mill expansion plan tamil nadu newsprint and papers ... · tamil nadu newsprint and papers limited...
TRANSCRIPT
EXECUTIVE SUMMARY
MILL EXPANSION PLAN
TAMIL NADU NEWSPRINT AND PAPERS LIMITED - UNIT II Mondipatti, Manapparai, Trichy District.
Project Proponent
TAMIL NADU NEWSPRINT AND PAPERS LIMITED Guindy, Chennai, Tamil Nadu
April 2018
EIA Consultant Project Consultant
Cholamandalam MS Risk Services Limited SPB Projects and Consultancy Limited
Parry House, 4th Floor, No.2, NSC Bose Road Esvin House, Perungudi, Chennai 600 001, Tamil Nadu Chennai 600096
QCI Accredited EIA Consultant Organization Tamil Nadu
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-2
Contents
Clause # Title Page #
1. INTRODUCTION ............................................................................................... 4
1.1. Preamble and Project Proponent ....................................................................... 4
1.2. Proposed Mill Expansion Plan (MEP) ................................................................ 4
1.3. Need for EIA Study ............................................................................................ 4
1.4. Project Screening and ToR ................................................................................ 5
1.5. EIA Study .......................................................................................................... 5
1.6. Environmental Setting of the Mill ....................................................................... 5
2. ENVIRONMENTAL MANAGEMENT ASPECTS IN EXISTING FACILITY .......... 7
3. DETAILS OF THE PROPOSED MILL EXPANSION .......................................... 7
3.1. Land for the Proposed Mill Expansion Plan ....................................................... 8
3.2. Materials and Resources Requirement ............................................................ 10
3.3. Project Cost ..................................................................................................... 12
4. DESCRIPTION OF THE BASELINE ENVIRONMENT ..................................... 12
4.1. Site Specific Meteorological Conditions ........................................................... 12
4.2. Ambient Air Quality Monitoring ........................................................................ 12
4.3. Water Environment .......................................................................................... 13
4.4. Noise Level Survey .......................................................................................... 14
4.5. Soil Environment ............................................................................................. 14
4.6. Flora and Fauna Studies ................................................................................. 14
4.7. Socio Economic Environment .......................................................................... 15
5. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
15
5.1. Impact during Construction Phase ................................................................... 15
5.2. Impact during Operation Phase ....................................................................... 15
5.3. Fugitive Emissions and Associated Environmental Impacts ............................. 16
5.4. Non Condensable Gas (NCG) Emissions and Control ..................................... 16
5.5. Traffic Impact ................................................................................................... 16
5.6. Noise Emissions and Control ........................................................................... 17
5.7. Impacts on the Water Environment .................................................................. 17
5.8. Soil and Groundwater Quality Related Impacts ................................................ 18
5.9. Impact of Solid Waste ...................................................................................... 18
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-3
5.10. Impacts on Ecological and Biological Environment .......................................... 18
5.11. Socio-economic Impact ................................................................................... 19
6. ENVIRONMENTAL MANAGEMENT PLAN ..................................................... 19
6.1. Environmental Management during Construction Phase ................................. 19
6.2. Air Quality Management during operation phase ............................................. 19
6.2.1. Management of Non Condensable Gases (NCG) Emission ............................. 20
6.3. Wastewater Management ................................................................................ 21
6.4. Solid Waste Management ................................................................................ 21
6.5. Ecology and Biodiversity Management Plan .................................................... 21
6.6. Captive Plantations .......................................................................................... 22
6.7. Community Development Plan under CSR Programs ...................................... 22
6.8. Budgetary Cost Estimates for Environmental Management ............................. 22
7. ADDITIONAL STUDIES ................................................................................... 22
7.1. Public Hearing ................................................................................................. 22
7.2. Risk Assessment Study and Risk Mitigation measures .................................... 22
7.3. Fire Hazards .................................................................................................... 23
7.4. Risks due to Storage and Handling of Coal and Risk Control Measures .......... 23
7.5. Occupational Health and Noise Management Plan .......................................... 23
8. PROJECT BENEFITS ..................................................................................... 24
9. CONCLUSIONS .............................................................................................. 24
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-4
1. INTRODUCTION
1.1. Preamble and Project Proponent
Tamil Nadu Newsprint and Papers Limited (TNPL) was established by the
Government of Tamil Nadu during early eighties to produce Newsprint and Printing
& writing Paper using Bagasse- sugarcane residue, as primary raw material. The
Unit I of TNPL located at Kagithapuram, Karur District (about 400 km southwest of
Chennai) was commissioned in October 1985 with an installed capacity of 90,000
tpa of Newsprint/Fine Paper, with a single machine. Over the years, the Company
has emerged as one of the largest bagasse based Paper Mills in the World with a
production capacity of 4 lakhs MT per annum. TNPL installed and commissioned
during January 2016, a New Green Field 200,000 MT per annum Multi Layer Coated
Boards, Unit II, at Mondipatti, Chettichatram and K.Periyapatti Villages at
Manapparai Taluk, Trichy District over a mill area of 303.35 acres and total land
area of 874.46 acres.
1.2. Proposed Mill Expansion Plan (MEP)
In order to further strengthen its position in printing and writing (P&W) paper
segment, TNPL is contemplating expansion of unit 2 by adding a P&W paper
machine along with a new chemical hard wood pulp mill, chemical recovery, power
plant and utilities. Total cost of the project is estimated at Rs.2100 Crores
The proposals covered under the Mill Expansion Plan (MEP) project are
Addition of one (1) new 1,65,000 tpa P&W paper machine .
To meet the pulp demand after MEP, New 1,40,000 BD tpa ECF Chemical
Wood Pulp Mill
One (1) new 130 tph AFBC boiler
Increasing the captive power generation capacity from 30 MW to 80 MW, by
installing two new Turbo Generators of total capacity 50 MW.
New Effluent treatment plant (ETP) with 15,000 m3/day capacity in addition to
augmentation of existing ETP from 9,000 m3/day to 12,000 m3/day
Adopting efficient water management and wastewater management program
to maximise recycling treated wastewater reduce specific water consumption
significantly
1.3. Need for EIA Study
According to the Environmental Impact Assessment Notification issued by Ministry
of Environment, Forests & Climate Change (MoEF&CC) under Environment
Protection Act, pulp and paper industries (excluding manufacture of paper from
waste paper) and captive co-generation power plant with a capacity greater than 5
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-5
MW are required to obtain environmental clearance for installation/ expansion or
modernization..
The proposed mill expansion project comprises of manufacture of pulp, which falls
under category “A” under sector 5(i) & enhancement of Captive Power Plant (CPP)
capacity from 30MW to 80 MW by installing 50 MW TGs and 130 tph capacity FBC
coal fired boiler, which falls under category “B” under sector 1(d) of the EIA
Notification 2006. Since the existing mill site does not fall under any notified
industrial area, public consultation will be conducted as per the Environmental
Impact Assessment (EIA) Notification 2006.
1.4. Project Screening and ToR
The proposed MEP was appraised by the Expert Appraisal Committee (Industry-I),
Ministry of Environment Forest and Climate change (MoEF&CC) in the 18th Expert
Appraisal Committee meeting held on 3rd to 5th May 2017 and based on the same,
Terms of Reference (ToR) vide File no. J-11011/172/2017-IA-II (I), dated, 22nd May
2017 was accorded.
1.5. EIA Study
The EIA study was undertaken in conformity with the guidelines and all the aspects
of the specific conditions mentioned in the Terms of Reference (ToR) issued by
MoEF&CC.
This EIA study was undertaken by M/s Cholamandalam MS Risk Services Limited, a
NABET accredited EIA consultant organisation, with specific project related inputs
required for undertaking the EIA studies from SPB Projects and Consultancy Ltd
(SPB-PC), Chennai.
1.6. Environmental Setting of the Mill
The proposed Mill Expansion Plan (MEP) will be located in the existing mill premises
at Mondipatti Village, Manapparai Taluk, Tiruchirappalli District, Tamil Nadu by
utilizing vacant space inside the existing mill.
The existing site is located at the intersection of latitude 10º 41' N and longitude 78º
26"E and falls in the Survey of India Topography Map number 58 J /6 / NE. Topo
sheet map of 10 km radius is given in Figure 1.
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-6
Figure 1: Topography Map of 10 km radius from project site
The details of environmental setting around the existing plant site are given in the
following Table 1.
Table1: Environmental Setting around the Existing Plant Site
S.No. Particulars Details
1
Location
Town/Village Mondipatti
Taluk Manapparai
District Tiruchirappalli
State Tamil Nadu
2 Latitude 100 41
‟ N
3 Longitude 780 26
‟ E
4 Elevation above mean sea level (MSL)
145 m
4 Climatic conditions as per IMD Belgaum
Annual Max. Temp 40 oC Annual Min. Temp 17.4 oC Annual total rainfall 880mm Predominant wind direction: West Wind Speed :13.3 kmph
5 Present land use at the proposed site Industrial land use
6 Nearest highway/road
National Highway (NH) 45- Trichy- Dindugal Road at distance 5 km, South
State Highway (SH) 71- Kulithalai- Manapparai Road at distance of 1
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-7
S.No. Particulars Details
km, West
7 Defence installations Nil within 7-km radius
8 Nearest railway station Manapparai Railway Station at distance of 7.5 Km, South
9 Nearest airport/air strip Tiruchirappalli International Airport at aerial distance of 32 Km
10 Nearest Village Mondipatti at aerial distance of 1.2 Km
11 Nearest Town Manapparai at aerial distance of 7.0 Km
12 Nearest River
River Ariyar -6.7 Km, East
Mamundi River (seasonal)- 7.6 Km, south
River Ponnani (Seasonal)- 8.6 Km, South
River Napili (Seasonal)- 10.0 Km, North East
13 Hills/ Valleys Thogamalai Hill at an aerial distance of 6.7 Km
14 Archaeologically important places Nil
15 Ecologically sensitive areas (National Parks/ Wildlife sanctuaries/bio-sphere reserves)
Nil within 10 Km radius
16 Reserved/Protected forests within 10 km radius
Viramalai RF 5.2 Km West
Naganur RF 5.6 Km North West
Amaiyapuram RF
9 Km South West
Thogaimalai Hill
6.7 Km South West
17 List of industries Nil
18 Topography of the plant site Flat Terrain
19 Nature of soil Sandy Loamy
2. ENVIRONMENTAL MANAGEMENT ASPECTS IN EXISTING FACILITY
The mill obtained Environmental Clearance for the “Project of 2, 00,000 tpa Multi
Layer Double Coated Paper Board with 30 MW Captive Power Plant, vide Letter
No.SEIAA-TN/F.No.1203/2013/5(i)&1(d)/EC-11/2014 dated, 06.02.2014.
TNPL obtained Consent for Establishment and subsequently obtained Consent for
Operation under the Water and Air Acts for Multi Layer Double Coated Paper Board
with 30 MW Captive Power Plant project from Tamil Nadu Pollution Control Board
during 2016.The unit was further obtained Renewal Consent for Operation till
31.03.2018. Further, the unit has also obtained Hazardous waste authorization, with
validity till 20.02.2022.
3. DETAILS OF THE PROPOSED MILL EXPANSION
The post-Mill Expansion Plan (MEP) capacity of the TNPL Unit 2 will be 3.65 lakh tpa
comprising 1.65 lakh tpa Printing and Writing paper in addition to exisiting paper
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-8
board production of 2.0 lakh tpa (increase by 1,65,000 tpa). Towards this, a with ECF
Chemical Wood Pulp Mill of capacity 1,40,000 BD tpa and chemical recovery section
will be installed in addition to augmentation of existing Captive Power Plant, Effluent
Treatment Plant and other infrastructure. The details of the plant capacities are
presented in Table 2.
Table 2: Plant Capacities – Existing, Post MEP and MEP Proposals
Description Unit Existing Incremental Post MEP MEP
Proposal
Paper Machines
Board Production tpa 2,00,000 -- -- No Change
Printing & Writing Paper machine
tpa 1,65,000 1,65,000 New
proposal
Total Board/Paper Production
tpa 2,00,000 1,65,000 3,65,000 --
ECF Chemical Wood Pulp Mill
BD tpa -- 1,40,000 1,40,000 New
proposal
Recovery plant, including Recovery Boiler
tpd of black liquor solids -- 1,100 1,100
New proposal
Lime kiln tpd of lime
-- 250 250 New
proposal
Power Boilers
- Power Boiler s tph of steam
2 x 90=180 1 x 130 310 Expansion
- Turbo Generators
MW of power
30 50 (1 x 30
MW +1 x 20 MW)
80 Expansion
Waste Water Treatment
m³/day 9000
From 9000 to 12,000 +
addition of new 15,000
27,000
Augmentation of existing ETP and addition of new for pulp mill stream,
3.1. Land for the Proposed Mill Expansion Plan
Since the available free space in the mill will be used for project facilities, no
additional land is required. Unit 2 has total land of 874.46 acres, with vacant spaces
and well covered with greenery.
For MEP project, around 100 acres will be utilised in the vacant land available in the
existing plant area of 303.35 acres. The land use break-up Post Project is given in
the following table. The vacant spaces available in the mill premises have been
identified and found to be suitable and adequate to accommodate all the new
facilities planned under project.
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-9
Table 3 Land Usage (area in Acres)
S.No Category Existing
(Acres)
Post MEP
(Acres)
A Mill Area
1 Plant & Building 32.00 56.05
2 Storage area 93.00 97.27
3 Roads/Drains 5.00 7.41
4 Vacant area (for future development) 70.00 7.27
5 Green belt/ green cover within mill
area
103.35 135.35
Total Mill area 303.35 303.35
B Colony 21.00 21.00
C Green belt/Green cover/Irrigation
using treated waste water
550.11 550.11
Total (A+B+C) 874.46 874.46
The overall mill layout is presented in Figure 2.
Figure 2- Proposed facility in the existing plant site
Existing WTP/ETP
Existing Board Machine
New ETPExisting Power Plant
Proposed Paper Machine
Pulp Mill Chemical Recovery
&Power Plant Area
Existing WTP/ETP
Existing Board Machine
New ETPExisting Power Plant
Proposed Paper Machine
Pulp Mill Chemical Recovery
&Power Plant Area
Existing WTP/ETP
Existing Board Machine
New ETPExisting Power Plant
Proposed Paper Machine
Pulp Mill Chemical Recovery
&Power Plant Area
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-10
3.2. Materials and Resources Requirement
3.2.1 Raw materials
The raw material requirement for the proposed MEP is presented in the Table 4
Table 4: Raw Materials Requirement
S.No Description Unit Existing Incremental Post MEP
Source
1 Wood tpa Nil 5,70,000 5,70,000
As per current practice in Unit-I viz., From TAFCON and captive plantations, farm forestry.
2 Hard wood pulp
tpa 36,800 Nil 32,800 -
3 Soft wood pulp
tpa 8,200 Nil 8,200 -
3.2.2 Chemicals Requirement
The major process chemicals required to be used and procured for the bleached
pulp production of 1,40,000 tpa is given in the following table. All the process
chemicals shall be procured from suppliers, shall be transported by trucks.
Table 4: Chemical Requirement during Post MEP
Chemicals Unit Existing Post MEP
Procured from Suppliers
Caustic tpa Nil 1,700
Hydrogen Peroxide tpa Nil 2,100
Sulphuric Acid tpa Nil 700
Lime stone tpa Nil 22,800
Captive
Oxygen tpa Nil 3,900
Chlorine Dioxide tpa Nil 1,400
Ozone tpa Nil 840
3.2.3 Fuel Requirement
Imported coal and furnace oil are the major source of fuel required. The quantity of
furnace oil and additional coal requirement is given below
Table 5: Fuel Requirement during Post MEP
Fuel Unit Existing Post MEP Incremental Source
Coal tpa 1,70,000 3,10,000 1,40,000 Additional coal will be Imported from Indonesia
Furnace oil kl Nil 5,600 5,600 Local market
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-11
3.2.4 Water Requirement
The fresh water requirement after MEP will be around 20,700 m³/day. Fresh water
will be sourced from River Cauvery through existing collector wells. Water
requirement will be within water drawal permission of 23,100 m3/day. The specific
water consumption will be maintained <25 m3 per tonne of paper production post
MEP.
As part of MEP, some more proposals are being planned to bring the fresh water
requirement to the stipulated norms during the post project scenario.
3.2.5 Wastewater Generation
The wastewater generated from the entire mill after MEP will be around 18,000
m³/day. Total treated wastewater reused in the plant will be around 3800 m3/day, out
of which 2000 m3/day of water is recycled directly from paper machine (P&W)
without treatment at ETP and the remaining 1800 m3/day of treated wastewater from
ETP will be recycled back to process. Total treated wastewater discharge from
WWTP will be 16,000 m³/day for irrigation.
Table 6: Proposed MEP Water Balance
Description Fresh water
make-up, m
3/day
Treated wastewater
reused, m
3/day
Evaporation/other losses
m3/day
Wastewater to ETP, m
3/day
Board Machine and SFT 2800 2900 1100 4600
Paper Machine (P&W) 6000 -- 720 3280
Pulp Mill 6000 -- 6000
Chemical recovery plant 4000 -- 880 3120
Power Plant 1200 800 1200 800
Others 700 100 600 200
Total Plant (A) 20700 3800 4500 18000
3.2.6 Wastewater Treatment and Discharge
Existing effluent treatment plant will be upgraded to treat total paper/board machines
effluent. A new ETP will be installed to treat pulp mill and recovery effluents.
Combined treated water meeting to the discharge standards prescribed by
CPCB/SPCB, will be used for green development/irrigation. As the areas around
the plant are only with rain fed cultivation, farmers are expected to be benefited by
using the treated wastewater for irrigation, as is being practiced currently in the
Unit# 1 & 2. TNPL Unit 2 has already covered around 650 acres of land for green
development using existing treated wastewater.
Total area requirement of land for irrigation using total treated wastewater after MEP
of 16,000 m3/day will be 1100 acres. While the existing green belt/ green cover/
plantation area is 650 acres, additional 500 acres is proposed to be covered through
contract farming or formation of society by the surrounding farmers as is done in
Unit 1.
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-12
3.2.7 Solid Waste and Hazardous Waste Generation and Disposal
The expected solid wastes generation from proposed project will be ash from the
proposed FBC boiler, additional sludge from ETP and used lube oils. The details of
solid waste generation and quantities with disposal methods are given in the Table
7.
Table 7: Details of Solid Waste Generation and Disposal
S.No Source Quantity in tpd
Disposal Method Existing Post MEP
1 Boiler ash 80 120 TNPL‟s own cement mill operating at Kagithapuram, Karur as raw material.
2 Primary Clarifier sludge
30
60 Primary sludge will disposed to cardboard manufacturers
3 Secondary Clarifier sludge
10 Secondary sludge will be used as a manure for green cover development and irrigation
4 Used oil 0.03 0.06 Disposed to SPCB‟s authorised recyclers
3.3. Project Cost
Total investment for the installation of project is Rs 2100 Crores and about Rs.200
Crores is allocated towards pollution control equipment and implementation of
environmental pollution control measures.
4. DESCRIPTION OF THE BASELINE ENVIRONMENT
As a part of EIA and in line with approved ToR, the primary baseline data monitoring
was carried out covered three (3) months i.e., from 8th June 2017 to 6th September
2017 and secondary data was collected from respective Government and other
authenticated sources. Summary of the baseline environmental study findings are
presented in the following subsections.
4.1. Site Specific Meteorological Conditions
The maximum mean ambient temperature observed during the study period is 40oC
and the minimum mean temperature is 23oC.The average hourly relative humidity
variation at site during the study period is 61%. The predominant wind direction
during the study period was from West and East. These readings are in line with
IMD long term data.
4.2. Ambient Air Quality Monitoring
Air quality monitoring at eight (8) locations was undertaken during the study period
as per the Central Pollution Control Board (CPCB) guidelines. The summary of the
average concentrations of ambient particulate matter (PM10), particulate matter
(PM2.5), Sulphur dioxide (SOx) and Oxides of Nitrogen (NO2) are presented in Table 8.
The results of the monitored data indicate that the average concentrations of air
pollutants in the entire study area are within the NAAQ standards.
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-13
Table 8: Summary of the Average Baseline Concentrations of Pollutants during the Study Period (8th June 2017 to 6th September 2017)
Code Location PM2.5
(µg/m3)
PM10 (µg/m
3)
SO2
(µg/m3)
NO2
(µg/m3)
Ozone (µg/m
3)
Ammonia (µg/m
3)
AAQ1 Existing Plant Site 35.1 73.1 6.3 18.8 21.0 23.9
AAQ2 Uthuppatti Village 28.4 61.5 5.3 17.5 21.4 23.8
AAQ3 Edayapatti Village 24.2 52.0 5.0 18.4 21.4 25.1
AAQ4 K.Periyapatty Village 22.5 48.1 4.5 15.5 19.0 22.5
AAQ5 Padhiripatti Village 23.5 52.1 3.9 12.5 20.9 23.7
AAQ6 K.Udayapatty Village 23.0 49.7 4.0 13.8 21.0 24.2
AAQ7 Chinna Reddypatti 31.0 65.5 6.0 18.1 22.9 26.5
AAQ8 Manapparai Town 34.2 72.3 7.8 22.4 25.3 25.7
NAAQ Standards 60 100 80 80 180 400
4.3. Water Environment
Since most of the rivers in study area are seasonal, no water was observed during
the study period. Hence, in order to assess the surface water quality of the study
area six samples from various lakes were and at various points around the project
site.
It is observed that pH of surface water around the project site is in the range of 6.6
to 7.6 which is neutral. The TDS levels in the surface water at various locations were
found to vary from 36 mg/L to 144 mg/L. The Total Hardness of the surface water
was found to be ranging from 17mg/l to 53 mg/l. The Fluoride concentration was
found to be in the range of 0.11 mg/l to 0.13 mg/l. The microbiological content as
total coliform was found to vary from <2 MPN/100ml at Inamkulathar Lake to 50
MPL/100ml at Samuthiram Lake. Heavy metal concentrations are below detectable
limit however traces of copper, nickel, zinc, manganese and aluminium were found
at all six lakes.
To assess the ground water quality of the study area, eight (8) ground water
sampling locations were selected. The pH of the ground water at eight locations
varied from 7.8 to 8.2 indicating that the water is alkaline. The Total Dissolved Solids
(TDS) was found to vary from 324 mg/L at plant site to 2716 at Manaparai Village.
The TDS value was higher than the permissible range of 2000 mg/L at Manaparai
Village. Similarly the hardness value was found to vary from 154 mg/L at Plant site
to 1368 mg/L at Manaparai Village and heavy metals were observed to be below
detectable limit
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-14
4.4. Noise Level Survey
Average day time and night time noise levels at Village areas in the study area was
found to be varying from 50.0 to 59.2 dB(A) and 39.5 dB(A) to 47 dB(A) respectively.
At the existing plant site the average noise level was found to be 62.3 dB (A) for day
time and 55 dB (A) for night time. The observed values are complying with the
standards of Residential, Commercial and Industrial area except at Chinna
Reddypatti Village, as the village is near to the State Highway.
4.5. Soil Environment
Eight (8) locations within the 10 km radius around the study area were selected for
soil sampling. The texture of the soil is mostly sandy. The pH of the soil was
observed to be in the range of 7.3 to 8.1 indicating that soil is alkaline. Available
Nitrogen level in the soil was observed to be in the range of 64 mg/kg to 184 mg/kg
and available phosphorus level was observed to be in the range of 118 mg/kg to 314
mg/kg indicating the presence of medium level of nutrients. Calcium was found to
be in the range of 20 to 79 mg/kg and magnesium was found to be in the range of
12 to 49 mg/kg.
4.6. Flora and Fauna Studies
During the survey of the study area, 119 floral components were recorded. Out of
these, 78 floral species (66%) belongs to trees, 16 species (13%) belong to shrubs
and 25 species (21%) belongs to herbs category. Among the tree species Ailanthus
excelsa, Albizzia lebback, Alstonia scholaris, Borassus flabellifer, Dalbergia latifolia,
Melia azardirachta, Azardiraccta indica, Pongamia pinnata, Ziziphus muritiana, etc
are common species. The species like Calotropis procera, Jatropha curcus, Opuntia
stricta and Ricinus communis are common shrub species. Species like Ipomoea
aquatica are common along the waste and wet places. Among the herbs species
like Acalypha indica, Boerhavia diffusa, Bulbostylis barbata, Cenchrus ciliaris,
Croton bonplandianus, Datura metel are commonly seen. The floral components
which were recorded during survey are enumerated with their family, vernacular
names and habitat.
The sighting of bird species was very less during the study period. Nineteen
species of birds could be located in the study area during the survey. Common
myna, Cattle egret, Southern Indian roller, house crow, Little egret, Parakeet etc are
the frequently spotted in the area. All species except Pavo cristatus are under
schedule IV of the IW(P)L Act, 1972; however, the Indian Peafowl is listed under
schedule-I. Among the herpetofauna, amphibians were represented by Frogs &
toads. These are noticed restricted to open waste land and marshy areas. No tailed
amphibians were cited during the survey. Reptilian fauna was found comparatively
richer.
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-15
4.7. Socio Economic Environment
The population in the study area is read using the 2011 census. The total
households in the study area ( identified thirty eight villages in 10 km radius) with a
total population of 4,40,681 in which 0 to 5 km radius the population is 72,551 and 5
to 10 km radius the population is 368130 respectively. In the study area, the main
occupation of the villagers is agriculture, labour work and small business of carving
items, painting, tailor etc. During the survey it was found that Mahatma Gandhi
National Rural Employment Guarantee Act, 2005 (MGNREGA) work was in process
which guarantees 100 days of employment in a financial year to rural household, for
which villagers were paid Rs 259/- per day. Water scarcity in the villages was
observed and the villagers were found to be dependent on the rainwater and
Cauvery water supply scheme (WSS).
5. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
5.1. Impact during Construction Phase
Unlike Greenfield projects, the proposed project will be limited to minor construction
activities such as earth work, foundations and flooring etc. Most of the construction
phase activities would exhibit reversible and short term impacts which can be readily
controlled and mitigated through robust and scientifically designed construction
work-method statements as per the best engineering and management practices to
comply with the Construction and Demolition Waste Management Rules, 2016 as
notified by the Ministry of Environment, Forests and Climate Change (MoEF&CC).
5.2. Impact during Operation Phase
5.2.1. Impact on Land
The proposed project will be within the existing plant premises, hence, there will not
be any change in the land use pattern in the study area due to the proposed MEP.
5.2.2. Sources of Emissions and Associated Environmental Impacts and its control
The major source of pollutants envisaged during the post project scenario will be
Particulate Matter (PM), Sulphur dioxide (SO2) and Oxides of Nitrogen (NOx) from
the proposed coal fired boiler, chemical recovery boiler and Lime kiln. Non
Condensable Gases (NCG) such as H2S and Mercaptans from pulp mill operations
are also envisaged.
In order to assess the likely possible impacts on the background air quality, air
quality modeling exercise was undertaken as per the CPCB guidelines. Site specific
meteorological data collected at the site was adopted while predicting the 2nd
highest 24 hours average ground level concentrations of Particulate Matter, sulphur
dioxide and oxides of nitrogen. ISCST3 air quality modeling tool, an MoEF&CC
approved software, was used for predicting the ground level concentrations in the
study area.
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-16
Hourly meteorological data collected from the site for the period 8th June 2017 to 7th
September 2017 has been adopted for modeling the 24-hours Ground Level
Concentrations (GLCs). The site specific mixing height data as obtained during the
EIA study of Greenfield project at TNPL unit 2 in the year 2014 were compared with
the IMD mixing heights Atlas, which were also considered for the modeling study.
5.2.3. Predicted Ground Level Concentration
The site specific meteorological information indicated that predominantly winds were
found to blow from west direction and hence the impact zone in the down wind
direction is located in the east direction.
The predicted cumulative 24 hours GLC of Particulate Matter (PM) in the study area
was reported to be in range of 48.15 μg/m3 to 73.1 μg/m3 which is within the
prescribed NAAQ standard of 100 µg/m3.
The predicted cumulative post project scenario of 24 hours average GLC of sulphur
dioxide in the study area was estimated to be in the range 3.9 μg/m3 to 10.4 μg/m3
µg/m3 which is within the prescribed NAAQ standard of 80 µg/m3.
The predicted 24 hours GLC of Oxides of Nitrogen in the study area was estimated
to be in the range 12.5 μg/m3 to 22.4 μg/m3 which are within the prescribed NAAQ
standard of 80 µg/m3.
Referring to the predicted GLC it can be observed that GLC levels of NOx are
concentrated towards Eastern side of the project site as the predominant wind blows
from West to East.
5.3. Fugitive Emissions and Associated Environmental Impacts
Fugitive emissions are defined as irregular and non point source emissions that
would be generated either from process operations or bulk material handling
facilities. In the current scenario, the proposed facility fugitive emissions may be
released due to handling of imported coal at the coal stock-yard. Extension of coal
handling plant for the proposed new boiler is envisaged with a dedicated water
sprinkling system along with proper enclosures to control the fugitive dust
emissions. Thus the envisaged fugitive coal dust emissions in the facility are
insignificant.
5.4. Non Condensable Gas (NCG) Emissions and Control
It is proposed to collect the HVLC and LVHC NCG gases separately which are
envisaged due to the proposed pulper operations by a NCG gas collection system
and burn it in the proposed rotary lime kiln within the main plant
5.5. Traffic Impact
At TNPL, Unit 2 the raw materials, finished products and coal are transported by
road in trucks and the same will be continued during the Post MEP. In order to
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-17
assess the impact of traffic due to the proposed MEP, present traffic scenario in the
study area was assessed by evaluating the current traffic volume and also additional
traffic requirements due to the proposed MEP was estimated based on the inventory
as per the raw material requirement. Additional trucks of about 213 per day will be
envisaged during the Post MEP. Hence additional Passenger Car Unit (PCU) /hr
can easily be accommodated in the existing two roads namely State Highway (SH-
71) and National Highway (NH-45).
5.6. Noise Emissions and Control
The major noise emitting sources at the proposed project site are power steam
turbine, paper machine and chipper house. Enclosures will be provided to noise
sources in order to attenuate noise emissions from the source. Hence the noise
levels of 75 dB (A) can be expected from the source after reduction and the same
noise levels are used to predict the propagation of noise levels due to the proposed
power house (boiler and turbo generator) and paper machine. Whereas 85 dB (A) of
noise power level is considered from the chipper house.
5.7. Impacts on the Water Environment
The fresh water requirement for the proposed MEP will be around 20,700 m³/day.
Water drawl permission of 23,100 m3/day has been obtained by TNPL unit 2 from
the Public Works Department (PWD). Hence the additional water required for the
proposed MEP will be sourced from River Cauvery. The specific water consumption
will be maintained <25 m3/t per tonne of paper production post MEP. Recycling of
treated final wastewater will be increased from 1000 m3/day to 3800 m3/day in the
paper mill.
About 18,000 m3/day of treated wastewater will be generated during the post project
scenario out of which 1800 m3/day will be recycled, 200 m3/day will be losses in ETP
and balance 16,000 m3/day of treated wastewater will be discharged for green belt/
cover and irrigation purpose.
From the baseline studies it was concluded that soil type in the study area of the
project site is mostly sandy. Although sandy soil demands more water for irrigation
as per the Indian Council for Agriculture Research1, the daily water application rate
is considered as 35 m3/ha/day for the calculation of requirement of land for irrigation.
Therefore total area requirement of land for irrigation using total treated wastewater
after MEP of 16,000 m3/day will be 1100 acres. TNPL Unit 2 has already covered
650 acres of land for green development using existing treated wastewater. While
the existing green belt/ green cover/ plantation area is 650 acres, additional 500
acres is proposed to be through contract farming or formation of society by the
surrounding farmers as is done in Unit 1.
1 Handbook of Agriculture- Indian Council for Agriculture Research,2012
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-18
As the areas around the plant are only with rain fed cultivation, farmers are expected
to be benefited by using the treated wastewater for irrigation, as is being practised
currently in the Unit # 1.
5.8. Soil and Groundwater Quality Related Impacts
While computing for ground water quality modeling, the worst case scenario was
considered for Low rainfall, natural recharge and high TDS value (2100 mg/L as per
the maximum permissible discharge standard).
Based on the above values the model was computed for 10 year period. The highest
predicted TDS value was found to be 1000 mg/L in the project site and the lowest
predicted value is 750 mg/L near the project site.
The induced recharge such as Ground water Recharge within the project area using
the surface run off generated from different surfaces and Artificial recharge of
ground water around the project site would improve the ground water quality.
The above indicate that there will be no adverse effect on ground water scenario
after the project .
5.9. Impact of Solid Waste
The expected solid wastes generation from proposed project includes ash from
boiler, additional sludge from ETP and lube oils. Fly ash generated from the boiler
will be stored in silos and will be disposed to cement manufacturing plant of TNPL
Kagithapuram, District Karur, Tamil Nadu. Fibre Sludge from the Primary Clarifier of
the ETP will be subjected to decanting and disposed to small cardboard
manufacturers as raw material. Secondary Sludge from Sludge Drying Bed will be
used as manure for Green Cover. The existing facility has obtained necessary
authorization from TNPCB for the collection, storage and disposal of hazardous
waste. MoU for the disposal of additional sludge and used oil during the proposed
MEP will be obtained.
5.10. Impacts on Ecological and Biological Environment
Any significant impact on the biodiversity of the area due to this proposed expansion
project is not anticipated as the TNPL unit II (total land 874.46 Acres), has sufficient
area to expand. No extra land is required for its expansion. Total area of the plant is
also well fenced by high rise boundary walls, not allowing any wildlife to enter within
the plant premises. The current facility has fully developed the green belt (650
Acres) in its premises to control the adverse impact of fugitive dust, noise and
aesthetics of the area, which usually have impact on the biodiversity. More than six
lakhs (6,01,364) plants from 79 species of horticultural importance have been
already planted till 2016. This has increased the biodiversity of the area up to a
greater extent by inviting not only many species of avifauna but many species of
vertebrates and invertebrates.
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-19
The present running plant has no significant impact on surrounding ecology and
biodiversity as pollution control equipments are of adequate efficiency, proper stack
height has been maintained and thick green belt has been developed in and around
the plant boundary which attenuates the noise & further improves the flora at site.
Besides above, no waste water from paper plant is being discharged outside the
plant premises; wastewater generated from the plant is being treated in ETP &
treated water is being utilized for greenbelt development/land irrigation and dust
suppression. The same will be maintained for proposed capacity enhancement.
Thus, no significant impact on biological environment is anticipated as a result of
proposed capacity enhancement project as effective management plan will be
implemented by TNPL.
5.11. Socio-economic Impact
Due to the proposed project there is no additional land required and the project is to
be developed within the existing site premises. Therefore Rehabilitation and
Resettlement process will not be applicable under “The Right to Fair Compensation
and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013”.
By extension of the proposed project, employment opportunities will be enhanced
and migration can be checked. The project will create direct employment to about
400 persons. In addition it would generate indirect employment to about 1000
persons in the industries and service organizations and material handling, etc.,
which will be supported by the operations of the mill.
6. ENVIRONMENTAL MANAGEMENT PLAN
6.1. Environmental Management during Construction Phase
The impacts during the construction phase on the environment would be
basically transient in nature and are expected to reduce gradually to localised
phenomena, except the permanent change in local landscape and land use pattern
of the Mill site.
6.2. Air Quality Management during operation phase
The existing facility has implemented various air quality management programs and
the stack emission test reports of TNPCB and external testing agency confirmed
that emissions were found to comply within stipulated standards. The following
environmental management plan will be adopted under proposed expansion plan:
Due to utilization of the high calorific imported coal with sulphur content less
than 1%, the specific SO2 emission rate from the proposed facility will be two
to three times lower than that of the conventional co-generation power plants
that are operated on Indian coal.
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-20
Dedicated Electrostatic Precipitators (ESP) will be installed for control of
Particulate Matter (PM) emissions from the proposed boiler in the captive
power plant. ESP will be designed to achieve emission norms of 30 mg/Nm3
as per MoEF&CC December 2015 regulations
A dry limestone/ lime sludge injection system shall be installed to meet the
SO2 emissions from boiler. Lime stone demand will be about 4 T/T of SO2
emissions from the facility and additional fly ash to the tune of 3 T/T of
SO2 will be generated from the proposed power boiler,
A 100 m tall stack will be installed to disperse the stack gases as per the
minimum stack height norms. The predicted ground level concentrations will
be complying with the NAAQ Standards
Stacks of height 90 m and 50 m (minimum) will be installed for chemical
recovery boiler and lime kiln respectively as per the minimum stack height
norms.
Like the existing boiler, continuous online stack emission monitoring unit will
be installed to monitor Particulate Matter, SO2 and NOx emissions for the
proposed boiler.
Existing Closed belt conveyors will be extended up to the new boiler for
controlling fugitive emissions
Adequately designed greenbelt is developed for further control the fugitive
emissions
6.2.1. Management of Non Condensable Gases (NCG) Emission
As a part of MEP it is proposed to install ECF Chemical Wood Pulp Mill which
consists of cooking process. Hence the following control measures and
management plan will be adopted for the control of NCG gases generated during
the Post MEP.
i. Emissions from digester relief and digester pulp discharge tanks will be
connected to water striping in the scrubber and the non-condensable gases will
be fired in the lime kiln.
ii. Emissions from digester tank and relief tanks will be connected to lime kiln
iii. Emissions from evaporator condenser, will be connected to lime kiln
iv. Vents from bleaching tanks will be connected to an alkali scrubber
Thus the NCGs and Mercaptans formed at the pulp mill section digesters, blow tank
systems and evaporators will be collected and burnt in Rotary Lime Kiln. H2S
emission testing will be carried out in the proposed limekiln stack on periodically
during Post MEP.
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-21
6.3. Wastewater Management
Fresh Water for the proposed MEP will be sourced from River Cauvery through
collector wells with the permission already obtained from State Government. Water
reuse and recycling will be carried out in the plant to maintain water consumption
less than 25 m3/t of Paper.
Total estimated wastewater quantity from the facility will be in the order of 18,000
m3/day during the post project scenario. It is proposed to augment the existing ETP
to accommodate the additional wastewater to be generated from the expansion
activities. The existing wastewater treatment plant can handle 9,000 m3/day of
wastewater. It is proposed to augment the existing ETP to treat 12,000 m3/day
board machine/ paper machine effluents. A separate ETP for treating wastewater
from hardwood pulp mill, chemical recovery and power plant effluents with a
capacity of 15,000 m3/day is proposed to be installed. After MEP Project, total ETP
capacity shall be 27,000 m3/day for handling wastewater from existing operations
and proposed project operations.
After utilization of considerable quantity of treated wastewater in the plant, the
excess, unutilized treated wastewater will be used for irrigation/greenbelt/green
cover development. Combined treated wastewater will be complying with the
discharge standards prescribed by CPCB/SPCB for discharge for irrigation. As the
areas around the plant are only with rain fed cultivation, farmers are expected to be
benefited by using the treated wastewater for irrigation, as is being practised
currently in the Unit # 1. TNPL Unit 2 has already covered 650 acres of land for
green development using existing treated wastewater.
6.4. Solid Waste Management
Solid waste generated from the plant are additional ash from proposed power boiler,
additional sludge from ETP and used lube oils. Fly ash generated from the proposed
boiler will be stored in silos and will be disposed to cement manufacturing plant of
TNPL Kagithapuram, District Karur, Tamil Nadu.
Fibre Sludge from the Primary Clarifier of the ETP will be subjected to decanting and
disposed to cardboard manufactures as raw material. Secondary Sludge from
Sludge Drying Bed will be composted and used as manure for Green Cover.
6.5. Ecology and Biodiversity Management Plan
As the new equipment for capacity enhancement project is proposed to be located
within the existing mill premises, no effect on vegetation is anticipated. Similarly,
there will not be any impact on the aquatic ecology as there are no aquatic bodies in
the plant site. A comprehensive greenbelt programme, which is already in place,
shall improve the ecological condition.
Green belt has already been developed in and around the Plant premises in about
650 Acres land. A sum of about six lakhs plants belonging to 79 species have been
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-22
planted among them species like Ficus, Eucalyptus, Neem, Ashok, Citrus, Coconut,
Artocarpus, Dalbergia, Melia, Pongamia, Syzygium etc. are some of them. Currently
TNPL has completed the plantation programme and in future it shall be maintained
to achieve proper development.
6.6. Captive Plantations
Tamil Nadu Newsprint and Papers Limited are committed to achieving quality and
excellence in the sphere of plantation by adopting superior technologies of plant
sciences and develop renewable and sustainable pulpwood plantations through
innovative methods of tree farming in degraded wasteland thereby conserving the
natural forest.
Under Captive Plantation Scheme, TNPL enters into a MoU with land owners for
establishment of plantation in their land either on lease rental or on gross revenue
sharing basis. As per the MoU, TNPL make all the expenditures right from land
development, planting, maintenance to harvesting.
6.7. Community Development Plan under CSR Programs
As per TNPL„s CSR policy, TNPL Unit-II has taken up community welfare activities
for the benefit of people living in nearby Panchayats such as Mondipatti,
K.Periyapatti and Chithanatham. In addition, need based activities are also be
carried out by Unit-II, on public request. TNPL has spent Rs.504.99 lakhs against
the allocated budget of Rs.500 lakhs for the year 2016-2017.
Need based CSR plan is developed based on the socio economic indicators, field
observations and based on the needs of the people assessed during the primary
survey. The need based CSR programs are proposed for the villages adjacent to the
project site. In addition to the existing CSR activities carried out by the company
additional support to be given to the proposed needs.
6.8. Budgetary Cost Estimates for Environmental Management
The estimated total cost of the proposed project is Rs.2100. Crores. Under the
project, an estimated investment of about Rs.200 crores is allocated towards
pollution control equipment and implementation of environmental pollution control
measures.
7. ADDITIONAL STUDIES
7.1. Public Hearing
This document is submitted for undertaking Public Hearing as per EIA notification &
its amendment.
7.2. Risk Assessment Study and Risk Mitigation measures
According to the standard ToR items 7(xiii) and 8 (i to iv) of the Terms of Reference
(ToR) issued for the project, preliminary hazard identification and risk assessment
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-23
was undertaken to quantify the possible fire and occupational health risks
associated with the operation of the project at the designated location. The good
engineering practices suggested by the Central Pollution Control Board for risk
assessment in industries (CPCB document Probes/133/2009-10) and CPR-18E risk
assessment procedures' guidelines which are widely accepted by the Ministry of
Environment, Forests and Climate Change (MoEF&CC) India, have been adopted
while assessing the residual risks associated with the operations of the project with
specific reference to fire hazards, chemical exposure hazards, occupational hazards
and natural hazards
7.3. Fire Hazards
The proposed project does not handle any major flammable materials except
furnace oil for the operation of Recovery boiler and kiln. The raw materials such as
ready pulp do not fall under fire hazard goods classification. The project will be
handling significant quantities of coal which is a combustible material. Apart from the
above, small quantities of combustible materials such as lube oils,latex and
synthetic thickeners will be used in the Mill, which will be received in sealed drums
and will be stored at dedicated locations in the stores as per the National Building
Codes.
In order to assess the heat radiation from the pool fire scenario of accidental spills
from furnace oil (full bore rupture of the storage tank), consequence modeling was
undertaken using ALOHA software, which is recommended by Ministry of
Environment and Forests, India. It was inferred from the model heat radiation
contours with 2 kW/m2 would occur within 20 m from furnace oil tank which is within
the facility boundary and hence the overall impacts due to any fire accidents will be
less significant.
7.4. Risks due to Storage and Handling of Coal and Risk Control Measures
Although coal fires are infrequent, there is a possibility of coal fires at the coal stock
yards during the summer conditions due to burning of volatile compounds. Coal
stock yard fires can be avoided by providing proper stacking design to prevent air
movement inside the coal lumps, minimising the duration of coal storage at the site
and water sprinkling operations to maintain adequate moisture.
7.5. Occupational Health and Noise Management Plan
The major noise generating sources are paper machine, vacuum pumps, air
compressors, chippers and turbo generators. TNPL will be procuring all the relevant
noise prone equipment with guaranteed noise levels less than 85 dBA at one (1)
metre distance from the respective machines/equipment. The predicted noise levels
indicate that additional noise emissions from the proposed project is insignificant
and well within the standards prescribed by the CPCB.
TNPL has full fledged Occupational Health Centre within the mill premises. OHC is
manned by a qualified one Medical Officer supported with 3 paramedical staffs. The
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-24
hospital has an ambulance which is equipped with oxygen cylinder and other
emergency items and manned by trained drivers as per the Factories Rules, Rule
88N.
8. PROJECT BENEFITS
As per TNPL‟s CSR policy, TNPL Unit-II is taking up community welfare activities for
the benefit of people living in nearby Panchayats such as Mondipatti, K.Periyapatti
and Chithanatham. In addition, need based activities are also carried out by Unit-II,
on public request.
Infrastructure / amenities available near the plant will be assessed based on the
need based survey and will be taken up under CSR scheme for development.
The project will create direct employment to about 400 persons. In addition it would
generate indirect employment to about 1000 persons in the industries and service
organizations and material handling, etc., which will be supported by the operations
of the mill.
The project is likely to generate income to the state by way of Goods and Service
Tax (GST) to the tune of Rs 20 crores per annum and by way of income tax to the
tune of Rs. 100 crores per annum.
As per Corporate Policy, TNPL will earmark budget and spend towards CSR and will
follow the policy by spending more on CSR activities in the region, benefiting local
people
9. CONCLUSIONS
Based on the findings of the detailed air quality modelling exercise, it has
been inferred that the resultant cumulative concentration at around 10 Kms
radius distance from proposed MEP project will comply with the NAAQ
Standards
Full fledged wastewater treatment facilities and high efficiency Electrostatic
Precipitators (ESP) and other pollution abatement measures will result in
minimising the adverse impacts on the environment.
In addition to the existing pollution control systems and environmental
management program of the existing facility it is proposed to invest
additionally about Rs.200 crores towards various pollution control and
environmental management programs under the MEP project
The management of TNPL has spent about Rs.3.69 crores and Rs.5 crores
on various CSR activities in the region during the year 2015-16 and 2016-17
respectively.As a continued support for the CSR activities, the management
of TNPL has proposed to spend about Rs. 10.5 Crores in the next five years
Tamil Nadu Newsprint and Papers Limited - Unit II EIA Report Mondipatti, Tiruchirappalli Dt, Tamil Nadu Mill Expansion Plan
Executive Summary
Prepared by & ES-25
for various CSR activities in the study area with a focused approach on
education, health, and disaster relief
The project will create direct employment to about 400 persons. In addition it
would generate indirect employment to about 1000 persons in the industries
and service organizations and material handling, etc., which will be
supported by the operations of the mill.
This project will have significant beneficial effects in terms of growth and
development of the regional economy.
The project will also pave way for additional growth of ancillary industries in
the region, which will not only increase the employment potential but also
further strengthen the economic base of the region.
The proposed project is structured to be in line with the requirements of
MoEF&CC/CPCB/ TNPCB