Minutes of Meeting
DESIGN REVIEW MEETING -4
PROJECT NAME: TVH AURORA, COIMBATORE
Venue : TVH AURORA, CoimbatoreDate : 05-04-11
Start Time : 11.30 am End Time : 2.30 pm
Organization and Participants:
Responsibility Organization Attended By
Client TVH
Mr.Viswanathan, Mr.Sanjiv, Mr.Sahul,
Mr. Sundaram, Mr.Senthilmanivannan,
Mr. Krishnakumar, Mr. Arunagiri
PMC MorpheusMr.Arokiadass, Mr. Balaji, Mr.Ilangovan,
Mr. satheesh
Architect Morphogenesis Ms. Archana
Structural Consultant Vintech Ms. Ajay Gupta
MEP Consultant SpEC
Mr. Syed Sabzada, Mr. Syraj Hamza, Mr.
Nabeel variz,
Mr. Vinod Kumar
Landscape Consultant Design Milieu
Main Civil Contractor TAVAS Mr. Ramadas Giriyan,
F FRESH A ACTIVE P PENDING C CRITICAL Z COMPLETED / CLOSED I
- INFORMATION
# 22, Maharaja Surya Rao, Alwarpet, Chennai
-
8/7/2019 MOM - DRM - 4
2/3
# 22, Maharaja Surya Rao, Alwarpet, Chennai
S.
NoDescription Status Action By
Target
Date
1Architectural & Structural:At the outset all the participants visited the site and
acquainted with the progress of work achieved.
2
It was explained to Architect that PMC in their MCP has
given various Milestones fro Phase-1 works and hence it
was emphasized that the schedule of drawings arerequired for achieving the progress at site.
Architect said that they are already coordinating with
the MEP consultant to provide MEP services involved
in Tower-1, as such efforts will be made to release MEP
services drawings on priority basis.
A Mpgs12-04-11
3
Mr. Ajay Gupta of Vintech consultants agreed toprovide the reinforcement details for Tower -4 along the
Phase-2 side within a couple of days as these details
were not given along the Tower -4 GFC drawings.
A Vintech/Mpgs 08-04-11
4
Details of stitching slab, sump pits, floor finish etc also
will be provided after the release of MEP services
drawings for Tower -1.
AMpgs
5
Expansion joint details with filler materials finalized by
the structural consultant are with the Architect & will be
released immediately.
A Mpgs 07-04-11
6
Architect said that the Anti-termite treatment is not
necessary below raft & stitching slab, however they
recommended the treatment along the retaining wall
refilling area.
AMpgs/
Vintech
7
Architect said that they are yet to finalize the finishing
specifications for Towers and this will be prepared incoordination with Mr. Vasanthan. Meeting for sample
approval from Chairman TVH will be arranged
thereafter.
A TVH/Mpgs
25-04-11
8
The drawing release schedule for structural & working
drawings for Towers above podium will be prepared &
send by the Architect.
A Mpgs 12-04-11
9Villas layout revised and forwarded to Mr. Vasanthanfor comments and as regards Mall, the cinema is not yet
finalized and hence it is kept in hold.
A TVH/Mpgs
10
Consultant TVH desired to have the filling methodology
above the stitching slab. Mr. Ajay Gupta from Vintech
said that 95% compaction to be achieved with the earthavailable at site.
A Vintech
11
The construction joint layout for the Phase-1 area was
asked by the Consultant TVH. Mr. Ajay Gupta agreed to
provide the same.
A Vintech 13-04-11
12
Mr. Ajay Gupta advised to pour a small stretch of
retaining wall with the shuttering as fixed at site & see
in case if any segregation/honey combing he
recommended to go for free flow concrete.
A Vintech
13The tower crane position layout will be prepared &forwarded to the structural consultant for the approval
along with the manufacturer details, load etc.
F Morpheus/Vintech
MEP:
MEP consultant said that they have finalized all the
-
8/7/2019 MOM - DRM - 4
3/3
Note:1) Any points which were discussed but not included in this MOM and the points to which objections are
raised, if any, should be brought to notice within 24hrs; otherwise this MOM is treated as final and binding
on all parties concerned.
2) The continual presence of the quorum (relevant to the issues under discussion) till the end of the
meeting is requested for achieving the objective of the progress review agenda.
Prepared by
S. Ilangovan
Morpheus
# 22, Maharaja Surya Rao, Alwarpet, Chennai
.required give a Presentation after detailed design of
MEP services of Towers.
2
Issue of GFC drawings for MEP services for Tower-1 to
4. Architect said that they are coordinating the MEP
services with all concerned and particularly now they
are concentrating on Tower-1 for release.
Architect also said that the electrical elevation details
with modular box details will be furnished by them.
I SpEC/Mpgs 12-04-11
3
The list of drawings to be released by the MEP
consultant was handed over to Architect. The drawings
required on priority will be listed out by Architect with
the date of requirement & accordingly the same will beprovided by MEP consultant.
A
Mpgs/SpE
C 09-04-11
4MEP consultant yet to commence their work on the
design of LP gas connection schematic drawings.A SpEC
5
Electrical conduit & circuit drawing for stilt floor for
Tower -1 will be provided by 15 th April -11. Since the
details of other Towers may not take much time & will
be released within reasonable time.
A SpEC15-04-11
6No trenches for electrical cables proposed in the panel
room of basement floor.A SpEC
7
The date of release for Electrical SLD drawings, BOQ& tender drawings for MEP services will be informed
by MEP consultant. However the BOQ & tender
documents & drawings for the MEP services will be
prepared by SpEC and top priority will be for electrical
system for which electrical contract will have to be
finalized to take up the work before casting of shear
walls.
A SpEC 10-04-11
8Phase-2 Pump house & UG sump provision will be
finalized later.A
SpEC/M
pgs
9
Podium floor drainage details finalized & submitted by
MEP consultant to Architect which will be coordinated
by Architect with car parking etc & will be releasedsoon.
FMpgs
10
Architect said that the size of the lift pit given are after
collecting the requirement from 3 different Venders by
Mr. Vasanthan and also recommended block work for
the front opening for the ease of providing electrical
boxes etc.
A
Mpgs
11
Waste line to STP will be taken only by gravity flow
and the pumping will be avoided. Architect said that the
depth of man hole near STP will be approximately
2.4mts below FFL.
A Mpgs/SpEC
12 The water supply line will be taken through internalOTS as already approved by Client/PMC. A Mpgs/SpEC
13Out-door unit of A/C in individual flats will be placed
over the clamps & chequered platform.A Mpgs/SpEC
14
MEP consultant said that they are working on Rain
water harvesting works & will be finalizing in
consultation with the landscape consultant.
F SpEC
15Architect said that the telescopic light system earlier
proposed by the MEP consultant is not feasible.A Mpgs/SpEC