module-iv bu pom notes

Upload: kazia-shamoon-ahmed

Post on 07-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Module-IV bu pom notes

    1/48

    Asst Prof Arvind GajakoshBE, MBA, NET

  • 8/6/2019 Module-IV bu pom notes

    2/48

    It is a simple system of calculating arithmetically the

    requirement of the i/p materials at different points

    of time, based on the plan or schedule of production

    of finished good. MRP is a computer based information system for

    scheduling production and purchase of dependent

    demand items.

    MRP is a system of planning & scheduling the item

    phased materials requirement for production

    operations.

  • 8/6/2019 Module-IV bu pom notes

    3/48

    Materials requirements planning (MRP) is a means fordetermining the number of parts, components, andmaterials needed to produce a product

    MRP provides time scheduling information specifyingwhen each of the materials, parts, and componentsshould be ordered or produced

    Dependent demand drives MRP

    MRP is a software system

  • 8/6/2019 Module-IV bu pom notes

    4/48

    Inventory reduction

    Reduction in production and delivery lead times

    Realistic commitments

  • 8/6/2019 Module-IV bu pom notes

    5/48

    Three major sources of information are mandatory in

    the MRP system. (i/p)

    A master production schedule (MPS)

    An inventory status file A bill of materials (BOM) file

    Using these three info sources the MRP processing

    logic provides following o/p.

    Order release requirement Order rescheduling

    Planned orders

  • 8/6/2019 Module-IV bu pom notes

    6/48

    6

    The McGraw-Hill Companies, Inc., 2004

    Firm orders

    from known

    customers

    Forecasts

    of demand

    from random

    customers

    Aggregate

    product

    plan

    Bill of

    material

    file

    Engineering

    design

    changes

    Inventory

    record file

    Inventory

    transactions

    Master production

    Schedule (MPS)

    Primary reports

    Secondary reports

    Planned order schedule for

    inventory and production control

    Exception reports

    Planning reports

    Reports for performance control

    aterial

    planning

    ( RP

    computer

    program)

    MRP Model/System

  • 8/6/2019 Module-IV bu pom notes

    7/48

    The MPS is developed from firms customer orders or

    from forecasts of demand before the MRP system

    begins to operate.

    The MPS is designed to meet market demand. Service components for customers are also entered

    as end items in the MPS.

    The MPS provides the focal info for the MRP system.

  • 8/6/2019 Module-IV bu pom notes

    8/48

    Based on a MPS (master production schedule), amaterial requirements planning system:

    Creates schedules identifying the specific parts and

    materials required to produce end items

    Determines exact unit numbers needed

    Determines the dates when orders for those

    materials should be released, based on lead times

  • 8/6/2019 Module-IV bu pom notes

    9/48

    It consists the complete documentation of the

    inventory status of each item in the product

    structure, on hand quantity safety stock level,

    quantity allocated and lead time. This file provides accurate info about of every item

    controlled by the MRP system.

    Pegging

    Identify each parent item that created demand

  • 8/6/2019 Module-IV bu pom notes

    10/48

    The BOM identifies how each end product is

    manufactured, specifying all sub component items,

    their sequence, their quantity in each finished unit.

    This info is obtained from product designdocuments, work flow analysis & other stdmanufacturing & industrial engg documentation.

    The primary info to the MRP from the BOM is the

    product structure.

  • 8/6/2019 Module-IV bu pom notes

    11/48

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    Product Structure Tree for Assembly A Lead Times

    A 1 day

    B 2 days

    C 1 day

    D 3 days

    E 4 days

    F 1 day

    Given theproduct structure tree for A and the lead time and demandinformation below, provide a materials requirements plan that defines thenumber of units of each component and when they will be needed

  • 8/6/2019 Module-IV bu pom notes

    12/48

    Planned orders to be released at a future time Order release notices to execute the planned

    orders

    hanges in due dates of open orders due torescheduling

    Cancellations or suspensions of open orders dueto cancellation or suspension of orders on themaster production schedule

    Inventory status data

  • 8/6/2019 Module-IV bu pom notes

    13/48

    Planning reports, for example, forecasting inventoryrequirements over a period of time

    Performance reports used to determine agreement

    between actual and programmed usage and costs

    Exception reports used to point out seriousdiscrepancies, such as late or overdue orders

  • 8/6/2019 Module-IV bu pom notes

    14/48

    As the MRP system is of dynamic nature, it reacts

    well to the changing conditions.

    MRP can identify potential bottlenecks and capacity

    problems far enough in advance to adapt theschedule to them.

    MRP system helps in planning & scheduling the item

    phased material requirement for the production

    operations.

  • 8/6/2019 Module-IV bu pom notes

    15/48

    A computer is necessary

    The product structure must be assembly oriented.

    A valid master schedule has to be prepared.

    BOM and inventory status info must be assembledand computerized.

    Unreliable inventory and transactions data from the

    shop floor can ruin a well planned MRP system.

  • 8/6/2019 Module-IV bu pom notes

    16/48

    Goal: Plan and monitor all resources of a

    manufacturing firm (closed loop):

    manufacturing

    marketing

    finance

    engineering

    MRPII

    is applicable to any manufacturing orgn,regardless of its size, location, product or process.

    It provides info abt inventory investment levels,

    plant expansion needs, & work force requirements.

  • 8/6/2019 Module-IV bu pom notes

    17/48

    Enterprise Resource Planning Defined

    R/3 System Components

    Reasons for Implementing R/3

    ERP

  • 8/6/2019 Module-IV bu pom notes

    18/48

    Enterprise Resource Planning Systems is a computer

    system that integrates application programs in

    accounting, sales, manufacturing, and other functions

    in the firm

    It is a software package developed for optimum use of

    resources of an enterprise in a planned manner.

    It integrates entire enterprise starting from the

    supplier to the customer, covering logistics, financial

    and human resources.

    This will enable the enterprise to increase

    productivity by reducing costs.

  • 8/6/2019 Module-IV bu pom notes

    19/48

    SAP AG, A German firm, is a world leader in ERPsoftware.

    -Designed to operate

    in a three-tierclient/serverconfiguration-Applications arefully integrated sothat data are shared

    between allapplications

  • 8/6/2019 Module-IV bu pom notes

    20/48

    R/3 SystemFunctional

    Components

    (ERP)

    Sales & Distribution Human Resources

    Manufacturing

    & Logistics

    Financial

    Accounting

  • 8/6/2019 Module-IV bu pom notes

    21/48

    Financials (daily transaction costs)

    Controlling (working capital mgmt)

    Asset management (current assets)

  • 8/6/2019 Module-IV bu pom notes

    22/48

    Payroll

    Benefits administration

    Applicant data administration

    Personnel development planningWorkforce planning

    Schedule & shift planning

    Time management

    Travel expense accounting

  • 8/6/2019 Module-IV bu pom notes

    23/48

    Materials management

    Plant maintenance

    Quality management

    Production planning & control

    Project management system

  • 8/6/2019 Module-IV bu pom notes

    24/48

    Prospect & customer management

    Sales order management

    Configuration management

    Distribution

    Export controls

    Shipping and transportation managementBilling, invoicing, and rebate processing

  • 8/6/2019 Module-IV bu pom notes

    25/48

    Desire to standardize and improve processes

    To improve the level of systems integration

    To improve information quality

  • 8/6/2019 Module-IV bu pom notes

    26/48

    Once a MPS is complete, we have to focus on

    PPC. There are four types of PPC system.

    Pond draining systems

    Push systems Pull systems

    Bottlenecks systems

  • 8/6/2019 Module-IV bu pom notes

    27/48

    In the pond draining approach to PPC, the

    emphasis is on holding reservoirs of materials tosupport production.

    Pond draining system can be used in eitherproduct-focusedorprocess focusedproduction.

    It requires little info about customers, suppliers

    and production.

    It may lead to excessive inventories to store RM.

  • 8/6/2019 Module-IV bu pom notes

    28/48

    In push system emphasis shifts to using info

    about customers, suppliers & production to

    manage material flow.

    Batches of RMs are planned to arrive at a factoryabout when needed to make batches of parts.

    Push systems have resulted in great reductions

    of RMs inventories & in greater worker and

    machine utilization when compared to pond

    draining systems.

  • 8/6/2019 Module-IV bu pom notes

    29/48

    In pull systems of PPC, the emphasis is on

    reducing inventory levels at every stage ofproduction.

    In pull systems we look only at t

    he next stageof production & determine what is needed there,

    and then we produce only that.

    RMs and parts are pulled from the back of the

    factory toward the front of the factory where

    they become FGs.

  • 8/6/2019 Module-IV bu pom notes

    30/48

    Some PPC systems focus on production

    bottlenecks that impede (delays) production

    because they have less capacity than upstream

    or downstream stages.

    At bottleneck operations, batches of products

    arrive faster than they can be completed.

  • 8/6/2019 Module-IV bu pom notes

    31/48

    It is nothing but deciding future courses of action of

    the orgzn well in advance so that executives at

    different level will play their role.

    PPC has three phases.

    Planning phase

    Action phase

    Control phase

  • 8/6/2019 Module-IV bu pom notes

    32/48

    It has two categories of a planning namely prior

    planning & active planning.

    Prior planning means pre-production planning.

    Active planning means the actual production

    planning which includes various activities directly

    related to the production at micro level

    immediately following the prior planning.

    The modules of prior planning are product

    development and design, forecasting, aggregateplanning etc.

    The modules of active planning are process

    planning and routing, loading, scheduling etc.

  • 8/6/2019 Module-IV bu pom notes

    33/48

    This phase has the major step of dispatching.

    Dispatching is the transition from planning phase to

    action phase.

    In this case the worker is ordered to start to

    manufacturing the product.

    The tasks which are included in dispatching are job

    order, inspection order etc.

  • 8/6/2019 Module-IV bu pom notes

    34/48

    This phase has the following two major modules.

    Progress reporting: here data regarding what ishappening with the job is collected. Also it helps

    to make comparison with the present level of

    performance.

    Corrective action: the tasks under correctiveaction primarily make provisions for an unexpected

    event. Some examples of corrective actions are:

    crating schedule flexibility, capacity modificationsetc.

  • 8/6/2019 Module-IV bu pom notes

    35/48

    Determination of plant capacity

    Production design is the first level planning for the

    inputs, conversion activities & outputs of a

    production operation.

    Design capacity: it is the rate of o/p of goods or

    services under full scale operating conditions.

    Ex: a cement factory may be designed to produce

    200 tons/day.

  • 8/6/2019 Module-IV bu pom notes

    36/48

    System capacity: the max. o/p of a specific product

    that the sys of workers & less equipments is

    capable of producing as an integrated whole is

    called system capacity.

    System capacity may be less than that of the designcapacity.

    System efficiency= Actual o/p___

    system capacity

  • 8/6/2019 Module-IV bu pom notes

    37/48

    Capacity is a measure of the ability to produce

    goods or services.

    Capacity planning is the task of determining the LT

    & ST capacity needs of an orgzn and then

    determining how these needs will be satisfied.

    LT capacity strategies:

    Develop a new product lines

    Expand existing facilities

    Construct production plants

    ST capacity strategies : capacity decision are takenby considering the fluctuations in demand caused

    by seasonal and economic factors.

  • 8/6/2019 Module-IV bu pom notes

    38/48

    Equipment selection is the process of identifying a

    set of suitable equipments which are most suitable

    for processing a set of products.

  • 8/6/2019 Module-IV bu pom notes

    39/48

    It arranges the sales forecasts & sales orders.

    It minimizes the working capital.

    It ensures a better control of material.

    It utilizes an optimum combination of resources andmethods to bring down production cost.

    It ensures an orderly flow of production resulting in

    the avoidance of rush orders, & minimizing

    overtime.

    It gives a better service to the customers by

    producing the right product in the right quality and

    at the right time.

  • 8/6/2019 Module-IV bu pom notes

    40/48

    It is a selection of path or route over which every

    piece is to travel in being transformed from RM into

    FP.

    Objectives of routing:

    To decide the most feasible sequence of operations

    and to ensure that the same are followed.

    To utilise inputs like machines, materials, men etc.

    in the most economical way.

    To influence the design of the factory layout,building, machines etc.

  • 8/6/2019 Module-IV bu pom notes

    41/48

    Value analysis is one of the major techniques of

    cost prevention.

    It is a disciplined approach that necessary functions

    at min. cost without compromising on quality,

    reliability, performance & appearance.

    The society of US Value engineering was found in

    1959.

    The society of Japan Value engineering was found

    in 1967. The society of India Value engineering was found in

    1977. (INVEST-Indian Value engineering Society)

  • 8/6/2019 Module-IV bu pom notes

    42/48

    Companys product shows decline in sales.

    Companys prices are higher than those of its

    competitors.

    RM cost has gone up suddenly.

    New designs are being introduced.

    Rate of return on investment has a falling trend.

  • 8/6/2019 Module-IV bu pom notes

    43/48

    Value analysis is the application of a set of

    techniques to an existing product with a view to

    improving its value.

    Value engg is the application of exactly the same

    set of techniques to a new product at the designstage, project concept or preliminary design.

  • 8/6/2019 Module-IV bu pom notes

    44/48

    Cost value (labor, material, OH cost)

    Exchange value (money or product)

    Use value (price paid by the buyer)

    Esteem value (appearance of the product)

    Value = Performance (utility)

    cost

    Value can be increased by increasing the utility for

    the same cost or by decreasing the cost for the

    same utlity.

  • 8/6/2019 Module-IV bu pom notes

    45/48

    Simplify the product.

    Use cheaper and better materials.

    Modify product design.

    Use efficient processes.

    Reduce the product cost.

    Increase the utility of the product.

    Save money or increase the profit.

  • 8/6/2019 Module-IV bu pom notes

    46/48

    Identify the product

    Collect relevant info

    Define different functions

    Different alternatives

    Critically evaluate the alternatives

    Develop the best alternative

    Implement the alternative.

  • 8/6/2019 Module-IV bu pom notes

    47/48

    It is much faster cost reduction technique.

    It is a less expensive technique.

    It reduces production costs and adds value to sales

    income of the product.

    Application of value engg: machine tool industries,

    auto industries etc.

  • 8/6/2019 Module-IV bu pom notes

    48/48

    Cost control:

    Manufacturing cost is controlled by wastage

    reduction, value analysis, inventory control and

    efficient utilization of all resources.

    Cost reduction:

    Here this focuses on how to reduce the existing

    cost of the product.