module 3 commissioning instrument transformers

80
06/06/22 Module Three 1 SUBSTATION COMMISSIONING COURSE MODULE THREE INSTRUMENT TRANSFORMER TESTING PROCEDURES

Upload: raymond-lee

Post on 29-Nov-2014

898 views

Category:

Documents


10 download

TRANSCRIPT

Page 1: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 1

SUBSTATION COMMISSIONING COURSE

MODULE THREE

INSTRUMENT TRANSFORMERTESTING PROCEDURES

Page 2: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 2

INTRODUCTION

• The electrical commissioning and acceptance testing of electric power systems is essential for the energization of any electrical system for the first time.

Page 3: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 3

INTRODUCTION

Module Three• Discuss theory and ratings• Safety issues• Test equipment operation &

hands on testing

Page 4: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 4

INTRODUCTION

Skills learned in MODULE THREE:• Acceptance testing for CTs and VTs• Operate CT tester• Apply safe work practices• Analyze test values• Complete test forms

Page 5: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 5

INSTRUMENT TRANSFORMERS

• A general classification

• Current transformers (CT)• Voltage transformers (VT)

• Isolate primary quantities and convert into useable secondary values via transformation

Standard secondary rating:• 5A for CT• 120V for VT < 24 kV• 115V for VT > 24 kV

Measurement values from CTs and VTs:

• Voltage, current, frequency, real / reactive power, energy, power factor, impedance

Page 6: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 6

INSTRUMENT TRANSFORMERS

Polarity markings

• A designation of the relative instantaneous direction of currents

• Current flowing into the polarity mark in the primary is relatively in phase with current flowing out the polarity mark in the secondary

• As if the primary and secondary are connected straight through

Page 7: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 7

INSTRUMENT TRANSFORMERS

Page 8: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 8

INSTRUMENT TRANSFORMERS

• Manufacturer’s name or trademark

• Manufacturer’s type• Serial number• Rated Voltage, maximum

voltage or nominal system voltage

• Rated frequency

• Basic impulse insulation level (N/A for bushing CT’s)

• Continuous rating factor for CT (1.0 or more)

• Thermal burden rating for VT (VA)

• Accuracy rating

Nameplate Data

Page 9: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 9

INSTRUMENT TRANSFORMERS

Ratio expression between winding groups

Example: VT with one primary and one secondary winding

14,400 : 120 VRatio 120 : 1

Ratio between primary and secondary amperes

Example: CT with one primary and one secondary winding

100 : 5 ARatio 20 : 1

Nameplate Symbols (: colon)

Page 10: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 10

INSTRUMENT TRANSFORMERS

Voltage rating or ratiosbetween winding groups

Example: VT with two windings for series or parallel connection

2,400 x 4800 VRatio 20 x 40 : 1

Current rating with two or more coils for series of parallel connection

Example: CT with two primary windings for series or parallel conn.

100 x 200 : 5 A

Nameplate Symbols (x multiplication sign)

Page 11: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 11

INSTRUMENT TRANSFORMERS

(Not used for VT) Ampere rating of separate secondary winding with independent core

Example: CT with two secondary windings and two cores.

100 : 5 // 5A

Nameplate Symbols (// double slant lines)

Page 12: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 12

INSTRUMENT TRANSFORMERS

Voltage rating or ratios of separate winding on one core.

Example: VT with one primary and two secondary winding

14,400 V: 120 & 72 VRatio 120 & 200:1

Ampere rating of separate primary winding on one core.

Example 1: CT with two primary windings designed to be used individually.

100 & 600 : 5A

Nameplate Symbols (& ampersand)

Page 13: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 13

INSTRUMENT TRANSFORMERS

Example 2: Totalizing CT with four primary windings designed to be used simultaneously.

5 & 5 & 5 & 5 : 5A

Nameplate Symbols (& ampersand)

Page 14: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 14

INSTRUMENT TRANSFORMERS

Example 3: CT for three-wire single phase.

100 & 100 : 5A

Nameplate Symbols (& ampersand)

Page 15: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 15

INSTRUMENT TRANSFORMERS

Two or more primary or secondary ratings obtained by taps in the secondary winding

Example 1: VT with secondary tap for more primary voltage rating

12,000/14,400 :120 VRatio 100/120 : 1

Different primary current ratings obtained by taps in the secondary winding

Example: CT with taps in the secondary for additional ratios

100 : 5 // 5A

Nameplate Symbols (/ single slant line)

Page 16: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 16

INSTRUMENT TRANSFORMERS

Example 2: VT with secondary tap for additional secondary voltage ratings

14,400 : 120/72 VRatio 120/200:1

Nameplate Symbols (/ single slant line)

Page 17: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 17

INSTRUMENT TRANSFORMERS

North American Standards• CSA

– Originated in 2007– An adoption of IEC 60044 part 1 to part 7

• ANSI/IEEE– IEEE C57.13-2008 Standard Requirements for

Instrument Transformers – ANSI/IEEE C57.13.1-1981 Guide for Field Testing of

Relaying Current Transformers

Page 18: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 18

INSTRUMENT TRANSFORMERS

• CSA Standards– CAN/CSA-C60044-1 to -8 (part 1 to part 8), 2007

• Part 1: Current Transformers• Part 2: Inductive Voltage transformers• Part 3: Combined Transformers• Part 4: N/A• Part 5: Capacitive Voltage transformers• Part 6: Requirements for Protective Current

Transformers for Transient Performance

• Part 7: Electronic Voltage Transformers• Part 8: Electronic Current Transformers

Page 19: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 19

INSTRUMENT TRANSFORMERS

What is a CT ?

• A device that isolates and transforms the primary current quantity into a proportional secondary current quantity

• The CT has:– Primary winding or primary conductor– Magnetic core– Secondary winding

Page 20: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 20

INSTRUMENT TRANSFORMERS

Distributed uniform winding with negligible Leakage Flux

Non-uniform distributedwinding with some Leakage Flux

Page 21: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 21

INSTRUMENT TRANSFORMERS

How does a CT work ?

• Primary current flows generates magnetic field around the conductor

• Magnetic field flows in the magnetic core• Magnetic field induces a voltage in the secondary

winding• Burden connected to secondary winding completes the

circuit and allows current to flow

Page 22: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 22

INSTRUMENT TRANSFORMERS

Ipri x Npri = Isec x Nsec

Ipri = Current flowing in primary winding

Isec = Current generated in secondary winding

Npri = Number of turns in primary winding

Nsec = Number of turns in secondary winding

Page 23: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 23

INSTRUMENT TRANSFORMERS

What is the secondary current ?

CT ratio: 5000:5A; 1000:1Iprimary = 1000A

Isec = 1000A / (ratio) = 1000A /1000= 1A

In reality, there will slightly less than 1A flowing.

The difference is the known as the Ratio Error in %

Page 24: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 24

INSTRUMENT TRANSFORMERS

“Never open the secondary of a CT when primary current is flowing because dangerous high voltages will appear”.

IEEE C57.13 allow open circuit crest voltages up to 3500 V peak without

voltage limiting devices.

Page 25: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 25

INSTRUMENT TRANSFORMERS

CT Types

• Torroidal • Wound Primary• Bar Type• Split Core

Tororoidal

• Low flux leakage• Typical of bushing and

window CTs• Primary conductor pass

through center• 600V insulation can be

used in MV application with insulated primary conductors

Page 26: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 26

INSTRUMENT TRANSFORMERS

CT Types

• Torroidal (donut)• Wound Primary• Bar Type• Split Core

Wound Primary• Has an internal primary

winding– Wound more than 1

full turn on the core• Core can be torroidal• Must be inserted in series

with the conductors• Bar provides primary

connection points, often mistaken for bar type

Page 27: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 27

INSTRUMENT TRANSFORMERS

CT Types

• Torroidal (donut)• Wound Primary• Bar Type• Split Core

Bar Type

• Has a continuous bar for the primary winding

• Only 1 turn primary• Core can be torroidal• Must be inserted in series

with the conductors• Primary insulation part of

CT construction

Page 28: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 28

INSTRUMENT TRANSFORMERS

CT Types

• Torroidal (donut)• Wound Primary• Bar Type• Split Core

Split Core

• Core is separated into two parts

• For use where primary conductor cannot be easily removed

Page 29: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 29

INSTRUMENT TRANSFORMERS

Page 30: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 30

INSTRUMENT TRANSFORMERS

CT Ratio

• Ratio or primary current to secondary current

– Expressed as current quantities• 1000 : 5 A

– Expressed as ratio numbers• 200 : 1

Page 31: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 31

INSTRUMENT TRANSFORMERS

Adjusting CT Ratio (low V)• For some applications• KA = (KN ± NSA) / NP

KA = Actual ratio

KN = Nameplate ratio

NSA = Number of adjusted secondary turns adjusted

To Add: loop X1 lead through H1.

To Subtract: loop X1 opposite H1)

NP = Number of primary turns

Page 32: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 32

INSTRUMENT TRANSFORMERS

CT Ratio Adjustment

• 20:5 CT needed• 50:5 CT available

• KA = (KN ± NSA) / NP = (10 + 2) / 3 = 4

or 4:1

• Actual CT Ratio = 20:5

Page 33: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 33

INSTRUMENT TRANSFORMERS

CT Standard Burden @ 5A, @ 60 Hz

Page 34: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 34

INSTRUMENT TRANSFORMERS

Basis for Accuracy class for Metering

• CTs and VTs correction factor is within specified limits for specified load conditions

• .6 lagging to unity PF

• CT operating between 10% to 100% rated current

• VT operating between 90% to 100% rated voltage

Page 35: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 35

INSTRUMENT TRANSFORMERS

IT Standard Accuracy Class for Metering @ 60 Hz

Page 36: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 36

INSTRUMENT TRANSFORMERS

CT Accuracy Rating for Metering

• Accuracy for a specified burdenExample: 0.3 B – 1.8.3% accuracy for all other burden up to 1.8Ω

Example: 0.3 B @ 0.2.3% accuracy for burden of .2 and 3Ω

Page 37: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 37

INSTRUMENT TRANSFORMERS

CT Accuracy Rating for Relaying @ 60 Hz

Accuracy classification apply to full winding unless specified

Page 38: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 38

INSTRUMENT TRANSFORMERS

Relaying CT Class

• C (Calculated)• T• X

Class C

• Low leakage flux CTs• Torroidal type• 3% error @ 5A• 10% error @ 100A

Page 39: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 39

INSTRUMENT TRANSFORMERS

Relaying CT Class

• C• T (Tested)• X

Class T

• High leakage flux CTs• Primary Wound type• % error obtained from

testing• Tested to 100A or > until

10% error is establish at specified burdens

• Test curve plotted for Ipr Vs Isec, the overcurrent curve

Page 40: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 40

INSTRUMENT TRANSFORMERS

Relaying CT Class

• C• T• X (Defined)

Class X

• User defined along with expected accuracy rating for protection application– Minimum knee point

voltage; Vk– Maximum excitation

current Ik at Vk– Maximum secondary

winding resistance at 75°C, Rs

Page 41: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 41

INSTRUMENT TRANSFORMERS

Secondary Terminal Voltage

• Saturation voltage level at 20X rated current

• 100 A

• Vsat = 100 A x Burden

Page 42: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 42

INSTRUMENT TRANSFORMERS

Saturation Curve

• B-H CurveExcitation Current Vs Excitation voltage

• Knee Point voltage, Vk

Δ 10% Ve → Δ 50% Ie

Page 43: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 43

INSTRUMENT TRANSFORMERS

Transformer Formula

• Erms = 2 π f N a Bpeak / √2 ≈ 4.44 f N a B

Where: f = the supply frequencyN = number of turnsa = cross sectional area of the coreB = peak magnetic flux density

Page 44: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 44

INSTRUMENT TRANSFORMERS

Class C Saturation Curve

• Plotted on log-log scale• Induced voltage Y-axis• Excitation current X-axis• Voltage begins at 1%• Voltage ends at 5X Irated• Vk identified where curve

is at 45° tangent axis

Page 45: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 45

INSTRUMENT TRANSFORMERS

Page 46: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 46

INSTRUMENT TRANSFORMERS

Class T O/C Ratio Curve

• Plotted of linear scale• Secondary current Y-axis• Primary current X-axis• 1 to 22 x rated I-primary

for all standard burdens• Curve identifies the

burden which causes 50% ratio correction

Page 47: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 47

INSTRUMENT TRANSFORMERS

What is a VT ?

• Isolate and transform the primary voltage into proportional secondary voltage

• Construction– Primary winding– Magnetic core– Secondary winding

Page 48: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 48

INSTRUMENT TRANSFORMERS

5 Groups of VT

• All capable of operating at 110% for emergency condition

• Emergency for 1 minute• Some have special emergency rating conditions• All must operate within thermal limits and or specified

temperature rise

Page 49: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 49

INSTRUMENT TRANSFORMERS

Page 50: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 50

INSTRUMENT TRANSFORMERS

VT Accuracy Rating

• Accuracy rating for each standard burden– For maximum burden– For specified burden

Example: 0.3 Z; 0.3 Y, 0.6 Z and 1.2 ZZ; 0.3 Z @ Y

• Accuracy for two 2ndary or tapped 2ndary windings– Burden is the total for the VT– Accuracy class apply with the burden divided between

the 2ndaries outputs in any manner

Page 51: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 51

INSTRUMENT TRANSFORMERS

Thermal Burden Rating

• The maximum volt-ampere (VA) it can carry within temperature design limits– Each winding can have its own rating– One specified rating is for combined distribution

between the 2ndaries, including taps

Page 52: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 52

TESTING INSTRUMENT TRANSFORMERS

Safety Consideration

• Many testing involves using high voltages• Should be done by trained qualified personnel• Safe work practice and procedures required

• Review Module 2• IEEE Standard 510 – 1983,

– Recommended Practice for Safety in High Voltage & High Power Testing

Page 53: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 53

TESTING INSTRUMENT TRANSFORMERS

CT Testing

• Primary Insulation Resistance

• Dielectric Withstand• Secondary Insulation

Resistance• Secondary Burden• Saturation• Ratio and Polarity

Page 54: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 54

TESTING INSTRUMENT TRANSFORMERS

CT Testing

• Primary Insulation Resistance

• Dielectric Withstand• Secondary Insulation

Resistance• Secondary Burden• Saturation• Ratio and Polarity

Primary Ins. Resistance Test

• For Bar and Primary wound CT’s

• DC voltage test at the rated crest voltage on the primary winding

• Secondary grounded• 1 minute test

Page 55: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 55

TESTING INSTRUMENT TRANSFORMERS

CT Insulation Resistance: Bar Type and Primary Wound

DC Voltage test

• Isolate Primary• Isolate & Gnd Secondary• Connect HV lead to H1/H2• Connect LV to Gnd /

2ndary• Test for 1 minute • Record test value

Page 56: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 56

TESTING INSTRUMENT TRANSFORMERS

CT Testing

• Primary Insulation Resistance

• Dielectric Withstand• Secondary Insulation

Resistance• Secondary Burden• Saturation• Ratio and Polarity

Dielectric Withstand Test • For Bar and Primary wound

CT’s• AC voltage test at the 75%

factory test voltage• Secondary grounded• 1 minute test

Page 57: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 57

TESTING INSTRUMENT TRANSFORMERS

CT Dielectric Withstand: Bar Type and Primary Wound

AC Voltage test

• Isolate & Gnd Secondary• Connect HV lead to H1/H2• Connect LV to Gnd /

2ndary• Test for 1 minute • Record test value

Page 58: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 58

TESTING INSTRUMENT TRANSFORMERS

CT Testing

• Primary Insulation Resistance

• Dielectric Withstand• Secondary Insulation

Resistance• Secondary Burden• Saturation• Ratio and Polarity

2ndary Ins. Resistance Test

• Test for secondary wiring• Secondary wiring isolated

and ungrounded• 1000 VDC• 1 minute test

Page 59: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 59

TESTING INSTRUMENT TRANSFORMERS

CT Secondary Circuit Insulation Test

Page 60: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 60

TESTING INSTRUMENT TRANSFORMERS

CT Testing

• Primary Insulation Resistance

• Dielectric Withstand• Secondary Insulation

Resistance• Secondary Burden• Saturation• Ratio and Polarity

2ndary Burden Test

• Conducted in 2 parts• Part 1, 1A current injection

– Measure circuit burden• Part 2, four-wire resistance

measurement– Measure secondary

winding resistance• Burden = part 1 + part 2

Page 61: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 61

TESTING INSTRUMENT TRANSFORMERS

Part 1: CT Secondary Circuit Burden Measurement

Page 62: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 62

TESTING INSTRUMENT TRANSFORMERS

Part 2: CT Secondary Winding Resistance Measurement

Page 63: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 63

TESTING INSTRUMENT TRANSFORMERS

Total burden calculation

ZT = RCT + (RL + ZB)

Where ZT = Total burden (Ω)

RCT = DC Winding resistance (Ω)RL = Lead resistance (Ω)ZB = Device impedance (Ω)

Page 64: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 64

TESTING INSTRUMENT TRANSFORMERS

CT Testing

• Primary Insulation Resistance

• Dielectric Withstand• Secondary Insulation

Resistance• Secondary Burden• Saturation• Ratio and Polarity

Saturation Test

• Secondary winding excitation test

• Primary open circuited• Step voltage increase,

current proportional• Test for knee-point voltage• Rapid rise is I-excitation • 10% Δ V = 50% Δ I

Page 65: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 65

TESTING INSTRUMENT TRANSFORMERS

CT Saturation test

Page 66: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 66

TESTING INSTRUMENT TRANSFORMERS

CT Testing

• Primary Insulation Resistance

• Dielectric Withstand• Secondary Insulation

Resistance• Secondary Burden• Saturation• Ratio and Polarity

Ratio and Polarity test

• Secondary winding excited at 1V per turn

• Primary open circuited• H1-H2 compared to X1-X2• Phase measured, ratio

calculated• Phase difference ≈ 0 means

polarity correct

Page 67: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 67

TESTING INSTRUMENT TRANSFORMERS

CT Ratio and Polarity Test

Page 68: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 68

TESTING INSTRUMENT TRANSFORMERS

CT Testing

• Primary Insulation Resistance

• Dielectric Withstand• Secondary Insulation

Resistance• Secondary Burden• Saturation• Ratio and Polarity

Ratio and Polarity test (ALT)

• Use individual meters, phase angle and voltmeter

• Secondary winding excited at 1V per turn

• Primary open circuited• H1-H2 compared to X1-X2• Phase measured, ratio

calculated• Phase difference ≈ 0 means

polarity correct

Page 69: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 69

TESTING INSTRUMENT TRANSFORMERS

CT Ratio and Polarity Test (alternate connections)

Page 70: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 70

TESTING INSTRUMENT TRANSFORMERS

VT Testing

• Insulation Resistance• Dielectric Withstand• Ratio and Polarity

Page 71: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 71

TESTING INSTRUMENT TRANSFORMERS

VT Testing

• Insulation Resistance• Dielectric Withstand• Ratio and Polarity

Insulation Resistance Test

• DC voltage test at the rated crest voltage

• 3 tests– HV to Gnd– HV to LV– LV to Gnd

Page 72: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 72

TESTING INSTRUMENT TRANSFORMERS

VT Insulation Resistance Tests

Page 73: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 73

TESTING INSTRUMENT TRANSFORMERS

VT Testing

• Insulation Resistance• Dielectric Withstand• Ratio and Polarity

Dielectric Withstand Test

• AC voltage test at the 75% factory test voltage

• Secondary grounded• 1 minute test

Page 74: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 74

TESTING INSTRUMENT TRANSFORMERS

VT Dielectric Withstand Tests

Page 75: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 75

TESTING INSTRUMENT TRANSFORMERS

VT Testing

• Insulation Resistance• Dielectric Withstand• Ratio and Polarity

Ratio and Polarity test

• Primary winding excited at 1V per turns ratio

• Secondary open circuited• X1-X2 compared to H1-H2• Phase measured, ratio

calculated• Phase difference ≈ 0° means

polarity correct• Compare ratio with

nameplate

Page 76: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 76

NETA STANDARD

5. NETA Acceptance Testing Procedure

5.1 Visual and Mechanical Inspection

5.2 Electrical Test 5.2.1 Current Transformer 5.2.2 Voltage Transformer

5.3 Test Value Analysis 5.3.1 Visual and Mechanical 5.3.2 CT Electrical Test 5.3.3 VT Electrical Test

Page 77: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 77

TEST SET MANUAL

Module 3: CT Tester

Module 2: 15 KV Insulation Resistance Test set AC High Potential Test set DC High Potential Test set Digital Low Resistance Test set

Page 78: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 78

TEST FORMS

Current Transformer Test Form

Voltage Transformer Test Form

Page 79: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 79

Page 80: Module 3 Commissioning Instrument Transformers

04/09/23 Module Three 80