MS Project: Resource allocation & levellingS13
L A R A T O O K E Y
![Page 2: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/2.jpg)
Project network times are not a schedule until resources have been assigned.◦ The implicit assumption is that resources will
be available in the required amounts when needed.
◦ A new projects requires making realistic judgments of resource availability and project durations.
![Page 3: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/3.jpg)
Resource PlanningDetermining what resources will be
required (labour, equipment, material)
What quantity for each resource will be required.
When are resources available to perform project activities.
![Page 4: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/4.jpg)
40 hrs
Wee
k 1
Wee
k 2
Wee
k 3
Wee
k 4
Wee
k 5
Wee
k 6
Wee
k 7
Wee
k 8
Resource Histogram
Resource ZZZ
![Page 5: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/5.jpg)
Resource HistogramA bar chart showing the amount of time
assigned to a resource for the time interval.
Resource availability is depicted as a line for comparison purposes.
Resources assigned more work than available hours are considered “over-allocated”.
![Page 6: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/6.jpg)
Resource Conflict & BalancingProject calendar:
◦ defines the workable time periods for the project.
◦ defines the workable time periods for the specific resource.
Conflicts in resource availability and schedule activity dates must be resolved to ensure the project will be completed according to accepted project objectives.
![Page 7: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/7.jpg)
The Resource Problem
![Page 8: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/8.jpg)
TIME
A project that must be completed by an imposed date◦ Time is fixed,
resources are flexible: additional resources are required to ensure project meets schedule.
RESOURCE
A project in which the level of resources available cannot be exceeded◦Resources are fixed,
time is flexible: inadequate resources will delay the project.
![Page 9: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/9.jpg)
TimeProjects that must be completed by an imposed
date
Require the use of leveling techniques that focus on balancing or smoothing resource demands by using positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project
◦ Peak resource demands are reduced.
◦ Fluctuation in resource demand is minimized.
![Page 10: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/10.jpg)
Botanical Garden
FIGURE 8.2
A
B
C
D
E
F
G
![Page 11: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/11.jpg)
Botanical Garden (cont’d)
![Page 12: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/12.jpg)
Resource levelling for TIMEAdvantages
◦ Peak resource demands are reduced.
◦ Fluctuation in resource demand is minimized.
Disadvantages
◦ Loss of flexibility that occurs from reducing slack
◦ Increases the criticality of all activities
![Page 13: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/13.jpg)
ResourceProjects that involve resources that are
limited in quantity or by their availability
![Page 14: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/14.jpg)
Splitting / MultitaskingA scheduling technique use to get a better
project schedule and/or increase resource utilization
◦ Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work
◦ Is feasible when startup and shutdown costs are low
◦ Is considered the major reason why projects fail to meet schedule
![Page 15: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/15.jpg)
Splitting/Multitasking
FIGURE 8.10
![Page 16: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/16.jpg)
Resource LevellingIdentifies under-allocated resources
Different methods for resource leveling
Project Manager analyzes effects on project objectives (time and cost) for resolving resource conflict.
![Page 17: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/17.jpg)
Resource levelling methods
![Page 18: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/18.jpg)
1. Do Nothing if over-allocation is within acceptable limitsSchedule/Time Impact
◦ None
Resource/Cost Impact◦ None
![Page 19: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/19.jpg)
2. Delay non-critical tasks within available floatSchedule/Time Impact
◦ None
Resource/Cost Impact◦ None (except for inflation effects)
![Page 20: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/20.jpg)
3. Extend non-critical task durations within the available float
Schedule/Time Impact◦ None
Resource/Cost Impact◦ None (except for inflation effects)
![Page 21: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/21.jpg)
4. Add / Substitute resource of equal or greater capabilitySchedule/Time Impact
◦ May need to consider learning curve for new resource. (Duration may shorten if resources are added – schedule crashing)
Resource/Cost Impact◦ Cost impact if substitute resource has higher costs
![Page 22: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/22.jpg)
5. Delay Critical Path tasksSchedule/Time Impact
◦ Schedule impact equal to the delay
Resource/Cost Impact◦ Cost impact due to project time extension and
inflation costs
![Page 23: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/23.jpg)
6. Extend Critical Path task durationsSchedule/Time Impact
◦ Schedule impact equal to the delay
Resource/Cost Impact◦ Cost impact due to project time extension and
inflation costs
![Page 24: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/24.jpg)
7. Authorise OvertimeSchedule/Time Impact
◦ Could shorten schedule (schedule crashing)
Resource/Cost Impact◦ Cost impact due to premium cost rates
![Page 25: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/25.jpg)
8. Split the task into non-sequential piecesSchedule/Time Impact
◦ Schedule impact if part of task extends beyond float (soft logic)
Resource/Cost Impact◦ Cost impact due to project time extension and
inflation costs and inefficiencies in splitting task
![Page 26: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/26.jpg)
9. Modify the ScopeSchedule/Time Impact
◦ Could shorten schedule due to less work or quality of work being accomplished.
Resource/Cost Impact◦ Could go either way.
![Page 27: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/27.jpg)
![Page 28: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/28.jpg)
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10
A
C
B
A
C
B
A
C
B
A
C
B
D
C
E
D
E
F
J
G
E
J
F
G
E
J
H
G
H
![Page 29: MS Project: Resource allocation & levelling](https://reader030.vdocuments.net/reader030/viewer/2022012016/615b2cab86c79f65e345ece7/html5/thumbnails/29.jpg)
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10
A
C
B
A
C
B
A
C
B
A
C
B
D
C
E
D
E
F
J
G
E
JF
G
E J
H
G
H