Earned Value Management (EVM)
Reference Card
EVM Terminology
ACWP Actual Cost of Work Performed (Actual cost incurred for work accomplished during a given period)
AUW Authorized Un-priced Work (Work contractually approved, but not yet negotiated)
BAC Budget At Completion (Total planned value for the project)
BCWS Budgeted Cost for Work Scheduled (Planned Value - budget assigned to the planned scheduled
work to be accomplished)
BCWP Budgeted Cost for Work Performed (Earned Value - budget value for the physical work
accomplished)
CA Control Account (Management control point to plan and control scope, schedule, and budget)
CBB Contract Budget Baseline (Total negotiated cost plus AUW)EAC Estimate At Completion (Expected total cost of the project when the scope of work will be
completed)
ETC Estimate To Complete (Expected cost needed to complete all remaining work)
MR Management Reserve (Budget withheld for unknowns / risk management)
NCC Negotiated Contract Cost (Contract price minus profit or fees or project value for in-house work)
OTB Over Target Baseline (Sum of CBB and recognized overrun)
PBB Project Budget Baseline (Same as CBB for in-house projects)
PMB Performance Measurement Baseline (Time-phased budget plan)
PP Planning Package (Far term effort within a CA not yet defined into WPs)
TAB Total Allocated Budget (Sum of all budgets for work on contract = NCC, CBB/PBB, or OTB)
TCPI To Complete Performance Index (Efficiency needed from status date to achieve an EAC or BAC)
UB Undistributed Budget (Broadly defined effort not distributed into CAs)
WP Work Package (Near term effort detailed planned within a CA)
Revised May 2012
For NASA in-house programs/projects and contract policies and requirements for the
application of EVM, please refer to the NASA EVM Website: http://evm.nasa.gov.
Performance Indices: (Favorable is > 1.0, Unfavorable is < 1.0)Cost Performance Index (Efficiency): CPI = BCWP / ACWPSchedule Performance Index (Efficiency): SPI = BCWP / BCWS
To Complete Performance Index (TCPI)TCPIEAC = Work Remaining / Cost Remaining = (BAC BCWPCum) / (EACACWPCum)TCPIBAC= Work Remaining / Budget Remaining = (BACBCWPCum) / (BACACWPCum)
Status Percentage
% Complete = BCWPCum/ BAC x 100
% Spent = ACWPCum/ BAC x 100
% Schedule = BCWSCum/ BAC x 100
CV
SV
Actual Costs(ACWP)
Earned Value(BCWP)
Planned Value(BCWS)
$
EAC
Time Now
Performance Measurement Baseline(PMB)
BAC
Time
Management Reserve (MR)
TAB(CBB or PBB)
Projected
Slippage
VAC
ETC
Variances: (Favorable is Positive, Unfavorable is Negative)
Cost Variance (CV): CV = BCWPACWP CV% = CV / BCWP x 100
Schedule Variance (SV): SV = BCWPBCWS SV% = SV / BCWS x 100
Variance at Completion (VAC): VAC = BACEAC VAC% = VAC / BAC x 100
UB
WPs PPs
CAs
PMB MR
CBB
Fee/Profit
(no Project analogy)
Contract Price (Project Price)
AUWOTB
TAB
PBB
NASA Contract / Project Hierarchy
NCC Plus
Overrun
Estimate at Completion (EAC) = ACWP + ETCEAC = Actuals to Date + Work Remaining / Performance FactorEACComposite= ACWPCum+ (BACBCWPCum) / (CPICumx SPICum)EACCPI = BAC / CPICum
Common EAC Calculations
http://evm.nasa.gov/http://evm.nasa.gov/