net present value risk analysis
TRANSCRIPT
CI05 M01 I02 Slide No. 1Net Present Value Risk Analysis
Net Present Value Risk Analysisan example of using risk management to shape a project’s solution
Martin Hopkinson
Net Present Value Risk AnalysisSlide No. 2
Common-practice Project Risk Management
Brainstorm, Checklists etc.
Risk Register
Prob -Impact Matrix
Actions
Project Objectives
Single Pass Process
Net Present Value Risk AnalysisSlide No. 3
Full Process - PRAM Guide (APM, 2004)
Multi-pass Process
Net Present Value Risk AnalysisSlide No. 4
Road Bridge Project
City
TownTown
Town
12
Two options for the location of a new road bridge
Regional authority invites tenders from industry
Option 2 is the higher capital cost
Net Present Value Risk AnalysisSlide No. 5
Conditions of the Invitation to Tender
• The contractor may bid for either Option 1, Option 2 or both options
• Selected contractor will be awarded a 20-year contract
• The contractor will bear the costs of building the bridge, but will have exclusive rights to collect tolls until the end of the 20-year period.
You are the project risk manager employed by one of the contractors in receipt of the invitation to tender
What is your advice?
Net Present Value Risk AnalysisSlide No. 6
A Useful Point about Risk Analysis
“The biggest uncertainty in a risk analysis is whether we started off analysing the right thing and in the right way”David Vose (2008) – Risk Analysis 3rd Edition
Risk analysis should be designed to answer specific questions. The first task is to verify that the right questions have been identified.
What are the right risk questions at this stage in the road bridge project?
1. Should the company pursue this opportunity?
2. If so, what are the most important sources of uncertainty to manage?
Net Present Value Risk AnalysisSlide No. 7
Should the Company Pursue this Opportunity?
Recommended approach – Net Present Value Risk Analysis
ΣNPV =t = 0
n
C / (1 + D)t
n
Ct = the net cash flow over a period of time (typically 1 year),
t = the period of time during which that cash flow takes place,
D = the discount rate (rate of real terms loss in the value of cash expressed as a percentage - typically per annum) and
n = the number of periods of time periods (typically years) over which NPV is calculated
Net Present Value Risk AnalysisSlide No. 8
Inputs to the NPV Risk Model
c/a = Contract award date
Net Present Value Risk AnalysisSlide No. 9
@RISK for Excel Net Present Value Risk Model
First cycle of the risk management process - Risk Model demonstration
Net Present Value Risk AnalysisSlide No. 10
Outputs from the NPV Risk Model
Answer to Question 1: A polite no bid letter
Net Present Value Risk AnalysisSlide No. 11
Outputs from the NPV Risk Model
Net Present Value Risk AnalysisSlide No. 12
A Graphical Representation of the NPV Risk Model
Net Present Value Risk AnalysisSlide No. 13
Improved Conditions of Invitation to Tender
• National government will fund 50% of the capital costs up to a maximum of £50M
• The contractor may bid for either Option 1, Option 2 or both options
• Selected contractor will be awarded a 20-year contract
• The contractor will bear the costs of building the bridge, but will have exclusive rights to collect tolls until the end of the 20-year period.
As your risk manager, what is your advice?
1. Rerun the first pass risk model with the changed condition
2. Develop a revenue risk model
3. Compare Options 1 and 2Second cycle of risk management process
Net Present Value Risk AnalysisSlide No. 14
Output from the Rerun First Pass Risk Model
Net Present Value Risk AnalysisSlide No. 15
@RISK for Excel Net Present Value Risk Model
Second cycle of the risk management process - Risk Model demonstration
Net Present Value Risk AnalysisSlide No. 16
Output from the Second Cycle of Risk Analysis
Option 2 is the better choice
Net Present Value Risk AnalysisSlide No. 17
Risk Management Process Third Cycle - Commercial Strategy
Revenue
Sources of uncertainty1. Future traffic trends
Future city development
Cost 2.
Opening date 3. Planning consentsConstruction time
Materials
Contracting strategy
Bridge design
Bridge design
Influenced by
Contractor
Contractor
Economic conditions
Regional authority
Contractor
Contractor
Regional authority
Economic growth
Mutual agreementToll charges
Net Present Value Risk AnalysisSlide No. 18
Summary of Important Points
• Risk Management can be used to shape the project solution
• An iterative top-down approach is required to do this
• The most important sources of uncertainty may be those associated with economic benefits rather that project delivery
• NPV risk analysis can be used to make choices between mutually exclusive options
• Understanding relevant sources of uncertainty is important
• The commercial solution should align liability for cost with influence over key sources of uncertainty
Net Present Value Risk AnalysisSlide No. 19
The Project Risk Maturity Model – Level 4
The risk management process leads to the selection of risk-efficient strategic choices when setting project objectives and choosing between options for project solutions or delivery. Sources of uncertainty that could affect the achievement of project objectives are managed systematically within the context of a team culture conducive to optimising project outcomes.