mustapha ffs

Upload: jayaarnav

Post on 04-Jun-2018

232 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Mustapha Ffs

    1/21

    June 2011

    Hannover

    Al l r ights reserved. No part of th is document may be reproduced, stored in a retr ieval system or transmi tted in any

    form or by any means (electronic, mechanical, photocopying, recording or o therwise) without the permission of

    the copyright owner. 1

    RISK & RELIABILITY BASED FITNESS FOR SERVICE (FFS) ASSESSMENT

    FOR SUBSEA PIPELINES

    By

    Ir. Muhd Ashri Mustapha & Dr. Yong BaI.

    6th Pipeline Technology Conference 2011

  • 8/13/2019 Mustapha Ffs

    2/21

    RAHSIA

    1. Introduction

    2. Objective

    3. Methodology and Principle

    4. QRA & Target Reliabil ity

    5. SRA, Retaining Pressure Capacity & FFS

    6. Examples

    7. Conclusion

    Table of Contents

  • 8/13/2019 Mustapha Ffs

    3/21

    RAHSIA

    The risk and reliability based fitness-for-services (FFS) assessment

    addressed in this paper is a quantitative risk assessment (QRA) based

    FFS study on subsea oil or gas pipelines.

    The main purpose of QRA is to determine the target reliabilities for

    different pipeline segments.

    Structure Reliability Assessment (SRA) method is used to calculate the

    maximum safe operating pressure, which indicates the pipeline retaining

    pressure capacity.

    QRA and SRA results will be used to conduct traditional FFS, which

    indicates whether the pipeline is fit for service or not by a comparison of

    pipeline retaining pressure capacity with given MAOP.

    1. Introduction

  • 8/13/2019 Mustapha Ffs

    4/21

    RAHSIA

    To portray pipeline present risk picture and define the target reliability of every

    pipeline segment;

    To determine the pressure containment capacity of the pipeline at the time it waslast inspected;

    To conduct the corrosion assessment to estimate the internal corrosion rates;

    To determine the remaining years for which the pipeline can be safely operated

    dated from the last inspection;

    To recommend suitable actions to be taken based on the assessment findings.

    2. Objectives

  • 8/13/2019 Mustapha Ffs

    5/21

    RAHSIA

    This risk and reliability based FFS study

    process will focus on pipeline corrosion

    defects only.

    First of all, QRA is performed to derive

    the pipeline target reliability.

    Then, using target reliability andstructure reliability analysis (SRA)

    method, the pipeline retaining pressure

    capacity Psafe will be obtained as the

    preparation of FFS.

    Finally, traditional FFS will be

    conducted to indicate whether the

    pipeline is fit for service or not by a

    comparison of pipeline retaining

    pressure capacity with given MAOP.

    3. Methodology and Principle

    Operating data

    Develop defects to

    remaining design life

    Psafe > MAOP?

    Yes

    Inspection data Design data

    QRA

    Corrosion rate Target reliability

    Pipeline

    Segmentation

    Defect assessment one

    by one based on SRA

    method

    No

    Psafe >MAOP?

    Calculate remaining

    design life capacity

    Remaining life to

    current MAOP

    Yes

    No

    Calculate de-rated

    capacity

  • 8/13/2019 Mustapha Ffs

    6/21

    RAHSIA

    This section intends to perform quantitative risk assessment (QRA) to establish

    the pipeline structure target reliability taking into account pipeline safety,

    environmental, and economic consequences.

    The QRA process will bring benefits to the following FFS analysis:

    Pipeline Segmentation - precise pipeline segmentation

    Probability of Failure (Pf)

    Consequences of Failure (Cof)

    Target Reliability - choice of pipeline target reliabilities

    4. QRA & Target Reliability

  • 8/13/2019 Mustapha Ffs

    7/21

    RAHSIA

    The risk evaluator must decide on a strategy for creating these sections in order to

    obtain an accurate risk picture.

    Each pipeline segment will have its own risk as the production of failure probabilityand failure consequence.

    A significant condition change must be determined by the evaluator with

    consideration given to data costs and desired accuracy.

    An example of a short list of prioritized conditions is as follows:

    Pipeline specification (wall thickness, diameter, etc.);

    Soil conditions (pH, moisture, etc.); Population density;

    Coating condition;

    Age of pipeline;

    Environmental sensitivity (Marine Park, Nature Reserve).

    4.1 Pipeline Segmentation

  • 8/13/2019 Mustapha Ffs

    8/21

    RAHSIA

    Pipeline failure usually takes the form of leakage, which is the initiate event

    resulting to serious consequences.

    Probability of Failure (Pf) is estimated as failure frequencies of different types ofdegradation mechanisms operating in the pipeline component.

    The failure frequency is calculated based on different damage causes. The main

    damage causes identified for subsea pipelines are listed below: Internal Corrosion

    External Corrosion

    Erosion

    External Impact

    Free-span

    On-bottom Stability

    The famous UK PARLOC 2001 database is proposed to be used for pipeline

    Pf assessment.

    4.2 Probability of Failure (Pf)

  • 8/13/2019 Mustapha Ffs

    9/21

    RAHSIA

    Consequence of failure can be expressed as number of people affected (injured or

    killed), property damage, amount of a spill, area affected, outage time, mission

    delay, money lost or any other measure of negative impact for the quantification of

    risk.

    It is usually divided into three categories of Safety, Economic and Environmental

    consequence to be analyzed respectively by qualitatively or quantitatively way.

    The consequence analysis is an extensive effort covering a series of steps

    including: Accident scenario analysis of possible event sequences (Event Tree Analysis for instance)

    Analysis of accidental loads, related to fire, explosion, impact

    Analysis of the response of systems and equipment to accidental loads

    Analysis of final consequences to personnel, environment, and assets

    Each of these steps may include extensive studies and modeling.

    4.3 Consequences of Failure (CoF)

  • 8/13/2019 Mustapha Ffs

    10/21

    RAHSIA

    To ensure certain safety levels of pipeline or pipeline segments, target reliability

    need to be settled and has to be met at pipeline design phase.

    Theoretically, a Life Cycle Cost-Benefit assessment should be a preferred methodfor determining the optimum target reliability.

    4.4 Target Reliability

    Reliability

    Cost

    Optimum Reliability

    Failure Cost

    Initial Investment and

    Maintenance Cost

    Total Cost

  • 8/13/2019 Mustapha Ffs

    11/21

    RAHSIA

    The selection of target reliability is based on consequences of failure, location and

    contents of pipelines, relevant rules, access to inspection and repair, etc.

    When conducting reliability based FFS analysis, target reliability levels in a givenreference time period and reference length of pipeline should be selected.

    The selection is based on consequence of failure, location and contents of

    pipelines, relevant rules, access to inspection and repair, etc.

    4.4 Target Reliability

    Limit StatesSafety Classes

    Low Normal High

    SLS 10

    -1

    ~10

    -2

    10

    -2

    ~10

    -3

    10

    -3

    ~10

    -4

    ULS 10-2~10-3 10-3~10-4 10-4~10-5

    FLS 10-2~10-3 10-3~10-4 10-4~10-5

    ALS 10-3~10-4 10-4~10-5 10-5~10-6

    Target reliabilities vs. Safety classes

  • 8/13/2019 Mustapha Ffs

    12/21

    RAHSIA

    The capacity of each defect will be assessed based on a structure reliability

    assessment (SRA) method and the target reliability above.

    The target reliability will be used according to the maximum allowable failure rateto deduce the maximum value of pipeline safe operating pressure Psafe, which will

    indicates the pipeline retaining pressure capacity (service limit state).

    The maximum value of pipeline safe operating pressure Psafe is not allowed to beless than the given MAOP.

    The safety index (API 2A-LRFD) is the most popular measure of reliability in

    industry. The safety index is related to the corresponding failure rate by formula:

    Where,(.) is the standard normal distribution function.

    5. SRA, FFS & Retaining Pressure

    Capacity

    ( ) ( ) == 1fP

  • 8/13/2019 Mustapha Ffs

    13/21

    RAHSIA

    A structure reliability assessment (SRA)

    method is used to calculate the pipeline

    failure rate and the reliability R= 1-Pf.

    An SRA model for the pipeline failure

    rate calculation is presented here fordamage from corrosion.

    The main steps of SRA method has

    been illustrated in the left figure.

    5.1 SRA Method

  • 8/13/2019 Mustapha Ffs

    14/21

    RAHSIA

    The target reliability is a structural safety requirement, which means the pipeline

    failure probability Pfis not allowed to be greater than it.

    If assign target reliability to failure rate Pf and deduce the value of pipeline safeoperating pressurePsafe by using the SRA method, this maximum value ofPsafe will

    indicates the pipeline retaining pressure capacity (service limit state).

    If this maximum safe operating pressure Psafe is identified to be less than MAOP,the defect is unacceptable and the pipeline is declared to be unfit for service.

    Using the SRA method described before, the pipeline maximum safe operating

    pressure (Psafe) equals to the mean load (Sm) divided by its bias:

    5.2 FFS & Retaining Pressure Capacity

    Smmsafe BSP /=

  • 8/13/2019 Mustapha Ffs

    15/21

    RAHSIA

    Flow-chart of Pressure Capacity Assessment can be expressed as follow:

    5.2 FFS & Retaining Pressure Capacity

  • 8/13/2019 Mustapha Ffs

    16/21

    RAHSIA

    Corrosion Rate:

    The corrosion caused by the incidences of CO2 represents the greatest risk to the integrity of carbon

    steel equipment in a production environment and is more common than damage related to fatigue,erosion, or stress corrosion cracking.

    De Waards models for corrosion rate have been programmed in-house software

    subsea pipeline integrity management software: PaRIS.

    The purpose of corrosion rate calculation is to predict corrosion defects

    development.

    According to the corrosion rate value (CR) and the retaining pressure capacity(Psafe), the pipeline remaining life can also be obtained.

    5.2 FFS & Retaining Pressure Capacity

  • 8/13/2019 Mustapha Ffs

    17/21

    RAHSIA

    One subsea oil export pipeline is installed at the year 1982, with design life of 20

    years. The table below is the general data of the pipeline with inspection results of

    corrosion defect at the 2003 incorporated:

    6. Examples

    Parameter Symbol [Unit] Value

    Outer diameter D[mm] 273.05

    Wall thickness t[mm] 8.5

    Standard deviation t[mm] 0.5

    Design factor F 0.72

    SMYS SMYS[MPa] 358.5

    MAOP MAOP[MPa] 9.3

    Operating Pressure Pop[MPa] 3

    Corrosion rate r[mm/year] 0.17

    Standard deviation r[mm/year] 0. 5

    Measured maximum defect depth do/t 0.45

    Standard deviation do 0.05

    Measured maximum defect length Lo[mm] 250

    Standard deviation Lo 5

  • 8/13/2019 Mustapha Ffs

    18/21

    RAHSIA

    To determine the pipeline safety level and target reliability accordingly, a complete

    risk assessment is supposed be performed.

    A sensitivity study at the target reliability has been performed to review thebenefits of using reliability based FFS in comparison to the using of other codes

    like ASME B31G and DNV RP F101.

    The results have been illustrated in the tables and figures bellow.

    6. Examples

  • 8/13/2019 Mustapha Ffs

    19/21

    RAHSIA6. Examples

  • 8/13/2019 Mustapha Ffs

    20/21

    RAHSIA

    The advantage of QRA based determination of target reliability is that the pipeline

    is segmented more scientifically from a risk perspective and every segment has its

    own target reliability.

    This assessment also benefits from making good use of available data and reports

    include: inspection data, monitoring data, pipeline repair and incident records,

    corrosion study report and QRA report (if any) etc.

    7. Conclusion

  • 8/13/2019 Mustapha Ffs

    21/21

    RAHSIA