The Rehabilitation of Road N14 between Litunde to Lichinga and Construction of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Contract No: 680/DIPRO/2008 Status and Monthly Progress Report No.19 Reporting Period: Until 31 October, 2015 CPG-Civil & Planning Group Av: Kwame Nkrumah, 1335 Maputo - Mozambique Tel +258 21 414506 / 414508 Fax +258 21 414515 Email: [email protected] Civil and Planning Group

Upload: elias-ibrahim

Post on 21-Jan-2017

218 views

Category:

Documents


20 download

TRANSCRIPT

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction of Seven Bridges between Litunde and Marrupa in Niassa

    Province, Mozambique

    Contract No: 680/DIPRO/2008

    Status and Monthly Progress Report No.19

    Reporting Period: Until 31 October, 2015

    CPG-Civil & Planning Group

    Av: Kwame Nkrumah, 1335

    Maputo - Mozambique Tel +258 21 414506 / 414508 Fax +258 21 414515 Email: [email protected]

    Civil and Planning Group

  • Rehabilitation of Road N14 between Lichinga and Litunde

    Construction of Seven Bridges between Litunde and Marrupa.

    Page i of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    Table OF CONTENTS

    1 INTRODUCTION ....................................................................................................................................... 6

    1.1 REPORT STRUCTURE ............................................................................................................... 6

    1.2 PROJECT OVERVIEW AND DESCRIPTION OF THE WORKS ........................................................ 6

    1.2.1 Overview .......................................................................................................................................... 6

    1.2.2 General Works .................................................................................................................................. 7

    1.2.3 Road Works ...................................................................................................................................... 7

    1.2.4 Drainage Works ................................................................................................................................ 7

    1.2.5 Bridge Works .................................................................................................................................... 7

    1.3 CONTRACT DETAILS ............................................................................................................... 8

    1.4 STATUS OF GUARANTEES AND INSURANCES .......................................................................... 9

    2 PHYSICAL PROGRESS OF WORKS .................................................................................................... 11

    2.1 OVERALL PROGRESS SUMMARY ........................................................................................... 11

    2.2 PROGRESS OF CULVERT CONSTRUCTION .............................................................................. 13

    2.3 PLANNED VS. ACTUAL PROGRESS BY WORKS COMPONENT ................................................ 13

    2.3.1 Survey &Setting out........................................................................................................................ 14

    2.3.2 Traffic Management ....................................................................................................................... 14

    2.3.3 Materials Laboratory....................................................................................................................... 15

    2.3.4 Engineers Facilities ....................................................................................................................... 15

    2.3.5 Major Equipment Mobilization Status ............................................................................................ 15

    2.3.6 Drainage Structures & Erosion Protection Works .......................................................................... 16

    2.3.7 Railway Crossing ............................................................................................................................ 17

    2.3.8 Clearing and Grubbing .................................................................................................................... 17

    2.3.9 Earthworks ...................................................................................................................................... 17

    2.3.10 Cement Stabilized Sub base ............................................................................................................ 17

    2.3.11 Cement stabilized Base ................................................................................................................... 17

    2.3.12 Quarry Production .......................................................................................................................... 17

    3 FINANCIAL REPORT ............................................................................................................................. 19

    3.1 ACCEPTED CONTRACT AMOUNT (ACA) BREAKDOWN ........................................................ 19

    3.2 ESTIMATED VALUE OF WORKS COMPLETED TO DATE ......................................................... 19

    3.3 CONTRACTORS STATEMENTS .............................................................................................. 20

    3.4 INTERIM PAYMENT CERTIFICATES ........................................................................................ 20

    3.5 PAYMENTS TO CONTRACTOR ................................................................................................ 20

    3.6 PROVISIONAL SUMS EXPENDED ............................................................................................ 21

    3.7 PRIME COST SUMS EXPENDED .............................................................................................. 22

    3.8 RETENTION MONEY .............................................................................................................. 22

    3.9 ACCEPTED CONTRACT AMOUNT ADJUSTMENT .................................................................... 22

    3.10 CLAIMS REVIEW .................................................................................................................... 23

    3.10.1 Employer Claims ............................................................................................................................ 23

    3.10.2 Contractor Claims and Notices ....................................................................................................... 23

    3.11 INSTRUCTIONS AND ORDERS ................................................................................................. 23

    3.11.1 Site Instructions .............................................................................................................................. 23

    3.11.2 Provisional Sum Orders .................................................................................................................. 23

    3.11.3 Variation Orders ............................................................................................................................. 23

  • Rehabilitation of Road N14 between Lichinga and Litunde

    Construction of Seven Bridges between Litunde and Marrupa.

    Page ii of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    3.12 MATERIAL ON SITE ............................................................................................................... 23

    4 CONTRACT ADMINISTRATION ......................................................................................................... 27

    4.1 CONTRACT SUPERINTENDENCE AND CHANGES .................................................................... 27

    4.2 CONTRACTORS ORGANIZATIONAL CHART .......................................................................... 28

    4.3 CONTRACT RECORDS ............................................................................................................ 28

    4.3.1 Daily Returns .................................................................................................................................. 28

    4.3.2 Mobilization of Equipment ............................................................................................................. 28

    4.3.3 Labour Return ................................................................................................................................. 28

    5 QUALITY ASSURANCE ......................................................................................................................... 30

    5.1 PROJECT QUALITY ASSURANCE PLAN (PQAP) .................................................................... 30

    5.2 IMPLEMENTATION OF CONTRACTORS QAP ......................................................................... 30

    5.2.1 Quality Control Plan ....................................................................................................................... 30

    5.3 GENERAL QUALITY CONTROL .............................................................................................. 30

    5.3.1 Pre works Compliance Checks ....................................................................................................... 30

    5.3.2 Contractors Supervision ................................................................................................................ 30

    5.3.3 Engineers Supervision ................................................................................................................... 30

    5.4 MATERIAL SAMPLING AND TESTING .................................................................................... 31

    5.4.1 Materials from Borrow pits ............................................................................................................. 31

    5.4.2 Material from Sub-base and Base Layers ....................................................................................... 31

    5.4.3 Aggregates for Surface Dressing .................................................................................................... 31

    5.4.4 Crushed Stone Base Aggregates from Stockpiles and the road ...................................................... 31

    5.4.5 Concrete Samples from Construction Site ...................................................................................... 31

    5.4.6 Bitumen Quality .............................................................................................................................. 31

    5.4.7 Prime Coat ...................................................................................................................................... 31

    5.4.8 Construction of 1st Seal ................................................................................................................... 31

    5.4.9 Construction of 2nd Seal. ................................................................................................................ 31

    5.5 SOURCES OF MATERIALS ...................................................................................................... 32

    5.6 DESIGN MODIFICATION ......................................................................................................... 32

    5.7 ISSUES, PROBLEMS AND SOLUTIONS ..................................................................................... 32

    5.7.1 Damaged base layer ........................................................................................................................ 32

    5.7.2 Railway Crossing ............................................................................................................................ 32

    5.7.3 Non-Conformances ......................................................................................................................... 32

    7 ANCILLARY ACTIVITIES ..................................................................................................................... 39

    7.1 CLIMATIC & WEATHER CONDITIONS AND CHARTS .............................................................. 39

    7.2 LAND ACQUISITION AND UTILITIES RELOCATION ................................................................ 39

    7.3 RESETTLEMENT ACTION PLAN (RAP) IMPLEMENTATION .............................................. 39

    7.4 OUTSTANDING RESETTLEMENT ACTION PLAN (RAP) ISSUES .................................. 39

    7.5 SUBCONTRACTING AND COMPLIANCE WITH ESMP IMPLEMENTATION PLAN ..................... 39

    7.6 CORRESPONDENCE ................................................................................................................ 39

    7.7 STATUS OF AS-BUILT DRAWINGS ......................................................................................... 39

    7.8 RECORD AND MINUTES OF MEETINGS .................................................................................. 39

    7.8.1 Minutes of Monthly Site Meeting ................................................................................................... 39

    7.8.2 Minutes of Technical Meeting ........................................................................................................ 39

    7.8.3 Minutes of EHS .............................................................................................................................. 39

  • Rehabilitation of Road N14 between Lichinga and Litunde

    Construction of Seven Bridges between Litunde and Marrupa.

    Page iii of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    7.9 VISITS .................................................................................................................................... 40

    7.10 PHOTOGRAPHIC RECORD ...................................................................................................... 40

    8 RISKS AND MITIGATION MEASURES .............................................................................................. 42

    8.1 RISKS TO SUCCESSFUL PROJECT IMPLEMENTATION ............................................. 42

    9 SUPERVISION SERVICES ..................................................................................................................... 44

    9.1 CONSULTANCY CONTRACT DETAIL ...................................................................................... 44

    9.2 ENGINEERS ORGANIZATIONAL STRUCTURE ........................................................................ 44

    9.2.1 Organizational Structure and Staffing............................................................................................. 44

    9.3 ENGINEERS REPORTING PERIOD ACTIVITY ......................................................................... 45

    9.3.1 General Supervision Activities ....................................................................................................... 45

    9.4 FINANCIAL DATA, INVOICING, ESTIMATE TO COMPLETION ................................................. 45

    9.4.1 Invoices to Date .............................................................................................................................. 45

    9.4.2 Invoice Payment Status ................................................................................................................... 46

    9.4.3 Contract Sum Adjustment ............................................................................................................... 46

    9.4.4 Claims ............................................................................................................................................. 46

    9.4.5 Deliverables and Timing ................................................................................................................. 46

    9.5 SUPERVISION SERVICE PERFORMANCE REVIEW ................................................................... 46

    9.5.1 Factors Affecting Performance ....................................................................................................... 46

    9.5.2 Engineers Programme Review ...................................................................................................... 47

    9.5.3 Engineers Recommendations. ....................................................................................................... 47

  • Rehabilitation of Road N14 between Lichinga and Litunde

    Construction of Seven Bridges between Litunde and Marrupa.

    Page iv of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    LIST OF APPENDICES

    APPENDIX 1.1 - PROJECT LOCATION MAP

    APPENDIX 2.1 - CULVERT SCHEDULE

    APPENDIX 3.1 - FINANCIAL PROGRESS, STATUS OF INVOICE AND S-CURVE

    APPENDIX 3.2 - CLAIMS REGISTER

    APPENDIX 3.3 - SCHEDULE OF STE INSTRUCTION

    APPENDIX 4 .1 - CONTRACTORS ORGANIZATIONAL CHART

    APPENDIX 4 .2 - EQUIPMENT MOBILIZATION

    APPENDIX 4 .3 - LABOUR RETURN

    APPENDIX 5 .1 - SCHEDULE OF REQUESTS FOR INSPECTION

    APPENDIX 5 .2 - SUMMARY OF LABORATORY TEST RESULTS

    APPENDIX 5 .2 - SOURCE OF MATERIAL AND APPROVAL STATUS

    APPENDIX 6. 1 - ACCIDENT/INCIDENT MONITORING RECORD

    APPENDIX 6.2 - HIV/AIDS AWARENESS AND PREVENTION

    APPENDIX 7.1 - WEATHER RECORD

    APPENDIX 7.2 - RESETTLEMENT ACTION PLAN

    APPENDIX 7.3 - CORRESPONDENCES REGISTER & IMPORTANT CORRESPONDENCES

    APPENDIX 7.4 - MINUTES OF TECHNICAL & MONTHLY PROGRESS SITE MEETINGS

    APPENDIX 7.5 - MINUTES OF OTHER MEETING

    APPENDIX 7.6 - PROJECT PHOTOGRAPHS

    APPENDIX 8.1 - ENGINEERS ORGANIZATIONAL CHART

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 5 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    SECTION 1: INTRODUCTION

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 6 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    1 INTRODUCTION

    1.1 REPORT STRUCTURE

    This report is structured as follows:

    Section 1: describes the report layout, gives the project overview, describes the works and presents the Contract data,

    Section 2: provides a detailed analysis of the physical progress of the works; evaluates the critical path activities and recommends mitigation measures to counter any

    slippages,

    Section 3: presents the projects current and projected financial status, Section 4: presents issues related to contract administration, contractors superintendence,

    contract records, site instructions and orders,

    Section 5: reports on project quality assurance and control issues, Section 6: provides information on the status of the Environmental, Health and Safety matters

    on the project,

    Section 7: reports on the ancillary activities of the project, Section 8: analyses current risks and presents recommendations for mitigation measures, and Section 9: reports on the Engineers project supervision activities during the reporting period.

    1.2 PROJECT OVERVIEW AND DESCRIPTION OF THE WORKS

    1.2.1 Overview

    Lichinga to Litunde Road Rehabilitation Project stretches for approximately 66 km between

    the roundabout in Lulimile suburb of Lichinga and Litunde in Niassa Province; refer to project

    location map under Appendix 1-1.

    The road is being upgraded by means of widening and strengthening and widening and

    resealing of the existing carriageway. The rehabilitated carriageway width will generally

    provide for 2 x 3.5m wide traffic lanes, 2 x 0.5m sealed shoulders and 2 x 1.0m cement

    stabilized gravel shoulders.

    The stretch between Lichinga and Litunde is subdivided in three distinct sections:

    1. The first 7 km section, km 0+000 to km 7+140, is an existing 6 m wide surfaced road

    that is in fair condition and is to be widened and to receive double seal surface treatment

    (DBST) as reseal.

    2. From km 7+140 to km 57+870 exists a 4 m wide surfaced road that was resealed not

    long ago and that is also in fair condition. In this section the pavement is to be

    strengthened, widened and DBST surfaced.

    3. From km 57+870 to km 66+200 the road has a width of 6.1 m to km 7.5, that in some

    stretches widens to 8 m, with a paved surface in good condition. This section is to be

    widened and resealed.

    The work consists also of five post stressed girder and slab, one three span and four single span,

    bridges that locate outside the project road, but along the same route, between Litunde and

    Marrupa.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 7 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    The road between Litunde and Marrupa had been upgraded recently to paved standard. In this

    section of the road five bridges, seven bridges as stated in the Contract, are to be constructed

    and the approaches widened to a width of 8.0 m.

    1.2.2 General Works

    The main activities carried out under this item of the contract are:

    Establishment on site of camp, offices, stores and plant including removal on completion of works.

    Provision of offices, housing, transport and communications for the Engineers supervisory staff,

    Provision of a joint laboratory,

    1.2.3 Road Works

    The road works included in this contract consist mainly of the following:

    Clearing and grubbing of the road reserve. Setting out of the works, including level control and measurement of the works. Mass earthworks including rock fill and pioneer layer, Construction of concrete lined drains, chutes, inlet and outlet structure, subsoil drainage

    systems, open channel and concrete kerbs.

    Construction of selected layer, cement stabilized gravel subbase and base layer consisting of 50% gravel and 50% crushed stone mix, required to rehabilitate the

    existing road.

    Construction of prime coat and double seal surfacing Construction of ancillary works including stone pitching, gabions, road markings, road

    signs, marker and kilometre posts, guardrails and landscaping and grassing.

    Accommodation of traffic and construction of diversions where required. Maintenance of the works where required.

    1.2.4 Drainage Works

    As per design drawing recommendations for drainage, structures are as follows:

    Total No. of Culverts = 56

    New Culverts = 7

    Replaced = 2

    Extension Required = 47

    1.2.5 Bridge Works

    There are a total of five High Level Double Carriage (HLDC) bridges along the same route but

    outside the project road section between Litunde and Marrupa which consist of post stressed

    girder and slab as shown in Table 1.1 below.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 8 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    Table 1.1: Bridges Details

    Bridge Name

    Location

    from km

    66+200

    Location

    from km

    0+000

    Type Span

    Messenguesse km 199+557 km 265+757 Single Span Post stressed

    Girder & Slab

    35m

    Lureco km 166+444 km 232+644 Single Span Post stressed

    Girder & Slab

    40m

    Necoleze km 114+508 km 180+708 Single Span Post stressed

    Girder & Slab

    35m

    Uriate km 99+997 km 166+197 Single Span Post stressed

    Girder & Slab

    35m

    Lugenda km 83+026 km 149+226 Three Span Post stressed

    Girder & Slab

    3x40 , Total

    Length = 120

    m

    All the bridges are to be constructed adjacent to existing crossings, outside the existing

    alignment and at a raised level (HLDC) which will result in mass earthworks for the

    construction of abutment embankment fills after realignment.

    The bridge railings are designed to be constructed in reinforced concrete.

    1.3 CONTRACT DETAILS

    Contract Name The Rehabilitation of Road N14 between Litunde to Lichinga (66 km) and the

    Construction of Seven Bridges between Litunde and Marrupa in Niassa

    Province, Mozambique

    Contract No. 680/DIPRO/2008

    Contract Amount MZM 1,271,280,675.49 (One Billion Two Hundred Seventy One Million Two

    Hundred Eighty Thousand Six Hundred Seventy Five Meticais and Forty Nine

    Cents), inclusive of contingencies and IVA

    Currency Proportion 80% Foreign Portion (Euro); 20 % Local Portion (Meticais); Exchange Rate 1

    Euro = MZM 37.79

    Employer Administrao Nacional de Estradas

    Contractor CMC/CMCAA Joint Venture, Maputo, Mozambique

    Consultant at commencement

    of the works SNC- Lavalin International Inc. CANADA

    Consultant after

    recommencement of

    suspended works

    CPG-Civil and Planning Group since March 2015

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 9 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    Date of Letter of Acceptance 1st February 2011

    Date of Commencement 20th February 2012

    Duration of Contract 24 Months, 731 days

    Expected Date of Completion 20th February 2014

    Time Elapsed to Date 1348 days (31 October, 2015)

    Extension of Time TBA

    Revised Completion Date TBA

    Estimated Contract Price to

    Date

    33,640,663.55

    1.4 STATUS OF GUARANTEES AND INSURANCES

    Table 1.2: Contract Guarantees and Insurance Details

    Item Ref. No Date

    Effected

    Bank/Insurance Company Amount

    (MZM)

    Amount

    (Euro)

    End/Release

    Date

    Remarks

    Performance Guarantee

    No.

    01GR8999/6027356

    23rd Feb.

    2011

    Bank Intesa Sanpaolo SpA

    c/o Banca Infrastructtura Innovazione e Sviluppo

    SpA, Via Montebello,

    18 20121 Milano, Italy.

    25,425,613.51 2,691,253.08 28 days from

    the date of issue

    of the certificate

    of completion,

    foreseen on 4th April 2014

    Expired

    Amendment No. 01 to

    Performance Guarantee No.

    01GR8999/6027356

    19

    March 2014

    28 days from

    the date of issue of the certificate

    of completion,

    foreseen on 30th

    November 2015

    Must follow

    contract completion date

    according to

    contractors

    current works

    programme.

    Advance Payment Guarantee

    No.

    01GR8999/6027562

    4th

    March 2011.

    Bank Intesa Sanpaolo SpA

    c/o Banca Infrastructtura Innovazione e Sviluppo

    SpA, Via Montebello, 18

    20121 Milano, Italy.

    50,851,227.02 5,382,506.17 Until full

    repayment

    Until full

    repayment to ANE

    Contract Works and Contractors Public Liability Insurance

    CAR Policy No.

    12.000504

    19th May

    2011

    EmpresaMoambicana de

    Seguros

    Contract

    Value , etc

    31st December

    2015

    Policy shall

    remain in full

    force and effect for additional

    period

    necessary.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 10 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    SECTION 2: PHYSICAL PROGRESS OF WORKS

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 11 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    2 PHYSICAL PROGRESS OF WORKS

    2.1 OVERALL PROGRESS SUMMARY

    Following suspension of the works in March 2014, partial works activities were resumed on 4th

    May 2015. These activities included only layer works up to subbase level without stabilization.

    Full resumption of the works was undertaken only in early July 2015. The cumulative progress

    of the construction works is therefore generally as achieved by the Contractor in since early

    July 2015 until end of October 2015 as shown in Table 2.1 below.

    Table 2.1: Progress Summary

    Works

    Component Start End Total

    (km) % Complete (*) and Remarks

    Progress: Overall (All Works) 77.44%

    Road Works

    Subgrade 0+000 57+870 57.870 100.00

    62+120 66+180 4.06 99.51

    Total 61.930 99.97%

    Cement Stab. S-

    Base

    0+000 47+860 47.860 72.30%

    Cement Stabilized

    Base

    0+000 7+140 7.14 Completed but traffic and rain

    damaged; both rhs and lhs shoulders

    7+140 10+900 3.76

    10+900 11+440 0.54 Base material spread, but not

    completed due to railway line

    crossing and associated levels issue.

    11+440 23+350 11.91

    23+350 25+860 2.510 Section rectified

    25+860 44+620 18.760

    Total completed 44.12 71.22%

    Prime Coat 0+000 7+140 7.14

    7+140 10+900 3.76

    10+900 11+440 0.54 Base material spread, but not

    completed due to railway line

    crossing and associated levels issue.

    11+440 23+350 11.91

    23+350 25+860 2.51

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 12 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    25+860 35+720 9.86

    35+720 44+620 8.90

    Total Completed 44.08 71.15%

    1st Seal 0+000 0+900 0.900

    0+900 7+140 Work not yet done

    66.2 7+140 10+900 3.760

    10+900 11+440 Work not yet done

    11+440 23+350 11.900

    23+350 37+520 14.17

    Total Completed 30.73 46.42%

    2nd Seal 0+000 0+900 0.900

    0+900 7+140 Work not yet done

    66.2 7+140 10+900 3.760

    10+900 11+440 Work not yet done

    11+440 29+100 17.660

    Total Completed 22.32 33.72%

    Box and PIPE Culvert Works

    Culvert works TBA Culvert construction works not yet

    fully commenced exception being

    one new culvert at km 45+038.

    Bridge Works

    Lugenda 94.00%

    Uriate 91.00%

    Necoleze 83.00%

    Lureco 81.00%

    Messenguele 74.00%

    Material

    Crushed Stone (m3) 20000

    Crushed stone- (m3) 13000

    9.5 mm (m3) 1800

    9.5 mm precoated (m3) 285

    19.0 mm (m3) 6000

    (*) Note: Road subdivided in three sections

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 13 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    1. km 0+000 to km 7+140 (7.14 km), is an existing 6 m wide surfaced road that requires widening to 10.0 m with 1.0 m wide unsurfaced shoulder on each side and resealing.

    2. From km 7+140 to km 57+870 and km 62+120 to km 66+200 (54.810 km) exists a 4 m to 4.5 m and 6 m wide road that requires pavement reconstruction and widening to

    10.0 m with 1.0 m wide unsurfaced shoulder on each side.

    3. From km 57+870 to km 62+120 (4.25 km) the existing road has a width of 6.1 m to 7.5m that in some places widens to 8 m, and requires also widening according to site

    condition and resealing.

    2.2 PROGRESS OF CULVERT CONSTRUCTION

    Progress of culvert construction is as depicted in the culvert schedule presented under Appendix

    2.1

    2.3 PLANNED VS. ACTUAL PROGRESS BY WORKS COMPONENT

    Table 2.2 Below gives current progress details.

    Table 2.2: Planned vs. Actual Progress 31 October 2015 (**)

    Activity Planned

    %

    Actual

    %

    Lead

    /Delay

    Comments

    Clearing and Grubbing

    100 100.00 Work was completed only

    early October 2015; was to

    be completed on 25/6/15

    Earthworks (road widening / fill) 100 99.97 Work was completed only

    delayed in early October

    2015; was to be completed on

    31/8/15

    Cement Treated Sub-base 100 72.30 Delay Work was to be completed on

    29/10/15

    Cement treated crushed stone-gravel

    mix base

    100 71.15 Lead Work is to be completed on

    3/12/15

    Prime (MC 30) 100 71.15 Lead Work is to be completed on

    26/12/15

    First Seal (19mm ) 100 46.42 Lead Work is to be completed on

    21/12/15

    Second Seal (9.5mm) 100 33.72 Lead Work was to be completed on

    22/12/15

    Culvert/Rehabilitation/Replacement/

    New works (structural only)

    100 Culvert extension work not

    yet commenced. One new

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 14 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    culvert completed

    Bridge works

    Lugenda Bridge 100 94.00 Delay Work was to be completed on

    28/8/15

    Uriate Bridge 100 91.00 Delay Work was to be completed on

    21/10/15

    Necoleze Bridge 100 83.00 Lead Work is to be completed on

    18/2/16

    Lureco Bridge 100 81.00 Delay Work was to be completed on

    26/10/15

    Messenguele Bridge 100 74.00 Lead Work is to be completed on

    12/12/15

    Quarry Production for Crushed

    Stone Base.

    Crushed Stone Base 100 TBA 20000

    Crushed stone-gravel mix 100 TBA 13000

    (**) The contractor submitted a revised program on 4th October 2015 to replace the June

    tentative Program. According to this current program and as can be observed from the above

    the Contractor is behind schedule in construction of sub-base and in construction of Lugenda,

    Uriate and Necoleze Bridges. During the review period production has been negiligible This

    was mainly due to unavailability of cement for the sub-base. There was also shortage of diesel

    internitently caused by cash flow problem. The Contractor needs to submit another revised

    program to reflect the real progress.

    2.3.1 Survey &Setting out

    During the review period survey activities consisted mainly of checks on Subgrade, sub-base

    and base for the purpose of compliance with the permissible level tolerance limits, setting out

    works on abutment embankment slopes and concrete lined side drains. All survey works

    concerning the road alignment and cross sections of the road have been completed.

    2.3.2 Traffic Management

    The status of Traffic Management is satisfactory with traffic management signs now being

    erected as necessary despite the problem faced with vandalism.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 15 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    2.3.3 Materials Laboratory

    The Materials Laboratory has been fully operational over the review period with all equipment

    supplied to the contract specifications and being in satisfactory condition and having been

    calibrated at project resumption. Further equipment calibration is being done as and when

    necessary..

    2.3.4 Engineers Facilities

    The Engineers houses and offices are satisfactory. Occupation of the same has been effected

    as necessary.

    The following project vehicles are available to the Engineer

    1 x 3000 diesel LWB Four by four double cab Toyota Raider.

    2 x NP 300 Nissan double cab four by four.

    2 x 3000 diesel LWB four by Four single cab Toyota Raider.

    2 x NP 300 Nissan single cab four by four

    2.3.5 Major Equipment Mobilization Status

    Table 2.5 below summarises the Major equipment mobilisation status as at the end of October,

    2015.

    Table 2-5: Major Equipment Mobilization Status

    Item

    No

    Type Minimum

    Requirement

    by the

    Contract

    Actual by

    Contractor

    Actual

    cw(**)

    Minimum

    Requirement

    Remarks

    1 Motorised

    grader

    4 10 +6 1.5 BD; 1 ID;

    1 Scrap;

    2 Dozer 1 10 +9 3 BD

    3 Excavator 3 11 +8 4 BD

    5 Front end

    loader

    3 10 +7 4 BD

    6 Tipper

    >10m3

    15 34 +19 6 BD

    7 Water

    bowser >

    7Kl

    6 14 +8

    1 BD

    8 Vibratory

    Roller >20t

    4 11 +7 1BD

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 16 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    Note:

    (**) cw = compared with

    BD = Breakdown

    2.3.6 Drainage Structures & Erosion Protection Works

    Due to the highly erodible nature of the soils encountered along the project, erosion

    protection works are critical. The contractor is being instructed accordingly as the

    works progress.

    The need for subsoil drainage at varying locations of the road is being assessed and

    instructions being issued as necessary.

    9 Pneumatic

    Roller

    4 3 -1 1 BD

    10 Crusher 1 1 +0 Consisting

    primary,

    secondary and

    tertiary and

    two screens.

    BD for one

    Week

    11 Concrete

    mixer

    trucks

    3 +3

    Mobile

    mixer 250

    ltr and 350

    ltr.

    2 +2

    12 Recycler 5 +5 All not capable

    of spraying

    water during

    mixing. 2 BD

    13 Chip

    spreader

    2 2 0 1 BD

    14 Mechanical

    Broom

    2 +2

    15 Bitumen

    Distributor

    2 3 +1 1 not in use

    Total No.

    of Items

    45 121 76 168.9%

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 2: Progress Status

    Page 17 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    2.3.7 Railway Crossing

    The stabilization works of the base layer and surfacing of the section km 10+900 to km 11+440

    could not be completed due to issues concerning level differences between the finished road

    level and the levels at which the railway lines were crossing. This had to be discussed with

    Corridor de Desenvolvimento de Norte (CDN) and Vale. This discussion was concluded on

    29th September 2015 and the two organizations have now given their concent that the road can

    be constructed at the current design levels. The Contractor had been instructed to proceed with

    the construction works in this section.

    2.3.8 Clearing and Grubbing

    This activity has been completed satisfactorily up to chainage 66+200.

    2.3.9 Earthworks

    Earthwork has progressed satisfactorily up to chainage 66+180

    2.3.10 Cement Stabilized Sub base

    The status of the progress on the construction of cement stabilized sub-base layer is at 47+860

    2.3.11 Cement stabilized Base

    Construction of the base layer consists of mechanical and chemical stabilization of natural

    gravel with 50 % crushed stone material and generally stabilized by 2,5% cement. The progress

    of construction works is at chainage 44+620.

    2.3.12 Quarry Production

    Production of crushed stone materials has been ongoing as necessary. Quantities are given

    above.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report

    Page 18 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    SECTION 3: FINANCIAL REPORT

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report

    Page 19 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    3 FINANCIAL REPORT

    3.1 ACCEPTED CONTRACT AMOUNT (ACA) BREAKDOWN

    Table 3-1: Accepted Contract Amount Breakdown

    Bill Description Amount (MZM) % of

    ACA

    A Road Works 766,214,271.59

    70.81

    B Bridges

    Messenguele Bridge 43,438,311.37

    4.014

    Loreco Bridge 46,171,757.31

    4.267

    Necoleze Bridge 65,609,291.38

    6.063

    Uriate 57,102,058.95

    5.277

    Lugenda 91,623,152.16

    8.467

    C Daywork 8,676,699.12 0.802

    D Social 3,289,650.06 0.304

    Total (excluding IVA) 1,082,125,191.94 100%

    3.2 ESTIMATED VALUE OF WORKS COMPLETED TO DATE

    Table 3.2: Value of Works Achieved to Date (Engineers Estimate)

    Bill Description Amount (ZMZ) Amountspent to

    Date (ZMZ)

    %

    A Road Works 766,214,271.59 638,935,000.31 83.38%

    B Bridges

    Messenguele Bridge 43,438,311.37 28,165,285.97 64.84%

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report

    Page 20 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    Loreco Bridge 46,171,757.31

    33,654,327.92 73.20%

    Necoleze Bridge 65,609,291.38 31,226,855.98 47.60%

    Uriate 57,102,058.95 31,419,716.72 55.02%

    Lugenda 91,623,152.16 74,929,225.33 81.78%

    C Daywork 8,676,699.12 62,120.34 0.72%

    D Social 3,289,650.06 3,289,650.06 100.00%

    Total (excluding IVA) 1,082,125,191.94 841,825,045.25 77.8%

    Total as % of Accepted Contract

    Amount 77.8%

    3.3 CONTRACTORS STATEMENTS

    For the review period the Contractor submitted the following Statement by way letter reference

    Prot.No.: 993-15-CMCAAJV-RL-AP-CPG dated 31st October 2015.

    Statement No.23 over an amount of MZM 368,544,824.12 and Euro 28,892,

    286.59 for the period 21st September to 20th October 2015.

    3.4 INTERIM PAYMENT CERTIFICATES

    For the review period the Engineer issued Interim Payment Certificate:

    1. IPC No.18 for an amount of MZM 57,416,571.65 on Statement No.23 for the period

    between 21st September to 20th October 2015.

    Details of IPCs issued to date are given in Table 3.6 at the end of this section of the report.

    3.5 PAYMENTS TO CONTRACTOR

    All interim payment certufificates issued to date are listed in Table 3.6 presented at the end of

    this section. All payments are done up to and including IPC 15. The last date for payment of IPC

    16 was 27th October 2015 and therefore expired. It is likely IPC 16 will attract interest charges.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report

    Page 21 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    3.6 PROVISIONAL SUMS EXPENDED

    Table 3.3: Provisional Sums Expended to Date

    Bill Item Prov. Sum

    Amount

    (MZM)

    Expenditure

    to Date

    (MZM)

    Balance ($)

    B13.03: Compensation for material

    damage suffered by the local

    population

    625,000.00 227,025.00 397,975.00

    B13.05: Payment to DRB 750,000.00 976,582.80 -226,582.80

    B14.07: Rented and hotel

    accommodation

    1,770,000.00 1,905,920.04 -135,920.04

    B14.15:The provision of furniture,

    appliances and additional appliances

    212,400.00 509,693.04 -297,293.04

    B14.17: Uninterrupted power supply

    (UPS)

    129,800.00 136,408.00 -6,608.00

    15.08:Repairs, alterations and/or

    additions to existing roads used as

    diversions

    200,000.00 80,000.00 120,000.00

    61.01: Additional Foundation

    Investigation: Messenguele Bridge

    354,000.00 729,609.95 -375,609.95

    61.01: Additional Foundation

    Investigation: Loreco Bridge

    354,000.00 689,118.58 -335,118.58

    61.01: Additional Foundation

    Investigation: Necoleze Bridge

    354,000.00 669,116.40 -315,116.40

    61.01: Additional Foundation

    Investigation: Uriate Bridge

    354,000.00 629,946.92 -275,946.92

    61.01: Additional Foundation

    Investigation: Lugenda Bridge

    354,000.00 655,201.84 -301,201.84

    100.3: HIV/AIDS Training 1,180,000.00 1,180,000.00 -

    Total 6,637,200.17 8,388,622.90 -1,751,422.73

    DW: Daywork 8,676,699.12 62,120.34 8,614,578.78

    Social 2,109,650.06 2,712,407.22 -602,757.16

    Total 10,786,349.18 2,774,527.56 8,011,821.62

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report

    Page 22 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    3.7 PRIME COST SUMS EXPENDED

    Table 3.4: Prime Cost Amounts Expended to Date

    Bill Item Prov. Sum

    Amount

    (MZM)

    Expenditure

    to Date

    (MZM)

    Balance

    (MZM)

    B14.03: Telephone and radios for

    Engineer

    1,416,000.00 1,449,117.51 -33,117.51

    B14.16:Supply of Office Stationary 76,700.00 675,425.75 -598,725.75

    25.06:Provision of vegetation destroyer

    and ant poison

    4720.08 0.00 4,720.08

    71.02: Special tests requested by

    Engineer

    118,000.00 0.00 118,000.00

    Total 1,615,420.08 2,124,543.26 -509,123.18

    3.8 RETENTION MONEY

    An amount of MZM 105, 956, 577. 30 has been retained until the end of the review period; this

    represents the amount withheld up to IPC No.18.

    Details of retentions made to date are given in Table 3.6 in this section of the report.

    3.9 ACCEPTED CONTRACT AMOUNT ADJUSTMENT

    The following table gives a breakdown of the anticipated Final Contract Sum following review

    of the Accepted Contract Amount (inclusive of provisional sums, prime cost items,

    contingencies and IVA) accounting for variations, claims, Contract Price Adjustment and cost of

    time extension.

    Table 3.5: Estimated Final Contract Sum

    Item Accepted

    Contract

    Amt. ()

    Final Contract

    Sum Amt. ()

    Difference

    Accepted Contract BoQ Value 33,640,663.54 33,640,663.54 NIL

    Variation Orders No. 1 TBA -

    Approved Claims TBA -

    Extension of Time Costs TBA -

    Contract Price Adjustment 5,761,861.000 -

    Totals 33,640,663.54 39,402,252.54 -

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report

    Page 23 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    3.10 CLAIMS REVIEW

    3.10.1 Employer Claims

    There were no Claims from the Employer that were known to the CPG Team at the time of

    reporting.

    3.10.2 Contractor Claims and Notices

    To date the Contractor has submitted a total of 6 notices and has 6 Claims. Engineers opinion

    concerning claims 2 and 5 is presented under Appendix 3.2. An Extension of Time resulting

    from Claims 2 and 5 in a number of 166 days had been included in Certificate No. 18 following

    an Authorization by Administrao Nacional de Estradas.

    3.11 INSTRUCTIONS AND ORDERS

    3.11.1 Site Instructions

    Register of Site Instructions issued by CPG is presented under Appendix 3.3

    3.11.2 Provisional Sum Orders

    Provisional Sum expended to date is as shown in Table 3.3 above.

    3.11.3 Variation Orders

    There is a Variation Order issued before suspension of the works. Details of this Variation

    Order will be given after thorough study and a register shall be set up.

    3.12 MATERIAL ON SITE

    The status of materials on site for the review period ending on 31 October 2015 is as shown

    here below.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report

    Page 24 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    ,

    MONTHLY STATEMENT N 23 MATERIALS ON SITE (MOS) PERIOD: 21 Sept to 20 October 2015

    Unit Rate Previous This Month To Date Previous This Month To Date

    1 Cimpor Cement (Cimentos de Mozambique) bags 501.54 13,875.00 -13,875.00 0.00 6,958,867.50 -6,958,867.50 0.00

    2 Rapid Setting Cement bags 550.01 0.00 0.00 0.00 0.00 0.00 0.00

    3 Pre-cast Kerbs Fig. 7 No 283.95 1,246.00 0.00 1,246.00 353,797.95 0.00 353,797.95

    4 Pre-cast Kerbs Fig. 8 No 283.95 314.00 0.00 314.00 89,159.36 0.00 89,159.36

    5 Pre-cast Kilometer Posts No 1,528.59 66.00 0.00 66.00 100,887.00 0.00 100,887.00

    6 Pre-cast 5 Kilometer Posts No 1,528.59 15.00 0.00 15.00 22,928.86 0.00 22,928.86

    7 Crushed Stone base m3 383.59 10,190.38 6,514.58 16,704.96 3,908,903.63 2,498,912.25 6,407,815.88

    8 19mm stone m3 1,225.64 2,857.26 293.33 3,150.59 3,501,964.51 359,516.20 3,861,480.70

    9 9.5mm stone m3 1,225.64 2,341.75 164.32 2,506.07 2,870,136.21 201,396.73 3,071,532.93

    10 Bitumen 80/100 Ton 27,606.90 160.014 0.00 160.01 4,453,528.39 0.00 4,453,528.39

    11 m2 10.17 2,790.00 0.00 2,790.00 112,814.72 0.00 112,814.72

    12 No 1,943.70 1,284.81 -968.81 316.00 2,497,289.51 -1,883,080.31 614,209.20

    13 Timber Posts 1,8X150-175mm No 297.83 0.00 426.00 426.00 0.00 126,873.45 126,873.45

    14 No 67.29 0.00 426.00 426.00 0.00 28,664.90 28,664.90

    15 No 88.29 0.00 426.00 426.00 0.00 37,612.82 37,612.82

    13 Geotextile Kaymat U24 (150mx5m) No 17,784.00 9.09 2.91 12.00 161,728.59 51,679.41 213,408.00

    14 No 485.93 1,471.56 -698.56 773.00 715,067.97 -339,447.95 375,620.03

    16 Gabions Boxes 2,0X1X1 Long Mesh No 956.18 119.28 325.72 445.00 114,052.12 311,445.76 425,497.88

    17 Gabions Boxes 3,0X1X1 Long Mesh No 564.30 0.00 102.00 102.00 0.00 57,558.60 57,558.60

    18 No Fines units 500 x 500 x 150mm in class No 165.30 6,440.00 -1,456.00 4,984.00 1,064,530.52 -240,676.47 823,854.06

    19 Ton 17,791.53 65.84 -8.14 57.70 1,171,394.47 -144,823.07 1,026,571.40

    18 Welded Mesh ref.395 (6mx2.5) No 2,000.00 234.00 -126.00 108.00 468,000.00 -252,000.00 216,000.00

    19 Welded Mesh ref.245 (6mx2.5) No 1,240.00 0.00 400.00 400.00 0.00 496,000.00 496,000.00

    20 Modified Bittumen Ton 34,497.30 109.18 -109.18 0.00 4,224,546.23 -3,766,415.57 458,130.67

    21 Colocote in Drums Ton 43,441.43 26.00 0.00 26.00 1,129,477.18 0.00 1,129,477.18

    22 Chryso Aditivs (1000 litre Containers) No 25,108.50 1.00 1.00 2.00 258,916.80 25,108.50 284,025.30

    23 Armco galvanized Pipe No 4,335.71 41.13 -21.13 20.00 178,339.25 -91,625.15 86,714.10

    TOTAL VALUE OF MATERIALS ON SITE (MOS) 34,356,330.77 -9,482,167.41 24,874,163.37

    DEDUCT : 25% OF VALUE OF MATERIALS ON SITE 8,589,082.69 -2,370,541.85 6,218,540.84

    TOTAL VALUE OF EXTRA WORK TO CARRY FORWARD TO SUMMARY STATEMENT 25,767,248.08 -7,111,625.56 18,655,622.53

    Item No DescriptionRates Quantities Amounts (Mzm)

    MATERIALS ON SITE (MOS)

    Polyethlene Sheeting 30mX3m

    Guard-Rails 3,81mx2.6mm

    Spacer Block for guardrails

    Bolt-Post 350 INCL WASHER

    Gabions Matresses 2X1X0,30

    Reinforcing Steel Bars

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 3: Financial Report

    CPG-Civil & Planning Group 25 Monthly Progress Report No 19: October 2015

    Table 3.6: Interim Payment Certificates

    Certificates Date Work done Claims Psums CPA Local CPA Euro MoS RetentionAdvance Payment

    RepaymentVAT Total

    Cert. 00 11-Mar-11 238,067,542.87 16,188,592.92 254,256,135.79

    Cert. 01C R3 6-Feb-13 56,032,074.65 3,177,420.90 5,628,197.77 13,331,778.76 (7,816,947.21) 0.00 5,315,524.10 75,668,048.97

    Cert. 02B R1 31-May-13 63,911,826.73 525,244.86 7,064,292.25 14,836,228.53 985,959.00 (8,732,355.14) 0.00 5,938,001.49 84,529,197.73

    Cert. 03A 19-Jul-13 44,424,859.24 261,602.90 5,927,450.99 9,669,055.74 9,036,587.89 (6,931,955.68) 0.00 4,713,729.86 67,101,330.94

    Cert. 04 3-Sep-13 35,679,710.62 262,603.55 4,206,645.01 8,141,544.22 3,145,719.89 (5,143,622.33) 0.00 3,497,663.18 49,790,264.14

    Cert. 05 3-Oct-13 33,062,921.78 193,105.41 3,615,313.28 6,468,664.81 1,058,498.60 (4,439,850.39) 0.00 3,019,098.26 42,977,751.76

    Cert. 06 A 25-Nov-13 19,242,671.53 16,340.64 1,755,309.07 2,682,797.83 (1,921,319.27) (2,177,579.98) 0.00 1,480,754.39 21,078,974.21

    Cert. 07 15-Jan-14 26,713,619.29 2,344,813.28 2,847,198.21 4,304,508.56 277,656.24 (2,390,469.32) (4,358,764.89) 2,184,774.09 31,923,335.46

    Cert. 08 8-Mar-14 24,260,591.90 199,901.93 4,385,099.61 5,566,782.91 13,866,877.78 (3,441,237.64) (7,724,017.82) 2,757,756.07 39,871,754.74

    Cert. 09 8-Apr-14 21,123,008.47 2,942,598.75 3,882,872.41 5,869,453.37 (2,794,847.96) (6,670,122.65) 1,846,051.10 26,199,013.49

    Cert. 10 30-May-14 25,653,761.99 3,063,995.72 4,253,191.31 3,071,967.13 (3,297,094.90) (12,917,990.38) 1,572,494.95 21,400,325.82

    Cert. 11A 7-Jul-14 29,044,691.62 3,827,816.58 5,555,667.77 5,978,526.05 (3,842,817.60) (9,171,593.89) 2,395,987.35 33,788,277.89

    Cert. 12 2-Sep-14 72,897,305.98 8,094,732.89 10,989,786.63 (2,113,508.96) (9,198,182.55) (23,019,162.83) 4,545,742.45 62,196,713.61

    Cert. 13 2-Oct-14 44,160,462.80 4,355,307.12 6,790,779.06 (3,779,139.62) (5,530,654.90) (13,944,779.85) 2,555,618.81 34,607,593.42

    Cert. 14 4-Mar-15 121,561,415.16 12,136,526.21 18,890,003.73 (7,872,951.75) (15,258,794.51) (44,839,526.90) 6,791,531.72 91,408,203.66

    Cert. 15 28-Jul-15 30,769,004.74 3,807,439.66 1,499,357.79 (285,329.89) (3,607,580.22) (10,257,461.90) 1,736,244.71 23,661,674.89

    Cert. 16 26-Aug-15 48,218,247.75 6,377,799.35 2,826,104.98 917,975.43 (5,742,215.21) (16,074,515.37) 2,874,061.63 39,397,458.56

    Cert. 17 3-Oct-15 80,671,266.34 9,985,438.40 1,593,483.59 (2,469,723.82) (9,225,018.83) (26,893,376.90) 4,276,321.96 57,938,390.73

    Cert. 18 31-Oct-15 57,416,571.65 6,116,433.25 320,524.61 (7,111,625.56) (6,385,352.95) (19,140,960.24) 2,556,864.17 33,772,454.93

    Cert. 19

    834,844,012.24 6,981,033.47 96,137,594.11 121,603,133.25 18,655,622.51 (105,956,577.30) 43,055,269.24 76,246,813.21 1,091,566,900.73

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 4: Contract Administration

    Page 26 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    SECTION 4: CONTRACT ADMINISTRATION

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 4: Contract Administration

    Page 27 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    4 CONTRACT ADMINISTRATION

    4.1 CONTRACT SUPERINTENDENCE AND CHANGES

    The Contractors key staff in attendance on the site during the reporting period are as presented

    here below in Table 4-1.

    Table 4-1: Contractors Key Staff

    Ord. Name Function Nacionalidade

    1 Alberto Piras Contractor Representative Italian

    2 Anteneh Mamo Wolde Mechanic Ethiopian

    3 Antonio Oliveira Fernando Ferreira Quantity Surveyor Portuguese

    4 Domingos Costa Workshop Manager Moz./Portuguese

    5 Fernando Alves Rajado Eletrician Portuguese

    6 Jay Bernardo Administrative Manager Philippine

    7 Marlon Estrada Fuel Controller Philippine

    8 Taib Hbabou Earthmoving Supervisor Moroccan

    9 Tamirat Chekol Mechanic Ethiopian

    10 Twaibu Kamsuli Laboratory Assistant Manager Malawian

    11 Luigi Fumagalli Production Manager Italian

    12 Gabriele Lazzari Administrative Manager Italian

    13 Kouka Mananga Concrete Foreman Congolese

    14 Gianluca de Lorenzo Warehouse Manager Italian

    15 Bana Abderrahman Earthmoving Supervisor Moroccan

    16 Roseller Roxas Surveyor Manager Philippine

    17 Gianni Baldisser Concrete Foreman Italian

    18 Martins Gonalo Workshop Manager Portuguese

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 4: Contract Administration

    Page 28 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    4.2 CONTRACTORS ORGANIZATIONAL CHART

    The Contractors organizational Charts will be presented as and when compilation of the same is

    completed and submitted by the contractor and will be included as Appendix 4.1.

    4.3 CONTRACT RECORDS

    4.3.1 Daily Returns

    The Daily Returns signed by both the Contractor and the Engineer has been compiled during

    the review period.

    4.3.2 Mobilization of Equipment

    The Contractor has satisfactorily mobilized all equipment to site as per contract requirements.

    A list of all equipment on site and their status is as presented under Appendix 4.2

    4.3.3 Labour Return

    The status of labour returns during the reporting period is as presented in Appendix 4.3.

    .

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 5: Quality Control

    Page 29 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    SECTION 5: QUALITY CONTROL

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 5: Quality Control

    Page 30 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    5 QUALITY ASSURANCE

    5.1 PROJECT QUALITY ASSURANCE PLAN (PQAP)

    The status of the project quality assurance plan will be given once adequate information has been

    received.

    5.2 IMPLEMENTATION OF CONTRACTORS QAP

    5.2.1 Quality Control Plan

    There are some forms/work sheets in the quality control plan that is being used currently for

    the day to day activities in the laboratory, site testing and reporting in general. The Quality

    Control Plan is a live document that can be continuously updated during the progress of work.

    5.3 GENERAL QUALITY CONTROL

    5.3.1 Pre works Compliance Checks

    The following are considered to be amongst the pre-work compliance checks

    Health and safety compliance checks

    Environment and social compliance checks

    Labour law compliance checks

    Traffic Management compliance checks

    Material testing facilities and calibration

    Material sources and suitability of materials

    Availability of resources; i.e., office equipment, personnel and office supplies

    Measurement and Survey equipment availability

    Measurements check

    Office facilities

    The Contractor and the Engineer will have to work towards fulfilling all the above throughout

    the time remaining.

    Currently Contractors request for inspection for any relevant activity is preceded by the

    compliance checks as applicable.

    5.3.2 Contractors Supervision

    The status of most of the components of the Contractors Quality Assurance Plan are not yet

    known to the current Engineer. The status concerning the Contractors Health and Safety

    Officer, Environmental Site Officer has not been obvious since recommencement of the works

    after suspension. However, laboratory personnel have been engaged in the implementation of

    the Quality Control Plan.

    5.3.3 Engineers Supervision

    The current Engineer, Civil and Planning Group (CPG), has been attending to Requests for

    Inspection and Approval submitted by the Contractor following completed works activities

    carried out on mainly fills, Subgrade, cement stabilized sub-base and base layers, earth and

    layerworks on bridge approaches construction works on concrete lined drains and gabion

    gravity wall and sampling and testing of materials during the review period.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 5: Quality Control

    Page 31 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    Schedule of Requests for Inspection received from the Contractor and Approvals given by the

    Engineer`s representative for the review period is presented under Appendix 5-1.

    5.4 MATERIAL SAMPLING AND TESTING

    The material sampling and the various types of tests conducted during the review period are

    described under the relevant sub-sections here below and summaries of tests and approval status

    are shown in the schedules presented under Appendix 5-2.

    5.4.1 Materials from Borrow pits

    Sampling and testing for confirmatory tests on CBR, UCS, ITS, durability, Atterberg Limits

    and Linear Shrinkage were carried out for the material that was used for construction of all

    layer works. The results submitted have been compliant and written approvals have been given

    to the contractor as necessary.

    5.4.2 Material from Sub-base and Base Layers

    Samples of materials from cement stabilized sub base and base layers worked on during the

    report period were tested for Indicators,field and laboratory Density, Optimum Moisture

    Content (OMC), Unconfined Compressive Strength (UCS) and Indirect Tensile Strength (ITS)

    tests and all test results are compliant.

    5.4.3 Aggregates for Surface Dressing

    Quality control tests were carried out during the month and all results were acceptable.

    5.4.4 Crushed Stone Base Aggregates from Stockpiles and the road

    Quality control tests were carried out during the month and all results were acceptable.

    5.4.5 Concrete Samples from Construction Site

    Concrete sampled from structural members of bridges as shown in Appendix 5.2 were tested

    for workability and strength and results were acceptable.

    5.4.6 Bitumen Quality

    No biumen was received on site over the report period. However previous supplies of Colflex

    SE1 bitumen last received in September 2015 and used on site were found acceptable as per

    Quality test results submitted by the Contractor and provided by the supplier.

    5.4.7 Prime Coat

    This activity was was not carried out this month.

    5.4.8 Construction of 1st Seal

    This activity was satisfactorily carried out for the section from km 23+500 to km 25+860

    5.4.9 Construction of 2nd Seal.

    This activity was satisfactorily carried out for the section from km 23+500 to km 29+100

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 5: Quality Control

    Page 32 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    5.5 SOURCES OF MATERIALS

    The sources of materials that have been identified and approved to date are as shown in the table

    included under Appendix 5.3.

    5.6 DESIGN MODIFICATION

    The Contractor proposed that the modified binder Colflex SE1 specified in the Lichinga Litunde

    Road Rehabilitation and Upgrading project to be replaced by the penetration grade bitumen

    70/100 of which 330 tons are available at their Montepois Works Yard. The proposal is done

    mainly due to the non availability of the SE1 binder at the Lichinga Site because of sever cash

    flow problem the Contractor is facing at this point in time. The contractors proposal is passed to

    the ANE with the Engineers recommendation for their consideration.

    5.7 ISSUES, PROBLEMS AND SOLUTIONS

    5.7.1 Damaged base layer

    The following two sections were rejected due to damage during the works suspension period

    caused by vehicular traffic and surface run-off during rains.

    The Base sections of the shoulders from chainage 0+900 to 7+140

    The full width base within chainages 23+350 to 25+860

    Instructions were issued to the contractor for rectification of both sections following which

    the section km 23+350 to km 25+860 had already been rectified during the month of

    September 2015.

    5.7.2 Railway Crossing

    The stabilization works of the base layer and surfacing of the section km 10+150 to km

    11+450 could not be completed due to issues concerning level differences between the

    finished road level and the levels at which the railway lines were crossing. This had to be

    discussed with Corridor de Desenvolvimento de Norte (CDN) and Vale. This discussion was

    concluded on 29th September 2015 and the two organizations have now given their consent

    that the road can be constructed at the current design levels. Instructions to proceed with the

    construction works had been issued to the Contractor early October 2015.

    5.7.3 Non-Conformances

    The following non-conformances, all caused by the Contractor, were discovered during the

    review period.

    Wrong alignment setting out on the Lichinga side approach of Uriate Bridge.

    Following the wrong setting out a wrong work was done which now needs

    rectification.

    Abutment embankment slope, left hand side on the Lichinga side, was set out

    wrongly and the slope is cut to the wrong inclination.

    Wrong design of inserting a left curve between two right curves instead of joining

    them with a tangent. Alignment looks aukward. Needs to be changed. But requires

    only minimal rectification.

    Wrong alignment setting out on Lichinga side of Lureco bridge approach. Work

    commenced on the wrong premise and therefore needs rectification by the Contractor.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety

    Page 33 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    SECTION 6: ENVIRONMENT, HEALTH AND SAFETY

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety

    Page 34 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    6 ENVIRONMENTAL MONITORING, HEALTH AND SAFETY

    6.1 QUALITY ASSURANCE DOCUMENTS

    The status of the Project Quality Assurance documents up to end of reporting period will be

    reported on as information becomes available:

    6.2 ESMP IMPLEMENTATION

    6.2.1 EHS Meeting/ Audit/ Inspection

    Will be reported on as and when information becomes available

    6.2.2 Induction/ Training/ Toolbox Talk/Inspection Monitoring

    Will be reported on as and when information becomes available.

    6.2.3 Monthly Environmental, Health and Safety Training Session

    Will be reported on as and when information becomes available..

    6.3 ENVIRONMENT MONITORING

    6.3.1 Environmental Baseline Survey Report (EBSR)

    Will be reported on as and when information becomes available

    6.3.2 Road Reserve

    Anthills

    Site Instructions were issued to the Contractor for removal of anthills within the realignment

    to Lugenda, Uriate , Nicoleze and Lureco bridge approaches as well as for the main road works

    section 23+350 to 66+200 as detailed in Appendix 3.3

    6.3.3 Camp site

    Hazardous Substance Management

    Will be reported on as information becomes available.

    Waste Management

    Will be reported on as information becomes available.

    6.3.4 Borrow Pits

    The status of the borrow pits during the reporting period is as shown in the table below.

    Borrow pits Station Side Status

    25+700 RHS In use for Base material

    29+960 LHS Not opened due to excessive haul distance

    36+640 LHS Not opened, Not required for subgrade

    38+400 LHS Used up; Pending rehabilitation

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety

    Page 35 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    47+400 LHS Used up; Pending rehabilitation

    47+800 LHS In Use for subbase

    74+800 LHS Stock piling in progress for subbase and base

    154+000 RHS Stock piling in progress for base blending with

    crushed stone.

    154+000 LHS Pending rehabilitation

    171+900 RHS Pending rehabilitation

    176+300 LHS Stock piling in progress for subbase and base

    186+300 L and In use for fill and preparation for Subbase stock

    187+200 LHS No Longer Required

    242+200 RHS Not yet opened for sub-base and base

    242+200 LHS Not yet opened for fill

    276+700 RHS Not yet opened for fill

    277+700 LHS Not yet opened for sub-base and base

    6.4 SAFETY MONITORING

    6.4.1 Accident/ Incident Records

    Will be reported on as information becomes available under Appedix 6.1.

    6.4.2 Road Safety Campaign

    Will be reported on as information becomes available.

    6.4.3 Personnel Protective Equipment

    All the Contractors employees were provided with basic safety equipment. But currently it is

    observed that some workers do not use PPE

    6.4.4 Fire Extinguisher

    Fire extinguishers have been distributed within the Campsite, Engineers facilities and the

    Quarry including the second camp site at Lugenda and efforts are being made to improve the

    current situation.

    6.4.5 Traffic Accommodation

    The deviation has been satisfactorily constructed between km 23+400 and km 66+200 and is

    currently open to traffic. The Contractor is currently working towards making the main road

    trafficable during the rainy season.

    6.5 HEALTH MONITORING

    6.5.1 Site Clinic

    A Clinic and an ambulance have been available to the workers and fully functional.

    6.5.2 Illness/ Injuries

    No Reports of injuries and illnesses have been recorded in this period.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety

    Page 36 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    6.5.3 Water for Human Consumption ( Laboratory Results)

    Reports will be made when more information is available.

    6.5.4 Toilets

    Reports will be made on portable toilets for field use when more information is received

    concerning this matter.

    6.5.5 First Aid Kits

    Reports will be made when more information is received concerning this matter.

    6.6 HIV/AIDS AWARENESS CAMPAIGN

    The Contractor held HIV/AIDS awareness and prevention campaign, the first after resumption

    of the works, using own trained staff. A report was also generated and submitted to the Engineer

    for review. This work is conducted at the Contractors own cost and will continue to be this way

    until the Environment, Health and Safety Officer and the HIV/AIDS awareness campaigner

    subcontractor have been remobilized. In addition, the Contractor has also submitted HIV/AIDS

    Awareness and Prevention Campaign Program covering the period from 20th October 2015 to

    17th December 2015. Copies of the above report and campaign program are presented under

    Appendix Appedix 6.2.

    6.7 TRAFFICKING IN PERSONS (TIP)

    Can only be reported as and when information is received.

    6.8 SOCIAL ISSUES

    6.8.1 Project Liaison Committee (PLC)

    Reports will be prepared once more information has been received.

    6.8.2 Employment and gender issues

    Statistics of number workers subdivided into gender during the life of the project to date will

    be given once it is made available.

    6.8.3 Non-conformances Monitoring

    This will be reported once the record has been made available or received under.

    6.9 PROJECT TECHNICAL ISSUES

    All the documents in the table below needed to have been submitted by the Contractor and

    checked and approved by the Engineer. Whether this had been done before the period of

    suspension of the works can only be reported when the information is received.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 6: Envir., Health & Safety

    Page 37 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    Description Date Submitted By Contractor

    Current Status Version 00 Version 01

    Waste Management Plan TBA

    HSE Awareness Training

    Plan TBA

    Environmental Method

    Statement (EMS) Camp

    Site Clearing and

    Grubbing

    TBA

    EMS Camp Site

    Establishment TBA

    EMS Road Maintenance TBA

    EMS Road Reserve

    Clearing and Grubbing TBA

    EMS Treatment of Ant

    hills TBA

    EMS Borrow pits TBA

    EMS Opening of

    Dumping Site TBA

    EMS Concrete Batching

    Plant localization TBA

    EMS for Quarry TBA

    EMS Quarry Rock

    Blasting TBA

    EMS Waste Management TBA

    EMS Chemical Products TBA

    EMS Deviations TBA

    EMS Rehabilitation of

    Borrow Pits TBA

    Road Awareness Plan TBA

    EMS Application of MC

    30 and Bitumen Products TBA

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 7: Ancillary Activity

    Page 38 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    SECTION 7: ANCILLARY ACTIVITIES

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 7: Ancillary Activity

    Page 39 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    7 ANCILLARY ACTIVITIES

    7.1 CLIMATIC & WEATHER CONDITIONS AND CHARTS

    Rain gauge readings for the month of October 2015 and a table showing the possible effects of

    the rains on the works are presented under Appendix 7.1.

    7.2 LAND ACQUISITION AND UTILITIES RELOCATION

    These two activities were not done during the review period.

    7.3 RESETTLEMENT ACTION PLAN (RAP) IMPLEMENTATION

    The work of RAP Implementation has been completed. There were some properties identified

    for compensation at Uriate and Lugenda Bridges. A list of names of property owners eligible for

    compensation will be presented under Appendix 7.2 as and when information is available.

    7.4 OUTSTANDING RESETTLEMENT ACTION PLAN (RAP) ISSUES

    There are no outstanding resettlement action plan issues.

    7.5 SUBCONTRACTING AND COMPLIANCE WITH ESMP IMPLEMENTATION PLAN

    There is no Subcontractor on the project site currently.

    7.6 CORRESPONDENCE

    The summary list of correspondence as well as some key correspondence for the review period

    is presented under Appendix 7.3.

    7.7 STATUS OF AS-BUILT DRAWINGS

    Preparation of as built drawings has not yet commenced.

    7.8 RECORD AND MINUTES OF MEETINGS

    7.8.1 Minutes of Monthly Site Meeting

    The monthly Progress Site Meeting was held on 27th and 28th October 2015. On 27th October

    2015 a site visit in connection with road works was conducted following which a Progress Site

    Meeting was held at the Engineers Office. On 28th October 2015 site vist was conducted in

    connection with the five bridges being constructed in the Litunde to Marrupa section. The

    minutes are presented under Appendix 7.4.

    7.8.2 Minutes of Technical Meeting

    Technical Meetings was held on 21st October 2015 minutes of which are presented under

    Appendix 7.4.

    7.8.3 Minutes of EHS

    No EHS meeting had been held during the review period.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 7: Ancillary Activity

    Page 40 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    7.9 VISITS

    Details if any will be presented under Appendix 7.5.

    7.10 PHOTOGRAPHIC RECORD

    Project photographic records are presented under Appendix 7.6.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services

    Page 41 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    SECTION 8: RISKS AND MITIGATION MEASURES

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services

    Page 42 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    8 RISKS AND MITIGATION MEASURES

    8.1 RISKS TO SUCCESSFUL PROJECT IMPLEMENTATION

    The tentative programme of works issued by the contractor in June 2015 had been replaced by a

    revised one on 4th October 2015. According to this program the work could be expected to be

    completed only in February 2016. But this is only possible if the following issues were resolved

    urgently.

    a) Settlement of all issues pertaining to Claims, certificates and extension of tim b) Revision of the tentative Program of Works and strict adherence to it by the

    Contractor.

    c) Urgent decision by Adiministraa Nacional de Estradas concerning the issue pertaining to replacement of SE-1 (SBR) bitumen currently in use by a common

    70/100 penetration grade bitumen.

    d) Resolving the problem faced by the Contractor in connection with cash flow and the resulting problem in purchasing cement, binder and diesel.

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services

    Page 43 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    SECTION 9: SUPERVISION SERVICES

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services

    Page 44 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    9 SUPERVISION SERVICES

    9.1 CONSULTANCY CONTRACT DETAIL

    Contract Name : Rehabilitation of Road N14 between Lichinga

    and Litunde

    Funding : AfDB

    Employer : Administrao Nacional de Estradas (ANE)

    Contract No. : TBA

    Contract Amount for Phase 3 : TBA

    Date of Contract Signing : TBA

    Commencement Date : TBA

    Completion Date : TBA

    Percentage Time Elapsed : TBA

    Revised Completion Date : TBA

    Revised Contract Amount : TBA

    9.2 ENGINEERS ORGANIZATIONAL STRUCTURE

    9.2.1 Organizational Structure and Staffing

    The Engineers organizational structure is as given in tabular form below.

    Table 9.1: Record of CPG Staffing

    Position Name Effective Base Work Permit Status

    Management

    Project Manager Rick Correia Maputo

    Engineer JP DAguiar Maputo

    Site Supervision Staff Lot C: Lichinga Litunde Road

    Resident Engineer Elias Ibrahim Lichinga, 5th April

    2015

    Issued

    Measurements D.R.

    Engineer

    Simon Nderi Lichinga,

    September,2015

    Issued

    Materials/A.R. Engineer Peter

    Mzarabani

    Lichinga, 15th March

    2015

    Issued

    Materials/D.R. Engineer Charles

    Munetsi

    Lichinga August,2015 Issued

    Inspector of Works Carlos

    Lourenzo

    Lichinga August,2015 Local

    Surveyor Salvadore

    Tamele

    Lichinga August,2015 Local

  • The Rehabilitation of Road N14 between Litunde to Lichinga and Construction

    of Seven Bridges between Litunde and Marrupa in Niassa Province, Mozambique Section 9: Supervision Services

    Page 45 of 48

    CPG-Civil & Planning Group Monthly Progress Report No 19: October 2015

    EHS Supervisor TBA

    9.3 ENGINEERS REPORTING PERIOD ACTIVITY

    9.3.1 General Supervision Activities

    Table 9.4: Supervision Activities Summary

    9.4 FINANCIAL DATA, INVOICING, ESTIMATE TO COMPLETION

    9.4.1 Invoices to Date

    The Status of invoices for the Supervision Services is as shown in the table below.

    Ac