    Minutes of Meeting

    DESIGN REVIEW MEETING -4

    PROJECT NAME: TVH AURORA, COIMBATORE

    Venue : TVH AURORA, CoimbatoreDate : 05-04-11

    Start Time : 11.30 am End Time : 2.30 pm

    Organization and Participants:

    Responsibility Organization Attended By

    Client TVH

    Mr.Viswanathan, Mr.Sanjiv, Mr.Sahul,

    Mr. Sundaram, Mr.Senthilmanivannan,

    Mr. Krishnakumar, Mr. Arunagiri

    PMC MorpheusMr.Arokiadass, Mr. Balaji, Mr.Ilangovan,

    Mr. satheesh

    Architect Morphogenesis Ms. Archana

    Structural Consultant Vintech Ms. Ajay Gupta

    MEP Consultant SpEC

    Mr. Syed Sabzada, Mr. Syraj Hamza, Mr.

    Nabeel variz,

    Mr. Vinod Kumar

    Landscape Consultant Design Milieu

    Main Civil Contractor TAVAS Mr. Ramadas Giriyan,

    F FRESH A ACTIVE P PENDING C CRITICAL Z COMPLETED / CLOSED I

    - INFORMATION

    # 22, Maharaja Surya Rao, Alwarpet, Chennai

  • 8/7/2019 MOM - DRM - 4

    2/3

    # 22, Maharaja Surya Rao, Alwarpet, Chennai

    S.

    NoDescription Status Action By

    Target

    Date

    1Architectural & Structural:At the outset all the participants visited the site and

    acquainted with the progress of work achieved.

    2

    It was explained to Architect that PMC in their MCP has

    given various Milestones fro Phase-1 works and hence it

    was emphasized that the schedule of drawings arerequired for achieving the progress at site.

    Architect said that they are already coordinating with

    the MEP consultant to provide MEP services involved

    in Tower-1, as such efforts will be made to release MEP

    services drawings on priority basis.

    A Mpgs12-04-11

    3

    Mr. Ajay Gupta of Vintech consultants agreed toprovide the reinforcement details for Tower -4 along the

    Phase-2 side within a couple of days as these details

    were not given along the Tower -4 GFC drawings.

    A Vintech/Mpgs 08-04-11

    4

    Details of stitching slab, sump pits, floor finish etc also

    will be provided after the release of MEP services

    drawings for Tower -1.

    AMpgs

    5

    Expansion joint details with filler materials finalized by

    the structural consultant are with the Architect & will be

    released immediately.

    A Mpgs 07-04-11

    6

    Architect said that the Anti-termite treatment is not

    necessary below raft & stitching slab, however they

    recommended the treatment along the retaining wall

    refilling area.

    AMpgs/

    Vintech

    7

    Architect said that they are yet to finalize the finishing

    specifications for Towers and this will be prepared incoordination with Mr. Vasanthan. Meeting for sample

    approval from Chairman TVH will be arranged

    thereafter.

    A TVH/Mpgs

    25-04-11

    8

    The drawing release schedule for structural & working

    drawings for Towers above podium will be prepared &

    send by the Architect.

    A Mpgs 12-04-11

    9Villas layout revised and forwarded to Mr. Vasanthanfor comments and as regards Mall, the cinema is not yet

    finalized and hence it is kept in hold.

    A TVH/Mpgs

    10

    Consultant TVH desired to have the filling methodology

    above the stitching slab. Mr. Ajay Gupta from Vintech

    said that 95% compaction to be achieved with the earthavailable at site.

    A Vintech

    11

    The construction joint layout for the Phase-1 area was

    asked by the Consultant TVH. Mr. Ajay Gupta agreed to

    provide the same.

    A Vintech 13-04-11

    12

    Mr. Ajay Gupta advised to pour a small stretch of

    retaining wall with the shuttering as fixed at site & see

    in case if any segregation/honey combing he

    recommended to go for free flow concrete.

    A Vintech

    13The tower crane position layout will be prepared &forwarded to the structural consultant for the approval

    along with the manufacturer details, load etc.

    F Morpheus/Vintech

    MEP:

    MEP consultant said that they have finalized all the

  • 8/7/2019 MOM - DRM - 4

    3/3

    Note:1) Any points which were discussed but not included in this MOM and the points to which objections are

    raised, if any, should be brought to notice within 24hrs; otherwise this MOM is treated as final and binding

    on all parties concerned.

    2) The continual presence of the quorum (relevant to the issues under discussion) till the end of the

    meeting is requested for achieving the objective of the progress review agenda.

    Prepared by

    S. Ilangovan

    Morpheus

    # 22, Maharaja Surya Rao, Alwarpet, Chennai

    .required give a Presentation after detailed design of

    MEP services of Towers.

    2

    Issue of GFC drawings for MEP services for Tower-1 to

    4. Architect said that they are coordinating the MEP

    services with all concerned and particularly now they

    are concentrating on Tower-1 for release.

    Architect also said that the electrical elevation details

    with modular box details will be furnished by them.

    I SpEC/Mpgs 12-04-11

    3

    The list of drawings to be released by the MEP

    consultant was handed over to Architect. The drawings

    required on priority will be listed out by Architect with

    the date of requirement & accordingly the same will beprovided by MEP consultant.

    A

    Mpgs/SpE

    C 09-04-11

    4MEP consultant yet to commence their work on the

    design of LP gas connection schematic drawings.A SpEC

    5

    Electrical conduit & circuit drawing for stilt floor for

    Tower -1 will be provided by 15 th April -11. Since the

    details of other Towers may not take much time & will

    be released within reasonable time.

    A SpEC15-04-11

    6No trenches for electrical cables proposed in the panel

    room of basement floor.A SpEC

    7

    The date of release for Electrical SLD drawings, BOQ& tender drawings for MEP services will be informed

    by MEP consultant. However the BOQ & tender

    documents & drawings for the MEP services will be

    prepared by SpEC and top priority will be for electrical

    system for which electrical contract will have to be

    finalized to take up the work before casting of shear

    walls.

    A SpEC 10-04-11

    8Phase-2 Pump house & UG sump provision will be

    finalized later.A

    SpEC/M

    pgs

    9

    Podium floor drainage details finalized & submitted by

    MEP consultant to Architect which will be coordinated

    by Architect with car parking etc & will be releasedsoon.

    FMpgs

    10

    Architect said that the size of the lift pit given are after

    collecting the requirement from 3 different Venders by

    Mr. Vasanthan and also recommended block work for

    the front opening for the ease of providing electrical

    boxes etc.

    A

    Mpgs

    11

    Waste line to STP will be taken only by gravity flow

    and the pumping will be avoided. Architect said that the

    depth of man hole near STP will be approximately

    2.4mts below FFL.

    A Mpgs/SpEC

    12 The water supply line will be taken through internalOTS as already approved by Client/PMC. A Mpgs/SpEC

    13Out-door unit of A/C in individual flats will be placed

    over the clamps & chequered platform.A Mpgs/SpEC

    14

    MEP consultant said that they are working on Rain

    water harvesting works & will be finalizing in

    consultation with the landscape consultant.

    F SpEC

    15Architect said that the telescopic light system earlier

    proposed by the MEP consultant is not feasible.A Mpgs/SpEC