbnails/34.jpg)
Thank YouThank You
Total MetricsTotal Metricswww.totalmetrics.comwww.totalmetrics.com