network quality & reliability of supply (nqrs) code audit 2017

28
Network Quality & Reliability of Supply (NQRS) Code Audit Review of systems relating to Code Part 2, Divisions 1 to 4 INDEPENDENT ASSURANCE REPORT August 2017

Upload: others

Post on 29-Oct-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Review of systems relating to Code Part 2, Divisions 1 to 4

INDEPENDENT ASSURANCE REPORT

August 2017

Page 2: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

i

Mr John Paolino

Senior Compliance Specialist

Regulatory Compliance

Western Power

363 Wellington Street

Perth WA 6000

25 August 2017

Dear John,

Re: 2016/17 Network Quality & Reliability of Supply (NQRS) Code Audit

I am pleased to provide our Independent Assurance Report resulting from the audit on the operation of the

systems that are in place to monitor compliance with Part 2 of the Electricity Industry (Network Quality &

Reliability of Supply) Code 2005 for the 2016/17 financial year.

I confirm my approval of the content of the report, and that it is an accurate presentation of the audit findings

and CutlerMerz’ opinions.

Sincerely,

Ryan Dudley

Principal

Page 3: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

ii

Table of Contents

Executive Summary ........................................................................................................ 1

1 Introduction ........................................................................................................... 2

1.1 Audit objective .................................................................................................................................... 2

1.2 Western Power’s key systems and procedures ................................................................................. 2

2 Audit Approach ..................................................................................................... 3

2.1 Audit scope ......................................................................................................................................... 3

2.2 Audit standard .................................................................................................................................... 3

2.3 Audit steps .......................................................................................................................................... 3

2.4 Audit team .......................................................................................................................................... 4

2.5 Western Power key staff..................................................................................................................... 4

2.6 Audit grades ....................................................................................................................................... 5

3 Western Power’s response to previous recommendations .............................. 6

4 Performance summary ......................................................................................... 8

5 Observations ....................................................................................................... 10

6 Recommendations .............................................................................................. 11

– Detailed findings ................................................................................. 12

– Information provided .......................................................................... 24

Page 4: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

1

Executive Summary

The Electricity Industry (Network Quality & Reliability of Supply) Code 2005 (the “Code”) requires that Western Power

arrange for an independent expert to audit, and report on, the operation of the systems in place for monitoring

compliance with Part 2 of the Code.

CutlerMerz (“we”) have been engaged by Western Power to conduct the independent audit for the 2016/17

financial year. As required by the Code, the objective of the audit is to assess whether Western Power has adequate

controls (Process and Systems) in place to monitor compliance with each obligation under the Code.

We conducted the audit in accordance with the Economic Regulation Authority Western Australia (ERA) Guidelines

for Audit and the Australian Standard on Performance Engagements (ASAE 3500). Accordingly, our audit report

provides reasonable assurance as defined in ASAE 3500.

The key findings, areas for improvement and observations arising from the audit are as follows.

Assessment of the adequacy of controls

In relation to Part 2 of the Code, we are of the opinion that Western Power has a strong control environment and

have assessed the adequacy of controls as “A – Adequate controls – no improvement needed”.

Observations

Overall, we consider Western Power’s systems in relation to Part 2 of the Code to be adequate. Notwithstanding

this, we observe that under the requirements of the Code, interruptions arising from weather events are included

(without any exceptions) in determining performance reliability. Consequently, Western Power consistently reports

a substantial number of breaches against a portion of the Code requirements (which Western Power advises are

predominantly due to outages occurring during extreme weather events). Western Power is also required to make

payments to customers where they make a claim against these breaches.

While we have assessed Western Power’s systems for monitoring reliability performance as being adequate, we are

aware that other jurisdictions (as well as the AER) allow for the exclusion of extreme weather events for reliability

reporting and compliance requirements. This contributes towards:

i. Service providers not being required to invest to reinforce the network to withstand extreme weather

events; and

ii. Underlying performance being more effectively monitored, rather than sustaining unrealistic reliability

targets which include the distortion from extreme weather event anomalies. Effective monitoring of

underlying performance drives a tighter focus on achieving the reliability objectives in general, and

particularly in remediating poor performing sections of the network.

We consider that it may be appropriate to consider amending the Code to allow for the exclusion of extreme

weather events, using well established principles, from the reliability performance measurements.

Page 5: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

2

1 Introduction

CutlerMerz was engaged by Western Power to conduct an independent audit and report on the operation of the

systems that are in place to monitor compliance with Part 2 of the Electricity Industry (Network Quality & Reliability

of Supply) Code 2005 (the “Code”) for the 2016/17 financial year.

The requirement for an audit of these systems relating to Part 2 of the Code is based on clause 26 of Part 4 –

Division 3, which reads as follows:

Part 4 — Duties incidental to the prescribed standards

Division 3 — Performance reporting

26. Annual report on monitoring systems

(1) A transmitter and a distributor must, as required by subsection (2), arrange for an

independent expert to audit, and report on, the operation of the systems that the

transmitter or the distributor has in place for monitoring its compliance with Part 2 or an

instrument made under section 14(3).

(2) An audit under subsection (1) is to be carried out in respect of the operation of such

systems during each year ending on 30 June.

1.1 Audit objective

The objective of the audit is to make an independent assessment of the operation of the systems used by Western

Power for monitoring its compliance with Part 2 of the Code between 1 July 2016 and 30 June 2017.

1.2 Western Power’s key systems and procedures

With regards to compliance with the Code, Western Power has implemented a number of systems and procedures

to support compliance. The key systems are identified below.

Reliability

• PowerOn Fusion (PoF): PoF is a leading industry tool for network control and management. It integrates

call centre, network control, and data capture and removes much of the manual processing that is

traditionally prone to human-error in relation to monitoring customer notifications and network reliability

data. Data is extracted and stored from PoF within the Data Warehouse, and then reliability data is

processed for reporting via the Network Reliability Data Validator (NRDV). Although there is always room

for improvement at data interface and processing points, CutlerMerz considers the PoF / Data Warehouse

/ NRDV system to be a strong system for capturing and processing customer and network information.

• Electronic Network Access Request (ENAR): The ENAR system is used to request planned outages and

capture information in relation to the works. It is a functional tool for ensuring compliance with the code in

relation to planned outage requirements.

Power quality

• Power quality: Power quality notifications are captured through PoF, before being actioned through

business as usual processes. CutlerMerz considers this to be a generally appropriate system for managing

power quality issues.

Page 6: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

3

2 Audit Approach

We assessed Western Power’s compliance with the applicable Code requirements by undertaking the following:

• A review of Western Power’s systems designed to meet the compliance requirements;

• A review of Western Power’s systems designed to monitor compliance; and

• Identifying any opportunities for improvement.

The full approach is summarised as follows (refer to the Audit Plan for further detail):

• A risk-based approach to focus the audit on higher risk areas – based on Australian/New Zealand Standard

31000:2009 (Risk Management – Principles and Guidelines);

• Fieldwork to interview Western Power personnel at the head office and operational office. This helped to

gain an appreciation of the control environment, information systems, control procedures, compliance

attitude and outcome compliance;

• Sampling procedures in accordance with ASA 500 and ASA 530 (Audit Sampling); and

• Reporting in accordance with using the format prescribed in the Authority Guidelines (Guidelines Section

11), ASAE 3000 and AEAE 3500.

2.1 Audit scope

The scope of the audit covers the systems in place at Western Power to monitor compliance against Part 2 of the

Code, which includes four divisions:

• Division 1 - Quality Standards

• Division 2 - Standards for the interruption of supply to individual customers

• Division 3 - Standards for the duration of interruptions of supply in particular areas

• Division 4 - Variations of obligations under this Part

2.2 Audit standard

The audit scope is based on the Audit Guidelines1. An audit plan was developed by the auditor based on the

requirements in the Audit Guidelines, a review of Part 2 of the Code and the auditors experience conducting

reviews and audits of the systems and procedures for monitoring quality and reliability of electricity network

businesses.

The audit scope was subsequently reviewed and approved by Western Power.

2.3 Audit steps

The audit steps are summarised in Table 1.

1 Audit and Review Guidelines: Electricity and Gas Licences, April 2014, Economic Regulation Authority Western Australia

Page 7: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

4

Table 1: Audit steps

Audit step Tasks

Planning Desktop review of policy and procedures

Prepare audit plan

Field audit

Control room visit Wednesday 20 August

Western Power office Thursday 21 August

Western Power office Friday 22 August

Off-site review and

reporting Review supplementary documentation and prepare audit report

2.4 Audit team

The audit team is outlined in Table 2.

Table 2: Audit team

Name Role Responsibility

Ryan Dudley Audit Director and

Lead Auditor

Overall responsibility for the delivery of the audit

Adam Homan Project Manager

and Auditor

Day-to-day management and delivery of the audit plan, field audits and audit

report

2.5 Western Power key staff

The key Western Power staff that have participated in the audit are identified in Table 3.

Table 3: Western Power key staff

Role(s) Key Area(s) of Discussion

Senior Planning Engineer – Distribution Planning Power quality

Business Solution Architect – Project Delivery IT systems

Operations Development Manager – Network Operations Development

Quality & Compliance Officer - Network Operations Development

SCADA Applications Specialist – Service Management & Support

Network operations

Customer & Outage Compliance Coordination Team Leader –

Scheduling & Dispatch

Planned Outage Notification Team Leader – Customer Experience

Planned outage notifications

Complaints & Resolutions Team Leader – Customer Experience

Customer Service Centre Team Leader – Customer Service Centre Complaints

Insight Analyst – Insight & Analytics

Senior Insight Analyst – Insight & Analytics Reporting

Access Solutions Manager Customer agreements and Instruments from the

Minister

Page 8: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

5

Role(s) Key Area(s) of Discussion

Strategic Planning & Standards Manager – Strategic Planning &

Standards Network planning

Senior Compliance Specialist Regulatory Compliance

2.6 Audit grades

The evaluation of compliance was undertaken by adapting the compliance grades outlined in the Audit Guidelines

to assess the adequacy of controls rating only. This is shown in Table 4.

Table 4: Audit compliance ratings

Performance audit compliance and controls rating scales (adapted from ERA Audit Guidelines)

Adequacy of Controls (Process and Systems) Rating

Rating Description

A Adequate controls – no improvement needed

B Generally adequate controls – improvement needed

C Inadequate controls – significant improvement required

D No controls evident

Page 9: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

6

3 Western Power’s response to previous recommendations

One recommendation was made for the precious audit which covered the 2014-15 period (provided in Table 5).

Table 5: Recommendation from FY16 Audit

Reference

(no. /

year)

Non Compliance / Controls improvement

(Rating / Legislative Obligation / Details of

Non Compliance or inadequacy of

controls)

Auditors’ recommendation

Management action

taken by end of audit

period

01/2016 Rating: B

Legislative Obligation: Electricity Industry

(Network Quality and Reliability of Supply) Code

2005 clause 10(2) – A distributor or transmitter

must consider whether, in specified circumstances,

it should supply electricity by alternative means to a

customer who will be affected by a proposed

interruption.

Details of inadequacy of controls: Whilst

Western Power’s ENAR system prompts the

planned outage requestor to state whether or

not mobile generation is required for a

planned outage, there does not appear to be

procedural guidance, based on the

requirements of the Code, as to when these

should be deployed. It is noted that Western

Power’s scheduling team has advised that

they do consider using mobile generators

under the circumstances specified by the

Code; however, CutlerMerz has not observed

a procedure to support this practice.

CutlerMerz has observed an outage example

of planned outage documentation where the

use of mobile generation may have been

considered appropriate based on the Code;

but the ENAR requestor did not request

mobile generation and it did not appear to be

deployed in this instance.

It is recommended that Western

Power introduce a process to

ensure that the use of alternate

power supplies is considered for

planned outages, in view of the

specific circumstances identified in

the Code.

Western Power will review,

and if required improve, its

current processes relating to

the use of alternative power

supply for planned outages in

circumstances identified in

clause 10(2) of the Code.

Due date: 31 December 2017

CutlerMerz has reviewed the ENAR system, which includes a “Strategy to Mitigate Customer Impact” in relation to

the prompt where the user enters whether an emergency generator is required to support the planned outage. A

relevant extract from the ENAR system is shown in Figure 1. We have also reviewed the referenced document

referenced within the ENAR system (DM #7747422), which provides consideration for planned interruptions during

hot weather.

Based on review of the ENAR systems and the Planned Interruptions in Hot Weather Management Guideline we are

satisfied that the recommendation is addressed.

Page 10: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

7

Figure 1: Extract from ENAR system showing consideration of Code requirements relating to the use of emergency

generator prompt

Page 11: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

8

4 Performance summary

Table 6 summarises the compliance rating for each Code related licence condition using the rating scale described

in Section 2.6.

As required by the Audit Guidelines, the primary objective of the audit ratings is to provide an independent

assessment of Western Power’s adequacy of controls for monitoring compliance to the Code licence conditions.

The observations supporting the ratings in Table 6 are discussed in Section 5 while the detailed findings for each

licence condition and additional information on the rationale for each of the ratings can be found in Appendix A.

Table 6: Audit ratings

Compliance

Obligation

Reference

No.

Licence Reference

Audit

Priority

applied

Adequacy of

Controls Rating

A B C D

462 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 5(1)

A distributor or transmitter must, as far as reasonably practicable, ensure

that electricity supply to a customer’s electrical installations complies with

prescribed standards.

4 ✓

463 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 8

A distributor or transmitter must, so far as reasonably practicable,

disconnect the supply of electricity to installations or property in specified

circumstances, unless it is in the interest of the customer to maintain the

supply.

4 ✓

464 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 9

A distributor or transmitter must, as far as reasonably practicable, ensure

that the supply of electricity is maintained and the occurrence and duration

of interruptions is kept to a minimum.

5 ✓

465 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 10(1)

A distributor or transmitter must, so far as reasonably practicable, reduce

the effect of any interruption on a customer.

4 ✓

466 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 10(2)

A distributor or transmitter must consider whether, in specified

circumstances, it should supply electricity by alternative means to a

customer who will be affected by a proposed interruption.

4 ✓

Page 12: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

9

Compliance

Obligation

Reference

No.

Licence Reference

Audit

Priority

applied

Adequacy of

Controls Rating

A B C D

467 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 12(3)

A distributor must take prescribed action in the event of a significant

interruption to a small use customer.

5 ✓

468 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 13(2)

A distributor or transmitter must, so far as reasonably practicable, ensure

that customers in specified areas do not have average total lengths of

interruptions of supply greater than specified durations.

4 ✓

469 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 13(3)

The average total length of interruptions of supply is to be calculated using

the specified method.

5 ✓

470 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 14(8)

A distributor or transmitter must, on request, provide to an affected

customer a free copy of an instrument issued by the Minister and of any

notice given under section 14(7) of the Electricity Industry (Network Quality

and Reliability of Supply) Code 2005.

5 ✓

471 Electricity Industry (Network Quality and Reliability of Supply) Code 2005

clause 15(2)

A distributor or transmitter that agrees with a customer to exclude or

modify certain provisions must set out the advantages and disadvantages

to the customer of doing so in their agreement.

3 ✓

Page 13: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

10

5 Observations

All Western Power personnel that participated in the audit process demonstrated an understanding of the Code

and its requirements, and a commitment to effective management of power quality and network reliability by the

business.

Overall, we consider Western Power’s systems in relation to Part 2 of the Code to be adequate . The systems in

effect are generally consistent with those effected by peer businesses, and we have observed some peers with less

robust systems in place.

Notwithstanding the above, we observe that leading peers tend to have a sharper focus on ensuring their specific

requirements are achieved; in terms of the specific requirements being embedded throughout strategic, tactical

and day-to-day decision marking criteria. Based on observations, we consider that there are likely to be three

factors contributing to this, which are linked to the mechanisms of Western Power’s regulatory regime rather than

system capability:

1. The inclusion of extreme weather events in the reporting of reliability metrics has the effect of reducing

emphasis on achieving the requirements, where:

• Reporting substantial breaches on an ongoing basis creates an environment where it is acceptable

that breaches are unavoidable; and

• The distortion of the metrics by these events masks the underlying performance, which in turn may

reduce focus on monitoring, tracking and remediating these sections of the network.

2. We understand that it is not a requirement for Western Power to be audited on compliance against the

specific performance targets, including a validation of the figures that are captured and reported. We

understand that this audit, which focuses on the operation of the systems that are in place to monitor

compliance, is the only audit required in relation to power quality and reliability. We have observed an

iterative effect within peers that are audited for compliance (including a data accuracy validation

component), where focus on the requirements is continually sharpened.

3. Western Power also has reliability targets prescribed under its access arrangements (Service Standard

Benchmarks – SSB), which are different from those required under the Code. The SSBs are linked to a

performance incentive scheme that has positive/negative financial outcomes. Whilst Western Power’s

documentation considers both the requirements of the Code and the SSBs, we consider that focus will

naturally be sharper on achieving the SSBs which are linked to financial incentives.

In relation to Clause 15(2), it is noted that Western Power has not entered into any agreements with customers in

relation to where the “prescribed standards” are not met. It may be considered appropriate under the Code for

Western Power to enter into agreements with customers based on the substantial number of breaches being

reported on an ongoing basis. However, in our view, it would be more appropriate to amend the relevant clauses

of the code to exclude extreme weather events. We consider that it would be impractical for Western Power to

enter into an agreement with each customer that may be subject to extreme weather events.

The detailed findings of the audit in relation to each obligation are provided in Appendix A.

Page 14: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

11

6 Recommendations

CutlerMerz considers that the opportunities for improvement that have been identified relate to the regulatory

regime rather than deficiencies in Western Power systems and processes (refer to Section 5). As such, no

recommendations have been made.

Page 15: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

12

– Detailed findings

The detailed findings from the audit are provided in Table 7.

Table 7: Detailed findings

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

An outline of the criteria for compliance Discussion of the evidence and how the compliance assessment was determined i.e. whether the evidence was sufficient to

demonstrate compliance or not.

Recommendations / Opportunities for Improvement are identified where relevant

Division 1 Compliance obligation reference No: 462

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 5(1)

Obligation: A distributor or transmitter must, as far as

reasonably practicable, ensure that electricity supply to a

customer’s electrical installations complies with

prescribed standards.

Context: The “prescribed standards” relates to the

standards for harmonics and voltage fluctuation – refer

to Code 2005, Part 2, Division 1, Clause 6(2) and Clause

7.

CutlerMerz has interviewed personnel responsible for power quality at Western Power, and reviewed relevant

information as appropriate. Based on this consultation, CutlerMerz considers that Western Power has a number of

systems, processes and mechanisms in place to practicably enable compliance with the standards for harmonics and

voltage fluctuations. These relate to:

• The design of the system and connections to the network;

• Proactive monitoring of power quality performance; and

• Reactive actions where Western Power becomes aware of a power quality issue.

Findings in relation to each of the above are discussed below.

System design

• It is understood that Western Power designs its system in accordance with the Australian standards for

Electromagnetic Compatibility (EMC)2. CutlerMerz has reviewed the standards and found them to be effectively

2 Standards Australia / Standards New Zealand, Technical Report – Electromagnetic compatibility (EMC) – Part 3.14: Limits–Assessment of emission limits for harmonics, interharmonics, voltage fluctuations and unbalance for the

connection of disturbing installations to LV power systems, SA/SNZ TR IEC 61000.3.14:2013, EC/TR 61000-3-14, Ed.1.0 (2011)

Page 16: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

13

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

consistent with the requirements of the Code in relation to both harmonics and voltage fluctuation (and where

inconsistent, require a higher standard than specified by the Code).

• The generator connection process requires a power quality assessment as part of the preliminary assessment phase

and a review of power quality commissioning results during the commissioning phase. CutlerMerz understands that

the assessments / reviews are based on the requirements of the standards. CutlerMerz has also reviewed “Allocation

Sheets” which require harmonic and flicker information to be provided and assessed for new connections.

• Based on design and commissioning in accordance with the aforementioned standards, it can be expected that the

system will meet the power quality requirements of the Code upon the commissioning of assets. However, it is noted

that power quality issues arise due to equipment that customers connect to the network (often post-commissioning)

– Western Power’s mechanisms for proactive monitoring of power quality and reactive action are discussed below.

Proactive monitoring:

• CutlerMerz considers that proactive monitoring of power quality at all customer connections would not be practical

based on the current metering technology employed within the network. This view is supported by the University of

Wollongong which undertook a National Long Term Power Quality Survey in 2013/14 in conjunction with Power

Quality Australia. Western Power participated in this survey. CutlerMerz understands that based on the survey it was

recommended that approximately 350 power quality meters distributed throughout Western Power’s network would

statistically provide a 95% confidence of power quality readings across the network. It is understood that Western

Power has installed 360 power meters throughout its network, which is above that recommended by the survey. The

meters are expected to provide 95% confidence level for both harmonics and voltage fluctuation across the network.

CutlerMerz has reviewed the resulting benchmarking report from the survey; where, Western Power outperforms the

national average for harmonics and flicker in relation the percentage of sites that exceeded the “limits” defined within

the survey.

• CutlerMerz understands that Western Power downloads and analyses the data from the power quality meters once

annually to proactively monitor power quality across the network. It is understood that these reviews are undertaken

to assess compliance with the standards. The data is also being provided to the University of Wollongong for analysis.

In addition, Western Power reactively investigates individual power quality cases where identified by field staff or

Page 17: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

14

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

through customer notification – Western Power’s mechanisms for reactive actions to address power quality issues are

discussed below.

Reactive action:

• CutlerMerz understands that Western Power has two primary mechanisms for “reactively” identifying power quality

issues: customer notification and when incidentally encountered by operational personnel.

• CutlerMerz has reviewed Western Power’s process and investigations manual for addressing power quality issues that

have been identified. These appear reasonable to ensure that power quality issues that have been identified will be

addressed.

• CutlerMerz has reviewed the process and question prompts followed by the call centre. Based on these it can be

expected that complaints relating to harmonics and flicker will be captured. A sample of complaints have been

reviewed, and for each compliant there is evidence of follow up actions that demonstrate power quality complaints

are being followed up and addressed.

Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, as far as

reasonably practicable, ensure that electricity supply to a customer’s electrical installations complies with prescribed

standards for power quality.

Compliance obligation reference No: 463

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 8

Obligation: A distributor or transmitter must, so far as

reasonably practicable, disconnect the supply of

electricity to installations or property in specified

circumstances, unless it is in the interest of the customer

to maintain the supply.

CutlerMerz has interviewed personnel responsible for power quality at Western Power, and reviewed relevant

information as appropriate. The power quality investigation process identifies decision points for customers to be

disconnected if:

• Harmonics or voltage fluctuation are present that will “damage customer equipment” and the customer agrees with

the disconnection; and

• If harmonics or voltage fluctuation are present that will “damage customer equipment” and the customer does not

agree with the disconnection, to disconnect “if there is a safety risk”.

Western Power has advised that during the auditable period there were no disconnections related to harmonics or

flicker.

Page 18: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

15

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

Context: The “specified circumstances” are when

compliance with the standards for harmonics and

voltage fluctuation (refer to Code 2005, Part 2, Division

1, Clause 6(2) and Clause 7) cannot be achieved, and this

may result in damage to a customer’s electrical

installations or property.

Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as

reasonably practicable, disconnect the supply of electricity to installations or property in specified circumstances, unless it

is in the interest of the customer to maintain the supply.

Division 2 Compliance obligation reference No: 464

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 9

Obligation: A distributor or transmitter must, as far as

reasonably practicable, ensure that the supply of

electricity is maintained and the occurrence and

duration of interruptions is kept to a minimum.

CutlerMerz has interviewed personnel responsible for reliability at Western Power, and reviewed relevant information as

appropriate. Based on this consultation, CutlerMerz considers that Western Power has a number of systems, processes

and mechanisms in place to practicably ensure that the supply of electricity is maintained and the occurrence and

duration of interruptions is kept to a minimum. These relate to:

• Network planning;

• Planned works management; and

• Unplanned outage management.

Findings in relation to each of the above are discussed below.

Network planning:

• CutlerMerz understands that Western Power designs its network in accordance with the Technical Rules prescribed by

the ERA and available on their website. CutlerMerz has also reviewed:

o Western Power’s Asset Management Objectives Report and Dx Reliability Strategy (for the distribution network)

– these documents both define reliability requirements in accordance with the Code.

o The ‘reliability monitoring spreadsheet” – which demonstrates that Western Power is monitoring its reliability

performance against the requirements of the Code.

o A business case for procuring a mobile transformer for emergency response – which demonstrates Western

Power taking actions to enable it to improve reliability performance against the requirements of the Code.

Page 19: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

16

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

• CutlerMerz understands that Western Power considers reliability as a key factor in prioritisation of maintenance

programmes and defect remediation.

• CutlerMerz considers the network planning processes outlined above to be broadly consistent with Western Powers

peers, and give due consideration to ensuring that the network is designed to minimise the occurrence and duration

of interruptions to customers.

Planned works management:

• CutlerMerz understands that Western Power’s processes for implementing planned works consider approaches to

minimise the frequency and duration of outages experienced by customers.

• CutlerMerz has reviewed the use of the Electronic Network Access Request (ENAR) user guide, and samples of ENAR

forms and has observed processes for the use of mobile generators to minimise outages to customers (i.e. completed

ENAR form).

• CutlerMerz has observed the ENAR strategy checklist which requires users to consider the use of mobile generators

specifically in view of the requirements of the Code. Sample ENAR forms demonstrate that the emergency generators

are being used in these circumstances.

Unplanned outage management:

• CutlerMerz understands that Western Power has several processes in place to minimise the duration and number of

customers affected during an unplanned outage. These relate to both control room procedures and procedures for

field personnel.

• It is noted that whilst field personnel make decisions on the ground regarding how to repair the network following a

fault, access to the network and all switching operations (both those performed remotely from the control room and

those performed by field switching operators) are executed under direction from the control room operator.

CutlerMerz has reviewed the procedures for fault restoration and priority restoration guideline. These documents

demonstrate that Western Power has processes in place to prudently restore power in a way that minimises the

duration and number of customers affected.

Page 20: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

17

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

• CutlerMerz understands that Western Power uses a “priority response” approach for unplanned outage management

in the field, which is aimed to make the network safe and restore power as soon as possible, and leaving major repair

works to be scheduled for regular maintenance crews. CutlerMerz has reviewed the dispatch procedures which

demonstrates the priority dispatch process.

• CutlerMerz understands that Western Power uses mobile generators during unplanned outages to minimise the

outage duration and customers affected. CutlerMerz has reviewed Western Power’s procedural document which

details the process for the deployment of generators during unplanned outages.

Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as

reasonably practicable, ensure that the supply of electricity is maintained and the occurrence and duration of

interruptions is kept to a minimum.

Compliance obligation reference No: 465

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 10(1)

Obligation: A distributor or transmitter must, so far as

reasonably practicable, reduce the effect of any

interruption on a customer.

CutlerMerz has interviewed personnel responsible for reliability at Western Power, and reviewed relevant information as

appropriate. Based on this consultation, CutlerMerz considers that Western Power has a number of systems, processes

and mechanisms in place to practicably reduce the effect of any interruption on a customer. These relate to:

• Reducing the frequency and duration of outages in general;

• Communication with customers in relation to outages; and

• Special consideration and prioritisation of customers likely to be most affected by an outage.

Findings in relation to each of the above are discussed below.

General measures for reducing the frequency and duration of outages:

Refer to discussion in relation to clause 9 above.

Customer communication:

CutlerMerz understands that Western Power has two primary mechanisms for communicating planned outages with

customers – posting letters in the mail and card drops. CutlerMerz has reviewed the process for notifying customers for

Page 21: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

18

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

planned outages which details the process. It is noted that through this process the identification of customers to be

notified relies on PowerOn Fusion (PoF) and the ENAR systems (refer to Section 2).

Customers likely to be most affected:

Western Power places increased effort on managing customers who are likely to be more adversely affected, or where an

outage to these customers will adversely affect the community more broadly. These customers include:

• Life support equipment (LSE) customers;

• Utilities and essential services (e.g. Main Roads, traffic lights); and

• Sensitive load customers (e.g. hospitals).

CutlerMerz has reviewed the procedural documents for customer notifications, fault restoration, the priority restoration

guideline, the priority dispatch procedures, and procedures for the deployment of generators during unplanned outages

– these procedures all give consideration to “sensitive” customers in some capacity.

Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as

reasonably practicable, reduce the effect of any interruption on a customer.

Compliance obligation reference No: 466

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 10(2)

Obligation: A distributor or transmitter must consider

whether, in specified circumstances, it should supply

electricity by alternative means to a customer who will

be affected by a proposed interruption.

CutlerMerz has interviewed personnel responsible for mobile generator dispatch at Western Power, and reviewed

relevant information as appropriate. Based on this consultation, CutlerMerz considers that Western Power has a number

of systems, processes and mechanisms in place to supply electricity by alternative means to a customer who will be

affected by a proposed interruption. These relate to:

• Planned outages; and

• Unplanned outages.

Findings in relation to each of the above are discussed below.

Planned outages:

Page 22: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

19

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

Context: The “specified circumstances” are when:

• The interruption is expected to exceed 6 hours, or 4

hours if forecast maximum temperatures are

expected to be greater than 30 degrees Celsius (as

issued by the Bureau of Meteorology in Perth);

• The effect of the interruption on the customers’

business is likely to be substantial; or

• The interruption will affect a person with life support

needs and requires electricity for the operation of

equipment that caters to those needs.

The ENAR system requires the originator of the outage request to consider whether mobile generation is required (in the

ENAR guide this is in the form of a prompt for a yes/no answer). CutlerMerz has observed the ENAR strategy checklist

which requires users to consider the use of mobile generators specifically in view of the requirements of the Code.

Sample ENAR forms demonstrate that the emergency generators are being used in these circumstances.

Unplanned outages:

It is noted that the Code refers to “proposed interruption[s]”. Notwithstanding, Western Power’s process for the use of

mobile generators during unplanned outages outlines that mobile generation should be considered if the estimated “fix

time” is less than 6 hours.

Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as

reasonably practicable, supply electricity by alternative means to a customer who will be affected by a proposed

interruption.

Compliance obligation reference No: 467

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 12(3)

Obligation: A distributor must take prescribed action in

the event of a significant interruption to a small use

customer.

Context:

The “prescribed actions” are:

CutlerMerz has interviewed personnel responsible for reliability at Western Power, and reviewed relevant information as

appropriate.

It is noted that Western Power has reported a substantial number of incidents where the “prescribed standards” have not

been met in previous years (for both outage duration and number of interruptions standards); and Western Power

advises the same outcome in 2016/17. It is understood that these cases are predominantly due to extreme weather

events. CutlerMerz considers it impractical for Western Power to meet the prescribed standards during extreme weather

events. It is noted that in other Australian jurisdictions such events would be excluded, which would allow the underlying

performance to be monitored. In CutlerMerz’ view, it would be appropriate to amend this clause of the code to exclude

extreme weather events.

Notwithstanding the above, it is understood that Western Power has a process for reviewing poor performing sections of

the network (referred to as “hot spots”). CutlerMerz has reviewed Western Power’s Dx Reliability Strategy and Hot Spots

Monitoring spreadsheet, which demonstrate that Western Power considers both its Service Standard Benchmarks (SSB)

Page 23: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

20

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

• To remedy the cause or causes of the interruption so

that the prescribed standard is met; or

• Enter into an agreement to the small use customer’s

satisfaction for the supply of electricity to the

customer.

The “prescribed standard” is the supply of electricity for

9 years in every 10 without the interruption of supply

exceeding:

• An interruption of more than 12 hours continuously;

or

• 9 interruptions in Perth CBD and urban areas, or 16

in other areas (in the preceding year).

The definition of “significant interruption” is not meeting

the prescribed standard.

applicable under its Access Arrangement, and the requirements of the Code; the strategy then forms a considered

position on remediating “hot spots”.

Western Power has advised that they have not entered into any agreements with small use customers in relation to

providing lower than the prescribed standards.

Finding: CutlerMerz notes that Western Power consistently reports a substantial number of incidents where the

“prescribed standards” are not met. This appears to be predominantly due to extreme weather events. In CutlerMerz’

view, it would be appropriate to amend this clause of the code to exclude extreme weather events. It is also noted that

Western Power has not entered into any agreements with small use customers in relation to providing lower than the

prescribed standards; further to the above, CutlerMerz considers that it would be impractical for Western Power to enter

into an agreement with each customer that may be subject to extreme weather events.

Notwithstanding the above, CutlerMerz considers that Western Power’s systems, processes and mechanisms can be

expected to, so far as reasonably practicable, remedy sections of the network with poor reliability.

Division 3 Compliance obligation reference No: 468

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 13(2)

Obligation: A distributor or transmitter must, so far as

reasonably practicable, ensure that customers in

specified areas do not have average total lengths of

interruptions of supply greater than specified durations.

Context:

CutlerMerz has interviewed personnel responsible for reliability at Western Power, and reviewed relevant information as

appropriate. The findings on Western Power’s processes and systems to ensure compliance with reliability obligations are

detailed within the findings relating to Division 2. It is noted that Western Power’s network planning and outage

management processes consistently consider risk factors in terms of reliability and customers affected, which naturally

leads to greater focus on reducing higher density areas i.e. Perth CBD, then other areas, then the remainder of the

network (assuming greater number of customers per feeder in higher density areas). The SSBs also drive focus in this

area. Further, Western Power’s Dx Reliability Strategy details how Western Power considers both its Service Standard

Benchmarks (SSB) applicable under its Access Arrangement, and the requirements of the Code; the strategy then forms a

considered position on remediating “hot spots”.

As per Division 2 - clause 12(3), CutlerMerz notes that the Code does not allow for the exclusion of extreme weather

events, which is understood to have resulted in Western Power not meeting its overall targets. Again, CutlerMerz

Page 24: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

21

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

The overall “specified durations” are:

• Perth CBD: 30 minutes

• Urban (other than Perth CBD): 160 minutes

• Other areas: 290 minutes

considers that this is due to impracticality of the Code (i.e. in not excluding extreme weather events) rather than due to

inappropriateness of Western Power’s processes and systems.

Finding: As per Division 2 - clause 12(3), CutlerMerz notes that Western Power consistently reports not meeting the

“specified durations”. This appears to be predominantly due to extreme weather events. Again, CutlerMerz’ considers it

would be appropriate to amend this clause of the Code to exclude extreme weather events.

Notwithstanding the above, CutlerMerz considers that Western Power’s systems, processes and mechanisms can be

expected to, ensure that customers in specified areas do not have average total lengths of interruptions of supply greater

than specified durations.

Compliance obligation reference No: 469

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 13(3)

Obligation: The average total length of interruptions of

supply is to be calculated using the specified method.

Context:

The overall “specified method” is to be calculated as at

30 June in each year:

• by taking the average total length, in minutes, of

interruptions of supply to customer premises in an

area during each year of the period of 4 years

ending on that day; and

• by then taking the average of the 4 annual figures

determined above.

CutlerMerz has interviewed personnel responsible for reliability systems and calculations at Western Power, and reviewed

relevant information as appropriate.

Western Power calculates the average total length of interruptions using its Network Reliability Data Validator (NRDV)

system. The NRDV system is configured to run Structured Query Language (SQL) to interrogate the Data Warehouse

(which captures and stores reliability data generated by PowerOn Fusion). CutlerMerz has observed the queries being run

in NRDV to produce the reliability calculations and considers this to be an appropriate system to generate the required

reports. It should be noted that CutlerMerz has not reviewed the SQL coding or attempted to reproduce the calculations

to verify their accuracy.

Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as

reasonably practicable, calculate the average total length of interruptions using the specified method.

Page 25: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

22

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

Division 4 Compliance obligation reference No: 470

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 14(8)

Obligation: A distributor or transmitter must, on request,

provide to an affected customer a free copy of an

instrument issued by the Minister and of any notice

given under section 14(7) of the Electricity Industry

(Network Quality and Reliability of Supply) Code 2005.

Context:

If, having regard to the advice of the Authority, the

Minister is satisfied that it is appropriate to do so, the

Minister may by “Instrument”:

• Exempt the transmitter or distributor from

compliance with the provision concerned; and

• Attach to the exemption a condition that another

provision, in place of the provision for which an

exemption is granted, is to be complied with by the

transmitter or distributor in the supply of electricity.

“Section 14(7)”- The Minister may at any time, after

obtaining the advice of the Authority, by notice in

writing to the transmitter or distributor revoke or vary an

instrument above including by imposing any further

CutlerMerz has interviewed personnel responsible for customer services at Western Power, and reviewed relevant

information as appropriate.

Western Power has advised that no “instruments” have been issued by the Minister during the audit period, and nor are

there any previously issued instruments that are applicable within the audit period.

Interaction with the Minister is through Western Power’s Government Relations division, and interactions with customers

is through Western Power’s Customer Services division. CutlerMerz considers that this would be an appropriate structure

to provide to an affected customer a free copy of an instrument issued by the Minister (should the Minister issue a notice

in future and a customer then request a copy of the instrument.

Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as

reasonably practicable, provide to an affected customer a free copy of an instrument issued by the Minister upon

request.

Page 26: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

23

NQRS

Code, Part

2: Division

#

Compliance Obligation and Context Findings

condition to be complied with by the transmitter or

distributor.

Compliance obligation reference No: 471

Clause: Electricity Industry (Network Quality and

Reliability of Supply) Code 2005 clause 15(2)

Obligation: A distributor or transmitter that agrees with

a customer to exclude or modify certain provisions must

set out the advantages and disadvantages to the

customer of doing so in their agreement.

CutlerMerz has interviewed personnel responsible for customer services at Western Power, and reviewed relevant

information as appropriate.

Western Power has advised that no “agreements” are in place with customers to exclude or modify certain provisions of

Part 2 of the Code. As noted in relation to Division 2 – clause 12(3), Western Power consistently reports a substantial

number of incidents where the “prescribed standards” are not met (which appears to be predominantly due to extreme

weather events).

Finding: It may be considered appropriate under the Code for Western Power to enter into agreements with customers

where the “prescribed standards” are not met. However, in CutlerMerz’ view, it would be more appropriate to amend the

relevant clauses of the code to exclude extreme weather events. CutlerMerz considers that it would be impractical for

Western Power to enter into an agreement with each customer that may be subject to extreme weather events.

Page 27: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

24

– Information provided

The information provided during the audit is provided in Table 8. It should be noted that Western Power also

responded directly via email and provided document hard-copies throughout the fieldwork – these items are not

included in Table 8.

Table 8: Information provided

Document name

RE NQRS Audit.msg

UoW PQ benchmarking results.pdf

Example_harmonic_Flicker_sheet.xlsx

WE_n1165772_POWER_QUALITY___TVI_COMPLAINT_HANDLING_PROCESS.PDF

PQ INVESTIGATIONS MANUAL.PDF

Technical Rules.pdf

Visio-Fault Response Group Process Map_.pdf

G 174 Fault Response Group Guideline_.pdf

Visio-Call Taker Wizard Question Flow_.pdf

Visio-Call Taker Prompts - Production - with Hazids_.pdf

Power Quality.xlsx

PQDetails.xlsx

G 249 Planned Interruptions in Hot Weather Management Guideline.pdf

Enar Strategy Checklist.pdf

G 245 Prioritizing Network Restoration Guideline (NWI 117) (8482502).pdf

SOP 163 Trouble Call Incident Management Rev 11.docx

SOP 163 Trouble Call Incident Management_.pdf

G 151 eNAR User Instructions.pdf

SOP 164 Restoration of Feeders and Reclosers (NWI 080) (1530872)_.pdf

SOP 163 Trouble Call Incident Management Rev 11.docx

SOP 163 Trouble Call Incident Management_.pdf

SOP 224 Emergency Response Generators (LV) (2123938).docx

SOP 178 Quality of Supply Resolution (NWI 007) (1531190)_.pdf

eNAR 300394 CA Notify.pdf

eNAR 301996 CA Notify.pdf

eNAR 307066 Hand Card Metro Planned.pdf

eNAR 308223 Hand Card .pdf

PLANNED OUTAGE NOTIFICATIONS PROCEDURE (8580227)_.pdf

Outage Coordination and Compliance Team Work Instructions_.pdf

Page 28: Network Quality & Reliability of Supply (NQRS) Code Audit 2017

Network Quality & Reliability of Supply (NQRS) Code Audit

Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit

25

Document name

Genset Provided for Outage eNAR 305882.pdf

Transformer Backfed eNAR 308385.pdf

Procedure for Customer Cmpls - Power Quality & Reliability. Alignment of NetCis Cases and DQM Reporting. (10415488)_.pdf

Validation Guide Checklist_.pdf

Reliability calculations for the NQRS report.pdf

Asset_Management_Objectives_Report_(12804096).pdf

Dx Reliability_Strategy (1).pdf

RE NQRS Audit Information.msg

Hot spot list on against NQRS and SSB criteria_.xlsb

RE NQRS Audit Information.msg

Business Case - N0439752 - Emergency Response Generator HV connection.docm