mrpjit

Upload: terminatrix

Post on 13-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 mrpjit

    1/72

    1

    Chapter 13

    MRP and ERP

  • 7/24/2019 mrpjit

    2/72

    2

    Material requirements planning (MRP):Computer-based information system (i.e. glorified database)for ordering and scheduling of dependentdemandinentories

    !t is a production planning process that starts from thedemand for finished products and plans the production

    step by step of subassemblies and parts.

    MRP

  • 7/24/2019 mrpjit

    3/72

    3

    !ndependent and "ependent "emand

    Independent Demand

    A

    B(4) C(2)

    D(2) E(1) D(3) F(2)

    Dependent Demand

    Independent demand is uncertain.De endent demand is certain.

    Independent demand# "emand for final products.Dependent demand:"emand fort items that are subassemblies or

    component parts to be used in production of finished goods.

  • 7/24/2019 mrpjit

    4/72

    4

    $he boo% claims that &the independent demand is continuous 'hile thedependent demand is lumpy. ! do notbeliee in this statement.

    !s "ependant "emand lumpier

    Time Time

    Time Time

    Indep.

    De

    mand

    Dep.

    Demand

    Stable demandLumpy demand

    Amountonha

    nd

    Amountonha

    nd

    Safety stock

  • 7/24/2019 mrpjit

    5/72

    5

    $he dependent demand is not necessarily anylumpier than the independent demand

    * E+ample# ,ay shoe demand rate is pairs per 'ee% at aretailer. $he demand rate for shoe sole is for left and for the right pair. $he demand rate for shoe laces is 1/per 'ee%.

    * E+ample continued# 0hat is the demand rate for the shoelace supplier ,till 1/ per 'ee%. ut if the orders for the

    laces are placed once a 'ee%2 lace demand is lumpy.

    Order once in a week Order twice Order 4 times

    Lumpy dependent

    demand

    Smooth dependent

    demand

  • 7/24/2019 mrpjit

    6/72

    6

    MR Inputs MR rocessin! MR "utputs

    Master

    schedule

    #ill of

    materials

    In$entory

    records

    MR computer

    pro!rams

    %han!es

    "rder releases

    lanned&order

    schedules

    '(ception reports

    lannin! reports

    erformance&

    control

    reports

    In$entory

    transaction

    rimary

    reports

    Secondary

    reports

  • 7/24/2019 mrpjit

    7/727

    * Master Production ,chedule# MP, $ime-phased plan specifying timing and 4uantity of production for

    each end item.

    MP, comes from sales and mar%eting

    MP, coers about 1-3 months into the future* Must coer cumulatie lead time

    Cumulative lead time# $he sum of the lead times thatse4uential phases of a process re4uire2 from ordering of

    parts or ra' materials to completion of final assembly. 5rom 6o' until Cumulatie lead time plans are generallyfro7en

    * ,ometimes MP, is capacity filtered8 MP, is curtailed afterta%ing the aailable capacity into account.

    MRP !nputs# 1. MP,

  • 7/24/2019 mrpjit

    8/728

    MRP inputs# 9. :M

    Bill of materials (BOM)#; listing of all of thera' materials2 parts2 subassemblies2 andassemblies needed to produce one unit of aproduct.

    Product structure tree#

  • 7/24/2019 mrpjit

    9/729

    Product ,tructure $ree

    %hair

    Seat

    Le!s )*+%ross

    #ar),+

    Side

    Rails ),+

    %ross

    bar

    #ack

    Supports )-+

    Le!Assembly

    #ackAssembly

    Le$el

    /

    ,

  • 7/24/2019 mrpjit

    10/7210

    E+plosion E+ample

    * =o' many leg assemblies are needed for 1chair

    * =o' many Cross bars are needed for > chairs

    * Computing ho' many parts are re4uired per afinal product is called :M e+plosion.

    * MRP ans'ers these 4uestions by ta%ingproduction lead times into account# 6ot only it

    tells ho' many2 but also 'hen.

  • 7/24/2019 mrpjit

    11/7211

    How many more of each component is needed to make 15 Xs ifthere are 5 of each already in stock?

    0

    1),+'),+'D)-+

    %#),+

    ill of Materials E+ample 1

    ')*

    +02/3 #2/43 %243 D2*3 '2 /53 124

  • 7/24/2019 mrpjit

    12/7212

    How many more of each component is needed to make 15 Xs ifthere are 8 of each already in stock?

    0

    1),+'),+'D)-+

    %#),+

    ill of Materials E+ample 9

    ')*

    +0263 #273 %23 D2/3 '2 -53 12

  • 7/24/2019 mrpjit

    13/7213

    Lead Times

    / , - * 4 7 6 5 8 /

    rocurement

    1abrication

    Subassembly

    Assembly

  • 7/24/2019 mrpjit

    14/7214

    ;ssembly $ime Chart

    / , - * 4 7 6 5 8 / //

    rocurement of

    ra9 material D

    rocurement of

    ra9 material 1rocurement of

    part %

    rocurement of

    part :

    rocurement ofra9 material I

    1abricationof part ;

    1abrication

    of part '

    Subassembly A

    Subassembly #

    1inal assembly

    and inspection

    ays

  • 7/24/2019 mrpjit

    15/7215

    MRP input# 3. !nentory leels

    * eginning inentory on hand

    * ,cheduled receipts

    Pipeline inentory not receied yet but it is in theprocess of coming to the inentory. 0e %no''hen this 'ill be aailable for use.

  • 7/24/2019 mrpjit

    16/7216

    MPR Processing

    * ?ross re4uirements

    $otal e+pected demand

    * ,cheduled receipts

    :pen orders scheduled to arrie

    * Planned on hand E+pected inentory on hand at the beginning of each time period

    * 6et re4uirements

    ;ctual amount needed in each time period

    * Planned-order receipts @uantity e+pected to receied at the beginning of the period

    :ffset by lead time

    * Planned-order releases

    Planned amount to order in each time period

  • 7/24/2019 mrpjit

    17/7217

    MRP Processing

    * ?ross re4uirements# (5orecasted)"emand period by period

    * 6et re4uirements(t)

    A?ross re4uirements(t)-ProBected inentory(t-1)

    -,cheduled receipt(t)

    * !f 6et re4uirement(t)

    set Planned order receipts(t)A6et re4uirement(t)

    * Planned-order receipts is the production planned

    * ProBected inentory(t)

    AProBected inentory(t-1)D,cheduled receipt(t)

    DPlanned order receipts(t)-?ross re4uirements(t)

    * Planned order release(t-$)APlanned-order receipts(t)

  • 7/24/2019 mrpjit

    18/7218

    MRP e+ample 'ith $A9 and 1 leel

    Periods 1 9 3

    ?ross re4uirements / 11 F

    ,cheduled receipts 9 3 ProBected on hand 1 /

    6et re4uirements 9 F

    Planned order receipts 9 F

    Planned order releases 9 F

    !nputs

    Outputs

  • 7/24/2019 mrpjit

    19/72

    19

    5igure 13-

  • 7/24/2019 mrpjit

    20/72

    20

    :ther Considerations

    * ,afety ,toc% 6ot much for items 'ith dependent demand

    * ot si7ing

    ot-for-lot ordering

    Economic order 4uantity

    5i+ed-period ordering

    Part-period model

  • 7/24/2019 mrpjit

    21/72

    21

    MRP e+ample 'ith ot si7eA>2 $A9 and 1 leel

    Periods 1 9 3

    ?ross re4uirements / 11 G

    ,cheduled receipts 9 3 ProBected on hand 1 / 3 H

    6et re4uirements > 1

    Planned order receipts > 1

    Planned order releases > 1

    !nputs

    Outputs

  • 7/24/2019 mrpjit

    22/72

    22

    5igure 13-G

  • 7/24/2019 mrpjit

    23/72

    23

    MRP updates

    * Regeneratie MRP

    "o the planning from scratch

    $ime bet'een regenerations is long

    :% for stable enironments

    * 6et Change MRP

    Ipdate the plan according to changes

  • 7/24/2019 mrpjit

    24/72

    24

    MRP :utputs

    * Planned orders - schedule indicating the amount and timingof future orders.

    * :rder releases - ;uthori7ation for the e+ecution of plannedorders.

    * Changes - reisions of due dates or order 4uantities2 orcancellations of orders.

    * Performance-control reports

    * Planning reports* E+ception reports

  • 7/24/2019 mrpjit

    25/72

    25

    Capacity Planning

    Capacity requirements planning# $he processof determining short-range capacity re4uirements.

    oad reports# "epartment or 'or% center reportsthat compare %no'n and e+pected future capacityre4uirements 'ith proBected capacity aailability.

    !ime fences#,eries of time interals during 'hichorder changes are allo'ed or restricted.

  • 7/24/2019 mrpjit

    26/72

    26

    MRP Planning

    De$elop a tentati$e

    master production

    schedule

    De$elop a tentati$emaster production

    schedule

  • 7/24/2019 mrpjit

    27/72

    27

    * 5ood catering serice

    End items are the catered food

    "ependent demands are ingredients foreach recipe2 i.e. bill of materials

    * $aco ell menu items

    * =otel renoation

    ;ctiities and materials &e+ploded intocomponent parts

    MRP in ,erices

  • 7/24/2019 mrpjit

    28/72

    28

    enefits of MRP

    * o' leels of in-process inentories

    * ;bility to trac% material re4uirements

    * ;bility to ealuate capacity re4uirements

    * Means of allocating production time

    Eentually it is a database 'ith limited decisionma%ing capability

  • 7/24/2019 mrpjit

    29/72

    29

    Re4uirements of MRP

    * Computer and necessary soft'are

    * ;ccurate and up-to-date inputs#

    Master schedules

    ills of materials

    !nentory records

    * !ntegrity of data

  • 7/24/2019 mrpjit

    30/72

    30

    * E+panded MRP 'ith and emphasisplaced on integration

    5inancial planning Mar%eting

    Engineering

    Purchasing

    Manufacturing

    MRP !!

  • 7/24/2019 mrpjit

    31/72

    31

    Market

    Demand

    roductionplan

    roblems>

    Rou!h&cut

    capacity plannin!

    ?es @o ?es@o

    1inance

    Marketin!

    Manufacturin!

    Adustproduction plan

    Master

    production schedule

    MR

    %apacity

    plannin!

    roblems>Re=uirements

    schedules

    Ad

    ustmasterschedule

    MRP !!

  • 7/24/2019 mrpjit

    32/72

    32

    * "nterprise resource planning ("RP):;n e(pandedeffort to integrate standardi7ed record

    %eeping that 'ill permit information sharing throughout

    the organi7ation* ,trategic considerations

    =igh initial cost

    =igh cost to maintain

    5uture upgrades $raining

    * ,ee ERP courses in the course catalog

    ERP

  • 7/24/2019 mrpjit

    33/72

    33

    ,ummary

    * MRP# "ependent s !ndependent demand

    !nputs (:M)2

    Processing2 :utputs

    enefits and re4uirements

    * Capacity planning

    * MRP-!! and ERP

  • 7/24/2019 mrpjit

    34/72

    34

    Practice @uestions

    1. $he master production schedule states 'hich end itemsare to be produced both 'hen and ho' many.

    ;ns'er# $rue Page# >FF

    9.oad reports sho' capacity re4uirements for departmentsor 'or% centers 'hich may be more or less than thecapacity aailable in that 'or% center.

    ;ns'er# $rue Page# >G3

    3.MRP !! permits the simultaneous planning of production2

    mar%eting2 and financial resources to support a productionplan.

    ;ns'er# $rue Page# >G9

  • 7/24/2019 mrpjit

    35/72

    35

    Practice @uestions

    * 1. $he output of MRP is#* ;) gross re4uirements

    * ) net re4uirements

    * C) a schedule of re4uirements for all partsand end items

    * ") inentory reorder points

    * E) economic order 4uantities and reorder

    points* ;ns'er# C Page# >FF

  • 7/24/2019 mrpjit

    36/72

    36

    Practice @uestions

    9. $he MRP input listing the assemblies2subassemblies2 parts2 and ra' materials neededto produce one unit of finished product is the#

    * ;) master production schedule* ) bill-of-materials

    * C) inentory-records

    * ") assembly-time chart

    * E) net-re4uirements chart

    * ;ns'er# Page# >F

  • 7/24/2019 mrpjit

    37/72

    37

    Practice @uestions

    * 3. 0hich one of the follo'ing most closely describesnet material re4uirements

    * ;) gross re4uirements - amount on-hand -scheduled receipts

    * ) gross re4uirements - planned receipts* C) gross re4uirements - order releases D

    amount on-hand

    * ") gross re4uirements - planned order releases

    * E) gross re4uirements - amount on-hand Dplanned order releases

    * ;ns'er# ; Page# >1

  • 7/24/2019 mrpjit

    38/72

    38

    Practice @uestions

    H.!n MRP2 Jscheduled receiptsJ are#

    * ;) identical to Jplanned-order receiptsJ

    * ) identical to Jplanned-order releasesJ* C) open orders (that is2 ordered before the

    first time buc%et2 but not deliered yet)

    * ") Jnet re4uirementsJ

    * E) aailable to promise inentory

    * ;ns'er# C Page# >9

  • 7/24/2019 mrpjit

    39/72

    39

    Practice @uestions

    >. 0hich is true of a net-change system

    ;) !t is a batch-type system 'hich is updatedperiodically.

    ) !t is usually run at the beginning of each month.C) $he basic production plan is modified to reflect

    changes as they occur.

    ") !t is used to authori7e the e+ecution of planned

    orders.E) !t indicates the amount and timing of future changes.

    * ;ns'er# C Page# >

  • 7/24/2019 mrpjit

    40/72

    40

    Chapter 1H

    Kust-!n-$ime,ystems

  • 7/24/2019 mrpjit

    41/72

    41

    K!$Lean Production

    * #ust$in$time# Repetitie production system in'hich processing and moement of materialsand goods occur Bust as they are needed2

    usually in small batches

    * K!$ is characteristic of lean productionsystems

    * K!$ operates 'ith ery little &fat

  • 7/24/2019 mrpjit

    42/72

    42

    K!$ ?oals

    * Eliminate disruptions

    * Ma%e system fle+ible by reduce

    setup and lead times* Eliminate 'aste2 especially e+cess

    inentory

  • 7/24/2019 mrpjit

    43/72

    43

    ,ources of 0aste

    * :erproduction

    * 0aiting time

    * Innecessary transportation* Processing 'aste

    * !nefficient 'or% methods

    * Product defects

  • 7/24/2019 mrpjit

    44/72

    44

    * ig K!$ broad focus

  • 7/24/2019 mrpjit

    45/72

    45

    K!$ uilding loc%s

    * 1. Product design

    * 9. Process design

    * 3. PersonnelLorgani7ational

    elements* H. Manufacturing

    planning and control

  • 7/24/2019 mrpjit

    46/72

    46

    1. Product "esign

    * ,tandard parts

    * Modular design

    * =ighly capable production systems

  • 7/24/2019 mrpjit

    47/72

    47

    9. Process "esign

    * ,mall lot si7es

    * ,etup time reduction

    * Manufacturing cells

    * imited 'or% in process

    * @uality improement

    * Production fle+ibility* ittle inentory storage

  • 7/24/2019 mrpjit

    48/72

    48

    enefits of ,mall ot ,i7es

    Reduces in$entory

    Less stora!e space

    Less re9ork

    roblems are more apparent

    Increases product fle(ibility

    'asier to balance operations

  • 7/24/2019 mrpjit

    49/72

    49

    Production 5le+ibility

    * Reduce do'ntime by reducingchangeoer time

    * Ise preentie maintenance to

    reduce brea%do'ns

    * Cross-train 'or%ers to help clearbottlenec%s

    * Resere capacity for importantcustomers

  • 7/24/2019 mrpjit

    50/72

    50

    3. PersonnelL:rgani7ational Elements

    * 0or%ers as assets

    * Cross-trained 'or%ers

    * Continuousimproement

    * Cost accounting

    * eadershipLproBectmanagement

  • 7/24/2019 mrpjit

    51/72

    51

    H. Manufacturing Planning and Control

    * eel loading

    * Pull systems

    *

  • 7/24/2019 mrpjit

    52/72

    52

    PullLPush ,ystems

    * Pull system# ,ystem for moing 'or%'here a 'or%station pulls output fromthe preceding station as needed. (e.g.

    anban)

    * Pus% system# ,ystem for moing 'or%'here output is pushed to the ne+tstation as it is completed

  • 7/24/2019 mrpjit

    53/72

    53

    anban Production Control ,ystem

    * &an'an#Card or other deice that communicates demand for'or% or materials from the preceding station

    * anban is the Kapanese 'ord meaning &signal or &isiblerecord

    * Paperless production control system

    * ;uthority to pull2 or produce comesfrom a do'nstream process.

  • 7/24/2019 mrpjit

    54/72

    54

    $raditional ,upplier 6et'or%

    BuyerBuyer

    SupplierSupplierSupplierSupplier SupplierSupplier SuppilerSuppiler

    SupplierSupplier

    SupplierSupplier

    SupplierSupplier

  • 7/24/2019 mrpjit

    55/72

    55

    $iered ,upplier 6et'or%

    SupplierSupplier

    SupplierSupplier

    SupplierSupplier

    SupplierSupplierSupplierSupplier SupplierSupplier

    BuyerBuyer

    SupplierSupplierFirst Tier Supplier

    Second Tier Supplier

    Third Tier Supplier

  • 7/24/2019 mrpjit

    56/72

    56

    ,ummary K!$ ?oals and uilding loc%s

    roduct

    Desi!n

    rocess

    Desi!n

    ersonnel

    'lements

    Manufactur&

    in! lannin!

    'liminate disruptionsMake the system fle(ible

    Reduce setup

    and lead times

    'liminate 9aste

    MinimiBe in$entories

    A

    balanced

    rapid flo9

  • 7/24/2019 mrpjit

    57/72

    57

    Conerting to a K!$ ,ystem

    * ?et top management commitment

    * "ecide 'hich parts need most effort

    * :btain support of 'or%ers

    * ,tart by trying to reduce setup times

    * ?radually conert operations

    * Conert suppliers to K!$

    * Prepare for obstacles

    : C

  • 7/24/2019 mrpjit

    58/72

    58

    :bstacles to Conersion

    * Management may not be committed

    * 0or%ersLmanagement may not becooperatie

    * ,uppliers mayresist

    K!$ i , i

  • 7/24/2019 mrpjit

    59/72

    59

    K!$ in ,erice

    The basic !oal of the demand flo9 technolo!y in the ser$ice or!aniBation is topro$ide optimum response to the customer 9ith the hi!hest =uality ser$ice

    and lo9est possible cost. Eliminate disruptions

    Ma%e system fle+ible

    Reduce setup and lead times

    Eliminate 'aste

    Minimi7e 0!P ,implify the process

    K!$ P h i

  • 7/24/2019 mrpjit

    60/72

    60

    * 6e' challenges

    Meeting manufacturing re4uirements

    Changing from traditional thin%ing and practices

    fre4uent on-time deliery of small 4uantities ong term relationships 'ith suppliers as

    partners

    * =o' about E+change purchasing# ;uctions

    K!$ Purchasing

    K!$ !!

  • 7/24/2019 mrpjit

    61/72

    61

    * K!$ !!# the practice of allo'ing endorsto manage some aspects of buying theirproducts or serices for the buyer

    K!$ !!

    fit f K!$ , t

  • 7/24/2019 mrpjit

    62/72

    62

    enefits of K!$ ,ystems

    * Reduced inentory leels* =igh 4uality

    * 5le+ibility

    * Reduced lead times

    * !ncreased productiity

    fit f K!$ , t ( tNd)

  • 7/24/2019 mrpjit

    63/72

    63

    enefits of K!$ ,ystems (contNd)

    * !ncreased e4uipment utili7ation

    * Reduced scrap and re'or%

    * Reduced space re4uirements

    * Pressure for good endor relationships

    * Reduced need for indirect labor

    El t f K!$

  • 7/24/2019 mrpjit

    64/72

    64

    * ,mooth flo' of 'or% (the ultimate goal)* Elimination of 'aste

    * Continuous improement

    * Eliminating anything that does not addalue

    * ,imple systems that are easy to manage

    * Ise of product layouts to minimi7e moing

    materials and parts* @uality at the source

    Elements of K!$

    El t f K!$ ( tNd)

  • 7/24/2019 mrpjit

    65/72

    65

    * Po%a-yo%e fail safe tools and methods* Preentatie maintenance

    * ?ood house%eeping

    * ,et-up time reduction

    * Cross-trained employees

    * ; pull system

    Elements of K!$ (contNd)

  • 7/24/2019 mrpjit

    66/72

    66

    Case ,tudy based on a trip on 6o 1G2 9

    6IMM!

  • 7/24/2019 mrpjit

    67/72

    67

    =istoryLProducts

    * ate FNs oil crisis* ?M closes 5remont2 C; plant firing / in 1G9

    * $oyota approaches ?M to set up $oyota production systemat a ?M plant2 Inited ;uto 0or%ers accepts the deal

    * ?M and $oyota put together OHM in 1GH. ?M o'ns theinfrastructure2 $oyota is the tenant.

    * 6ummi A 6e' Inited Motor Manufacturing2 !nc is born in1GH as the uni4ue e+ample of a $oyota ?M Boint enture

    * Products# $oyota Corolla2 $acoma $ruc%s2 Pontiac

  • 7/24/2019 mrpjit

    68/72

    68

    0or%ers

    * 6ummi has about H> unioni7ed 'or%ers* 0or%ers are under t'o types#

    Production2 high school graduates

    Maintenance

    * 0or%ers 'or% in teams of H-/

    * 0or%ers in a team rotate the tas%s eery 1-3 hours

    * $eam leader is responsible for the rotation.

    * $eam leader 'ithdra's parts from the inentory (eery 1-9 hours) and proides the tools as necessary

    * 0or%ers ma%e O1F per hour

  • 7/24/2019 mrpjit

    69/72

    69

    Capacity

    * 6ummi has a cycle time of / seconds for Corolla2 1 body

    9 seconds for $acoma2 3 bodies (only cabin isproduced at 6ummi2 the bottom and the bac% are

    bought from suppliers)* 6ummi 'or%s in t'o shifts

    !# /#-1H#32 !!# 1/#3-1#

    Each shift has 1 hour lunchLdinner brea%

    ,tarting the first shift at /# 'or%ers aoid heaymorning traffic

    $'o hours bet'een shifts ! and !! is to allo' foroertime after the first shift 'hen necessary

  • 7/24/2019 mrpjit

    70/72

    70

    0or% 5lo'

    * ,tamping# 5orming metal (side2 bac%2 front) panels 'ith presses* ody 0eld# Putting panels together

    * Paint# Paint inspection is the current bottlenec%

    Primer body paint applied by robots (chemically ha7ardous

    tas%) "oor Bambs painted manually

    * Plastics# Ma%ing bumpers2 inside panels

    * ;ssembly# Putting in tires2 engine2 seats2 bumpers2 harnessing.

    Cars 2 truc%s on 9 %m 2 . %m coneyors* Cars contain uilding manifest A :M A !ngredients list at eery

    step of these operations

  • 7/24/2019 mrpjit

    71/72

    71

    Kust in time

    * ai7en# continuous improement

    * anban# replenishment eery 1-9 hours

    * Kido%a# ;ssure 1Q 4uality. :ther'ise pull the ;ndonchord 1 times per shift

    GQ of line stops are longer than 3 seconds

    ine stops longer than an hour once eery month

    * Muda# 0aste to be eliminated

    * ?enchi ?enbutsu# ?o to the source to learn and to solethe problems

    * $his Kapanese terminology is all oer the boards in theplant

  • 7/24/2019 mrpjit

    72/72

    Creatie $ool L 0or% Place "esign

    * "ie change at the stamping in 3 hours* $ilted storage bins for ease of access

    * Collapsing storage bo+es 'hen empty

    $o reduce the empty bo+ storage re4uirements intruc%s returning to suppliers2 say in !ndiana

    $hese bo+es sae about O1M annually

    $he 'or%er 'ho suggested the bo+es earned seeral

    thousand points. 1 point A O1.* More info '''.nummi.com