Daily Observations Milliken Landfill Solar Project Preparer: Robert Fritz Date: 10.28.16 Weather: Overcast, high of 82, wind: W 11mph Mangan personnel on site: Todd Boyle, Sam Anvari, Darrin (Tank) Vaughn Number of AeroTek personnel on site: Deliveries to Site: PLANNED WORK NEXT WEEK • Continuation racking system assembly in Area 1 • Pouring concrete in Area 1 • Install Panels in Area 1 SITE OBSERVATIONS Area 1: Mangan CM: Todd/Sam/Dustin # Aerotek Personnel: Area 2: Mangan CM: Todd/ Sam/Dustin # Aerotek Personnel: 26 Area 3: Mangan CM: Todd/ Sam/Dustin # Aerotek Personnel: Visitors on site: Tina Insana and Shannon Williams (SB County) OTHER NOTES: 48% of panels now installed. (4,546 Panels of 9,460 now installed) 75% of Tubs now poured (4,407 Tubs of 2,510 now poured) •Complete Racking Erection •Complete QA/QC in area 3 •Concrete Pouring Areas 2; begin Area 3) •Install Panels in Area 2+1 PLANNED WORK THIS WEEK Work Performed: 139 Panels Installed Concrete/Erection/QA-QC complete Work Performed: Work Performed:

Upload: robert-fritz

Post on 12-Jan-2017

75 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Milliken Daily Report_10.28.16

Daily ObservationsMilliken Landfill Solar Project

Preparer: Robert FritzDate: 10.28.16 Weather: Overcast, high of 82, wind: W 11mphMangan personnel on site: Todd Boyle, Sam Anvari, Darrin (Tank) VaughnNumber of AeroTek personnel on site:

Deliveries to Site:

PLANNED WORK NEXT WEEK

• Continuation racking system assembly in Area 1 • Pouring concrete in Area 1• Install Panels in Area 1

SITE OBSERVATIONS

Area 1:Mangan CM: Todd/Sam/Dustin # Aerotek Personnel:

Area 2:Mangan CM: Todd/ Sam/Dustin # Aerotek Personnel: 26

Area 3:Mangan CM: Todd/ Sam/Dustin # Aerotek Personnel:

Visitors on site: Tina Insana and Shannon Williams (SB County)

OTHER NOTES:48% of panels now installed. (4,546 Panels of 9,460 now installed)75% of Tubs now poured (4,407 Tubs of 2,510 now poured)

•Complete Racking Erection•Complete QA/QC in area 3•Concrete Pouring Areas 2; begin Area 3)•Install Panels in Area 2+1

PLANNED WORK THIS WEEK

Work Performed:139 Panels Installed Concrete/Erection/QA-QC complete

Work Performed:

Work Performed:

Page 2: Milliken Daily Report_10.28.16

0

200

400

600

800

1000

1200

1400

0

10

20

30

40

50

60

70

80

90

100

Daily

Uni

ts C

ompl

eted

Perc

ent C

ompl

ete

Daily Numberof Tubs filled

Daily Numberof PanelsInstalled

% TubsPoured

% PanelsInstalled

Page 3: Milliken Daily Report_10.28.16

Rain Gauge installed

Page 4: Milliken Daily Report_10.28.16

The county has expressed concern with these panels as they may interfere with Large equipment that may need to access this road.