monthly__progress_report march draft .docx
TRANSCRIPT
Contents
1. CHAPTER 1: CONTRACT STATUS & PROJECT PARTIES...........................................................................5
1.0. CONTRACT STATUS.............................................................................................................................51.1. PROJECT PARTIES................................................................................................................................51.2. INSURANCES AND BONDS..................................................................................................................61.3. VALUATION........................................................................................................................................71.4. CONTRACTOR SITE ORGANIZATION CHART...................................................................................................8
2. CHAPTER 2: OVERVIEW...................................................................................................................... 9
2.0. PROJECT SCOPE..................................................................................................................................92.1. PROGRESS UP TO 01/25/2016..........................................................................................................102.2. REASONS OF DELAY...............................................................................................................................102.3. PROJECT LOCATION..........................................................................................................................11
3. CHAPTER 3: NOTIFICATIONS, SITE INSTRUCTIONS, CLAIMS AND VARIATION ORDERS........................12
3.0. NOTIFICATIONS................................................................................................................................123.1. SITE INSTRUCTIONS..........................................................................................................................143.2. CLAIMS.............................................................................................................................................153.3. VARIATION ORDER...........................................................................................................................16
4. CHAPTER 4 HSE MONTHLY DETAILED REPORT FOR THE MONTH OF JANUARY 2016............................17
4.0. HIGHLIGHTS:........................................................................................................................................174.1. STATUS OF H & S ACTIVITIES DONE IN JANUARY 2016................................................................................174.2. H & S ACTION PLAN FOR NEXT MONTH FEBRUARY 2016.............................................................................184.3. RECORD OF INCIDENTS / ACCIDENTS DETAILS OF INCIDENTS..........................................................................19
4.3.1. Details of First aid injuries:.........................................................................................20
4.3.2. Traffic / Road Incidents:..............................................................................................21
4.4. SAFETY INSPECTIONS CONDUCTED DURING THE MONTH:...............................................................................214.5. H & S STATISTICS REPORT. (25TH DECEMBER –25TH JANUARY 2016)..............................................................224.6. SAFETY TRAININGS...............................................................................................................................224.7. SAFETY VIOLATIONS:..............................................................................................................................234.8. COMPLIANCE WITH LABOR LAW...............................................................................................................23
5. CHAPTER 5 ENGINEERING.................................................................................................................. 24
5.0. ACTIVITIES PERFORMED...................................................................................................................245.1. ACTIVITIES TO PERFORM NEXT MONTH...........................................................................................245.2. HOT POINTS......................................................................................................................................245.3. BLOCKING POINTS............................................................................................................................24
6. CHAPTER 6 MATERIAL....................................................................................................................... 25
6.0. ACTIVITIES PEFORMED.....................................................................................................................256.1. ACTIVITIES TO PERFORM NEXT MONTH...........................................................................................256.2. HOT POINTS......................................................................................................................................256.3. BLOCKING POINTS............................................................................................................................25
7. CHAPTER 7: CONSTRUCTION............................................................................................................. 26
7.0. ACTIVITIES PERFORMED...................................................................................................................267.1. ACTIVITIES TO PERFORM NEXT MONTH...........................................................................................277.2. HOT POINTS......................................................................................................................................27
1
7.3. BLOCKING POINTS............................................................................................................................277.4. AREA OF CONCERN...........................................................................................................................287.5. PROGRESS.........................................................................................................................................297.6. QUANTITIES PROGRESS...........................................................................................................................307.7. PROGRESS S CURVE..........................................................................................................................317.8. DIRECT MANPOWER DISTRIBUTION.................................................................................................327.9. MANPOWER HISTOGRAM................................................................................................................337.10. EQUIPMENT DISTRIBUTION..............................................................................................................347.11. EQUIPMENT HISTOGRAM.................................................................................................................35
8. CHAPTER 8 QUALITY.......................................................................................................................... 36
8.0. ACTIVITY PERFORMED......................................................................................................................368.1. ACTIVITY TO PERFORM NEXT MONTH..............................................................................................378.2. HOT POINTS......................................................................................................................................398.3. BLOCKING POINTS............................................................................................................................39
9. CHAPTER 9: LOG & REGISTERS........................................................................................................... 40
9.0. SUBMITTAL STATUS SUMMARY........................................................................................................419.1. REQUEST FOR INSPECTION (RFI).......................................................................................................429.2. MATERIAL SUBMITTAL REGISTER.....................................................................................................439.3. METHOD STATEMENT REGISTER......................................................................................................449.4. CORRESPONDENCES REGISTER.........................................................................................................459.5. SHOP DRAWINGS REGISTER.............................................................................................................469.6. NCR REGISTER..................................................................................................................................479.7. RO (ROAD OPENING) STATUS...........................................................................................................48
10. APPENDIX A.................................................................................................................................. 49
10.0. EXECUTION PROGRAMME UPDATE..................................................................................................5010.1. THREE MONTHS ROLLING PROGRAMME..........................................................................................5110.2. PROGRESS DETAILS STATUS..............................................................................................................5210.3. PROGRESS DRAWING UP TO 01/25/2016.........................................................................................5310.4. PROGRESS S-CURVE..........................................................................................................................54
10.5. EXPECTED CASH FLOW.....................................................................................................................55
11. APPENDIX B.................................................................................................................................. 56
11.0. PHOTOGRAPHIC RECORDS FROM 25TH DECEMBER– 25THJANUARY PERIOD...........................................57
2
1. CHAPTER 1: CONTRACT STATUS & PROJECT PARTIES
1.0. CONTRACT STATUS
PROJECT START DATE: 5 th January 2014
ORIGINAL PROJECT COMPLETION DATE
4th May 2015
PROJECT COMPLETION DATE AS PER VARIATION No 3
16th February 2016
PROJECT DURATION: 485 CALENDAR DAYSREVISED PROJECT DURATION:
773 CALENDAR DAYS
MAINTENANCE PERIOD: 400 CALENDAR DAYS
PROJECT BUDGET (QR): 313,000,000.00 QAR
REVISED PROJECT BUDGET AS PER BASELINE REV 6.0
327,653,158.00 QAR
1.1. PROJECT PARTIES
CLIENT:
CONSULTANT:
3
CONTRACTOR
1.2. INSURANCES AND BONDS
Documents Validity
Contractor’s All Risks Insurance Policy 19th May 2016 plus 400
days maintenance periodWorkmen Compensation Insurance Policy
31st May 2016Professional Indemnity Insurance
19th May 2016 plus 400 days maintenance period
Performance Bond 20th June 2017
Advance Payment Guarantee Valid till PWA receive full
payment of the advance payment amount
Retention Guarantee 16th May 2016
4
Executed1 Advance Payment - 31,300,000.00 Paid 2 Feb.14 3,650,177.01 3,102,650.46 Paid
3 Mar.14 759,233.21 949,200.45 Paid
4 Apr.14 1,733,962.73 1,790,435.92 Paid
5 May.14 2,201,205.73 2,051,076.98 Paid
6 J un.14 6,545,711.51 7,146,863.20 Paid
7 J ul.14 6,163,707.54 6,217,213.74 Paid
8 Aug.14 8,882,054.21 7,743,461.22 Paid
9 Sep.14 10,431,507.36 8,412,300.09 Paid
10 Oct.14 13,003,479.12 10,939,175.85 Paid
11 Nov.14 14,805,968.30 12,467,352.62 Paid
14 Feb.15 14,282,674.21 12,391,255.77 Paid
15 Mar.15 15,342,198.34 13,009,376.62 Paid
16 Apr.15 11,119,071.81 10,178,426.33 Paid
17 May.15 8,310,716.70 6,937,792.04 Paid
18 J un.15 11,346,845.46 9,645,201.18 Paid
19 J ul.15 5,134,586.52 4,389,090.24 Paid
20 Aug.15 6,934,670.96 6,658,755.46 Paid
21 Sep.15 7,552,777.51 6,423,528.08 Paid
22 Oct.15 7,293,164.08 6,094,395.62 With PWA
23 Nov.15 6,446,196.37 5,607,257.48 With PWA
24 Dec.15 4,251,544.27 3,418,718.00 With PWA
206,107,812.58 176,899,051.20
Duration
Total=
Certified Amounts (QR)IPC No. Remarks
12 Dec.14 19,469,069.77 14,570,711.71
Paid
Paid
16,754,812.14 13 20,447,289.86 J an.15
5
1.3. VALUATION
6
1.4. CONTRACTOR SITE ORGANIZATION CHART
7
2. CHAPTER 2: OVERVIEW
2.0. PROJECT SCOPE
The ALKHEESA North and East Package 01 – C2013/73 is located in the Al RAWDAT AL HAMANA District .Once completed, the project will provide infrastructure including a sewage network, a new road network, traffic signals and street landscaping for the residents of Rawdat. The project has started in 5th January 2014 and will end in May 2015. The works has been
extended recently to 16th of February 2016.
The Project scope of work are as follows :
Demolition, Site Clearance and Earthworks
Storm Water Drainage
o Microtunneling
Foul Sewer
o Microtunneling
Treatment Sewage Effluents
Balancing & Attenuation Tanks
Electrical Works
Utility com Services Works
Roads and Pavement
Traffic Sign and Roads Marking
Street light Works
Landscaping and Irrigation
8
2.1. PROGRESS UP TO 01/25/2016
TITLES PREVIOUS CURRENT TOTALAct % Pl % Act % Pl % Act % Pl %
Overall Progress % 68.21% 72.06%
3.47% 7.40%
71.68%
79.46%
Overall Progress *% 67.16% 99.48%
4.63% 0.39%
71.79%
99.87%
Variance % -24.39% 16.61% -7.78%Variance *% -32.84% 4.76% -28.08%Delay (days ) -138 -50 -188Delay *(days ) -219 4 -215
Construction Progress %
68.20% 72.35%
3.69% 7.94%
71.89%
80.29%
Construction Progress* %
67.05% 99.52%
5.08% 0.47%
72.13%
99.99%
Variance % -24.50% 16.10% -8.40%Variance *% -32.95% 5.09% -27.86%Expected Delay (days)
-138 -50 -188
Expected Delay* (days)
-219 15 -204
Expected Completion date
3-Jul-16 22-Aug-16
Expected Completion date*
16-Oct-16 18-Sep-16
*The symbol (*) indicates the progress & delay from the Original Baseline
2.2. REASONS OF DELAY
1. Electrical scheme which will prevent to issue SIS
2. Reinforcement for TSE Chambers
3. Ooredoo scope of Works
4. Site instruction approval
5. Waterline protection
6. Street parking maximization
9
2.3. PROJECT LOCATION
10
Roads and Infrastructure in Al-Kheesa (Rawdat Al-Hamana District), Package 01
3. CHAPTER 3: NOTIFICATIONS, SITE INSTRUCTIONS, CLAIMS AND VARIATION ORDERS
3.0. NOTIFICATIONS
# CONTENT LETTER REFERENCE DATE
1 Interference of another Contractor water lines works with the project
DN07-P01-CGC-SACYR-HYD-LET-00169-14
11/05/2014
2 Combined Trench DN071-P01-CGC-SACYR-HYD-LET-00179-14
06/08/2014
3 Third Party Obstructing works at site DN071-P01-CGC-SACYR-HYD-LET-00255
02/08/2014
4 Grouting of cavity between shafts SH1/40/021 and SH1/40/020
DN071-P01-CGC-SACYR-HYD-LET-00265
08/08/2014
5 Clashing of shafts excavation with third party works
DN071-P01-CGC-SACYR-HYD-LET-00274
13/09/2014
5 Relocation /Diversion of Electrical Cables DN071-P01-CGC-SACYR-HYD-LET-00346
09/09/2014
6 Material Submittals Delay DN071-P01-CGC-HYD-LET-A10071
11/19/2014
7 TSE Chambers Reinforcement Drawings DN071-P01-CGC-HYD-LET-A10071
11/22/2014
8 Flow Control Manholes DN071-P01-CGC-HYD-LET-A10094
12/04/2014
9 Road 55 DN071-P01-CGC-HYD-LET-A10098
12/06/2014
10 Provisional Sum LDN071-P01-CGC-HYD-LET-A10102
12/07/2014
11 Geotextile membrane for foul sewer trenches DN071-P01-CGC-HYD-LET-A10103
12/08/2014
14 Rework (Foul sewer house connection relocated to next manhole in road D47)
DN071-P01-CGC-HYD-LET-A10119
20/12/2014
15 Shortage of washed sand /concrete price's hike
DN071-P01-CGC-HYD-LET-A10121
12/21/2014
17 Notice of claim N09-Car parking Maximization
DN071-P01-CGC-HYD-LET-A10153
01/03/2015
18 Road Work s& Duct Crossing DN071-P01-CGC-HYD-LET-A10163
01/07/2015
19 KAHRAMAA Notice to stop the works DN071-P01-CGC-HYD-LET-A10171
01/10/2015
20 Site Instruction N06 DN071-P01-CGC-HYD-LET-A10200
01/28/2015
11
21 Notice of claim No10 Replacement of site concrete barriers
DN071-P01-CGC-HYD-LET-A10204
01/30/2015
CONTENT LETTER REFERENCE DATE
22 Diesel price hike DN071-P01-CGC-HYD-LET-A10205
01/31/2015
23 Cost of processed (crushing & screening) backfilling material
DN071-P01-CGC-HYD-LET-A10206
01/31/2015
24 On Street parking maximization DN071-P01-CGC-HYD-LET-A10222
02/09/2015
26 D65 5 th reminder DN071-P01-CGC-HYD-LET-A10489
06/08/2015
27 Concrete Interlock tiles with granite Effect DN071-P01-CGC-HYD-LET-A10294
03/12/2015
28 Missing Item of excavation in bill N0 7(half perforated )
DN071-P01-CGC-HYD-LET-A10376 23/04/2015
29 Notice of claim 14-Revised Cost of balancing Tank
DN071-P01-CGC-HYD-LET-A10424
05/13/2015
30 Notice of claim No15-tack coat for 2nd layer of Asphalt base course
DN071-P01-CGC-HYD-LET-A10428
05/14/2015
34 Additional cost of project Insurance, bond renewed for extended period
DN071-P01-CGC-HYD-LET-A10463
05/28/2015
35 Project prelim for extended period DN071-P01-CGC-HYD-LET-A10464
05/28/2015
36 Street Lighting Luminaires DN071-P01-CGC-HYD-LET-A10504
06/14/2015
37 Road 65 and Drainage layout plan sheet 37 DN071-P01-CGC-HYD-LET-A10526
06/28/2015
38 Claim for 2nd layer of tack coat in Asphalt base course
DN071-P01-CGC-HYD-LET-A10663
10/18/2015
39 Missing Item in BOQ-4Cx25mm2cable for road Lighting Distribution
DN071-P01-CGC-HYD-LET-A10678
26/10/2015
12
3.1. SITE INSTRUCTIONS
# CONTENT LETTER REF. DATECGC-
SACYR REPLY
1 Deleting 6nos Attenuation tank including modular unit
DN071-P01-CGC-SACYR-HYD-LET-00350
2/25/2014 9/11/2014
2 Epoxy coating for storm water structureDN071-P01-CGC-SACYR-HYD-LET-00397
6/14/2014 10/2/2014
3 Revised site boundary/ limit of /works , additional ground investigation field works
DN071-P01-CGC-SACYR-HYD-LET-00257
7/3/2014 8/3/2014
4 Balancing tanks on hold Cancelled
5 Add Electrical ducts DN071-P01-CGC-HYD-LET-A10435 1/28/2015 8/19/2015
6 Change As per CB Drawings Revision DN071-P01-CGC-HYD-LET-A10540 1/28/2015 7/5/2015
7 Add extra Bore Holes DN071-P01-CGC-HYD-LET-A10589 10/21/2014 8/13/2015
8 Changing Street Lighting LUMINAIRES HPS TO LED
DN071-P01-CGC-HYD-LET-A10688 5/17/2015 11/2/2015
9 Add # 6N0s Attenuation Tanks DN071-P01-CGC-HYD-LET-A10356 12/29/2015 4/13/2015
10 Add #3N0s Attenuation Tanks Cancelled
11 Ooredoo scope of works Cancelled
12 Maximization of street parking DN071-P01-CGC-HYD-LET-A10802 3/1/2015 1/21/2016
13 Changes of pavements Type B under non traffic Areas
DN071-P01-CGC-HYD-LET-A10242 2/4/2015 2/17/2015
14 Water ducts and protections DN071-P01-CGC-HYD-LET-A10502 5/21/2015 6/14/2015
15 Additional IFC drawings for Attenuation Tanks
DN071-P01-HYD-CGC-LET-A10531 5/23/2015 8/26/2015
16 Duct crossing for future utility connection of potable water
DN071-P01-CGC-HYD-LET-A10483 5/23/2015 6/8/2015
13
3.2. CLAIMS
# CONTENT SUBMITTED DATE
COMMENTS
1 Balancing tank 11/29/2014
2 Obstruction at Road D55 (EOT & Prolongation Cost) Not submitted
3 TSE Chambers Reinforcement (Construction Cost) 6/20/2015
4 Sikkat lighting Not submitted
5 Geotextile membrane for Foul Sewer Tranches 11/23/2015
6 Re-work (Foul sewer house connection relocated to next manhole in road D47) 12/20/2014
7 Shortage of washed sand and concrete price hike Not submitted
8 Add 6 Nos of Attenuation 6/20/2015
9 Maximization of street parking 3/19/2015
10 Cost of replacement of site concrete barriers 3/29/2015
11 Increase of Diesel price Not submitted
12 Backfill material as crushing for backfilling (Cost) Not submitted
13
Missing Item of Excavation in Bill No.7 (Half Perforated) ESVC Pipe all dia 6/21/2015
14 Revised Rate of Balancing Tank Not submitted
15
Tack Coat missing quantity in Bill No.4 for 2nd Layer of Asphalt Base Course 5/20/2015
16
Additional Cost of Project Insurances, Bonds Renewed for Extended Period Not submitted
17 Project Prelims for Extended Period Not submitted
18
Missing Item in BOQ – 4Cx25mm2 Cable for Road Lighting Distribution 11/23/2015
19 RC 1200MM dia pipe 10/9/2014
20 Unit rate of the Item's not included in the BOQ of storm water 9/6/2014
21 Back / Ramp drop item's 12/21/2014
22 Upvc gully connections 2/7/2015
23 Street lighting duct type (SL-2) 3/23/2015
24
Providing Metering for all Feeder Pillar & LV loads as per KM requirements Not submitted
25 Unit rate of the Item's not included in the BOQ of Foul Sewer 6/9/2014
2 Additional Excavation + Separation Wall + Backfilling in Not submitted
14
6 Combined Trenches27 Cavity at balancing tank (Excavation+Disposal+Concrete Filling) 2/3/2015
28
Additional Excavation + Separation Wall + Backing in Combined Trenches 4/21/2015
29 Cavity at balancing tank (Excavation+Disposal+Backfilling) 8/27/2015
30 Acceleration cost of the works at Roads D21 & D22 5/30/2015
3.3. VARIATION ORDER
# CONTENT DATE COSTS
1 Changes as per CB drawing (cost) 07/05/2015 28273.82
2 Changes as per CB drawing (prolongation cost)
3 Add Extra N0 Bore Holes 21/10/2014 77102.99
4 Add Epoxy coating & Delete bituminous painting
09/11/2014 401,270.02
5 Missing Item of excavation in bill N0 7(half perforated )
23/11/2015 4565924.09
6 Tack coat missing quantity in bill N0.4For 2nd layer of asphalt base course
20/05/2015 92610.75
7 RC pipes 1200 mm 09/10/2014 398791.63
8 Street lighting Ducts Sl2 23/03/2015 249,930.36
9 Item's not in the BOQ of storm water & foul sewer
09/06/2014 291,899.39
10 Back / Ramp drop item's 21/12/2014 350000.00
11 Upvc gully connections 07/02/2015 139463.76
12 Reduction in verges subgrade layer 17/02/2015 3785993.25
13 Protection slab for existing potable water pipe crossing asphalt
14/06/2015 924,505.84
14 Additional IFC drawings for Attenuation Tanks (Hydrodynamic Separator Details)
08/09/2015 288,738.94
15 Providing Metering for all Feeder Pillar & LV loadsas per KM requirements
23/11/2015 499,648.51
16 Duct crossing for future utility connection of potable water
06/07/2015 1,287,320.06
17 Missing Item in BOQ – 4Cx25mm2 Cable for 23/11/2015 499,648.51
15
RoadLighting Distribution
18 Missing Item of Excavation in Bill No.7 (Half Perforated) ESVC Pipe all dia
21/06/2015 4,565,924.09
19 Replacement of HPS Luminaires with LED Luminaires
16
4. CHAPTER 4 HSE MONTHLY DETAILED REPORT FOR THE MONTH OF MARCH 2016
4.0. HIGHLIGHTS:
Continues repair of public protection fences and installation of edge protection for trenches.
Conducted internal training sections as per training matrix.
Conducted confined space recue drill.
Safety activities conducted as per the action plan for the month of March 2016; to ensure safe site conditions, implementation of safe working procedures during construction activities, and for enhancing safety culture among all site employees.
4.1. STATUS OF H & S ACTIVITIES DONE IN MARCH 2016.
Sl # ObjectivesSTATUS OF ACTION TAKEN
(MARCH 2016)1 To identify and control unsafe acts, unsafe
conditions, hazards and risks on site during on-going activities.
HSE Inspection of site were carried out by HSE Officers, lapses will be discussed with Foremen and corrective actions ensured. Inspection Reports submitted on major issues to Project Director, and Ensure corrective actions.
2 To discuss safety lapses and to enhance coordination between construction staff and HSE dept. for implementation of safety requirements
HSE Meetings for Construction staff conducted on weekly basis.
3 To inculcate safety culture and enhance Safety Awareness on among all site employees.
Safety Inductions for all New employees, and visitors.Safety training – as per training matrix.Tool box meetings - weekly
4 To inspect housekeeping issues at site. Regular Inspections conducted.
5 To ensure Traffic diversion are as per T D P & regular maintenance
Regular Inspections conducted.
6 To ensure all workers getting cool water for drinking during working hours.
Conducted through monitoring.
17
7 To identify and control unsafe acts, unsafe conditions, hazards and risks on site during on-going activities.
Conducted through monitoring and routine inspections.
Sl # Objectives Status of action taken (March 2016)
8All rescue equipment and full body harness must be inspected.
All rescue equipment and full body harness inspected.
9 First aid training for 24 staff and operatives.
Conducted.
10 Emergency evacuation drill for excavation. Conducted. 11 To ensure scaffolding is properly erected
with trained workers for work at height activities
Conducted through monitoring and daily/weekly inspections. And scafftag systems implemented.
12 Placing of concrete barriers in front of Qatari residences
On-going.
13 Reward system for workers. 2 foremen and 2 workers were selected for monthly HSE award system.
14 MSDS training for store related personals Conducted.
4.2. H & S ACTION PLAN FOR NEXT MONTH APRIL 2016
Sl # Objectives Status of action Planned (April 2016)1 To identify and control unsafe acts, unsafe
conditions, hazards and risks on site during on-going activities.
HSE Inspection of site will be carried out by HSE Officers, lapses will be discussed with Foremen and corrective actions will be ensured. Inspection Reports will be submitted on major issues to Project Director, Ensure corrective actions.
2 To discuss safety lapses and to enhance coordination between construction staff and HSE dept. for implementation of safety requirements
HSE Meetings for Construction staff to be conducted.
3 To inculcate safety culture and enhance Safety Awareness on among all site employees.
Safety Inductions for all New employees, and visitors.Safety training – as per training matrix.Tool box meetings - weekly
4 To inspect housekeeping issues at site. Regular Inspections to be conducted.5 To ensure Traffic diversion are as per T D
P & regular maintenance Regular Inspections to be conducted.
6 To ensure all workers getting cool water for drinking during working hours.
Conduct through monitoring.
7 To identify and control unsafe acts, unsafe conditions, hazards and risks on site during on-going activities.
HSE Inspection of site will be carried out by HSE Officers, lapses will be discussed with Foremen and corrective actions will be ensured.
18
Inspection Reports will be submitted on major issues to Project Director, Ensure corrective actions.
Sl # Objectives Status of action planned (APRIL 2016)
8All rescue equipment and full body harness must be inspected.
All rescue equipment and full body harness will be inspected.
9 Confined space training for 4 operatives. To be conducted.10 Emergency evacuation drill for work at
height. To be conducted.
11 To ensure scaffolding is properly erected with trained workers for work at height activities
Conduct through monitoring and daily/weekly inspections. And scafftag systems have to be implemented.
12 Placing of concrete barriers in front of Qatari residences
To be done.
13 Reward system for workers. Monthly Once.14 Oil spillage response training for store
related personals To be conducted.
4.3. RECORD OF INCIDENTS / ACCIDENTS DETAILS OF INCIDENTS
Description of incidents / accidents Reported / Recorded.Man-hours worked till date 3124265First Aid injuries 202Sickness spells 03Loss Time Injuries 1Fatalities 0Near Miss 22Property Damage 4Fire Incidents 0Environmental incidents 0
19
4.3.1. Details of First aid injuries:
Nature of Injury
Nos Body part affected Root Cause Identified
01
Abrasion 05
1. Head
2. Left hand middle finger
3. Left leg knee
4. Right hand thump
5. Right hand index finger.
1. Abrasion on back side of head, he got hit with steel while he was sleeping in rest area.
2. Mild abrasion on left hand middle finger. He got hit with hammer, while he was fixing nail.
3. Mild abrasion on left leg knee, he tripped and fell on the floor.
4. Mild abrasion on right hand thump. He got hit with pipe, while he was placing the pipe on the floor.
5. Abrasion on right index finger, he got hit with steel, while he was working at the site.
02
Laceration 02
1. Right leg bellow knee
2. Right leg bellow knee
1. Lacerated wound on right leg bellow knee. He got hit with stone while he was cutting stone with hammer.
2. Laceration on right leg bellow knee, he got hit with steel while he was transferring steel from the vehicle.
03
Bruising 01 1. Right leg feet
1. Bruising on right leg feet generator fell on his leg, while he was trying to lifting the generator.
04
Puncture 02
1. Right leg foot
2. Right leg foot
1. Nail prick on right leg under the feet, while he stepped over the plywood.
2. Nail prick on right leg feet, he got hit with nail while he stepped over the plywood.
20
05 Others 02
1. Head
2. Right leg
1. Pain and swelling on left side check. He got hit with shutter while he was transferring from vehicle.
2. Pain and swelling on right Lower leg, due to hit by plywood.
4.3.2. Traffic / Road Incidents:
Incident Recorded Incidents Ref: Report No.Vehicle accidents 0 Not applicableProperty Damage 0 Not applicableFatal Accident 0 Not applicableFirst Aid cases 12 Not applicable
4.4. SAFETY INSPECTIONS CONDUCTED DURING THE MONTH:
Sr. No Equipment Quantity8.5.1 Heavy Mobile Equipment
1 Excavator equipment(Jack hammer / bucket) 002 Loader / shovel 023 Backhoe 024 Drum Cutter 005 Truck mounted crane 00
Equipment Quantity6 Roller 057 Bobcat 048 Mobile Crane 02
8.5.2 Portable / Stationary equipment1 Generators 92 Welding Machine 013 Tower light 014 Plate Compactor 025 Power tools 206 Fire Extinguishers 447 Inspection of Site clinic and welfare facilities 4 times8 Site Inspection (observation) Reports 10
Total number of inspections during the month 106
21
4.5. H & S STATISTICS REPORT. (25TH FEBRUARY –25TH MARCH 2016)
Sl # Description Till last month
This Month
Total
Total Man hours worked 2995961 128304 31242651 Incidents 12 1 132 No. of Lost time incident (LTI ) 1 0 13 Medical Treatment cases 2 0 24 First Aid cases 197 5 2025 Sickness spells 3 0 37 Restricted work duty cases 0 0 08 Fatal accidents 0 0 09 Near-miss 20 2 22
10 Fire Incidents. 0 0 011 Road Traffic Accidents (RTA) 5 0 512 Property Damage
(Other than Fire incidents)4 0 4
13 Subcontractor accidents 0 0 014 Environmental incidents 0 0 015 Dangerous occurrences 1 0 116 Statistics17 LTI Frequency Rate 0.0350 0 0.032018 LTI Severity Rate 1.158 0 1.05619 Man hours worked without LTI 1989854 128304 2118158
4.6. SAFETY TRAININGS
Sl # Description Till last month
This Month
Total
1 No. of employees attended safety induction
1625 12 1637
1 No. of safety Internal trainings conducted
65 3 68
2 No. of external trainings attended by CGC Jv Sacyr employees.
22 3 25
3 Emergency mock drill 10 1 114 No. of tool box meetings 223 4 2275 No. HSE Meetings conducted 28 1 29
22
4.7. SAFETY VIOLATIONS:
Description Till last month This Month Total1 Warning given 58 3 61
Penalties issue 0 0 0
4.8. COMPLIANCE WITH LABOR LAW
Company is complying with all the relevant requirements. A copy of legal requirements is readily available at the CGC-Sacyr JV site office.
Qatar Labor Law Qatar Construction Specification 2010 Ministry of Environment Act, Qatar
The company will continue to ensure compliance with legal and other requirements and update them referring government orders and websites.
Prepared By Reviewed By Approved ByMr.Faizal Butt Eng.Loveson Glariyans Eng. Ruben Estraviz
23
5. CHAPTER 5 ENGINEERING
5.0. ACTIVITIES PERFORMED
Re Submitting Production shop drawing Road works due to gate relocation
Submitting production shop drawing of Electrical Ducts Re Submitting production shop drawing of Gullies due to
additional parking maximization. Re Submitting production shop drawing of Street Lighting Ducts
due to additional parking maximization QAF & Ooredoo due to additional parking maximization
5.1. ACTIVITIES TO PERFORM NEXT MONTH
Submitting FCR for utilities clashes at site Some gate location as per site (FCR) Starting AS build drawings
5.2. HOT POINTS
Road work as per additional parking
FCR for Storm water and Gully
FCR for house connections
Soft landscaping, Irrigation drawing are on hold due to issue CB drawings
Hard landscaping drawings are an hold due to issue CB drawings
5.3. BLOCKING POINTS
NIL
24
6. CHAPTER 6 MATERIAL
6.0. ACTIVITIES PEFORMED
Material submittal ( 0 No’s) Material delivery(Sub Base Class-C & B, Aggregate 10mm & 20mm,
Kerbstone, Granite Affect Paving Blocks, 60 & 80mm Red Paving Blocks, Hydro Brake-Flow Control, Hydrodynamic Separators)
Material ordered (Sub Base Class-B Material, Sub base Class-C Material )
Material testing (Sub Base Class-C & B Suitability Tests, In-situ Density testing for Backfill, Subgrade & Sub base , Cube Compressive Strength & Durability, Selected Fill Suitability Testing , Interlock Tiles Crushing Strength & Water Absorption, Asphalt Marshall , Extraction & Compaction)
6.1. ACTIVITIES TO PERFORM NEXT MONTH
Material submittal ( 2 Nos ) Material delivery (Sub Base Class-C, Sub Base Class-B, Short
Blasted Granite Effect Paving Block, Aggregate 20mm & 10mm, Kerbstones, 60mm & 80mm Red Interlock Tiles, Traffic Signs).
Material testing (Sub Base Class-C & B Suitability Tests, In-situ Density testing for Backfill, Subgrade & Sub base , Cube Compressive Strength & Durability, Aggregate Pipe Bedding & Surround, Selected Fill Suitability Testing , Interlock Tiles Crushing Strength & Water Absorption, Asphalt Marshall, Extraction & Compaction)
6.2. HOT POINTS
NIL
6.3. BLOCKING POINTS
NIL
25
7. CHAPTER 7: CONSTRUCTION
7.0. ACTIVITIES PERFORMED
MANHOLES WORKS
1. Blinding/Waterproofing Membrane/protective screed2. Concrete casting (Fix Forms, Rebar’s & Water stop) - Manhole Base3. Concrete casting (Fix Forms, Rebar’s & Water stop) - Wall (1st. Lift)
HOUSE CONNECTION WORKS :RD86, RD27, RD37 ;RD107
GULLIES CONNECTION WORKS :RD37; RD29; RD32, RD30, RD24; RD27; RD30; RD25; RD58; RD86
DUCTS WORKS RD37; RD29; RD32, RD24; RD27; RD30; RD25, RD28; RD86RD104; RD105; RD106; RD118, RD119, RD113; RD58
SUBGRADE WORKSRD37; RD58; RD26; RD86; RD31; RD32; RD25RD29; RD35; RD28; RD25; RD24; RD30
SUBBASE FOR ROAD : RD37; RD58; RD26; RD29; RD35; RD28; RD30
ASPHALT FOR ROAD BASE :
RD64, RD63, RD37, RD29; RD35, RD58
PARKING TILES WORKS (ON HOLD )
EDGE KERBSTONE WORKS (ON HOLD)
STREET LIGTHING WORKS
KERBSTONE.WORKS
FOOTWAY TILES (ON HOLD)
SHAFT WORKS
MANHOLES CLEANING
ATTENUATION TANKS WORKS 47 : WATERPROOFING
ATTENUATION TANKS WORKS 4 : LEAKAGE TEST
26
ATTENUATION TANKS WORKS 63 : CLEANNING
ATTENUATION TANKS WORKS 39 : WATERPROOFING
BALANCING TANKS WORKS
ATTENUATION TANKS WORKS ACCESSORIES
7.1. HOT POINTS
NIL
7.2. BLOCKING POINTS
27
7.3. ACTIVITIES TO PERFORM NEXT MONTH
MANHOLES WORKS
4. Blinding/Waterproofing Membrane/protective screed5. Concrete casting (Fix Forms, Rebar’s & Water stop) - Manhole Base6. Concrete casting (Fix Forms, Rebar’s & Water stop) - Wall (1st. Lift)
HOUSE CONNECTION WORKS :RD86, RD27, RD37
GULLIES CONNECTION WORKS :RD37; RD29; RD32, RD33, RD24; RD27; RD30; RD25;RD26
SUBBASE FOR ROAD : RD37; RD58; RD26RD29; RD27; RD 61; RD35; RD28; RD25; RD24; RD30,RD107
ASPHALTFOR ROAD BASE :
RD62; RD61; RD60, RD64, RD63, RD37, RD26, RD104, RD105, RD107RD29; RD27; RD 61; RD35; RD28; RD25; RD24; RD30,RD110,RD58
PARKING TILES WORKS
EDGE KERBSTONE WORKS (ON HOLD)
STREET LIGTHING WORKS
KERBSTONE.WORKS
FOOTWAY TILES (ON HOLD)
SHAFT WORKS
ATTENUATION TANKS WORKS 63 : LEAKAGE TEST
ATTENUATION TANKS WORKS 4 : LEAKAGE TEST
ATTENUATION TANKS WORKS 39 : LEAKAGE TEST
ATTENUATION TANKS WORKS ACCESSORIES
7.4. HOT POINTS
NIL
7.5. BLOCKING POINTS
NIL
28
7.6. AREA OF CONCERN
29
7.7. PROGRESS
Progress %
GROUPS
Previous month Current month Total Completed
Act*. %
Act. % P.l. % Act*.
%Act. %
P.l. %
Act*. %
Act. % P.l. % Delay
(**)
GROUP 01 54.61%
55.48%
63.66%
7.72%
6.42%
12.53%
62.33%
61.90%
76.19%
14.29%
GROUP 02 47.70%
48.17%
60.87%
5.58%
4.66%
10.69%
53.28%
52.83%
71.56%
18.73%
GROUP 03 56.50%
59.04%
64.05%
5.05%
3.88%
5.24%
61.55%
62.92%
69.29% 6.37%
GROUP 04 37.63%
36.85%
43.86%
1.65%
1.92%
8.52%
39.28%
38.77%
52.38%
13.61%
GROUP 05 43.88%
47.28%
55.70%
0.00%
4.72%
12.55%
43.88%
52.00%
68.25%
16.25%
GROUP 06 49.29%
50.72%
58.53%
6.01%
3.13%
7.42%
55.30%
53.85%
65.95%
12.10%
GROUP 07 90.17%
90.26%
91.60%
0.00%
0.00%
2.30%
90.17%
90.26%
93.90% 3.64%
Overall 67.05%
68.20%
72.35%
5.08%
3.69%
7.94%
72.13%
71.89%
80.29% 8.40%
(*) the symbol indicates the progress based on the baseline programme
30
7.8. QUANTITIES PROGRESS
Previous Month
Current Month
Completed total
January Trade Act Pl Act Pl Act PlStorm water Excavatio
n95.85% 100.00
%0.53% 0.00
%96.38%
100.00%
Pipe laying
95.24% 100.00%
1.23% 0.00%
96.47%
100.00%
Backfilling
93.02% 100.00%
0.18% 0.00%
93.20%
100.00%
Foul Sewer Excavation
99.68% 100.00%
0.08% 0.00%
99.76%
100.00%
Pipe laying
99.40% 100.00%
0.00% 0.00%
99.40%
100.00%
Backfilling
99.41% 100.00%
0.00% 0.00%
99.41%
100.00%
TSE Excavation
87.21% 100.00%
2.69% 0.00%
89.90%
100.00%
Pipe laying
70.59% 100.00%
5.84% 0.00%
76.43%
100.00%
Backfilling
68.97% 100.00%
5.95% 0.00%
74.92%
100.00%
House connections
Excavation
88.38% 100.00%
0.39% 0.00%
88.77%
100.00%
Gullies Excavation
67.94% 100.00%
3.09% 0.00%
71.03%
100.00%
Manholes Storm water
Walls 94.90% 100.00%
0.55% 0.00%
95.45%
100.00%
Manholes Foul sewer
Walls 94.94% 100.00%
0.00% 0.00%
94.94%
100.00%
Chamber Walls 52.56% 100.00%
9.03% 0.00%
61.59%
100.00%
QAf Duct Laying 49.06% 100.00%
5.66% 0.00%
54.72%
100.00%
Electrical Duct Pipelaying
Laying 50.75% 100.00%
1.68% 0.00%
52.43%
100.00%
Subgrade 79.60% 100.00%
1.02% 0.00%
80.62%
100.00%
Kerbs - LayingKerbs
Laying 50.08% 100.00%
4.34% 0.00%
54.42%
100.00%
Subbase 45.82% 100.00%
11.10%
0.00%
56.92%
100.00%
HardscapingInstalling Edgine kerbs
Laying 20.28% 100.00%
1.75% 0.00%
22.03%
100.00%
Paving - Laying 200x100x80mm Precast Concrete
Laying 21.64% 100.00%
2.33% 0.00%
23.97%
100.00%
31
Block PaversLaying of Precast Concrete Blocks@ Verges
Laying 9.85% 100.00%
8.77% 0.00%
18.62%
100.00%
Road Base - Apply Prime Coat & Asphalt
45.35% 100.00%
1.91% 0.00%
47.26%
100.00%
Wearing Course - Apply Tact Coat & Asphalt
0.00% 100.00%
0.00% 0.00%
0.00% 100.00%
Roads Marking - 100.00%
- 0.00%
- 100.00%
Road Signs - 100.00%
- 0.00%
- 100.00%
32
7.9. PROGRESS S CURVE
See Appendix A
33
7.10. DIRECT MANPOWER DISTRIBUTION
34
7.11. MANPOWER HISTOGRAM
35
7.12. EQUIPMENT DISTRIBUTION
36
7.13. EQUIPMENT HISTOGRAM
37
8. CHAPTER 8 QUALITY
8.0. ACTIVITY PERFORMED
1. Inspection Request for the following activities for Foul Sewer, Storm water & House connection, attenuation tanks concrete, Balancing Tank, TSE & Roadwork.
2. Inspection Request for the following activities for Foul Sewer, Storm water & House connection, attenuation tanks concrete, Balancing Tank, TSE & Roadwork.
1. Trench Excavation2. Formation level3. Installation of Geotextile4. Gravel bedding5. VC pipe laying6. Air Test7. Gravel surround pipe8. Back filling works for trenches9. Compaction Test (FDT)10. Manholes Excavation for house connection11. Blinding Concrete 12. Bitumen Primer13. Tanking Membrane14. Protection Board 15. Formworks and Reinforcement16. Concrete of base slab & Wall Manhole17. Backfilling works for manholes18. Installation of manhole cover19. Rocker Pipes Connection20. Backdrop Pipe Installation21. House Connection Pipeline22. Roadwork (Sub-grade, Formation, Sub-base)23. Kerbstone foundation24. Installation of Kerbstone
Micro-Tunneling shaft concrete blinding Micro-Tunneling shaft formworks & reinforcement installation Micro-Tunneling shaft Concrete Manhole Manholes base and wall concrete with cover slab (Group 1,2,3,4,5 & 6) TSE Pipeline (Road D-20, 21, 22, 23, 24, 27, 28, 29, 31, 32, 37, 40, 51,55, 56, 58, 60,
62, ,63, ,64, 65, 86, 103, 113, 114)1. Excavation/Formation Level2. Geotextile Installation3. Gravel Bedding4. Pipe Laying5. Granular surround 6. Pressure testing of pipeline7. Backfill visual checking8. Compaction (FDT)
TSE Chamber (Road D-20, 21, 22, 23, 24, 27, 28, 29, 31, 32, 37, 40, 51, 56, 58, 60, 62, ,63, 64, 65, 86, 103, 113, 114)
1. Excavation38
2. Blinding Concrete3. Water proofing4. Concrete screed5. Base slab6. Concrete wall7. Cover slab8. Protection board Cover Slab)9. Compaction test (FDT)
Gully Pot & Pipe connection (Group 1, 2, 3, 4 & 5)1. Excavation2. Precast gully pot installation3. Precast manhole cover slab installation4. Backfilling
Street Lighting (D-45, 50, D-49, D-48, D-51, D-53, D-56, D-54, D-57, 108, 109, 111,103, 115, 107, 114, 116, 119, )
1. Excavation2. Bedding, Cable laying, Dune sand surround3. Precast Foundation Installation4. Electrical pole installation
Asphalting Works (Sub-grade, Sub-base & Base coarse) D-20, 21, 22, 39, 40, 41, 45, 46, 47, 48, 49, 50, 51, 53, 54, 56, 57, 103, 105, 106, 107, 108, 109, 111, 112, 113, 114, 115, 116, 118, 119
Cube Crushing at QIL Lab. Installation of Precast Manholes Concrete Cover Balancing Tank
Dewatering House Keeping
Attenuation Tank (Activities) AT - 23/000
Grout filling for tie rod hole Application for joint sealant for construction joint Water filling
AT – 4/000 Grout filling for tie rod hole Application of joint sealant for construction joint Water filling
AT – 75/000 Water tightness test
AT – 63/000 Water filling
AT – 39/000 Water filling
AT – 47/000 Water tightness test
8.1. ACTIVITY TO PERFORM NEXT MONTH
Method Statement:
39
1. ITP & Checklist for Traffic Signs2. ITP & Checklist for Micro tunnelling Joint filling
Inspection for the following activities for Group 1, 2,3,4, 5 and Group 61. Trench Excavation 2. Formation level3. Installation of Geotextile4. Gravel bedding5. VC pipe laying6. Air test7. Gravel surround pipe8. Backfilling works for trenches9. Compaction Test (FDT)10. Manholes Construction Excavation11. Blinding Concrete 12. Waterproofing 13. Protection Board14. Reinforcement15. Formwork16. Concrete17. Rocker Pipes18. Backdrop pipes Installation19. Primer Coat 20. Backfilling works for manholes21. House Connection Pipeline22. Roadwork (Sub-grade, Sub-base)23. Concrete paving block works24. Kerbstone Installation
Concrete blinding of manhole for Group 1, 2, 3, 4, 5 & 6 Concrete of manhole base & walls for Group 1, 2, 3, 4, 5 & 6 Backfilling of Trench FDT and Test result Rocker Pipe Prime coat Water proofing TSE Pipeline and Chamber Works (Group 1, 2, 3, 4, 5 & 6) Gully pot & Pipe connection (Group 1, 2, 3, 4, & 5) Precast Concrete Cover Slab for Manhole Street Lighting Activities (Group 1, 2, 3, 4, & 5)
1. Excavation2. Bedding, Cable Laying, Dune sand surround3. Precast Foundation Installation4. Electrical pole installation
Sub-grade & Sub-base preparation (Group 1, 2, 3, 4, 5 & 6) Asphalting work (Base Coarse) Group 1, 2, 3, 4, 5, & 6 Cube Crushing at QIL Lab. Micro-tunneling Shaft
Concrete Blinding Water Proofing membrane installation Concrete Manhole
Balancing Tank Application of bitumen primer
40
Installation of Tanking membrane and protection board Backfilling
Attenuation Tank (Activities) AT - 23/000
Water tightness Test Application of bitumen primer Installation of tanking membrane and protection board backfilling
AT – 4/000 Water tightness Test Application of bitumen primer Installation of tanking membrane and protection board backfilling
AT – 75/000 Application of bitumen primer Installation of tanking membrane and protection board backfilling
AT – 63/000 Water tightness Test Application of bitumen primer Installation of tanking membrane and protection board backfilling
AT – 39/000 Water tightness Test Application of bitumen primer Installation of tanking membrane and protection board backfilling
AT – 47/000 Application of bitumen primer Installation of tanking membrane and protection board Backfilling
8.2. HOT POINTS
NIL
8.3. BLOCKING POINTS
NIL
41
42
9. CHAPTER 9: LOG & REGISTERS
43
9.0. SUBMITTAL STATUS SUMMARY
44
9.1. REQUEST FOR INSPECTION (RFI)
45
9.2. MATERIAL SUBMITTAL REGISTER
46
9.3. METHOD STATEMENT REGISTER
47
9.4. CORRESPONDENCES REGISTER
48
9.5. SHOP DRAWINGS REGISTER
49
9.6. NCR REGISTER
50
9.7. RO (ROAD OPENING) STATUS
51
10. APPENDIX A
52
10.0. EXECUTION PROGRAMME UPDATE
53
10.1. THREE MONTHS ROLLING PROGRAMME
54
10.2. PROGRESS DETAILS STATUS
55
10.3. PROGRESS DRAWING UP TO 01/25/2016
56
10.4. PROGRESS S-CURVE
57
10.5. EXPECTED CASH FLOW
58
11. APPENDIX B
59
11.0. PHOTOGRAPHIC RECORDS FROM
25TH DECEMBER– 25THJANUARY PERIOD
60