    Earned Value Management (EVM)

    Reference Card

    EVM Terminology

    ACWP Actual Cost of Work Performed (Actual cost incurred for work accomplished during a given period)

    AUW Authorized Un-priced Work (Work contractually approved, but not yet negotiated)

    BAC Budget At Completion (Total planned value for the project)

    BCWS Budgeted Cost for Work Scheduled (Planned Value - budget assigned to the planned scheduled

    work to be accomplished)

    BCWP Budgeted Cost for Work Performed (Earned Value - budget value for the physical work

    accomplished)

    CA Control Account (Management control point to plan and control scope, schedule, and budget)

    CBB Contract Budget Baseline (Total negotiated cost plus AUW)EAC Estimate At Completion (Expected total cost of the project when the scope of work will be

    completed)

    ETC Estimate To Complete (Expected cost needed to complete all remaining work)

    MR Management Reserve (Budget withheld for unknowns / risk management)

    NCC Negotiated Contract Cost (Contract price minus profit or fees or project value for in-house work)

    OTB Over Target Baseline (Sum of CBB and recognized overrun)

    PBB Project Budget Baseline (Same as CBB for in-house projects)

    PMB Performance Measurement Baseline (Time-phased budget plan)

    PP Planning Package (Far term effort within a CA not yet defined into WPs)

    TAB Total Allocated Budget (Sum of all budgets for work on contract = NCC, CBB/PBB, or OTB)

    TCPI To Complete Performance Index (Efficiency needed from status date to achieve an EAC or BAC)

    UB Undistributed Budget (Broadly defined effort not distributed into CAs)

    WP Work Package (Near term effort detailed planned within a CA)

    Revised May 2012

    For NASA in-house programs/projects and contract policies and requirements for the

    application of EVM, please refer to the NASA EVM Website: http://evm.nasa.gov.

    Performance Indices: (Favorable is > 1.0, Unfavorable is < 1.0)Cost Performance Index (Efficiency): CPI = BCWP / ACWPSchedule Performance Index (Efficiency): SPI = BCWP / BCWS

    To Complete Performance Index (TCPI)TCPIEAC = Work Remaining / Cost Remaining = (BAC BCWPCum) / (EACACWPCum)TCPIBAC= Work Remaining / Budget Remaining = (BACBCWPCum) / (BACACWPCum)

    Status Percentage

    % Complete = BCWPCum/ BAC x 100

    % Spent = ACWPCum/ BAC x 100

    % Schedule = BCWSCum/ BAC x 100

    CV

    SV

    Actual Costs(ACWP)

    Earned Value(BCWP)

    Planned Value(BCWS)

    $

    EAC

    Time Now

    Performance Measurement Baseline(PMB)

    BAC

    Time

    Management Reserve (MR)

    TAB(CBB or PBB)

    Projected

    Slippage

    VAC

    ETC

    Variances: (Favorable is Positive, Unfavorable is Negative)

    Cost Variance (CV): CV = BCWPACWP CV% = CV / BCWP x 100

    Schedule Variance (SV): SV = BCWPBCWS SV% = SV / BCWS x 100

    Variance at Completion (VAC): VAC = BACEAC VAC% = VAC / BAC x 100

    UB

    WPs PPs

    CAs

    PMB MR

    CBB

    Fee/Profit

    (no Project analogy)

    Contract Price (Project Price)

    AUWOTB

    TAB

    PBB

    NASA Contract / Project Hierarchy

    NCC Plus

    Overrun

    Estimate at Completion (EAC) = ACWP + ETCEAC = Actuals to Date + Work Remaining / Performance FactorEACComposite= ACWPCum+ (BACBCWPCum) / (CPICumx SPICum)EACCPI = BAC / CPICum

    Common EAC Calculations