NewbuildupdateSeptember2016
ThenewschoolbuildTheviewfromthesportshalltowardsthegroundfloor
SEN
Englishclassrooms
Staircase
Reception
Mainoffice
LookingfromtheCopsewoodRoad/SkillsCentrecorner
Sciencerooms
Englishrooms
Photographyrooms
Staircase/entrance
TheNewBuild– updateMainsteelframe:• Qtr 1&Qtr 2– CopsewoodRoadtoDimondRoadfulllengthofbuildinginplace.HalfdepthtowardsOaktreeRoadcomplete
• Qtr 3&Qtr 4– tobecompletedbyendofSeptember.• Floorbeamstotheground,firstandsecondfloorsonQtr 1ongoing
Ongoing/whatishappeningnext• Steelworkandfloors• Externalwalls/envelopeofthebuilding• Roof• Drainageandservices• Groundwork/framefortheactivitystudios
ThesportshallblockThesportshallbuildinghasnowbeenhandedback:• 2xlargermainchangingroomstoreplacethemainschoolchangingroomblock.
• 2xnewsmallerchangingrooms.• Newmale/femaletoiletblockseparatefromthechangingrooms.
• Revamp/newlocationsforPEoffices.
Logistics:• AllPElessonsstudentchangingtothesportshall.• Dancelessonchangingonlytothemainblockchangingrooms.• TemporaryentrancebehindMFLhutstobeusedbystudents.• 2xMFLclassroomsbacktoclassrooms.