Monthly Progress Report No.10 for November 2015

PADMA MULTIPURPOSE BRIDGE PROJECT

RIVER TRAINING WORKS

CONTRACTOR’S MONTHLY PROGRESS REPORT

NO.10 FOR NOVEMBER 2015

Project Padma Multipurpose Bridge project-River Training Works

ClientTHE BANGLADESH BRIDGE AUTHORITY Representative

Ministry of Road Transport and Bridges Mr. Shafiqul Islam

Engineer Construction Supervision ConsultantKorea Expressway Corporation & Associates

Representative

Mr. Robert Aves

ContractorSinohydro Corporation Ltd. Representative

House No. 17, Road No.7, Baridhara Diplomatic Area, Dhaka-1212 Mr. Qu Yan

dell
新建图章
Page 3: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Table of ContentsCHAPTER-1.....................................................................................................................1

PROJECT OVERVIEW & CONTRACT PARTICULAR..........................................1

CHAPTER-2.....................................................................................................................3

MEMORABILIA............................................................................................................. 3

CHAPTER-3.....................................................................................................................6

PROGRESS OF WORK IMPLEMENTATION.......................................................... 6

CHAPTER-4...................................................................................................................28

FINANCIAL & CONTRACTUAL MATTERS..........................................................28

CHAPTER-5...................................................................................................................30

ORGANIZATION CHART.......................................................................................... 30

CHAPTER-6...................................................................................................................32

STATEMENT OF MANPOWER, MATERIAL, EQUPIMENT AND PLANT......32

CHAPTER-7...................................................................................................................38

STATEMENT OF MAJOR TEST CONDUCTE....................................................... 38

CHAPTER-8...................................................................................................................41

HEAITH, SAFETY AND ENVIRONMENT...............................................................41

CHAPTER-9...................................................................................................................45

KEY EMPHASIS AND PLAN FOR NEXT MONTH WORK..................................45

CHAPTER-10.................................................................................................................47

WEATHER & HYDROLOGICAL REPORT............................................................ 47

CHAPTER-11.................................................................................................................52

PROGRESS PHOTOGRAPHS.................................................................................... 52

SUMMARY OF REPLIED STATUS OF CORRESPONDENCES WITH BBA &

CSC..................................................................................................................................57

dell
文本框
dell
新建图章
Page 4: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 1

CHAPTER-1

PROJECT OVERVIEW & CONTRACT PARTICULAR

Page 5: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 2

Name of the Project Padma Multipurpose Bridge project-River Training WorksContract

Location North Bank (Mawa side) & South Bank (Janjira side)

Client Bangladesh Bridge Authority(BBA)

Consultant Korea Expressway & Associates

Contractor Sinohydro Corporation Limited

Date of Project Awarded 26th Oct. 2014

Date of Contract Signing 10th Nov. 2014

Date of Commencement 31st Dec. 2014

Contract Duration

a) Original 1460 days

Defects Notification Period 365 days

Total Contract Amount

a) Original BDT: 87,078,141,446.97

Finance Resource The Government of the People’s Republic of Bangladesh

Foreign Currency USD $

Exchange Rate 1USD=78.25BDT

Scope of Work

The river training system consists of a guiding revetment

along both banks of the Padma River, extending upstream

and downstream from the bridge axis. The proposed length

of revetment along the North Bank (Mawa side) and South

Bank (Janjira side) is about 1.5km and 11.5km respectively.

Page 6: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 3

CHAPTER-2

MEMORABILIA

Page 7: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 4

Claim Report for the Emergency Repairing Cost of the Temporary Jetty on the South Bankwas submitted on 1st November, 2015;

Request for Assistance on Indian Stone Supply was submitted on 1st November, 2015;

Interim Payment Application No.08 was submitted on 1st November, 2015;

Recharge Cards for the Month of November of 2015 was delivered on 3rd November,2015;

Monthly Environmental Report No.8 for the Month of October 2015 was submitted on 3rdNovember, 2015;

Monthly Healthy and Safety Report No.8 for the Month of October 2015 was Submittedon 3rd November, 2015;

Accident Report of Injured Labor dated 25th Oct. 2015 was submitted on 4th November,2015;

Supplementary Information of Dredged Materials Management Plan was submitted on 4thNovember, 2015;

Supplementary Information of Seven Ring Cement (Khulna Factory) was Submitted on 6thNovember, 2015;

Dredging Plan of the Janjira RTW Trial Section was submitted on 6th November, 2015;

Progress Meeting between BBA, Consultant and Contractor (SINOHYDRO)representatives was held on 7th November, 2015 in SA1;

Request for Practical Access to and Possession of Construction Site at Mawa side wassubmitted on 9th November, 2015;

Fifth Joint Interim Survey Report Initial Dredging Area from Sta. 7+540 to Sta. 8+260 inSouth Bank was submitted on 9th November, 2015;

Proposal of the Fourth Geo-textile Material Supplier was submitted on 10th November,2015;

Method Statement of Pre-Construction Geophysical Survey was submitted on 10thNovember, 2015;

SINOHYDRO Dredger J06 & J07 Technical specifications 7025MP were submitted on10th November, 2015;

Monthly Progress Report No.9 for October 2015 was submitted on 11st November, 2015;

Accident Report on the Injured Labor Happening at Ya Sheng CC Block Molding Machinedated 9th November, 2015 was submitted on 13th November, 2015;

Request for Approval of CC Block Manufactured prior to 30th September 2015 wassubmitted on 14th November, 2015;

HSE Training Report of SINOHYDRO was submitted on 15th November, 2015;

Page 8: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 5

Final Copy of Construction Environmental Action Plan (Eighth Edition) was submitted on16th November, 2015;

Request to Stop the Operation of Dredgers from other Parties within RTW ConstructionSite for the Smooth Execution of this Project was submitted on 20th November, 2015;

Progress Meeting between BBA, Consultant and Contractor (SINOHYDRO)representatives was held on 21st November, 2015 in SA1;

Water Quality Test Report from Outlet of Disposal Area in Kawrakandi was submitted on21st November, 2015;

Response to Janjira Side Dredge Disposal - embankment collapse was submitted on 21stNovember, 2015;

Test Reports IX of 400 GSM Geo-bags and 600 GSM Geo-bags was submitted on 24thNovember, 2015;

Survey Report (BIWTA) was submitted on 24thNovember, 2015;

Inspection Report III on Noise Measurement of Mawa Site was submitted on 25thNovember, 2015;

Supplementary Information of the Fourth Geo-textile Material Supplier was submitted on25thNovember, 2015;

Application of Vessels Removal in Mawa RTW Construction Area was submitted on 27thNovember, 2015.

SINOHYDRO’s Suggestion regarding the Works Programme of Mawa after RevisedDesign was submitted on 27th November, 2015.

Revised Construction Programme of PMBP-RTW was submitted on 27th November, 2015.

Response to CSC’s Instruction to Commence Preparations for Mawa RTW to beconstructed during the 2015/2016 Dry Season was submitted on 28th November, 2015.

Written Confirmation of BBA’s Oral Instruction Concerning Honorable Prime Minister’sVisit on PMBP-RTW was submitted on 29th November, 2015.

Air Quality Monitoring Report of Mawa and Janjira Side was submitted on 30th November,2015.

Survey Drawings of Slope in Janjira Trail Section by Dredger J07 was submitted on 30thNovember, 2015.

Page 9: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 6

CHAPTER-3

PROGRESS OF WORK IMPLEMENTATION

Page 10: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 7

3.1 Accomplishment Summary

SINOHYDRO Dredger J07 construction team started to execute the permanent dredgingworks at South Bank (Sat. 0-300m to Sta. 0-500m of Trial Section) on 9th November, 2015,intending to obtain the experience of forming a stable design slope (slope ratio 1:6), so thatto be prepared to the further permanent works in the future.

SINOHYDRO currently has ten CC Block production lines, including eight moldingmachine production lines producing 400 * 400 * 400mm CC Block in three constructionyards (Mawa, Majhikandi and Kaorakandi), and two manual production lines producing400 * 400 * 300mm CC Block respectively in North Bank (Mawa Side) and South Bankdownstream (Majhikandi). At present, the RTW Contractor has accumulated a wealth ofexperience after five months of production: the workmanship of producing CC Block isquite mature and successful, having a group of experienced site managing personnel andlocal labor. As a result, the quality of produced CC Block can be ensured, at the same time,the production rates has been gradually increased with the highest daily productionreaching to 18,900 nos. per day.

The rock ripraps, coarse aggregates and fine aggregates are continuously delivered to thestockyards in North Bank (Mawa Side), South Bank (Majhikandi) and South Bankupstream area (Kaorakandi) subjecting to the procurement/production program so that toensure the production demand.

3.1.1 The volume of Construction

1) Quantity of Produced CC Block at Mawa Side (North Bank)

SLNo Type Up to Oct. This Month Accumulated Size

1 Mawa BP01- Manual 26,445 17,529 43,974

400x400x4002 Mawa BP02-QFT8 69,703 73,165 142,868

3 Mawa BP03-QFT8 - 63,382 63,382

Sub-total 96,148 154,076 250,224

4 Mawa BP01- Manual - 13,077 13,077 400x400x300

2) Quantity of Produced CC Block at Janjira Side (South Bank Downstream)

SL No Type Up to Oct. This Month Accumulated Size

1 BP01-WZY40 144,017 49,672 193,689400x400x400

2 BP02-QFT8 264,226 71,141 335,367

Page 11: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 8

3 BP03-Manual 57,408 32,729 90,137

4 BP04-QFT8 116,284 82,966 199,250

Sub-total 581,935 236,508 818,443

5 BP03-Manual - 17,106 17,106 400x400x300

3) Quantity of Produced CC Block at Kaorakandi (South Bank Upstream)

SL No Type Up to Oct. This Month Accumulated Size

1 Kaorakandi BP01-QFT8 0 28,233 28,233 400x400x400

4) Dredging Quantity of Janjira Dredging Area

SL No Description of work (This Month)

1

1) Dredger: Cutter suction dredger J07;2) Dredge Sections of Initial Dredging at Janjira side from Chainage 0-300 to Chainage

0-500;3) Disposal area: Temporary cofferdam from Chainage 0+100 to Chainage 0+550;4) According to Submittal of Survey Drawings of Slope in Janjira Trail Section by

Dredger J07, Estimated volume is 0.1Mm3

3.1.2 Survey Work

Site survey on Mawa Interim RTW area is preceding now, in the meantime, the followingwork is carried out as required by BBA and CSC.

1) On 27th October, 2015, the dredging quantity survey was conducted by usingmultiple-beam echosounder in the dredging area excavated by SINOHYDRO DredgerJ06;

2) On 29th October, 2015, in response to the requirement of Consultant, the CC Block wasdumped to the end area of South Bank downstream to be used in the testing survey byusing multiple-beam echosounder; and the GPS positioning equipment in DredgerSINOHYDRO J08 was calibrated at that day.

3) On 3rd November, 2015, the testing survey was conducted by using multiple-beamechosounder jointly with Consultant, and the acceptance survey of MBEC dredgingwork at South Bank was also conducted by using multiple-beam echosounder jointlywith Consultant at that day, then the the survey data was submitted to the Consultantand the Employer.

4) On 5th November, 2015, the boundary coordinates of dredged material disposal area atSouth Bank was surveyed and the survey data was submitted to the Consultant and theEmployer.

Page 12: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 9

5) From 8th to 10th November, 2015, a bathymetric survey was conducted by usingmultiple-beam echosounder in the South Bank downstream area (Sta. 0-300 to Sta.0-500) jointly with Consultant; and the setting out works was conducted in the cementpiles boundary line of North Bank construction site. Then the the survey data wassubmitted to the Consultant and the Employer.

6) On 14th November, 2015, the excavated slope in South Bank downstream area (Sta.0-300 to Sta. 0-700) was monitored and surveyed by using multiple-beamechosounder.

7) From 16th to 17th November, 2015, the RTW Contractor representatives accompaniedthe Employer and Consultant personnel to confirm the boundary piles of constructionarea at North Bank, the submitted the survey data to them. In the meanwhile, themultibeam echosounder was calibrated at both North South and South bank.

8) From 19th to 25th November, 2015, the original topography survey was conducted inthe company of Consultant, then the survey data was submitted to the Consultant andthe Employer.

3.1.3 Dredging Work

SINOHYDRO Dredger J07 construction team started to execute the permanent dredgingworks at South Bank (Sat. 0-300m to Sta. 0-500m of Trial Section) on 9th November, 2015and completed it on 27th November, 2015. The actual quantity is now under review and therelated joint survey report will be submitted the Employer and Consultant in December,2015.

3.1.4 Contractor’s Documents

1) Daily Report, Monthly Report have been submitted in due course.

2) Other Documents:

SL No Item SubmittedDate Letter No.

1 Interim Payment Application No.08 01-11-2015 SHCL-258-CSC

2 The Technical Proposals for theConstruction of Temporary Jetties 02-11-2015 SHCL-260-CSC

3 The Dredging Plan of the Janjira RTWTrial Section 06-11-2015 SHCL-264-CSC

4The Fifth Joint Interim Survey ReportInitial Dredging Area from Sta. 7+540 toSta.8+260 in South Bank

09-11-2015 SHCL-265-CSC

5Request for Practical Access to andPossession of Construction Site at Mawaside

09-11-2015 SHCL-179-BBA

Page 13: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 10

6 TheMethod Statement of Pre-ConstructionGeophysical Survey 10-11-2015 SHCL-267-CSC

7Request for Approval of CC BlockManufactured prior to 30th September2015

14-11-2015 SHCL-269-CSC

8

Request to Stop the Operation of Dredgersfrom other Parties within RTWConstruction Site for the SmoothExecution of this Project

20-11-2015 SHCL-184-BBA

9 The Test Reports IX of 400 GSMGeo-bags and 600 GSM Geo-bags 24-10-2015 SHCL-273-CSC

10 The Supplementary Information of theFourth Geo-textile Material Supplier 25-11-2015 SHCL-276-CSC

11 Application of Vessels Removal in MawaRTW Construction Area 27-11-2015 SHCL-186-BBA

12Sinohydro’s Suggestion regarding theworks programme of Mawa after RevisedDesign

27-11-2015 SHCL-277-CSC

13 The Revised Construction Programme ofPMBP-RTW 27-11-2015 SHCL-278-CSC

14

Response to CSC’s Instruction toCommence Preparations for Mawa RTWto be Constructed during the 20152016Dry Season

28-11-2015 SHCL-279-CSC

15Written Confirmation of BBA’s OralInstruction Concerning Honorable PrimeMinister’s Visit on PMBP-RTW

29-11-2015 SHCL-191-BBA

16 The Survey Drawings of Slope in JanjiraTrail Section by Dredger J07 30-11-2015

Page 14: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

SINOHYDRO CORPORATION LIMITED

Construction Works Schedule(First Draft)Construction Works Schedule(First Draft)P j P d M l i B id P j Ri T i i W k

2012

Project :Padma Multipurpose Bridge Project River Training Works2016 2017 2018Amount 20152012

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48WeightedProgress

2016 2017 2018Sum

AssignedWeight

ActualProgessDescription Unit Q'ty

Amount(BDT/ Assigned

Weight (%)

2015

Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18

g(%)

g(%)

g(%)

p Q y (million)

Weight (%)

1. Preliminary and General 100

6.77 0.90 13.39 13.64 14.42 13.83 13.81 0.09 0.09 0.09 1.76 6.17 0.09 0.09 0.09 0.09 0.09 5.75 0.09 0.09 0.09 0.09 2.18 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 2.18 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 1.82 0.50 0.08 100.000.72 0.10 1.43 1.46 1.54 1.48 1.47 0.01 0.01 0.01 0.19 0.66 0.01 0.01 0.01 0.01 0.01 0.61 0.01 0.01 0.01 0.01 0.23 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.23 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.19 0.05 0.01 10.67 79.97 8.531) Contractor Requirements Sum 1 6 663 10 67% 10.67%

3.51 2.37 0.52 0.17 0.15 0.00 0.29 0.12 1.13 0.15 0.13 8.5332.91 22.18 4.91 1.60 1.38 0.00 2.71 1.12 10.55 1.39 1.21 79.97

0 26 0 26 1 28 15 09 18 73 17 12 10 82 2 79 2 65 0 60 2 84 4 77 0 60 0 60 0 60 0 60 0 60 0 60 0 60 0 60 0 60 1 00 0 60 0 60 0 60 0 60 0 60 0 60 0 60 0 60 0 60 0 60 0 60 1 00 0 60 0 60 0 60 0 60 0 60 0 60 0 60 1 00 0 60 0 60 0 60 0 60 0 60 0 60 100.00

79.97 8.531) Contractor Requirements Sum 1 6,663 10.67% 10.67%

0.26 0.26 1.28 15.09 18.73 17.12 10.82 2.79 2.65 0.60 2.84 4.77 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 1.00 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 1.00 0.60 0.60 0.60 0.60 0.60 0.60 0.60 1.00 0.60 0.60 0.60 0.60 0.60 0.60 100.000.00 0.00 0.01 0.10 0.12 0.11 0.07 0.02 0.02 0.00 0.02 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.65

0.085 0.029 0.145 0.002 0.000 0.006 0.002 0.015 0.016 0.302) Engineer and Employer Services Sum 1 406 0.65% 0.65% 46.24 0.30

13.02 4.52 22.31 0.32 0.07 0.93 0.30 2.31 2.46 46.24

2 L d P ti E ti d E th k

4 24 8 98 3 99 4 67 3 99 10 97 10 97 13 77 13 77 4 25 4 33 10 19 5 86 100 00

2. Land Preparation, Excavation and Earthworks90

4.24 8.98 3.99 4.67 3.99 10.97 10.97 13.77 13.77 4.25 4.33 10.19 5.86 100.000.01 0.01 0.01 0.01 0.01 0.01 0.01 0.02 0.02 0.01 0.01 0.01 0.01 0.13

0.01 0.01 0.021) Land Clearing and Preparation Sum 1 82 0.13% 0.13% 11.47 0.020.01 0.01 0.024.24 7.23 11.47

1.46 4.08 4.27 4.27 4.27 2.56 6.24 7.26 3.48 3.48 9.27 10.89 6.77 5.30 4.52 8.72 13.16 100.000 01 0 02 0 02 0 02 0 02 0 01 0 03 0 04 0 02 0 02 0 05 0 05 0 03 0 03 0 02 0 04 0 06 0 490.01 0.02 0.02 0.02 0.02 0.01 0.03 0.04 0.02 0.02 0.05 0.05 0.03 0.03 0.02 0.04 0.06 0.49

0.01 0.01 0.021.46 2.49 3.95

2) Excavation and Earthworks Sum 1 306 0.49% 0.49% 3.95 0.02

1.46 2.49 3.959.50 14.38 14.38 7.90 6.39 4.48 4.48 4.48 4.48 4.48 3.42 6.21 6.21 3.42 3.42 0.22 0.90 0.61 0.61 100.000.02 0.03 0.03 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.19 0.00 0.003) Dry Filling cu m 660 000 118 0 19% 0.19%0.00

0.000.70 0.70 0.70 0.91 0.91 0.91 0.91 0.91 1.28 1.28 1.28 1.28 1.28 0.00 2.81 2.77 2.81 2.81 2.69 3.42 3.32 3.36 3.32 3.36 3.36 0.92 3.18 3.17 3.17 1.29 1.29 2.29 2.29 2.29 2.16 2.16 2.16 4.52 6.50 8.14 7.43 100.00

0.00 0.00

4) Dredging and Reclamation(Including

3) Dry Filling cu.m 660,000 118 0.19% 0.19%80

0.70 0.70 0.70 0.91 0.91 0.91 0.91 0.91 1.28 1.28 1.28 1.28 1.28 0.00 2.81 2.77 2.81 2.81 2.69 3.42 3.32 3.36 3.32 3.36 3.36 0.92 3.18 3.17 3.17 1.29 1.29 2.29 2.29 2.29 2.16 2.16 2.16 4.52 6.50 8.14 7.43 100.000.15 0.15 0.15 0.20 0.20 0.20 0.20 0.20 0.28 0.28 0.28 0.28 0.28 0.00 0.62 0.61 0.62 0.62 0.59 0.75 0.73 0.74 0.73 0.74 0.74 0.20 0.70 0.70 0.70 0.28 0.28 0.50 0.50 0.50 0.47 0.47 0.47 0.99 1.43 1.79 1.64 22.01

0.026 0.128 0.117 0.093 0.098 0.027 0.49

4) Dredging and Reclamation(Includingdredging & reclamation work at north bank: Sum 1 13,739 22.01% 22.01% 2.22 0.49

0.12 0.58 0.53 0.42 0.45 0.12 2.22Mawa Side)3 R t t d C t P t ti C t ti3. Revetment and Crest Protection Construction

1.44 1.88 1.88 2.06 16.07 18.37 19.11 15.45 13.42 1.49 0.94 1.60 1.72 1.72 1.49 1.37 100.000.05 0.06 0.06 0.07 0.52 0.60 0.62 0.50 0.44 0.05 0.03 0.05 0.06 0.06 0.05 0.04 3.24

0 265 0 112 0 020 0 006 0.401) North Bank Sum 1 2,026 3.24% 3.24% 12.43 0.400.265 0.112 0.020 0.006 0.408.18 3.46 0.61 0.18 12.43

0.10 1.62 2.84 2.98 2.41 1.98 0.29 0.20 1.67 3.96 4.83 5.14 4.02 3.50 0.95 0.86 0.35 0.35 0.35 0.49 2.35 4.78 5.63 5.71 4.06 3.43 0.98 0.93 16.62 16.62 100.00

)70

0.02 0.25 0.44 0.46 0.37 0.30 0.04 0.03 0.26 0.61 0.74 0.79 0.62 0.54 0.15 0.13 0.05 0.05 0.05 0.08 0.36 0.73 0.86 0.88 0.62 0.53 0.15 0.14 2.55 2.55 15.360.000 00

0.00 0.002) South Bank Sum 1 9,588 15.36% 15.36%

0.0033.33 33.33 33.33 100.000.52 0.52 0.52 1.56 0 00 0 003) Materials for Employer Sum 1 972 1 56% 1 56%0.00

0.00

0.00 0.003) Materials for Employer Sum 1 972 1.56% 1.56%

4. Offtakes and End Treatment7.43 7.43 16.32 8.48 0.34 30.00 30.00 100.000 02 0 02 0 04 0 02 0 00 0 08 0 08 0 261) S th B k Offt k 5 162 0 26%

600.02 0.02 0.04 0.02 0.00 0.08 0.08 0.26

0.000.00

1) South Bank Offtakes nr 5 162 0.26% 0.26% 0.00 0.00

1.15 3.57 3.45 5.36 1.79 1.79 1.79 3.74 3.74 3.74 3.74 7.30 7.30 3.56 3.56 3.56 6.09 6.09 6.09 7.66 7.89 1.99 2.78 1.24 1.00 100.000.06 0.20 0.19 0.30 0.10 0.10 0.10 0.21 0.21 0.21 0.21 0.40 0.40 0.20 0.20 0.20 0.34 0.34 0.34 0.42 0.44 0.11 0.15 0.07 0.06 5.51

0 00 0.00 0.002) End treatment Sum 1 3,442 5.51% 5.51%0.000.00

)

5. Materials0.54 0.65 0.78 0.78 0.78 0.78 2.39 5.34 5.34 5.34 5.34 5.34 1.82 1.82 1.82 1.36 1.36 1.36 1.82 1.82 1.82 2.29 2.29 2.29 2.16 2.16 2.16 1.26 1.26 1.26 1.68 1.68 1.68 1.68 1.68 1.68 2.71 2.71 2.71 2.71 2.71 2.71 2.71 2.71 2.71 100.000.06 0.07 0.08 0.08 0.08 0.08 0.26 0.58 0.58 0.58 0.58 0.58 0.20 0.20 0.20 0.15 0.15 0.15 0.20 0.20 0.20 0.25 0.25 0.25 0.24 0.24 0.24 0.14 0.14 0.14 0.18 0.18 0.18 0.18 0.18 0.18 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 10.941) Rock Rip Rap cu m 928 350 6 828 10 94% 10 94% 10 47 1 15

50

0.044 0.048 0.097 0.268 0.224 0.109 0.199 0.156 1.150.40 0.44 0.89 2.45 2.05 0.99 1.82 1.43 10.47

0 52 0 52 0 77 1 57 1 57 1 57 1 57 1 41 1 41 1 41 1 41 1 41 1 66 1 66 1 66 1 66 1 38 1 38 1 38 1 66 1 66 1 66 1 66 1 66 1 66 2 83 2 83 2 83 2 12 2 12 2 12 2 83 2 83 2 83 2 83 2 83 2 83 3 58 3 58 3 58 3 58 3 58 3 58 3 58 3 58 3 58 100 00

1) Rock Rip Rap cu.m 928,350 6,828 10.94% 10.94% 10.47 1.15

0.52 0.52 0.77 1.57 1.57 1.57 1.57 1.41 1.41 1.41 1.41 1.41 1.66 1.66 1.66 1.66 1.38 1.38 1.38 1.66 1.66 1.66 1.66 1.66 1.66 2.83 2.83 2.83 2.12 2.12 2.12 2.83 2.83 2.83 2.83 2.83 2.83 3.58 3.58 3.58 3.58 3.58 3.58 3.58 3.58 3.58 100.000.03 0.03 0.05 0.09 0.09 0.09 0.09 0.08 0.08 0.08 0.08 0.08 0.10 0.10 0.10 0.10 0.08 0.08 0.08 0.10 0.10 0.10 0.10 0.10 0.10 0.17 0.17 0.17 0.13 0.13 0.13 0.17 0.17 0.17 0.17 0.17 0.17 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 6.01

0.013 0.037 0.189 0.028 0.000 0.093 0.055 0.41 6.90 0.412) 800kg Geobags 800kg nr 3,907,500 3,751 6.01% 6.01%

0.21 0.61 3.15 0.46 0.00 1.54 0.92 6.901.26 1.26 0.60 3.29 3.29 3.29 3.29 2.75 2.75 2.75 2.75 2.75 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 2.28 0.48 3.50 3.50 3.50 3.50 3.50 4.26 4.26 4.26 4.26 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 100.000 07 0 07 0 03 0 18 0 18 0 18 0 18 0 15 0 15 0 15 0 15 0 15 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 03 0 19 0 19 0 19 0 19 0 19 0 23 0 23 0 23 0 23 0 03 0 03 0 03 0 03 0 03 0 03 0 03 0 03 0 03 0 03 0 03 5 343) 12 k G b 12 k 1 26 00 3 332 34% 0.07 0.07 0.03 0.18 0.18 0.18 0.18 0.15 0.15 0.15 0.15 0.15 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.03 0.19 0.19 0.19 0.19 0.19 0.23 0.23 0.23 0.23 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 5.34

0.047 0.141 0.047 0.117 0.105 0.121 0.145 0.062 0.790.89 2.64 0.89 2.20 1.97 2.26 2.71 1.16 14.72

3) 125kg Geobags 125kg nr 17,267,500 3,332 5.34% 5.34% 14.72 0.79

0.81 0.81 0.39 1.57 3.85 3.85 3.85 3.85 2.25 0.51 2.05 4.60 4.60 4.60 4.60 4.60 0.86 3.46 9.24 9.24 9.24 5.59 5.59 1.00 4.49 4.49 100.000.02 0.02 0.01 0.04 0.09 0.09 0.09 0.09 0.05 0.01 0.05 0.11 0.11 0.11 0.11 0.11 0.02 0.08 0.22 0.22 0.22 0.14 0.14 0.02 0.11 0.11 2.43

0 000 0 003 0 006 0 005 0 01 0.61 0.014) Sand(For Filling of Geo-bags and Bedding Layer) cu.m 4,224,519 1,517 2.43% 2.43%40

0.000 0.003 0.006 0.005 0.010.02 0.13 0.26 0.21 0.61

0.89 0.90 0.90 0.90 2.15 2.15 2.15 2.15 2.15 2.15 2.15 1.11 1.11 1.11 1.11 1.11 1.58 1.58 1.58 1.58 1.58 1.86 1.86 2.96 2.96 2.29 2.29 2.29 3.01 3.01 3.01 3.01 3.01 3.01 2.68 3.83 3.83 3.83 3.83 3.83 3.83 3.83 3.83 100.00

) g g g y , , ,

0.05 0.05 0.05 0.05 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.06 0.06 0.06 0.06 0.06 0.08 0.08 0.08 0.08 0.08 0.10 0.10 0.16 0.16 0.12 0.12 0.12 0.16 0.16 0.16 0.16 0.16 0.16 0.14 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 5.340.004 0.014 0.027 0.034 0.090 0.068 0.186 0.086 0.510 07 0 26 0 51 0 64 1 69 1 27 3 49 1 61 9 53

5) Cement t 281,176 3,336 5.34% 5.34% 9.53 0.51

0.07 0.26 0.51 0.64 1.69 1.27 3.49 1.61 9.531.12 1.31 1.49 1.68 2.61 2.61 2.61 2.61 2.61 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 1.39 2.96 2.96 2.96 2.96 2.29 2.29 2.29 3.07 3.07 3.07 3.07 3.07 3.06 3.06 3.06 3.06 3.06 3.06 3.06 3.06 3.06 3.06 100.000.08 0.09 0.11 0.12 0.19 0.19 0.19 0.19 0.19 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.22 0.22 0.22 0.22 0.17 0.17 0.17 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 7.27 21 47 1 566) Aggregate cu m 1 136 180 4 541 7 27% 7 27%

0.017 0.127 0.277 0.323 0.328 0.175 0.226 0.090 1.560.23 1.74 3.80 4.44 4.50 2.40 3.11 1.24 21.47

0 61 0 61 0 61 0 99 3 20 3 20 3 20 3 20 3 20 1 79 1 93 1 93 1 93 1 62 2 40 1 62 1 93 1 93 1 93 1 93 1 93 2 69 2 56 2 56 2 56 2 62 3 36 2 56 2 89 2 89 2 89 2 89 2 76 2 94 2 38 2 38 2 38 2 58 2 66 2 58 2 38 2 38 2 38 100 00

21.47 1.566) Aggregate cu.m 1,136,180 4,541 7.27% 7.27%

0.61 0.61 0.61 0.99 3.20 3.20 3.20 3.20 3.20 1.79 1.93 1.93 1.93 1.62 2.40 1.62 1.93 1.93 1.93 1.93 1.93 2.69 2.56 2.56 2.56 2.62 3.36 2.56 2.89 2.89 2.89 2.89 2.76 2.94 2.38 2.38 2.38 2.58 2.66 2.58 2.38 2.38 2.38 100.000.01 0.01 0.01 0.01 0.03 0.03 0.03 0.03 0.03 0.02 0.02 0.02 0.02 0.01 0.02 0.01 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.03 0.02 0.03 0.03 0.03 0.03 0.02 0.03 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.90

0.018 0.037 0.006 0.067) Other Materials Sum 1 564 0.90% 0.90% 6.71 0.0630

2.00 4.05 0.67 6.71

6 Land Restoration North Bank Drainages 6. Land Restoration,North Bank Drainagesand Special Provisions

0.00 6.36 7.71 7.71 1.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.75 5.69 5.69 2.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.20 10.48 8.29 4.28 0.00 30.57 100.000.00 0.01 0.02 0.02 0.00 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.02 0.02 0.01 0.00 0.07 0.22

0 001) Land Restoration sq.m 1,094,500 140 0.22% 0.22% 0.00 0.000.000.00

25.00 25.00 25.00 25.00 100.00

1) Land Restoration q , ,

0.00 0.00 0.00 0.00 0.00450.000 00

0.00 0.002) North Bank Drainage Sum 1 3 0.0045% 0.00%200.00

3.45 10.41 23.63 18.22 44.29 100.000.00 0.00 0.01 0.00 0.01 0.02646 0 00 0 003) Special Provisions Sum 1 17 0 03% 0 03%0.00

0.00

0.00 0.003) Special Provisions Sum 1 17 0.03% 0.03%

7. Works Trial Section20.00 20.00 20.00 20.00 20.00 100.000 01 0 01 0 01 0 01 0 01 0 061) Additional Costs associated with the 0.01 0.01 0.01 0.01 0.01 0.06

0.000.00

1) Additional Costs associated with theconstruction of the Trial Section Sum 1 39 0.06% 0.06% 0.00 0.00

10

8. Special Maintenance of Works33.33 33.33 33.33 100.001) S i l M i t f RTW

8. Special Maintenance of Works

0.03 0.03 0.03 0.080.000 00

1) Special Maintenance of RTW(Defects Notification Period) Sum 1 48 0.08% 0.08% 0.00 0.00

0.003.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 100.000.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 1.309 Dayworks and Provisional Sums Sum 1 813 1 30% 1 30% 0 02 0 00

0.0000 0.0000 0.0002 0.000.0028 0.00 0.02 0.02

9. Dayworks and Provisional Sums Sum 1 813 1.30% 1.30% 0.02 0.000

Monthly Progress Rate(%) 0.00 0.72 0.10 1.60 1.79 1.87 2.24 2.20 0.70 0.57 0.91 1.69 2.27 2.33 2.65 2.65 2.07 1.98 1.75 1.04 0.97 0.60 1.39 1.68 1.69 2.30 2.39 2.74 2.38 2.73 2.34 1.90 1.82 1.29 1.96 2.35 2.74 2.73 2.57 2.88 2.60 2.24 1.85 1.71 1.54 2.05 3.33 6.19 5.89 100.00 Accumulated Progress Rate(%) 0. 00 0 72 0 82 2 42 4 22 6 09 8 33 10 53 11 23 11 80 12 71 14 40 16 67 19 00 21 65 24 30 26 36 28 35 30 10 31 14 32 12 32 71 34 11 35 79 37 48 39 78 42 17 44 91 47 29 50 03 52 36 54 27 56 09 57 39 59 34 61 69 64 43 67 16 69 73 72 61 75 20 77 45 79 29 81 00 82 54 84 59 87 92 94 11 100 00Accumulated Progress Rate(%) 0.72 0.82 2.42 4.22 6.09 8.33 10.53 11.23 11.80 12.71 14.40 16.67 19.00 21.65 24.30 26.36 28.35 30.10 31.14 32.12 32.71 34.11 35.79 37.48 39.78 42.17 44.91 47.29 50.03 52.36 54.27 56.09 57.39 59.34 61.69 64.43 67.16 69.73 72.61 75.20 77.45 79.29 81.00 82.54 84.59 87.92 94.11 100.00

Achieved (%) 0.00 3.51 2.45 0.82 0.60 0.70 0.78 1.13 1.00 1.60 1.07 0.60 14.25 62,433 100.00% 100.00% 14.25

Achieved Cumulative (%) 0.00 3.51 5.96 6.78 7.38 8.08 8.86 9.99 10.99 12.59 13.65 14.25

Achieved Rate(%) 0% 427% 246% 161% 121% 97% 84% 89% 93% 99% 95% 86%Achieved Rate(%) 0% 427% 246% 161% 121% 97% 84% 89% 93% 99% 95% 86%452 61 1,001 1,119 1,168 1,401 1,374 436 356 568 1,053 1,419 1,458 1,652 1,654 1,289 1,239 1,092 652 608 373 871 1,050 1,055 1,437 1,493 1,710 1,487 1,707 1,460 1,188 1,139 808 1,222 1,466 1,708 1,707 1,604 1,795 1,620 1,401 1,154 1,065 963 1,278 2,076 7,544 62,433 Monthly Progress Amount(Million BDT) ,452 513 1,514 2,633 3,800 5,201 6,575 7,012 7,367 7,935 8,988 10,407 11,864 13,516 15,170 16,460 17,699 18,790 19,442 20,050 20,423 21,294 22,344 23,399 24,836 26,329 28,040 29,526 31,233 32,693 33,881 35,020 35,828 37,050 38,516 40,224 41,932 43,536 45,331 46,951 48,352 49,506 50,571 51,534 52,812 54,888 62,433 62,433

A hi d I t i P t (Milli BDT)

y gCumulative Progress Amount(Million BDT)

13,062 2,193 1,531 522 641 274 158 672 19,053 13,062 15,254 15,254 16,785 17,308 17,308 17,949 17,949 18,223 18,381 19,053

Achieved Interim Payment (Million BDT)Cumulative Achieved Amount (Million BDT) 13,062 15,254 15,254 16,785 17,308 17,308 17,949 17,949 18,223 18,381 19,053

LEGEND: Planned S-CURVE: Planned

Cumulative Achieved Amount (Million BDT)

Achieved Achieved

dell
打字机文本
dell
打字机文本
Page 11
dell
打字机文本
dell
打字机文本
dell
打字机文本
Page 15: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 12

3.3 Overall Progress

The assessed overall progress for each construction contract package calculated againstprogram is given in the following:

Analysis of “S”-Curve for RTW by SINOHYDRO

SL.No.

Physical Progresson November, 2015

Physical Progressup to November, 2015

Variance (%)MonthlyTarget (%)

MonthlyAchieved (%)

CumulativeTarget (%)

CumulativeAchieved (%)

1 1.69% 1.07% 14.40% 13.65% -0.75%

Based on the analysis of ‘S’ Curve and take a comprehensive consideration, the plannedproduction value was not achieved this month, and the main reason for that is Consultant didnot issue order about Permanent RTW works to be Constructed during the 2015/2016 DrySeason.

3.4 Status List of Hand-Over WorkNone.

Page 16: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 13

3.5 Accomplishment as BOQ

Bill No.1 Preliminary and General:

Item Description Unit Quantity Previous This Month Remarks

1.1 Contractual Requirements

1.1.1 performance Bond sum 1 1 0

1.1.2 Insurance of Works sum 1 1 0

1.1.3 Insurance of Contractor’s Equipment sum 1 0.25 0

1.1.4 Third Party Insurance sum 1 1 0

1.1.5 Insurance against Accident to Workmen sum 1 0.25 0

1.1.6 Compliance with Conditions of Contract not includedelsewhere sum 1 0.5135 0.0125

1.2 Specified Requirements

1.2.1 Setting out and Bankline Surveys sum 1 0.34 0

1.2.2 Bathymetry surveys for monitoring of apronperformance and river planform sum 1 0.168 0

1.2.3 Pre-construction sub-surface investigations sum 1 0 0

1.2.4 Diving Team(s) (personnel, equipment, support,accommodation, etc)

team*month 48 0 0

1.2.5 Sign boards sum 1 1 0

1.2.6 Progress Photographs and Video Record includingmonitoring videos during revetment construction month 48 9 1

1.2.7 Prepare Construction Environmental Action Plan sum 1 0 1

Page 17: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 14

Item Description Unit Quantity Previous This Month Remarks

1.2.8 Implement Construction Environmental Action Plan month 60 7 1

1.2.9 Provide and establish water level gauging stations nr 2 0.8 0

1.2.10 Operate and maintain water level gauging stations unit*month 120 0 0

1.2.11 Operation and Maintenance Manuals includingAs-Built drawings sum 1 0 0

1.2.12 Compliance with specified requirements not includedelsewhere sum 1 0 0

1.3 Contractor’s Mobilisation

1.3.1 Contractor’s offices, laboratories, stores, workshopsand accommodation sum 1 0.82 0.01

1.3.2 Contractor’s berthing facilities sum 1 0.82 0.005

1.3.3 Concrete block production, storage, handling anddelivery facilities sum 1 0.77 0.03

1.3.4 Geobag production, storage, filling, handling anddelivery facilities sum 1 0.724 0

1.3.5 Rip Rap storage, handling and delivery facilities sum 1 0.82 0.005

1.3.6 Dredging plant and equipment sum 1 1 0

1.3.7 Earthworks plant and equipment sum 1 1 0

1.3.8

Plant and equipment required for Ground Treatmentworks (stone columns) [Provisional Item to beconfirmed when BBA has made decision as to thenature and extent (if any) of Ground Treatment worksto be included in the Contract scope of works]

sum 1 0 0

1.3.9 All other plant, equipment, small tools and facilitiesnot covered above sum 1 0 0

Page 18: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 15

Item Description Unit Quantity Previous This Month Remarks

1.4 Contractor’s Demobilization 0 0

1.4.1 Contractor’s offices, laboratories, stores, workshopsand accommodation sum 1 0 0

1.4.2 Contractor’s berthing facilities sum 1 0 0

1.4.3 Concrete block production, storage, handling anddelivery facilities sum 1 0 0

1.4.4 Geobag production, storage, filling, handling anddelivery facilities sum 1 0 0

1.4.5 Rock Rip Rap storage, handling and delivery facilities sum 1 0 0

1.4.6 Dredging plant and equipment sum 1 0 0

1.4.7 Earthworks plant and equipment sum 1 0 0

1.4.8

Plant and equipment required for Ground Treatmentworks (stone columns) [Provisional Item to beconfirmed when BBA has made decision as to thenature and extent (if any) of Ground Treatment worksto be included in the Contract scope of works]

sum 1 0 0

1.4.9 All other plant, equipment, small tools and facilitiesnot covered above sum 1 0 0

1.5 Contractor’s Site Access 0 0

1.5.1Provide, maintain and remove on completion all siteaccess requirements to enable access to undertake theworks by land or water.

month 60 0 0

Page 19: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 16

Item Description Unit Quantity Previous This Month Remarks

1.6 Engineer’s Mobile Site Laboratory

1.6.1 Provide Engineer’s mobile site laboratory nr 2 1 0

1.6.2Provide, install and maintain laboratory furnishings,equipment and built-in fittings in the Engineer’smobile site laboratory

nr 2 0 0

1.6.3 Move and re-establish mobile site laboratory to suitworks requirements as directed by the Engineer

lab*move 10 0 0

1.6.4 Provide consumables and maintain all services toEngineer’s mobile site laboratory

lab*month 96 0 0

1.6.5 Supply of Standards and Codes as specified sum 1 0 1

1.7 Engineer’s Communications and Survey Equipment

1.7.1 Provide communications facilities sum 1 1 0

1.7.2 Maintain communications facilities month 60 10 1

1.7.3 Provide land survey equipment, software andconsumables sum 1 0 0

1.7.4 Provide hydrographic and bathymetric surveyequipment, software and consumables sum 1 1 0

1.7.5 Provide and install GPS Reference System equipment,software and consumables sum 1 1 0

1.7.6 Operate and maintain all survey and GPS referencesystem equipment month 48 9 1

1.7.7 Training of Engineer’s and Employer’s personnel nr 8 8 0

Page 20: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 17

Item Description Unit Quantity Previous This Month Remarks

1.8 Engineer’s Transport

1.8.1 7 seater LWB 4WD Station Wagon nr 3 3 0

1.8.2 5 seater 4WD Double Cab Pickup nr 12 0 0

1.8.3 12 seater Minibus nr 1 1 0

1.8.4 Enduro motorbike nr 3 0 0

1.8.5 6m - 8m Survey Vessel 6~8m nr 1 0 0

1.8.6 6m Work Boat 6m nr 6 4 2

1.8.7 Maintain and operate station wagon, pickup andminibus

vehicle*month 864 8 2

1.8.8 Maintain and operate motorbikes vehicle*month 162 0 0

1.8.9 Maintain and operate survey vessel boat*month 60 4 0

1.8.10 Maintain and operate workboats boat*month 324 12 4

1.8.11 Construct and maintain suitable berthing and relatedshore-based facilities for launches and workboats nr 2 0 0

1.9 Site PersonnelProvide the following site personnel to work underthe sole direction of the Engineer / Employer for up to12 hours per day and 7 days per week:

0 0

1.9.1 Experienced Laboratory Technicians man*month 216 12 3

1.9.2 Laboratory and Field Assistants man*month 108 23.71 3

1.9.3 Drivers man*month 864 8 2

1.9.4 Boatmen man*month 378 12 6

Page 21: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 18

BILL No.2 Land Preparation, Excavation

Item Description Unit Quantity Previous This Month Remarks

2.1 Land Clearing and Preparation

2.1.1

Clearance (and disposal off site) of areas prior to dryexcavation, reclamation or other fill operations fromtrees, debris and unsuitable material required to enableconstruction of the Permanent Works - North Bank

sq. m 323500 0 0

2.1.2 Clearance (and disposal off site) of brick kiln andmanufacturing debris - North Bank sum 1 0 0

2.1.3

Clearance (and disposal off site) of areas prior to dryexcavation, reclamation or other fill operations fromtrees, debris and unsuitable material required to enableconstruction of the Permanent Works - South Bankdownstream of Sta 3,000

sq. m 960500 160688.12 0

2.1.4

Clearance (and disposal off site) of areas prior to dryexcavation, reclamation or other fill operations fromtrees, debris and unsuitable material required to enableconstruction of the Permanent Works - South Bankupstream of Sta 3,000

sq. m 803500 80505.4 0

2.2 Excavation and Earthworks

2.2.1Top soil stripping (and Stockpiling) in areas to beoccupied by the permanent Works. Thickness notexceeding 150mm deep and stockpile - North Bank

sq.m 291000 0 0

2.2.2

Top soil stripping (and Stockpiling) in areas to beoccupied by the permanent Works. Thickness notexceeding 150mm deep and stockpile - South Bankdownstream of Sta 3000

sq.m 960500 160688.12 0

Page 22: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 19

Item Description Unit Quantity Previous This Month Remarks

2.2.3

Top soil stripping (and Stockpiling) in areas to beoccupied by the permanent Works. Thickness notexceeding 150mm deep and stockpile - South Bankupstream of Sta 3000

sq.m 803500 80505.4 0

2.2.4Dry Excavation and compaction to form slopes ofrevetment and stockpile or disposal of the material asper direction of the Engineer - North Bank

cu.m 200000 0 0

2.2.5

Dry Excavation and compaction to form slopes ofrevetment and stockpile or disposal of the material asper direction of the Engineer - South Bankdownstream of Sta 3000

cu.m 420000 0 0

2.2.6

Dry Excavation and compaction to form slopes ofrevetment and stockpile or disposal of the material asper direction of the Engineer - South Bank upstream ofSta 3000

cu.m 660000 0 0

2.2.7

Excavate, disposal, and replacement of unsuitablematerial as directed by the Engineer; including supplyand compaction of replacement material - Does notinclude North Bank Ponds (PROVISIONALQUANTITY)

cu.m 69600 0 0

2.2.8

Additional Cost for Dry Excavation in area of GroundTreatment (stone columns) - North Bank [ProvisionalItem to be confirmed when BBA has made decision asto the nature and extent (if any) of Ground Treatmentworks to be included in the Contract scope of works]

sq.m 26000 0 0

2.2.9

Additional Cost for Dry Excavation in area of GroundTreatment (stone columns) - South Bank [ProvisionalItem to be confirmed when BBA has made decision asto the nature and extent (if any) of Ground Treatmentworks to be included in the Contract scope of works]

sq.m 26000 0 0

Page 23: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 20

Item Description Unit Quantity Previous This Month Remarks

2.3 Dry Filling

2.3.1

Filling and compaction required to build up and formembankment and surface treatment foundation usingdredged material or similar material from othersources - North Bank

cu.m 190000 0 0

2.3.2

Filling and compaction required to build up and formembankment/crest protection and surface treatmentfoundation using dredged material or similar materialfrom other sources - South Bank downstream of Sta3000

cu.m 390000 0 0

2.3.3

Filling and compaction required to build up and formslopes of revetment and crest protection ,and surfacetreatment foundation using dredged material or similarmaterial from other sources - South Bank upstream ofSta 3000

cu.m 30000 0 0

2.3.4 Filling of North Bank Ponds and Depressions. cu.m 50000 0 0

2.4 Dredging and Reclamation

2.4.1

Dredge excavation to form slopes and platforms forconstruction of revetment, dredge material handling,stockpiling, and disposal as accepted by the Engineer,inclusive of any containment bunds required. - NorthBank

cu.m 9,920,000 0 0

2.4.2

Dredge excavation to form slopes and platforms forconstruction of revetment, dredge material handling,stockpiling, and disposal as accepted by the Engineer,inclusive of any containment bunds required. - SouthBank downstream of Sta 3000

cu.m 24,060,000 1436333 103862

Page 24: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 21

Item Description Unit Quantity Previous This Month Remarks

2.4.3

Dredge excavation to form slopes and platforms forconstruction of revetment, dredge material handling,stockpiling, and disposal as accepted by the Engineer,inclusive of any containment bunds required. - SouthBank upstream of Sta 3000

cu.m 25,500,000 0 0

2.4.4 Backfilling of trench after completion and acceptanceof protection works. - North Bank cu.m 5,185,000 0 0

2.4.5Backfilling of trench after completion and acceptanceof protection works. - South Bank downstream of Sta3000

cu.m 13,165,000 0 0

2.4.6Backfilling of trench after completion and acceptanceof protection works. - South Bank upstream of Sta3000

cu.m 13,570,000 0 0

2.4.7

Additional Cost for Dredging in area of GroundTreatment (stone columns) and completed piers- NorthBank [Provisional Item to be confirmed when BBAhas made decision as to the nature and extent (if any)of Ground Treatment works to be included in theContract scope of works]

sq.m 33,000 0 0

2.4.8

Additional Cost for Dredging in area of GroundTreatment (stone columns) and completed piers- SouthBank [Provisional Item to be confirmed when BBAhas made decision as to the nature and extent (if any)of Ground Treatment works to be included in theContract scope of works]

sq.m 33000 0 0

Page 25: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 22

Bill No.3 Revetment and Crest Protection Construction:

Item Description Unit Quantity Previous This Month Remarks

3.1.1Supply, Filling, Stockpiling and Placement of5 Layers of 800 kg geobags forming theLaunching Apron/Toe Apron 800kg.

nr 342500 40,957 0

3.1.2Supply, Filling, stockpiling and Placement of3 Layers 125 kg geobags forming the lowerslope revetment filter layer.

nr 1477500 471,247 0

3.1.3

Supply, Stockpiling and Placement ofminimum 900 mm thick layer of rock rip rapover geobag filter on lower slope revetment.900mm

sq.m 246000 0 0

3.1.4 Construction/Placement of RCAnchor Beam m 1700 0 0

3.1.5 Supply and Placement of geotextile filter sq.m 144500 0 0

3.1.6Supply, Stockpiling and Placement of Sandbedding Layer for CC-Blocks and othersurface treatments

sq.m 90000 0 0

3.1.7Supply, Stockpiling and Placement of BrokenBrick bedding layer (Low Water Transitionbelow 2.5m PWD)

sq.m 59500 0 0

3.1.8Supply, Stockpiling and Dumping of CCBlocks (Low Water Transition below 2.5 mPWD)

nr 785000 0 0

3.1.9 Supply and Filling of CC Block voids withconcrete (EL + 2.5m to EL + 1.5m) cu.m 2000 0 0

3.1.10

Supply, Stockpiling and Placement of UpperSlope CC Blocks (above 2.5 m PWD)including cast in situ anchors at transitions inslope, profile, alignment and treatments, andthe filling of joints with sand

sq.m 80000 0 0

Page 26: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 23

Item Description Unit Quantity Previous This Month Remarks

3.1.11 Supply, Stocking and Placement of brickchip/sand mix bedding layer sq.m 13000 0 0

3.1.12 Supply, Stockpiling and Placement of SandyLoam sq.m 21000 0 0

3.1.13 Supply, Stockpiling and Placement ofOpen-celled Concrete Pavers sq.m 6000 0 0

3.1.14 Supply, Stockpiling and Placement of BrickSurfacing for Road on embankment sq.m 13000 0 0

3.2.1Supply, Filling, Stockpiling and Placement of5 Layers of 800 kg geobags forming theLaunching Apron/Toe Apron 800kg

nr 862500 0 0

3.2.2Supply, Filling, Stockpiling and Placement of3 Layers 125 kg geobags forming the lowerslope revetment filter (Areas C & partial B)

nr 3310000 0 0

3.2.3

Supply, Stockpiling and Placement ofminimum 900 mm thick layer of rock rip rapover geobag filter on lower slope revetment(Areas C & Partial B)

sq.m 551500 0 0

3.2.4 Construction/Placement of RCAnchor Beam m 4100 0 0

3.2.5 Supply and Placement of geotextile filter sq.m 357000 0 0

3.2.6Supply, Stockpiling and Placement of Sandbedding Layer for CC-Blocks and othersurface treatments

sq.m 254000 0 0

3.2.7Supply, Stockpiling and Placement of BrokenBrick bedding layer (Low Water Transitionbelow 2.5m PWD)

sq.m 144000 0 0

3.2.8Supply, Stockpiling and Dumping of CCBlocks (Low Water Transition below 2.5 mPWD)

nr 1900000 0 0

Page 27: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 24

Item Description Unit Quantity Previous This Month Remarks

3.2.9 Supply and Filling of CC Block voids withconcrete (EL + 2.5m to EL + 1.5m) cu.m 4900 0 0

3.2.10

Supply, Stockpiling and Placement of UpperSlope CC Blocks (above 2.5 m PWD)including cast in situ anchors at transitions inslope, profile, alignment and treatments, andthe filling of joints with sand

sq.m 204500 0 0

3.2.11 Supply, Stockpiling and Placement of brickchip/sand mix bedding layer sq.m 22000 0 0

3.2.12 Supply, Stockpiling and Placement of SandyLoam sq.m 70500 0 0

3.2.13 Supply, Stockpiling and Placement ofOpen-celled Concrete Pavers sq.m 14500 0 0

3.2.14 Supply, Stockpiling and Placement of BrickSurfacing for Road on embankment sq.m 22000 0 0

3.3.1Supply, Filling, Stockpiling and Placement of5 Layers of 800 kg geobags forming theLaunching Apron/Toe Apron

nr 1225000 0 0

3.3.2Supply, Filling, Stockpiling and Placement of4 Layers 800 kg geobags forming the lowerslope revetment (Area A)

nr 1477500 0 0

3.3.3Supply, Filling, Stockpiling and Placement of3 Layers 125 kg geobags forming the lowerslope revetment filter (Areas partial B)

nr 1405000 0 0

3.3.4

Supply, Stockpiling and Placement ofminimum 900 mm thick layer of rock rip rapover geobag filter on lower slope revetment(Areas Partial B)

sq.m 234000 0 0

3.3.5 Construction/Placement of RCAnchor Beam m 8200 0 0

Page 28: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 25

Item Description Unit Quantity Previous This Month Remarks

3.3.6 Supply and Placement of geotextile filter sq.m 606500 0 0

3.3.7Supply, Stockpiling and Placement of Sandbedding Layer for CC-Blocks and othersurface treatments

sq.m 351500 0 0

3.3.8Supply, Stockpiling and Placement of BrokenBrick bedding layer (Low Water Transitionbelow 2.5m PWD)

sq.m 282000 0 0

3.3.9Supply, Stockpiling and Dumping of CCBlocks (Low Water Transition below 2.5 mPWD)

nr 3730000 0 0

3.3.10 Supply and Filling of CC Block voids withconcrete (EL + 2.5m to EL + 1.5m) cu.m 9800 0 0

3.3.11

Supply, Stockpiling and Placement of UpperSlope CC Blocks (above 2.5 m PWD)including cast in situ anchors at transitions inslope, profile, alignment and treatments, andthe filling of joints with sand

sq.m 680000 0 0

3.4.1 Supply and Stockpile Rock Rip Rap materialfor future use by Employer cu.m 100000 0 0

3.4.2 Supply and Stockpile 800 kg Geobags(unfilled) for future use by Employer nr 100000 0 0

Page 29: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 26

BILL No.9 Dayworks & Provisional SumItem Description Unit Quantity Previous This Month Remarks9.1.1 - operational day 30 0 09.1.2 - standing day 60 0 09.1.3 Expatriate Plant Operator Supervisor hour 300 0 09.1.4 Expatriate Heavy Plant Operator hour 300 0 09.1.5 Expatriate Light Plant Operator hour 300 0 09.1.6 Expatriate Tradesman hour 300 0 09.1.7 Expatriate Surveyor hour 300 0 09.1.8 Expatriate Survey Boat Operator hour 500 0 09.1.9 Expatriate Diver hour 200 0 09.1.10 Local Plant Operator hour 500 0 09.1.11 Local Surveyor hour 300 0 09.1.12 Local Diver hour 400 16 09.1.13 Local Survey Boat Operator hour 500 0 09.1.14 Local Survey Assistant hour 700 0 09.1.15 Local Driver hour 500 0 09.1.16 Local Skilled hour 500 16 09.1.17 Local Semi-skilled hour 500 358 459.1.18 Local Unskilled hour 500 0 09.1.19 Additional labour PS 0 09.1.20 SUB TOTAL 0 0

9.1.21 Allow -13-- percent of SUB TOTAL forContractor’s overhead, profit, etc.

9.2.1 Rock Rip Rap (D50 450 mm) cu.m 20000 0 09.2.2 Cast Concrete Blocks (400x400x200mm) unit 1000 0 09.2.3 Cast Concrete Blocks (400x400x300mm) unit 1000 0 09.2.4 Cast Concrete Blocks (400x400x400mm) unit 1000 0 09.2.5 Cast Concrete Blocks (600x600x600mm) unit 5000 0 09.2.6 Geotextile Filter (400 g/sq. m) sq.m 5000 0 09.2.7 Geotextile bag (filled) - 125 kg unit 100000 0 0

Page 30: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 27

Item Description Unit Quantity Previous This Month Remarks9.2.8 Geotextile bag (filled) - 800 kg unit 200000 0 09.2.9 Concrete (20 Mpa) cu.m 50 0 09.2.10 High yield Reinforcement (Grade 460) tonne 0.5 0 09.2.11 Mild Steel Reinforcement tonne 0.5 0 09.2.12 HD Galvanized Steel HD tonne 1 0 09.2.13 Temporary Formwork sq.m 100 0 09.2.14 Additional materials PS 0 0

9.2.15 Allow --13 - percent of SUB TOTAL forContractor’s overhead, profit, etc.

9.3.1 Dredging equipment complete withattendant plant - operational day 30 0 0

9.3.2 Dredging equipment complete withattendant plant - standing day 60 0 0

9.3.3 Tug for barge 500 to 750 HP hour 500 0 09.3.4 Flat top barge 1000t capacity hour 500 0 09.3.5 Excavator (Samsung 350 or equivalent) hour 500 0 109.3.6 Excavator (Samsung 210 or equivalent) hour 500 0 09.3.7 100t Crawler Crane hour 100 0 09.3.8 25t Mobile crane hour 100 0 09.3.9 30 cu.m/hr concrete batching plant hour 100 0 0

9.3.10 Hydrographic Survey Vessel (crew andequipment) hour 500 0 0

9.3.11 Geobag placement in launching aprons day 60 0 09.3.12 Rock Rip Rap placement in revetments day 30 0 09.3.13 Additional Contractor’s Equipment PS 0 0

9.3.14 Allow ---13---percent of SUB TOTAL forContractor’s overhead, profit, etc. 0 0

9.4.1 Miscellaneous Accounts of Engineer 25,000,000 0 0

Page 31: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 28

CHAPTER-4

FINANCIAL & CONTRACTUAL MATTERS

Page 32: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 29

4.1 Interim Payment

Up to now, Eight nos. Interim Payment Applications have been submitted by thecontractor and have been approved by the Engineer, and then the Contractor has receivedeight sum of money. The 1st Interim Payment Application is for advance payment, the 2nd,3rd, 4th, 5th, 6th, 7th and 8th interim payment Application for works completed to the monthof January, February, March & April, May &June, July, August ,September and October.The cumulative amount of approved interim payment is BDT 19,052,824,791.66/-(including the amount of Advance Payment-BDT 13,061,721,217.00/-). The actual amountof payment is BDT 5,099,974,628.92/- and USD 154,270,378.53/- after deduction ofretention money and tax.

4.2 Record of Notice and Claim

4.2.1 Issues Concerning the Commencement of 2015/2016 Dry SeasonAt present, it has come into the best construction time of 2015/2016 dry season, the RTWContractor requested for commencement of the permanent works on the south bank via anofficial letter to Consultant dated 14th Oct. 2015. However, the commencement order hasnot been issues by the Consultant, and their official reply is that the RTW Contractor hassome problem: the shortage of purchased materials; the inaccuracy of pre-dredging survey;the excavation inaccuracy of dredging equipment; the operational capability problem ofdredger’s operator; the arrangement and preparation of disposal area; the improvement ofmethod statement of 800kg geobags dumping works and rock riprap dumping works. Now,the RTW Contractor is rectifying their deficiencies as per the comments and opinions ofConsultant in the purpose of receiving commencement order in an early time.4.2.2 Issues Concerning the Disposal Area for Dredging SpoilsThe RTW Contractor submitted an official letter to Consultant on 15th Aug. 2015 in whichhe states that the identification of suitable disposal area is the responsibility of theEmployer. As to the dredged material disposal area in 2015/2016 dry season ofconstruction, at present the Employer BBA tends to allow the RTW Contractor to disposedredged material into main channel of Padma River (Area BL-1), and the RTW Contractoris purchasing the discharging pipeline of 4km length to solve the problem of shortage ofpipeline.

4.3 Variation

4.3.1 Claim Extra Cost for 800kg Geo-bags size adjustmentDue to the size of 800kg Geo-bags (1.7m×1.25m) mentioned in specification is notsufficient to achieve the minimum dry weight, while the sand used in the trial fillingcompletely meet the requirement of specification. Proposal of 800kg Geo-bags sizeadjustment (2.1m×1.5m) has been approved by the consultant. In fact the size adjustmentwill cause a large sum of extra cost, the RTW Contractor has submitted the Claim report of800kg Geo-bag Size Adjustment to the Employer, however has not yet received anyresponse from the Employer or the Consultant.

Page 33: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 30

CHAPTER-5

ORGANIZATION CHART

Page 34: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 31

Page 35: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 32

CHAPTER-6

STATEMENT OF MANPOWER, MATERIAL,

EQUPIMENT AND PLANT

Page 36: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 33

6.1 Monthly Manpower Utilization Report (Up to November,2015)

Item Description Previous This month AccumulatedI Key Positions 7 0 7

Project Manager – Mr. Qu Yan 1 0 1Deputy Project Manager for Equipment andChief Security Officer– Mr. Wang Zhiqing 1 0 1

Deputy Project Manager and ChiefEngineer –Mr. Fu Guangjin 1 0 1

Deputy Project Manager for Account andAdministrator– Mr. Ren Xiaogang 1 0 1

Deputy Project Manager for Contract andCommercial– Mr. Zhu KeSheng 1 0 1

Deputy project Manager – Mr. Li Shao Hua 1 0 1Deputy Project Manager– Mr. Zhou Lin 1 0 1

II Department 53 0 49Engineering Management Department 6 0 6Quality Management Department 2 0 2Contract Management Department 10 0 10Equipment and Material Department 13 0 13Laboratory 6 0 2Financial & Account Department 4 0 4Administration Department 3 0 3H.S.E. Department 3 0 3Survey Team 6 0 6

III Construction Teams 131 +4 133Dredging & Reclamation Construction Team 60 0 60Geo-Bags Dumping Team 14 0 14Rip-Rap Dumping Team 14 0 14Earthwork Team 10 0 10Land Slope Protection Construction Team 28 0 28Mechanical Maintenance Team 3 0 3Pipeline Laying Construction Team 0 +4 4

IV Sub-Total=I+II+III 191 +4 191V Local staff 611 +195 806

Security Guard 8 0 8Operator 30 0 30Skilled Labor 43 0 43Drivers 36 0 36Labor 494 +195 689

VI TOTAL=IV+V 802 +199 1001

Page 37: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 34

6.2 Equipment & Plant Statistics(Up to November,2015)

No. Item Description Capacity

No. of Units Mobilized

TotalRemarks(WorkingCondition)

Up toPreviousMonth

Arrivingin thisMonth

Departurein thisMonth

1 Cutter Suction Dredger - J06 6155KW 1 1 normal2 Cutter Suction Dredger - J07 6155KW 1 1 normal3 Cutter Suction Dredger - J08 13000KW 1 14 Floating Crane-QZ01 250ton 1 1 normal5 Floating Pile Ship DZ01 55m 1 1 normal6 Anchor Boat-M05 600KW 1 1 normal7 Anchor Boat-M06 600KW 1 1 normal8 Anchor Boat-M09 900HP 1 1 normal9 Anchor Boat-M10 975.5KW 1 1 normal10 Grab Dredger –Z02 1413kw 1 1 normal11 Tug Boat-T03 900hp 1 1 normal12 Barge-05 (100t) 100Ton 1 1 normal13 Barge-07 (400t) 400Ton 1 1 normal14 Barge-06 (1000t) 1000Ton 1 1 normal15 Barge-09(600t) 600Ton 1 1 normal16 dumping barge 200ton 1 1 normal17 Positioning Barge 36M 3 3 normal18 Sand Vessel 250ton 9 9 normal19 Floating Pipes Φ700*11.8m 102 102 normal20 Steel Pipes Φ700*12m 345 345 normal21 Rubber Pipes Φ700*1.8m 37 37 normal22 Rubber Pipes Φ900*1.18m 30 30 normal23 Self-dumper 213KW 4 4 normal24 Self-dumper 280KW 10 10 normal25 Excavator 184KW 2 2 normal26 Excavator 128.5KW 3 327 Excavator 125KW 4 4 normal28 Excavator 66KW 3 3 normal29 Loader 92kw 5 5 normal30 Loader 162KW 10 1031 Dozer 162kw 3 3 normal32 Forklift 36.8kw 32 32 normal33 Forklift 40KW 4 4 normal

Page 38: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 35

34 Forklift 82.4KW 2 2 normal35 Tractor 62.5KW 19 19 normal36 Vibration Roller(XS-142) 1 1 normal37 Vibration Roller(BW216-40) 2 2 normal38 concrete mixer JS500 1 1 normal39 concrete mixer JS750 1 1 normal40 concrete mixer vehicle 247KW 2 2 normal41 Water Sprinkler 8ton 1 1 normal42 Oil Tanker 8ton 1 1 normal43 Mobile Repair Truck 1 1 normal44 Light Truck 2 2 normal45 Crawler Crane 50ton 1 1 normal46 Truck Crane(QY25K5) 25ton 1 1 normal47 Bag Grab/Catch Machine 1ton 1 1 normal48 CC Block Molding Machine 140kw 4 4 normal49 speed boat 40HP 7 7 normal50 Toyota Camry car 118kw 1 1 normal51 Toyota minibus 118kw 2 2 normal52 Toyota pick-up 118kw 8 8 normal53 Generator 30KW 4 4 normal54 Generator 50KW 2 2 normal55 Generator 80KW 2 2 normal56 Generator 120KW 4 4 normal57 Generator 200KW 10 10 normal58 canon printer 2 2 normal59 GPS 3 3 normal60 distance meter 2 2 normal61 clinometer 2 2 normal62 X-r alarm 1 1 normal63 laptop 10 10 normal64 interphone 2 2 normal65 monitor 1 1 normal66 camera 1 1 normal67 vidicon 1 1 normal68 Air compressor 0.6/12.5 9 9 normal69 grader 2 2 normal

Page 39: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 36

6.3 Material Statistics (Up to November, 2015)

No. Item Description Unit Original

Procurement & DeliveryUp to

PreviousMonth

ThisMonth Total

1 fuel oil L BANGLADESH 1843170.49 237288.86 2080459.35

2 engine oil Drums BANGLADESH 199 82 281

3 hydraulic oil Drums BANGLADESH 114 60 174

4 gear oil Drums BANGLADESH 16 10 26

5 grease Drums BANGLADESH 440 120 560

6 bricks pcs BANGLADESH 15345910 3355718 18701628

7 125KG Geo-textile bag pcs BANGLADESH 1967150 568300 2535450

8 800kg Geo-textile bag pcs BANGLADESH 195450 38360 233810

9 cement pocket BANGLADESH 147100 47900 195000

10 cement ton BANGLADESH 9084.78 8562.14 17646.92

11 filling sand m3 BANGLADESH 42543 42543

12 Fine aggregate cft BANGLADESH 618951 618951

13 Coarse aggregate cft BANGLADESH 417760.3 417760.3

14 Rock riprap ton INDIA 39592.312 39592.312

15 safety helmet PCS BANGLADESH 234 234

16 life jacket PCS BANGLADESH 306 306

17 oxygen bottle BANGLADESH 340 90 430

18 steel plate kg BANGLADESH 142807 22324.5 165131.5

19 SS pipe meter BANGLADESH 824 824

20 U-steel meter BANGLADESH 2688 2688

21 angle steel meter BANGLADESH 5120 20847.5 25967.5

22 wire rope meter BANGLADESH 7650 7650

23 electrode kg BANGLADESH 4915 4915

Page 40: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 37

6.4 Status of Procurement of Materials for the RTW (Up to November, 2015)

SI.No Name of materials Unit Total Required

QuantityPlanned for production /

collection during 2015-2016Produced/collectedup to last month

Produced/collectedduring this month

Total quantityproduced/collected

1

CC Block Production

400 X 400 X 400 No 8,867,240 1,841,474 732,159 364,731 1,096,890

400 X 400 X 300 No 3,908,134 443,453 - 30,183 30,183

400 X 400 X 200 No 490,874 174,068 - - -

2 Rock Rip-Rap Cu 928,350 311,626 76,400 18,564 94,964

3 Coarse Aggregates Cu 1,136,180 104,934 96,408 4,734 101,142

4 Fine Aggregates Cu 573,829 107,076 150,270 18,632 168,902

5 Cement Ton 281,176 52,467 16,327 1,320 17,647

6 800 Kg Geo-bags No 3,907,500 551,481 183,150 50,660 233,810

7 125 Kg Geo-bags No 17,267,500 4,750,703 1,967,150 16,734,478 18,701,628

8 Geo-textile Sq. 122,300 215,731 48,000 - 48,000

9 Filling Sand Cu 4,224,519 828,309 - 20,960 20,960

Page 41: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 38

CHAPTER-7

STATEMENT OF MAJOR TEST CONDUCTE

Page 42: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 39

No Material Name Type/model ManufactureName Arrival date Arrival

quantityNumberof Testing Unit Test Purpose Test item Test result

1 Rock Rip-Rap / / 2015/11/1-30 / 5 sample routine test

specific gravity Qualified

water absorption Qualified

ACV TFV Qualified

2 Geo-BagFilling Sand FM>1 / 2015/11/1-30 / 31 sample routine test

FM Qualified

%passing0.1mm Qualified

%passing0.075mm Qualified

3 MixDesign / / 2015/11/1-30 / 1 sample /

CA 5~20mmGRADING Qualified

Concrete Cube Qualified

design calculation Qualified

FA GRADING Qualified

LAA Qualified

Moisture of Aggregate Qualified

Specific Gravity of CA Qualified

Specific Gravity of FA Qualified

4 Geo Textile / / 2015/11/1-30 / 1 sample routine test

Seam Strength Qualified

water Permeability Qualified

Weight Qualified

Page 43: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 40

Tensile Strength Qualified

Elongation QualifiedCBR PunctureResistance Qualified

Opening Size Qualified

Thickness Qualified

5 Concrete Sand FM>2.3 / 2015/11/1-30 / 22 sample routine testFM>2.3 Qualified

grading Qualified

6 CoarseAggregate / / 2015/11/1-30 / 6 sample routine test

specific gravity Qualified

water absorption Qualified

7 ConcreteCylinder / / 2015/11/1-30 / 176 sample routine test

ACV TFV Qualified

Slump Qualified

Density Qualified

8 Concrete Block / / 2015/11/1-30 / 65 sample routine test

Compress strength Qualified

Slump Qualified

Density Qualified

Page 44: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 41

CHAPTER-8

HEAITH, SAFETY AND ENVIRONMENT

Page 45: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 42

8.1 Safety CommitteeSafety management committee and site safety environmental protection department havebeen established by the Contractor, and the qualified construction safety managementpersonnel have been selected and assigned to implement construction safety procedures, sothat the contract can be fulfilled smoothly and safely.The safety management committee is comprised of project manager, project safetymanager, safety officer (full time), safety officer (part time), etc. and project manager isthe first responsible person.

8.2 Major ActivityIn response to the inspection comment raised by the Environmental and Security Engineersin September 2015, the RTW Contractor takes following security assurance andenvironment-friendly measures in both south and north banks:

8.2.1 Health Activity1) The drinking water in Construction yards of South Bank and North Bank (Mawa,

Mahjikandi and Kaorakandi) was sampled and sent to be tested in the laboratory(Department of Public Health Engineering Central Laboratory). The test result indicatedthat the drinking water is qualified and safe to be drank.

2) The information of Chinese doctor was sent to Consultant, and the Official approvalof Chinese doctor from BMDC (Bangladesh Medical & Dental Council) is underprocess.

3) To ensure the health of project personnel, a health examination was jointly proceededby the H.S.E. Department and Clinic of SINOHYDRO. As a result, the RTWContractor can have a better knowledge of every personnel’s physical condition andset up a personal health record for each personnel.

8.2.2 Safety Activity1) The Monthly Health and Safety Report no. 9 for November, 2015 will be submitted

to the Senior OSH Specialist of Consultant in early day of December, 2015.2) The site safety management was strengthen by preparing Site Safety Manual in

Bengali which have been handed out to the construction teams, so that the labors canlearn the safety knowledge and the safety management system can be implementedvery well.

3) The security management was strengthen to ensure the safety of construction yards bymaking and handing out ID cards to the site labors. There were already 400 nos. IDcards up to the end of October, 2015 and this month SINOHYDRO have made a newbatch of ID card, including the ID cards for the important material supplier for theirconvenience to deliver material to the stockpile of construction yard.

4) The daily safety inspection was strengthen: once the dangerous behavior is found, itwill be stopped immediately. The electric welding works, forklift operation, manualCC Block production and other important works have especially being monitoredand tested, the hidden danger founded when inspecting these works have been urged

Page 46: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 43

to rectify, and the operator who violated the specification and regulation will be punished.5) The personnel/specialists of HSE department conduct safety training and technical

education to the Chinese personnel who are working in the new CC Block moldingmachine and manual CC Block production team which started production a few daysago.In addition, the poster with safety operation regulations and warning sign was

6) The newly-built houses were equipped with fire extinguisher; the internal inspectionwas conducted to examine condition of fire extinguisher equipped in the constructionyards and construction sites, and the result indicated that the condition of fireextinguisher is good.

7) The personnel/specialists of HSE department conduct safety education to the driversof Dumper and light vehicles in Mawa Side to improve all the drivers’ safetyawareness. In addition, The personnel/specialists of HSE department conduct safetyeducation to the drivers of forklift in Janjira Side, making live presentation of theeasily-happened accidents in site, so as to improve all the drivers’ safety awareness.

8) The RTW Contractor submitted the HSE training report covering the safety educationand safety training works from January to November, 2015 to the Senior OSH

9) The safety warning notices against the recent heavy foggy days were sent to everypersonnel in time, so that everyone can be careful and take safetyprecautionary measure.

10) The RTW Contractor, local police, Army, Consultant and Employer representativesheld the regular security meeting every week in Janjira main construction yard,discussing how to dissolve recent safety problems and how to perfect the securitymeasures.

8.2.3 Environment Activity1) The Monthly Environmental Report no. 9 for November, 2015 will be submitted to

the Senior environmental Specialist in early day of December, 2015.2) The concrete pit for waste is under construction and the litter box is in placed in

Kaorakandi construction yard3) As per the requirement of Senior Environmental Specialist of Consultant, concrete

paving of fuel station area in Janjira Side to control spillages and prevent soilcontamination is under progress.

4) The RTW Contractor have prepared submitted the dredged material management planfor the construction of disposal area in Majhikandi, and raised reasonable suggestionand sent written reply in response to the the replied comments of SeniorEnvironmental Specialist of Consultant.

5) On 9th November, 2015, the RTW Contractor tested the air quality of Mwa andJanjira Construction site, and the test result indicated the concentration of particulatematter (PM10 and PM2.5) is normal and lower the Bangladesh Air quality standards.

6) The water from the outlet of disposal area in Kaorakandi and Majhikandi wassampled and sent to laboratory (Department of Public Health Engineering CentralLaboratory) to be tested, then the tested result was submitted to the SeniorEnvironmental Specialist of Consultant.

Page 47: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 44

8.3 Accident and Incident

Up to now, no quality incident takes place, HSE works run smoothly.

8.4 Environment Action Plan & Monthly Report

SLNo Item Submitted

Date Letter No.

1 Monthly Environmental Report No.8 for theMonth of October 2015 03-11-2015 SHCL-261-CSC

2 Monthly Healthy and Safety Report No.8 forthe Month of October 2015 03-11-2015 SHCL-262-CSC

3 Accident Report of Injured Labor dated 25thOct. 2015 04-11-2015

4 Supplementary Information of DredgedMaterials Management Plan 04-11-2015

5Accident Report on the Injured LaborHappening at Ya Sheng CC Block MoldingMachine dated 9th November, 2015

13-11-2015

6 HSE Training Report of SINOHYDRO fromMarch to November, 2015 15-10-2015 SHCL-270-CSC

7 Final Copy of Construction EnvironmentalAction Plan (Eighth Edition) 16-10-2015 SHCL-271-CSC

8 Water Quality Test Report from Outlet ofDisposal Area 21-11-2015 SHCL-272-CSC

9 Inspection Report III on Noise Measurementin Mawa Side 25-11-2015 SHCL-275-CSC

10 Air Quality Monitoring Report in both MawaSide and Janjira Side 30-11-2015 SHCL-280-CSC

Page 48: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 45

CHAPTER-9

KEY EMPHASIS AND PLAN FOR NEXT

MONTH WORK

Page 49: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 46

9.1 North Bank (Mawa Side)1) Ensured the supplied material in the North Bank could be delivered to the site in an

effective way,2) Ensured CC blocks could be manufactured by molding machines & batching plant

continuously.3) Ensured the curing and stockpiling yards of CC blocks were paved with bricks and

hardened.

4)Ensure the smooth construction of the Mawa RTW.

9.2 South Bank1) The adjusted dredging work plan for the downstream end of the trial section on the

South Bank (Sta.0-300 to 0-500 1:6) with a length of 200m was implemented andthe best way of excavation of permanent slope was summarized. Sinohydro plannedto draft a summary report on the test of dredging techniques.

2) Ensured CC blocks could be manufactured by molding machines & batching plantcontinuously.

3) Ensured the supplied material could be delivered to the site in an effective way.

Page 50: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 47

CHAPTER-10

WEATHER & HYDROLOGICAL REPORT

Page 51: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 48

10.1 Meteorological Data

Meteorological Data of November, 2015

Date WeatherTemperature(°C) RH at 06 P.M.

Of Dhaka Wind direction and speed at DhakaMaximum Minimum

01-11-2015 Sunny 29.3 22.5 71% East/ Northeasterly, 08-12 kph.02-11-2015 Sunny 30.0 22.0 70% East/ Southeasterly, 05-10 kph03-11-2015 Sunny 31.4 21.0 70% East/ Southeasterly, 08-12 kph.04-11-2015 Sunny 32.0 22.4 94% North/Northeasterly, 06-12 kph.05-11-2015 Sunny 31.2 22.4 73% North/Northeasterly, 06-12 kph06-11-2015 Sunny 32.0 22.0 63% North/Northeasterly, 06-12 kph07-11-2015 Sunny 31.5 21.0 64% North/Northeasterly, 08-12 kph.08-11-2015 Sunny 31.5 21.0 64% North/Northeasterly, 08-12 kph.09-11-2015 Sunny 29.6 19.0 58% Northwest/Northerly, 05-10 kph.10-11-2015 Sunny 30.6 19.2 64% North/Northeasterly, 06-12 kph11-11-2015 Sunny 30.6 19.6 59% North/Northeasterly, 08-12 kph.12-11-2015 Sunny 31.0 19.8 58% North/Northeasterly, 05-10 kph.13-11-2015 Foggy 30.5 19.3 56% North/Northeasterly, 08-12 kph.14-11-2015 Foggy 30.6 19.6 62% North/Northeasterly, 08-12 kph15-11-2015 Foggy 29.3 31.2 68% North/Northeasterly, 06-12 kph.16-11-2015 Foggy 30.5 20.2 70% North/Northwesterly, 05-10 kph17-11-2015 Foggy 28.5 21.5 76% North/Northwesterly, 05-10 kph18-11-2015 Foggy 28.5 21.0 94% North/Northeasterly, 06-12 kph.19-11-2015 Foggy 28.5 21.0 94% North/Northeasterly, 06-12 kph.20-11-2015 Foggy 31.6 18.8 61% North/Northeasterly, 06-12 kph.21-11-2015 Foggy 31.8 18.8 55% North/Northeasterly, 05-10 kph.22-11-2015 Foggy 31.4 18.5 61% North/Northeasterly, 05-10 kph.23-11-2015 Foggy 30.2 17.5 61% North/Northeasterly, 05-10 kph.24-11-2015 Foggy 30.0 18.2 62% North/Northeasterly, 06-12 kph.25-11-2015 Foggy 30.0 18.2 62% North/Northeasterly, 06-12 kph.26-11-2015 Foggy 28.5 17.6 62% North/Northeasterly, 06-12 kph.27-11-2015 Foggy 27.6 17.6 67% North/Northeasterly, 06-12 kph.28-11-2015 Foggy 28.6 18.5 69% North/Northeasterly, 08-12 kph.29-11-2015 Foggy 29.8 18.0 62% North/Northeasterly, 06-12 kph.30-11-2015 Foggy 29.8 18.5 58% North/Northeasterly, 06-12 kph.

Page 52: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 49

10.2 Water Level Record

Water Level Record at North Bank (Mawa Side) of November, 2015Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Time 11:30A.M 1:00P.M 4:00A.M 3:30A.M 4:00A.M 5:00A.M 6:30A.M 6:30A.M 7:00A.M 7:30A.M 8:00A.M 8:30A.M 8:30A.M 9:30A.M 10:00A.M

High Tide 2.90 2.82 2.74 2.55 2.45 2.36 2.36 2.32 2.35 2.40 2.47 2.49 2.50 2.52 2.53

Time 8:00A.M 11:30P.M 11:30P.M 11:30P.M 11:00P.M 12:00P.M 2:30P.M 3:00P.M 4:00A.M 4:30A.M 3:30A.M 5:00A.M 5:30A.M 6:00A.M 6:30A.M

Low Tide 2.55 2.50 2.38 2.29 2.22 2.14 2.19 2.13 2.10 2.14 2.16 2.20 2.20 2.20 2.20

Date 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Time 10:30A.M 0:30A.M 12:00A.M 1:00A.M 5:00A.M 6:30A.M 6:30A.M 6:30A.M 7:00A.M 8:00A.M 7:30A.M 8:30A.M 9:00A.M 9:30A.M 11:00A.M

High Tide 2.49 2.45 2.42 2.38 2.12 2.08 2.08 2.17 2.25 2.37 2.46 2.48 2.42 2.27 2.18

Time 7:30P.M 7:30A.M 8:00A.M 11:30P.M 0:30A.M 1:30A.M 4:00A.M 1:30A.M 3:00A.M 3:30A.M 4:00A.M 4:30A.M 5:30A.M 6:30A.M 7:30A.M

Low Tide 2.18 2.16 2.10 1.92 1.90 1.88 1.82 1.88 1.88 1.94 2.00 2.00 2.00 1.90 1.84

Page 53: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 50

Water Level Record at South Bank Downstream (Janjira Side) of November, 2015Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Time 11:00A.M 12:00A.M 4:00A.M 2:00A.M 4:00A.M 6:30A.M 6:30A.M 8:00A.M 7:30A.M 7:30A.M 8:00A.M 8:30A.M 9:00A.M 10:00A.M 11:00A.M

High Tide 2.82 2.77 2.60 2.45 2.36 2.32 2.30 2.26 2.29 2.34 2.40 2.43 2.45 2.46 2.46

Time 6:30A.M 9:00P.M 10:30P.M 11:30P.M 11:30P.M 1:30P.M 2:30A.M 3:30P.M 2:00A.M 4:00A.M 4:00A.M 5:30P.M 5:30:A.M 6:30:A.M 6:00:A.M

Low Tide 2.52 2.46 2.36 2.26 2.20 2.18 2.12 2.08 2.09 2.07 2.11 2.15 2.14 2.15 2.15

Date 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Time 11:00A.M 11:30A.M 0:30P.M 1:30A.M 2:30A.M 4:30P.M 6:30A.M 6:00A.M 6:00A.M 7:30A.M 7:30A.M 8:30A.M 9:30A.M 9:00A.M 9:00A.M

High Tide 2.44 2.37 2.30 2.20 2.07 2.03 2.08 2.10 2.20 2.31 2.39 2.41 2.39 2.39 2.39

Time 7:00A.M 7:30A.M 8:30A.M 10:00P.M 11:30P.M 12:00A.M 2:00P.M 2:00A.M 2:00A.M 2:30A.M 3:30A.M 5:00A.M 6:30P.M 6:00P.M 6:00A.M

Low Tide 2.14 2.12 2.05 1.95 1.88 1.87 1.83 1.81 1.86 1.91 1.96 1.97 1.94 1.94 1.94

Page 54: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 51

Water Level Record at South Bank Upstream (Kaorakandi) of November, 2015Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Time 10:00A.M 12:00A.M 0:30A.M 0:30A.M 2:30A.M 4:00A.M 5:30P.M 6:30A.M 6:00A.M 7:30P.M 7:30A.M 8:30A.M 8:00A.M 9:00A.M 9:30A.M

High Tide 4.89 4.80 4.63 4.49 4.30 4.11 4.08 4.07 3.96 3.92 3.83 3.78 3.83 3.81 3.75

Time 8:00P.M 7:30P.M 9:00P.M 11:00P.M 11:30P.M 11:30P.M 1:30A.M 2:00A.M 3:30P.M 3:00P.M 4:00P.M 4:30P.M 5:00P.M 4:30A.M 4:00P.M

Low Tide 4.56 4.45 4.33 4.14 3.98 3.90 3.86 3.80 3.68 3.61 3.52 3.45 3.45 3.40 3.34

Date 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Time 10:30A.M 10:30A.M 12:00P.M 2:00A.M 3:00A.M 3:30A.M 5:00A.M 6:00P.M 7:00P.M 7:00P.M 7:30A.M 8:00A.M 8:00A.M 9:30A.M 10:30A.M

High Tide 3.53 3.43 3.37 3.26 3.22 3.00 2.94 2.92 2.94 2.98 3.04 3.12 3.10 3.08 2.97

Time 7:00P.M 7:30P.M 9:30P.M 9:30P.M 11:30P.M 11:30P.M 1:30A.M 3:00A.M 3:30A.M 4:00A.M 4:30A.M 5:00P.M 5:00A.M 5:30A.M 7:30P.M

Low Tide 3.17 3.11 2.99 2.90 2.80 2.77 2.70 2.67 2.60 2.66 2.70 2.70 2.67 2.65 2.58

Page 55: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

CHAPTER-11

PROGRESS PHOTOGRAPHS

dell
打字机文本
Page 52
dell
打字机文本
dell
打字机文本
Page 56: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 53

Picture 1: Permanent Dredging works by SINOHYDRO Dredger J07 at South BankDownstream (Sat. 0-300m to Sta. 0-500m of Trial Section)

Page 57: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 54

Picture 2: Standing Secretary of Ministry of Road Transport & Bridges and Mr. Md. ShafiqulIslam, Project Director of Padma Multipurpose Bridge Project, Government of

the people’s Republic of Bangladesh visiting the RTW site

Picture 3: Unloading Rock Riprap to the Stockpile in South Bank Upstream(Majhikandi)

Page 58: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 55

Picture 4: Live-action Photo of Main Construction Yard in Majhikandi (Janjira Side)

Page 59: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 56

Picture 5: Photo of CC Block Production Yard in South Bank Downstream (Janjira Side)

Picture 6:Photo of CC Block Production Lines in North Bank (Mawa Side)

Page 60: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Monthly Progress Report No.10 for November 2015

Page 57

SUMMARY OF REPLIED STATUS OF

CORRESPONDENCES WITH BBA & CSC

dell
打字机文本
dell
打字机文本
dell
打字机文本
-
dell
打字机文本
dell
打字机文本
dell
打字机文本
dell
打字机文本
dell
打字机文本
dell
打字机文本
dell
打字机文本
dell
打字机文本
Page 61: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

Padma Multipurpose Bridge River Training Works ProjectSinohydro Co. Ltd. (SHCL) from Nov. 2014 to Nov. 2015

Status of Submissions

Sl. No. Master Our Ref. Title of Submission Submission

Date Replied Ref. Replied Date Status

1 SHCL/PMBRTW/BBA/2014/006 Application for Advance Payment 27/11/2014 Approved2 SHCL/PMBRTW/BBA/2014/008 Request for Assistance regarding AIT Exemption Order from NBR 02/12/2014 Approved

3 SHCL/PMBRTW/BBA/2014/009 Request for Assistance regarding issuance of VAT Registration Certification 02/12/2014 Approved

4 SHCL/PMBRTW/CSC/2014/003 Submittal of the Updated Schedule of Survey Equipments to Be Supplied 28/12/2014 KEC-001-SIN Approved

5 SHCL/PMBRTW/BBA/2014/014 Land Possesion Handover 30/12/2014 None Reply

6 SHCL/PMBRTW/BBA/2014/016 Application of Electricity for RTW Construction Yard 01/01/2015 50.01.0000.201.14.738.2014-1140 05/01/2015 Approved

7 SHCL/PMBRTW/BBA/2014/018

To Ensure Safety at and adjacent to Submersing Point at Kutubdia Deep Sea Point Arrival of Dredgers, Multipurpose Ship and Anchor boats under Invoice # GH-PADMA-20141102 dated 11/12/2014 and B/L # TIAN/FU/CHI-001, dated 19/12/2014, Vessel : ZHENHUA V. 22 (142203)

01/01/2015 50.01.0000.201.14.743.14 -1141 05/01/2015 Approved

8 SHCL/PMBRTW/CSC/2014/004 Request to Provide the Coordinates of Survey Control Points (RTW) 01/01/2015 Email: 17:03 03/01/2015 03/01/20159 SHCL/PMBRTW/CSC/2014/005 Request to Clarify the Coordinate of Control Point BM03 01/01/2015 Email: 17:03 03/01/2015 03/01/2015

10 SHCL/PMBRTW/BBA/2015/020 Request to Stop Sand Excavation in RTW Construction Area 06/01/2015 None Reply11 SHCL/PMBRTW/BBA/2015/021 Dredger's Steel Discharge Pipe Offloading Area& Storage Area 06/01/2015 None Reply

12 SHCL/PMBRTW/BBA/2015/022 Submittal of Schesule of the First Construction Season (RTW) 06/01/2015Request for

more information

13 SHCL/PMBRTW/CSC/2015/006 Survey Equipemnt Issues 06/01/2015 KEC-004-SIN 11/01/2015 Approved14 SHCL/PMBRTW/CSC/2015/008 Proposal of Road Vehicles 06/01/2015 KEC-002-SIN 8/01/2015 Approved

15 SHCL/PMBRTW/CSC/2015/009 Proposal of Communications Facilities to be Supplied 10/01/2015 KEC-003-SIN 10/01/2015Request for

more information

16 SHCL/PMBRTW/BBA/2015/030 Submittal of Site Access Channel Dredging Proposal 11/01/2015 KEC-005-SIN 14/01/2015Request for

more information

dell
打字机文本
Page 58
dell
打字机文本
dell
打字机文本
dell
打字机文本
dell
新建图章
Page 62: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

17 SHCL/PMBRTW/BBA/2015/032 Submittal of Monthly Wise Schedule&Yearly Wise Payment Schedule 12/01/2015 None Reply18 SHCL/PMBRTW/CSC/2015/011 Submittal of the Updated Construction Yard Layout Plan 13/01/2015 None Reply

19 SHCL/PMBRTW/CSC/2015/013 Proposal of Survey Vessels and Work Boats to be Supplied 14/01/2015 KEC-009-SIN 27/01/2015Request for

more information

20 SHCL/PMBRTW/BBA/2014/035 Submittal of Construction Programme 15/01/2015 None Reply

21 SHCL/PMBRTW/CSC/2015/014 Proposal of Geo-textile Material Supplier 18/01/2015Request for

more information

22 SHCL/PMBRTW/CSC/2015/015 Submittal of Laboratory Equipment Schedule 18/01/2015 Email: 18:39 01/02/2015 01/02/2015Request for

more information

23 SHCL/PMBRTW/CSC/2015/016 Proposal of Updated Communications Facilities to be Supplied 18/01/2015 KEC-008-SIN 26/01/2015 Approved24 SHCL/PMBRTW/CSC/2015/017 Submittal of Two Field Assistants’ CV 18/01/2015 Not Approved25 SHCL/PMBRTW/CSC/2015/018 Submittal of detailed certificate of cement to be supplied 18/01/2015 None Reply

26 SHCL/PMBRTW/CSC/2015/020 Response to the Consultant Review of First Construction Season (RTW) Submittal 26/1/2015 None Reply

27 SHCL/PMBRTW/CSC/2015/021 Submittal of Additional Certificate of Geo-textile Supplier 26/01/2015 Email 20:11 29/01/2015 29/01/2015 Approved

28 SHCL/PMBRTW/CSC/2015/023 Submittal of Report for Establishment of Construction Control Network & Survey Results of Checking Control Points’ Coordinates 27/01/2015 None Reply

29 SHCL/PMBRTW/CSC/2015/024 Submittal of Construction Proposal for the Temporary Jetty at South Bank Downstream 26/01/2015 Email 18:29 03/02/2015 03/02/2015 Approved

30 SHCL/PMBRTW/CSC/2015/025 Proposal of Coarse Aggregate Supplier 28/01/2015 Email 17:24 15/02/2015 15/02/2015 Conditionally Approved

31 SHCL/PMBRTW/CSC/2015/026 Proposal of Filling Sand Supplier 29/01/2015 Email 16:09 15/02/2015 15/02/2015 Not Arrpoved

32 SHCL/PMBRTW/BBA/2015/048 Proposal of Dispute Board Members 02/02/2015 26-50.01.0000.201. 04.759.15-123

Request more information

33 SHCL/PMBRTW/BBA/2015/049 Notice of Force Majeure 02/02/2015 None Reply34 SHCL/PMBRTW/CSC/2015/029 Proposal of Filling Sand Supplier 03/02/2015 Email 16:09 15/02/2015 15/02/2015 Not Approved35 SHCL/PMBRTW/CSC/2015/032 Application for Pre-dredging Survey to Chainage -800~ -200 04/02/2015 None Reply36 SHCL/PMBRTW/CSC/2015/031 Proposal of Additional Cement Supplier 05/02/2015 KEC-033-SIN 29/06/2015 Approved37 SHCL/PMBRTW/CSC/2015/034 Submittal of Dredging and Reclamation Method Statement 08/02/2015 None Reply38 SHCL/PMBRTW/CSC/2015/039 Request for Source Approval Bushundhara Cement 10/02/2015 E-mail 19:32 22/02/2015 22/02/2015 Approved39 SHCL/PMBRTW/CSC/2015/038 Submittal of Health and Safety Plan 11/02/2015 None Reply40 SHCL/PMBRTW/CSC/2015/040 Submittal of Quality Control Plan 11/02/2015 None Reply41 SHCL/PMBRTW/CSC/2015/041 Submittal of Environmental Management Plan 11/02/2015 None Reply

dell
打字机文本
Page 59
dell
打字机文本
dell
新建图章
Page 63: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

42 SHCL/PMBRTW/CSC/2015/042 Submittal of Construction Management Plan for the First Construction Season 11/02/2015 None Reply

43 SHCL/PMBRTW/CSC/2015/043 Proposal of Fine Aggregate Supplier 11/02/2015 None Reply

44 SHCL/PMBRTW/CSC/2015/044 Proposal of the Third Cement Supplier 11/02/2015 KEC-034-SIN 29/06/2015 Conditionally Approved

45 SHCL/PMBRTW/CSC/2015/045 Submittal of Supplementary Certifucate of Fine Aggregate Supplier 15/02/2015 None Reply

46 SHCL/PMBRTW/CSC/2015/046 Submittal of the Anti-Corrosion Measurement of the Temporary Jetty at South Bank Downstream 15/02/2015 None Reply

47 SHCL/PMBRTW/CSC/2015/047 Submittal of Construction Proposal for Pre-Ground Treatment Ground Investigation Works 15/02/2015 50.01.0000.201.14.

738.14-185 18/02/2015No need to proceed this

works48 SHCL/PMBRTW/CSC/2015/048 Submittal of the Dredged Material Disposal Area 15/02/2015 E-mail 15:26 23/02/2015 23/02/2015 Replied

49 SHCL/PMBRTW/CSC/2015/049 Proposal of the Second Geo-textile Material Supplier 15/02/2015 E-mail 14:16 24/02/2015 24/02/2015 Conditionally Approved

50 SHCL/PMBRTW/BBA/2015/058 Preparation of Slope Protection Construction on North Bank 22/02/2015 E-mail 14:57 25/02-2015 25/02-2015 Approved

51 SHCL/PMBRTW/BBA/2015/059 Request to Build Cofferdam Construction in the Disposal Area on South Bank

24/02/2015 None Reply

52 SHCL/PMBRTW/BBA/2015/063 Submittal of Claim for Extra Cost of Temporary Cofferdam at Disposal Area in Front of Construction Yard 26/02/2015 50.01.0000.201.99.760.15

- 581 07/06/2015 Not Approved

53 SHCL/PMBRTW/CSC/2015/050 Proposal of the Third Filling Sand Supplier 26/02/2015 None Reply54 SHCL/PMBRTW/CSC/2015/051 Proposal of Rock Riprap Supplier 26/02/2015 KEC-037-SIN 06/08/2015 Not Approved

55 SHCL/PMBRTW/CSC/2015/054 Application for Commencement of Temporary Channel Excavation in Janjira Site 24/02/2015

E-mail 17:57 03/03 2015 03/03 2015

Request more information

56 SHCL/PMBRTW/CSC/2015/056 Submittal of Construction Plan of Dredging Works before Monsoon in 2015

28/02/2015 Not Approved

57 SHCL/PMBRTW/CSC/2015/057 Submittal of Construction Environmental Action plan 28/02/2015 KEC-018-SIN 12/03/2015 Not Approved

58 SHCL/PMBRTW/CSC/2015/059 Submittal of Certification No.03 for Interim Payment Application 04/03/2015 KEC-017-SIN 12/03/2015 Requst Re-submission

59 SHCL/PMBRTW/CSC/2015/060 Submittal of the OrganogramChart and Key Person 08/03/2015 KEC-016-SIN 10/03/2016 Request more information

60 SHCL/PMBRTW/CSC/2015/062 Submittal of Re-Test Result of Filling Sand 08/03/2015 E-mail 15:49 07/03/2015 07/03/2015 Conditionally Approved

61 SHCL/PMBRTW/CSC/2015/063 Proposal of the Forth Cement Supplier 08/03/2015 E-mail 14:32 24/03/2015 24/03/2015 Not Approved62 SHCL/PMBRTW/CSC/2015/064 Submittal of Proposal for Safety and Environment Warning Signages 08/03/2015 None Reply

63 SHCL/PMBRTW/CSC/2015/065 Submittal of Method Statement of Interim RTW on Mawa Side (Left Bank) 08/03/2015 None Reply

dell
打字机文本
Page 60
dell
打字机文本
dell
新建图章
Page 64: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

64 SHCL/PMBRTW/BBA/2015/072 Proposal of Interim Public Liability Insurance 10/03/2015 E-mail: 19:32 12/03/2015 03/12/2015 Some Comment65 SHCL/PMBRTW/BBA/2015/073 Proposal of One More Dispute Board Member 10/03/2015 None Reply66 SHCL/PMBRTW/BBA/2015/074 Application of Electricity for RTW Construction Yard at Mawa 11/03/2015 Approved67 SHCL/PMBRTW/CSC/2015/066 Supplement for Dredging Proposal in Temporary Channel 11/03/2015 None Reply

68 SHCL/PMBRTW/CSC/2015/067 Submittal of Construction Proposal for River Training Project on South Bank before the Monsoon of 2015 11/03/2015 None Reply

69 SHCL/PMBRTW/CSC/2015/069 Proposal of the Fourth Filling Sand Supplier 11/03/2015 None Reply70 SHCL/PMBRTW/BBA/2015/076 Application for Adjusting the Size of 800 Kg Geo-bags 19/03/2015 E-mail: 15:05 18/03/2015 03/18/2015 Approved

71 SHCL/PMBRTW/BBA/2015/077 Submittal of Technology Proposal for Stitching and Mouth Closure of Geo-bag 19/03/2015 E-mail: 18:08 21/03/2015 03/21/2015 Ask for more

information72 SHCL/PMBRTW/CSC/2015/070 Proposal of One Laboratory Labourer to be Supplied 28/03/2015 Approved

73 SHCL/PMBRTW/CSC/2015/071 Submmital of ISO Certification of Bashundhara Industrial Complex Limited Madangonj factory 24/03/2015 E-mail 17:24 24/03/2015 24/03/2015 Ask for more

information74 SHCL/PMBRTW/CSC/2015/072 Proposal of the Fifth Filling Sand Supplier 24/03/2015 None Reply

75 SHCL/PMBRTW/CSC/2015/073 Reply on Approval of Adjusting the 800kg Geo-bags Size 24/03/2015 E-mail 17:51 21/03/2015 21/03/2015 Conditionally Approved

76 SHCL/PMBRTW/CSC/2015/074 Proposal of Safety Specialist 24/03/2015 KEC-020-SIN 22/03/2015 Approved

77 SHCL/PMBRTW/CSC/2015/075 Submittal of Quality Assurance Plan & Sand Extraction Permission of Royal Stone Developments Ltd. 24/03/2015 None Reply

78 SHCL/PMBRTW/CSC/2015/076 Submittal of Revised Interim Payment Application No.03 24/03/2015 KEC-071-BBA 20/03/2015 Approved79 SHCL/PMBRTW/BBA/2015/084 Application for variation of 800kg Geo-bags size adjustment 25/03/2015 E-mail: 20:34 03/25/2015 03/25/2015 Not Arrpoved80 SHCL/PMBRTW/BBA/2015/085 Notice of Claim for 800kg Geo-bag Size Adjustment 01/04/2015 None Reply

81 SHCL/PMBRTW/CSC/2015/081 Submittal of Construction Programme of Protection Works on North Bank before Monsoon 02/04/2015 None Reply

82 SHCL/PMBRTW/CSC/2015/082 Proposal of the Fifth Cement Supplier—SHAH Cement 05/04/2015 None Reply83 SHCL/PMBRTW/CSC/2015/083 Submittal of Revised Health and Safety Plan (Second Edition) 11/04/2015 None Reply84 SHCL/PMBRTW/BBA/2015/092 Proposal of Revised Interim Public Liability Insurance 09/04/2015 E-mail16:09 17/04/2015 17/04/2015 Replied

85 SHCL/PMBRTW/CSC/2015/084 Submittal of Supplementary Documents of Filling Sand from BANG JIN GEO-TEXTILE LTD 11/04/2015 None Reply

86 SHCL/PMBRTW/CSC/2015/085 Proposal of Concrete Mixing Water in Majikandi Construction Area 11/04/2015 None Reply87 SHCL/PMBRTW/CSC/2015/086 Proposal of one Laboratory Assistant to be Supplied 11/04/2015 E-mail 21:39 07/04/2015 07/04/2015 Approved88 SHCL/PMBRTW/CSC/2015/087 Submittal of ‘S’ Curve of River Training Works 11/04/2015 Not Approved

89 SHCL/PMBRTW/CSC/2015/089 Delivery of 02 (Two) Brand New Work Boats 11/04/2015 KEC-026-SIN 12/04/2015 Conditionally Approved

90 SHCL/PMBRTW/CSC/2015/090 Sign Boards for River Training Works Contract 11/04/2015 None Reply

dell
打字机文本
Page 61
dell
打字机文本
dell
新建图章
Page 65: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

91 SHCL/PMBRTW/CSC/2015/092 Submittal of Monthly Progress Report No.2 for the Month of March 2015 11/04/2015 E-mail 18:45 09/04 2015 09/04 2015 Require for

more 92 SHCL/PMBRTW/CSC/2015/093 Submittal of the Revised Construction Yard Layout Plan 11/04/2015 None Reply93 SHCL/PMBRTW/CSC/2015/094 Submittal of 2 (two) Boatmen’s Personal Data 11/04/2015 E-mai 12:19 02/07/2015 02/07/2015 Approved

94 SHCL/PMBRTW/CSC/2015/095 Proposal of Two Laboratory Technicians to be Supplied 11/04/2015 E-mail 19:16 15/04/2015 15/04/2015 Approved one of two

95 SHCL/PMBRTW/CSC/2015/096 Submittal of the Revised Survey Vessel Design Drawing & Specification 11/04/2015 E-mail 12:34 20/04/2015 20/04/2015 Some Comments

96 SHCL/PMBRTW/CSC/2015/097 Submittal of Water Quality Testing ReportChinese Water Treatment Equipment Certifiacates 11/04/2015 E-mail 14:54 22/04/2015 22/04/2015 Some

Comments97 SHCL/PMBRTW/CSC/2015/098 Proposal of the Third Geo-textile Material Supplier 11/04/2015 KEC-035-SIN 29/06/2015 Approved98 SHCL/PMBRTW/CSC/2015/100 Report on the Event of Shipwrecks 11/04/2015 None Reply99 SHCL/PMBRTW/CSC/2015/101 Proposal of Environmental Specialist 16/04/2015 E-mail 12:17 17/04/2015 18/04/2015 Replied

100 SHCL/PMBRTW/CSC/2015/102 Proposal of the Third Laboratory Technician to be Supplied 16/04/2015 E-mail 19:16 15/04/2015 15/04/2015 Approved

101 SHCL/PMBRTW/CSC/2015/103 Submittal of the Construction Method of Access Road Broadening to Stone Yards at South Bank Upstream 26/04/2015 E-mail 19:07 14/04/2015 14/04/2015 Approved

102 SHCL/PMBRTW/CSC/2015/104 Proposal of the Disposal Area on South Bank 26/04/2015 E-mail 21:06 16/04/2015 16/04/2015 Some Comments

103 SHCL/PMBRTW/CSC/2015/105 Submittal of Monthly Environmental Report No.1 for the Month of March 2015 19/04/2015 E-mail 14:07 22/04/2015 22/04/2015 Not Approved

104 SHCL/PMBRTW/CSC/2015/106 Submittal of Revised Construction Proposal of Dredging Works on South Bank before Monsoon in 2015 (Second Edition) 26/04/2015 None Reply

105 SHCL/PMBRTW/CSC/2015/108 Submittal of 125Kg Geo-bags Dumping Method Statement 26/04/2015 None Reply

106 SHCL/PMBRTW/CSC/2015/109 Submittal of Monthly Environmental Report No.1 for the Month of March 2015 (Revised Edition) 26/04/2015 E-mail 17:11 26/04/2015 26/04/2015 Not Approved

107 SHCL/PMBRTW/CSC/2015/110 Proposal of the Second Rock Riprap Supplier 26/04/2015 KEC-037-SIN 06/08/2015 Conditionally Approved

108 SHCL/PMBRTW/CSC/2015/111 Proposal of the Third Rock Riprap Supplier 26/04/2015 KEC-037-SIN 06/08/2015 Not Approved109 SHCL/PMBRTW/CSC/2015/112 Proposal of the Forth Rock Riprap Supplier 26/04/2015 KEC-037-SIN 06/08/2015 Not Approved110 SHCL/PMBRTW/CSC/2015/113 Submittal of Construction Environmental Action Plan (Second Edition) 26/04/2015 E-mail 08:37 07/05/2015 07/05/2015 Not Approved111 SHCL/PMBRTW/CSC/2015/114 Submittal of Water Quality Testing Report 26/04/2015 E-mail 17:07 26/04/2015 26/04/2015 Replied112 SHCL/PMBRTW/BBA/2015/095 Submittal of Claim Report of 800Kg Geobags Size Adjustment 22/04/2015 None Reply113 SHCL/PMBRTW/BBA/2015/098 Submittal of Hard Copy of Interim Public Liability Insurance 30/04/2015 E-mail: 17:33 04/29/2015 04/29/2015 Approved114 SHCL/PMBRTW/BBA/2015/099 Request to Start Initial Dredging Work on Janjira Side 30/04/2015 None Reply115 SHCL/PMBRTW/CSC/2015/115 Submittal of 800Kg Geo-bags Dumping Method Statement 04/05/2015 E-mail 11:00 06/05/2015 06/05/2015 Replied

dell
打字机文本
Page 62
dell
打字机文本
dell
打字机文本
dell
新建图章
Page 66: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

116 SHCL/PMBRTW/CSC/2015/116 Submittal of Test Reports of 125Kg Geo-bags Filling Sand for the Month of March and April of 2015 30/04/2015 None Reply

117 SHCL/PMBRTW/CSC/2015/118 Proposal of the Replaced Laboratory Assistant to be Supplied 03/05/2015 None Reply

118 SHCL/PMBRTW/CSC/2015/120 Submittal of Monthly Environmental Report No.2 for the Month of April 2015 03/05/2015 None Reply

119 SHCL/PMBRTW/CSC/2015/121 Submittal of Test Reports of 800Kg Geo-bags Filling Sand for the Month of March and April of 2015 07/05/2015 None Reply

120 SHCL/PMBRTW/BBA/2015/100 Submittal of Required Documents of Interim Public Liability Insurance 07/05/2015 None Reply121 SHCL/PMBRTW/CSC/2015/123 Submittal of Rock Riprap Dumping Work Method Statement 09/05/2015 E-mail 19:11 16/06/2015 16/06/2015 None Reply122 SHCL/PMBRTW/CSC/2015/126 Submittal of List of HSE Expert 09/05/2015 None Reply123 SHCL/PMBRTW/CSC/2015/127 Proposal of Four Drivers to be Supplied 09/05/2015 KEC-031-SIN 21/05/2015 Approved

124 SHCL/PMBRTW/BBA/2015/102 Submittal of List of Foreign Employees Working at Padma Multipurpose Bridge Project (PMBP) with Passport Numbers 12/05/2015 None Reply

125 SHCL/PMBRTW/BBA/2015/103 Submittal of Curriculum Vitae of Key Personnel 13/05/2015 None Reply126 SHCL/PMBRTW/BBA/2015/106 Application for Removal of Houses from Construction Yard 13/05/2015 Took Actions 127 SHCL/PMBRTW/BBA/2015/107 Request for Returning the Bid Security 13/05/2015 None Reply

128 SHCL/PMBRTW/CSC/2015/128 Application for commencement of Dredging on Janjira Side -800m -300m 16/05/2015 E-mail 14:44 28/05/2015 28/05/2015 Approved

129 SHCL/PMBRTW/CSC/2015/129 Submittal of Dredging Material Management Plan 16/05/2015 E-mail 13:26 14/05/2015 14/05/2015 Not Approved

130 SHCL/PMBRTW/CSC/2015/130 Submmital of ISO Certification II of Bashundhara Industrial Complex Limited Madangonj Factory 16/05/2015 KEC-032-SIN 29/06/2015 Approved

131 SHCL/PMBRTW/CSC/2015/131 Submittal of Interim Payment Application No.04 14/05/2015 Need to be revised

132 SHCL/PMBRTW/CSC/2015/132 Proposal of the Fifth Driver to be Supplied 18/05/2015 KEC-031-SIN 21/05/2015 Approved133 SHCL/PMBRTW/CSC/2015/133 Submittal of Curriculum Vitae of HSE Expert 18/05/2015 None Reply134 SHCL/PMBRTW/CSC/2015/134 Submittal of Dredging Material Management Plan (Revised Edition) 18/05/2015 E-mail 13:44 19/05/2015 19/05/2015 Not Approved

135 SHCL/PMBRTW/CSC/2015/135 Submittal of Report on Conflict between Labor and Chinese Personnel 18/05/2015 None Reply

136 SHCL/PMBRTW/CSC/2015/136 Submittal of Curriculum Vitae of Project Doctor 18/05/2015 E-mail 16:24 18/04/2015 18/04/2015 Require for more

137 SHCL/PMBRTW/BBA/2015/108 Submittal of Hard Copy of Insurance against Accident to Workmen 20/05/2015 None Reply

138 SHCL/PMBRTW/CSC/2015/137 Submittal of Proposed Concrete Mix Design of CC Block of Block Molding Machine 26/05/2015 None Reply

139 SHCL/PMBRTW/CSC/2015/138 Submittal of CC Block Production Method Statement 24/05/2015 None Reply

140 SHCL/PMBRTW/CSC/2015/139 Submittal of PMIS (Project Management Information System) User Information 26/05/2015 None Reply

dell
打字机文本
Page 63
dell
打字机文本
dell
打字机文本
dell
新建图章
Page 67: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

141 SHCL/PMBRTW/CSC/2015/140 Application for using Yamaha 115HP 2-Strock instead of 115HP 4-Strock for Survey Boat 26/05/2015 Email: 15:58 11/06/2015 11/06/2015 Approved

142 SHCL/PMBRTW/CSC/2015/141 Submittal of Licensed Certificate of Project Doctor 26/05/2015 None Reply143 SHCL/PMBRTW/CSC/2015/142 Submittal of Test Reports of 400 GSM Geo-bag and 600 GSM Geo-bag 26/05/2015 None Reply144 SHCL/PMBRTW/CSC/2015/143 Notification the Road Vehicles’ Arrival 27/05/2015 None Reply145 SHCL/PMBRTW/BBA/2015/110 Application II for Removal of Houses from Construction Yard 31/05/2015 Took Actions

146 SHCL/PMBRTW/CSC/2015/144 Submittal of Revised Interim Payment Application No.04 28/5/2015 50.01.0000.201.02.742.14-594 11/06/2015 Approved

147 SHCL/PMBRTW/CSC/2015/145 Submittal of WBS Plan Schedule 30/5/2015 None Reply148 SHCL/PMBRTW/CSC/2015/146 Submittal of Required Water Quality Testing Report 30/5/2015 None Reply149 SHCL/PMBRTW/CSC/2015/148 Submittal of Material Procurement Programme 04/06/2015 None Reply

150 SHCL/PMBRTW/CSC/2015/149 Submittal of 125Kg Geo-bags Stockpiling Programme 04/06/2015 E-mail: 09:40 06/06/2015 06/06/2015 Ask for more information

151 SHCL/PMBRTW/CSC/2015/150 Submittal of Revised Construction Programme of PMBP-RTW 04/06/2015 None Reply152 SHCL/PMBRTW/CSC/2015/151 Delivery of Four Road Vehicles 04/06/2015 None Reply153 SHCL/PMBRTW/CSC/2015/152 Proposal of the Laboratory Technician to be Supplied 04/06/2015 E-mail: 11:24 07/06/2015 07/06/2015 Approved154 SHCL/PMBRTW/CSC/2015/153 CSC-Submittal of More Test Reports of 400 GSM Geo-bag 04/06/2015 None Reply

155 SHCL/PMBRTW/CSC/2015/154 Proposal of Location and Installation Plan and Monitoring System for the Water Level Gauging Station 04/06/2015 E-mail: 24:29 06/08/2015 06/08/2015 Approved

156 SHCL/PMBRTW/CSC/2015/156 Submittal of Inspection Report on Noise measurement 15/06/2015 E-mail: 15:27 11/06/2015 11/06/2015 Need to take more action

157 SHCL/PMBRTW/CSC/2015/157 The Second Delivery of Bathymetric and Hydrographic Equipment 15/06/2015 None Reply158 SHCL/PMBRTW/CSC/2015/158 The Second Delivery of Land Survey Equipment 15/06/2015 None Reply159 SHCL/PMBRTW/CSC/2015/159 Submittal of Land Clearing and Top Soil Stripping Work Method 15/06/2015 E-mail: 17:53 16/06/2015 16/06/2015 Approved

160 SHCL/PMBRTW/CSC/2015/162 Submittal of Monthly Environmental Report No.3 for the Month of May 2015 (Second Edition) 15/06/2015 E-mail: 09:48 14/06/2015 14/06/2015 Some Comment

161 SHCL/PMBRTW/CSC/2015/163 Notification on the Completion of Sign Boards Installation work 15/06/2015 None Reply162 SHCL/PMBRTW/CSC/2015/164 Proposal of the Replaced Laboratory Assistant to be Supplied 15/06/2015 E-mail: 09: 18 17/06/2015 17/06/2015 Approved

163 SHCL/PMBRTW/CSC/2015/165 Submittal of List of Chinese Staff and Bangladeshi Labours of PMBP-RTW 15/06/2015 None Reply

164 SHCL/PMBRTW/CSC/2015/166 Submittal of Proposed Concrete Mix Design of Cast in Situs CC Block 15/06/2015 E-mail: 13: 44 14/07/2015 14/07/2015 Some Comments

165 SHCL/PMBRTW/CSC/2015/167 Submittal of Interim Payment Application No.05 18/06/2015 Need to be revised

166 SHCL/PMBRTW/CSC/2015/168 Proposal of the Sixth Filling Sand Supplier 18/06/2015 None Reply167 SHCL/PMBRTW/CSC/2015/169 Submittal of Revised Rock Riprap Dumping Work Method Statement 21/06/2015 None Reply

dell
打字机文本
Page 64
dell
新建图章
Page 68: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

168 SHCL/PMBRTW/BBA/2015/113 Application of Time Loss Recovery due to Delay of Awarding and Signing of the Contract 21/06/2015 50.01.0000.201.99.760.15

-724 08/07/2015 Not Approved

169 SHCL/PMBRTW/BBA/2015/114 Notification the Present Status of the Required Road Vehicles 21/06/2015 None Reply

170 SHCL/PMBRTW/BBA/2015/117 Request to Issue a Letter for Indian Visa 23/06/2015 50.01.0000.201.24.752.2014-640

Given Assistance

171 SHCL/PMBRTW/CSC/2015/170 Submittal of Stockpile Schedule of 125kg & 800kg Geo-bags before October 2015 24/06/2015 None Reply

172 SHCL/PMBRTW/CSC/2015/171 Submittal of Revised Interim Payment Application No.05 25/06/2015 50.01.0000.201.02.742.14-676 29/06/2015 Approved

173 SHCL/PMBRTW/CSC/2015/172 Submittal of First Joint Interim-Dredging Survey Report of Dredging Area (Chainage -350 to Chainage-760) in South Bank (Janjira Side) 27/06/2015 None Reply

174 SHCL/PMBRTW/CSC/2015/173 Submittal of HIV (AIDS) Prevention and Monitoring Plan 27/06/2015 Email: 09:28 28/06/2015 28/06/2015 Need to be revised

175 SHCL/PMBRTW/CSC/2015/174 Submittal of Required Water Quality Testing Report and Soil Analysis Report 27/06/2015 None Reply

176 SHCL/PMBRTW/CSC/2015/175 Submittal of 800Kg Geo-bags Dumping Method Statement (Second Edition)

27/06/2015 None Reply

177 SHCL/PMBRTW/CSC/2015/177 Proposal of the Second Coarse Aggregate Supplier 06/07/2015 None Reply

178 SHCL/PMBRTW/CSC/2015/178 Submittal of Test Reports III of 400 GSM Geo-bag and 600 GSM Geo-bag

06/07/2015 None Reply

179 SHCL/PMBRTW/BBA/2015/118 Proposal of theForth Duputy Board Member 09/07/2015 None Reply

180 SHCL/PMBRTW/CSC/2015/181 Submittal of Inspection Report II on Noise Measurement for the Month of July 2015 09/07/2015 None Reply

181 SHCL/PMBRTW/CSC/2015/182 Submittal of Supplemental Document of Yamaha 2-Strock Engines 09/07/2015 None Reply

182 SHCL/PMBRTW/CSC/2015/183 Submittal of The Initial Dredging and Reclamation Programme on the South Bank during Monsoon Season 2015 09/07/2015 None Reply

183 SHCL/PMBRTW/CSC/2015/185 Submittal of Calibration Report 09/07/2015 None Reply184 SHCL/PMBRTW/CSC/2015/186 Proposal of the Third Coarse Aggregate Supplier 09/07/2015 None Reply185 SHCL/PMBRTW/BBA/2015/124 Submittal of Draft Copy of Contractor’s All Risks Insurance Policy 14/07/2015 None Reply

186 SHCL/PMBRTW/BBA/2015/125 Request Assistance for Obtaining the Sand Excavation Permits 16/07/2015 50.01.0000.201.14.738.14 (part-1)-778 27/07/2015 Given

Assistance

187 SHCL/PMBRTW/BBA/2015/127 Coorperation to Avoid Local Vessels Entering into the Construction Area 20/07/2015 50.01.0000.201.14.73.14

(part-1)-774 26/07/2015 Given Assistance

188 SHCL/PMBRTW/CSC/2015/187 Submittal of Test Reports IV of 400 GSM Geo-bags 23/07/2015 None Reply189 SHCL/PMBRTW/CSC/2015/188 Submittal of Diving Method 23/07/2015 None Reply

190 SHCL/PMBRTW/CSC/2015/189 Request to Provide the Revised Design Drawing of River Training Works on Mawa

23/07/2015 Email: 15:00 18/07/2015 18/07/2015 Not Approved

dell
打字机文本
dell
打字机文本
Page 65
dell
打字机文本
dell
打字机文本
dell
新建图章
Page 69: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

191 SHCL/PMBRTW/CSC/2015/190 Submittal of The Initial Dredging and Reclamation Programme on the South Bank during Monsoon Season 2015 (Second Edition) 23/07/2015 Email: 21:40 24/07/2015 24/07/2015 Some

Comments192 SHCL/PMBRTW/BBA/2015/130 Submittal of Marine Equipment Insurance Policy 24/07/2015 None Reply193 SHCL/PMBRTW/BBA/2015/131 Reply on the Letter of Extension 24/07/2015 None Reply

194 SHCL/PMBRTW/CSC/2015/191 Submittal of Construction Proposal of Dredging Works on South Bank during Monsoon in 2015 (Third Edition) 26/07/2015 None Reply

195 SHCL/PMBRTW/CSC/2015/192 Submittal of HIV/AIDS Prevention and Monitoring Plan (Revised Edition) 27/07/2015 None Reply

196 SHCL/PMBRTW/CSC/2015/193 Submittal of Technical Proposal for Subsoil Investigation Work 28/07/2015 None Reply197 SHCL/PMBRTW/BBA/2015/140 Notice of Force Majeure 23/08/2015 None Reply

198 SHCL/PMBRTW/BBA/2015/144 Request for the Right of Possessing Extra Construction Yard Adjacent to MBEC Site in Janjira 26/08/2015 None Reply

199 SHCL/PMBRTW/BBA/2015/146 Submittal of updated Draft Copy of Contractor’s All Risks Insurance Issued by Sadharan Bima Corporation 31/08/2015 None Reply

200 SHCL/PMBRTW/CSC/2015/194 Submittal of Monthly Environmental Report No.5 for the Month ofJuly 2015

06/08/2015 Email: 14:17 10/08/2015 10/08/2015 some comments

201 SHCL/PMBRTW/CSC/2015/195 Submittal of Monthly Healthy and Safety Report No.5 for the Month ofJuly 2015

06/08/2015 None Reply

202 SHCL/PMBRTW/CSC/2015/198 Submittal of Construction Environmental Action Plan (Third Edition) 07/08/2015 Email: 09:15 11/08/2015 11/08/2015 some comments

203 SHCL/PMBRTW/CSC/2015/199Submittal of of Adjusted Construction Procedure based on The Initial Dredging and Reclamation Programme on the South Bank during Monsoon Season 2015 (Third Edition)

16/08/2015 None Reply

204 SHCL/PMBRTW/CSC/2015/200 Submittal of Test Reports V of 400 GSM Geo-bags, 600 GSM Geo-bags and Sewing Thread 16/08/2015 None Reply

205 SHCL/PMBRTW/CSC/2015/201 Proposal of the Second Fine Aggregate Supplier 16/08/2015 None Reply

206 SHCL/PMBRTW/CSC/2015/202 Contractor’s Clarification on the Contractual Liability of Providing the Additional Disposal Area 16/08/2015 None Reply

207 SHCL/PMBRTW/BBA/2015/138 Power of Attorney 19/08/2015 None Reply

208 SHCL/PMBRTW/CSC/2015/203 Submittal of Second Joint Interim-Dredging Survey Report, From Chainage -530 to Chainage-980, Janjira Side 20/08/2015 None Reply

209 SHCL/PMBRTW/CSC/2015/204 Submittal of the Third Boatmen’s Personal Data 20/08/2015 None Reply210 SHCL/PMBRTW/CSC/2015/205 Proposal of the Fifth Candidate of Laboratory Technician to be supplied 20/08/2015 None Reply

211 SHCL/PMBRTW/CSC/2015/206 Application for Advance Payment of Supplying & Stockpiling of 0.4m×0.4m×0.4m CC Blocks 26/08/2015 None Reply

212 SHCL/PMBRTW/CSC/2015/207 Submittal of the Fourth Boatman Candidate ’s Personal Data 31/08/2015 None Reply213 SHCL/PMBRTW/CSC/2015/208 Submittal of Supporting Documents for Concrete Mix Design 26/08/2015 None Reply

dell
打字机文本
Page 66
dell
打字机文本
dell
打字机文本
dell
打字机文本
dell
打字机文本
dell
打字机文本
dell
新建图章
Page 70: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

214 SHCL/PMBRTW/CSC/2015/209 Submittal of Original Water Quality Test Report before Dredging Works 31/08/2015 None Reply215 SHCL/PMBRTW/CSC/2015/210 Submittal of Proposal of Berthing Facilities for Boats 31/08/2015 None Reply

216 SHCL/PMBRTW/CSC/2015/211 Request for Commencement of Initial Dredging in Janjira from K0-300m to K0+300m

30/08/2015 Email:17:05 30/08/ 2015 30/08/ 2015 Ask for more information

217 SHCL/PMBRTW/CSC/2015/212 Submittal of Construction Environmental Action Plan (Fourth Edition) 31/08/2015 None Reply218 SHCL/PMBRTW/CSC/2015/214 Delivery of Another Two Brand New Work Boats 02/09/2015 Processing

219 SHCL/PMBRTW/CSC/2015/215 Submittal of Interim Payment Application No.06 02/09/2015 KEC-043-SHCL 13/09/2015 Need to be revised

220 SHCL/PMBRTW/BBA/2015/148 Submittal of final Draft Copy of Contractor’s All Risks Insurance Issued by Sadharan Bima Corporation 03/09/2015 None Reply

221 SHCL/PMBRTW/CSC/2015/218 Submittal of Dredging Quantity and Payment Proposal for BIWTA Ferry Route 10/09/2015 Email: 16:50 27/09/2015 27/09/2015 Ask for more

information

222 SHCL/PMBRTW/CSC/2015/219 Submittal of Third Joint Interim Survey Report: Initial Dredging Area, from Chainage -300 to Chainage-800, Janjira Side 10/09/2015 None Reply

223 SHCL/PMBRTW/CSC/2015/220 Summary of the Meeting Discussion about the Measurement and Payment concerning BIWTA Ferry Route Dredging 10/09/2015 None Reply

224 SHCL/PMBRTW/CSC/2015/222 Submittal of Test Reports VI of 400 GSM Geo-bags and 600 GSM Geo-bags 28/09/2015 None Reply

225 SHCL/PMBRTW/CSC/2015/223 Submittal of Surface Water Quality Test Report and Dredging Water Quality Test Report 15/09/2015 None Reply

226 SHCL/PMBRTW/CSC/2015/224 Submittal of Final Copy of Construction Environmental Action Plan (Fifth Edition) 15/09/2015 Email: 19:04 19/09/2015 19/09/2015 Need to be

revised227 SHCL/PMBRTW/CSC/2015/225 Submittal of Revised Interim Payment Application No.06 15/09/2015 Approved

228 SHCL/PMBRTW/BBA/2015/149 Claim No. 4 Notice of Claim for Collapse of Temporary Jetty at Janjira 20/09/2015 None Reply

229 SHCL/PMBRTW/BBA/2015/153 Request for Practical Access to and Possession of New Portion of Site Sta. 0+200~1+700 and Sta. 7+100~8+167 at Janjira 21/09/2015 None Reply

230 SHCL/PMBRTW/CSC/2015/226 Submittal of Final Copy of Construction Environmental Action Plan (Sixth Edition) 28/09/2015 None Reply

231 SHCL/PMBRTW/BBA/2015/160 Request for BBA’s Assistance in Obtaining Permission from Ministry of Home Affairs 29/09/2015 Email:14:09 27/09/2015 27/09/2015 Replied

232 SHCL/PMBRTW/BBA/2015/161 Request for BBA’s Assistance in Customs Clearance of Indian Stone’s Importation 29/09/2015 None Reply

233 SHCL/PMBRTW/BBA/2015/162 Submittal of the Breakdown of Estimated Unit Price for the Shimulia-Charjanajat Ferry Route Dredging Works 04/10/2015 None Reply

234 SHCL/PMBRTW/CSC/2015/227 Submittal of Proposal for Adjusting the Proportions of Rock Rip Rap of Various Gradations 04/10/2015 None Reply

235 SHCL/PMBRTW/BBA/2015/165 Submittal of the Contractor’s All Risks Insurance Policy and The Third Party Liability Insurance Policy Issued by Sadharan Bima Corporation 06/10/2015 None Reply

dell
打字机文本
Page 67
dell
打字机文本
dell
新建图章
Page 71: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

236 SHCL/PMBRTW/BBA/2015/166 Application of Electricity for RTW Construction Yard at Kaora kandi 06/10/2015 50.201.000.00.00.710.2014-1054 06/10/2015 Replied

237 SHCL/PMBRTW/CSC/2015/229 Submittal of Proposal of Open-Celled Concrete Pavers 07/10/2015 None Reply

238 SHCL/PMBRTW/CSC/2015/230 Submittal of Monthly Environmental Report No.7 for the Month of September 2015 07/10/2015 Email:10:31 04/10/2015 04/10/2015 Need to be

revised

239 SHCL/PMBRTW/CSC/2015/231 Submittal of Monthly Healthy and Safety Report No.7 for the Month of September 2015 07/10/2015 None Reply

240 SHCL/PMBRTW/CSC/2015/232 Submittal of Monthly Environmental Report No.7 for the Month of September 2015 (Second Edition) 07/10/2015 None Reply

241 SHCL/PMBRTW/CSC/2015/233 Submittal of Proposal of Expanding the Construction Site at Kaora kandi 07/10/2015 Email: 17:38 10/06/2015 10/06/2015 Replied

242 SHCL/PMBRTW/CSC/2015/234 Submittal of Interim Payment Application No.07 06/10/2015 Need to be revised

243 SHCL/PMBRTW/CSC/2015/235 Submittal of Test Reports VII of 400 GSM Geo-bags and 600 GSM Geo-bags 08/10/2015 None Reply

244 SHCL/PMBRTW/CSC/2015/236 Submittal of Fourth Joint Interim Survey Report: Initial Dredging Area from Sta. 0-800 to Sta. 0+000 in South Bank (Janjira Side) 07/10/2015 None Reply

245 SHCL/PMBRTW/CSC/2015/237 Submittal of Dredged Material Management Plan 11/10/2015 None Reply

246 SHCL/PMBRTW/CSC/2015/239 Request for Getting Access to and Possession of B1 as the Dredging Material Disposal Area in 20152016 Dry Season 11/10/2015 None Reply

247 SHCL/PMBRTW/CSC/2015/240 Submittal of Adjusted Proposal of Excavating Approach Channel at Kaora Kandi 11/10/2015 Email: 20:23 13/10/2015 13/10/2015 Replied

248 SHCL/PMBRTW/CSC/2015/241 Request for Commencement of the Permanent Works on the South Bank 15/10/2015 Email: 15:57 24/10/2015 24/10/2015 Not Approved

249 SHCL/PMBRTW/CSC/2015/242 Submittal of Final Copy of Construction Environmental Action Plan (Seventh Edition) 15/10/2015 Email: 15:34 18/10/2015 18/10/2015 Approved

250 SHCL/PMBRTW/CSC/2015/243 Submittal of Revised Interim Payment Application No.07 15/10/2015 KEC-180-SIN 19/10/2015 Approved251 SHCL/PMBRTW/CSC/2015/244 Report of Pending Issues to be Resolved 01/11/2015 Email:13:22 25/10/2015 25/10/2015 Replied

252 SHCL/PMBRTW/BBA/2015/171 Request for BBA’s Assistance in Waiving of Branch Office Set Up Permission Registration 18/10/2015 50.01.0000.201.14.738(P-

1)-14-1096 15/10/2015 Replied

253 SHCL/PMBRTW/BBA/2015/172 Request for Possessing more land as Construction Yard on South Bank 19/10/2015 50.01.0000.201.14.745.14-1149 28/10/2015 Replied

254 SHCL/PMBRTW/CSC/2015/245 Submittal of Revised Proposal of Open-Celled Concrete Pavers 19/10/2015 Email: 17:46 28/10/2015 28/10/2015 Approved

255 SHCL/PMBRTW/CSC/2015/246 Apply to Stop the Use of Cylinder Specimens on CC Block Molding Machine 19/10/2015 None Reply

256 SHCL/PMBRTW/CSC/2015/247 Submmital of ISO Certification of Seven Circle (Bangladesh) Limited Khulna Factory 19/10/2015 None Reply

257 SHCL/PMBRTW/CSC/2015/248 Submittal of Revised Proposal of Berthing Facilities for Boats 19/10/2015 None Reply258 SHCL/PMBRTW/CSC/2015/249 Submittal of Technical Proposal for 2015-2016 Dry Season 19/10/2015 None Reply

dell
打字机文本
Page 68
dell
打字机文本
dell
新建图章
Page 72: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

259 SHCL/PMBRTW/CSC/2015/250 Clarification of Application for Commencement of the Permanent Works on South Bank 19/10/2015 Email: 15:57 24/10/2015 24/10/2015 Not Approved

260 SHCL/PMBRTW/CSC/2015/251 Submittal of Supplementary Information of Diving Method 29/10/2015 None Reply

261 SHCL/PMBRTW/CSC/2015/252 Submittal of Proposal on the Storage of Backfilling Material used for Embankment Construction in 2015-2016 Dry Season 29/10/2015 None Reply

262 SHCL/PMBRTW/CSC/2015/253 Submittal of Test Reports VIII of 400 GSM Geo-bags and 600 GSM Geo-bags 27/10/2015 None Reply

263 SHCL/PMBRTW/CSC/2015/254 Submittal of Post-monsoon Survey Data on Mawa Side 30/10/2015 None Reply264 SHCL/PMBRTW/CSC/2015/255 Reply for CSC Letter about Report of Pending Issues to be Resolved 30/10/2015 None Reply265 SHCL/PMBRTW/CSC/2015/256 Submittal of Dredged Materials Management Plan (DMMP) 01/11/2015 None Reply266 SHCL/PMBRTW/CSC/2015/257 Delivery of Reference Standards and Codes as Specified 30/10/2015 None Reply

267 SHCL/PMBRTW/BBA/2015/174 Request for Approval to the Mode of Advance Payment of Raw Materials and CC Blocks 03/11/2015 None Reply

268 SHCL/PMBRTW/BBA/2015/175 Claim Report for the Emergency Repairing Cost of the Temporary Jetty on the South Bank 03/11/2015 None Reply

269 SHCL/PMBRTW/BBA/2015/176 Request for Assistance on Indian Stone Supply 03/11/2015 Taken action270 SHCL/PMBRTW/CSC/2015/258 Submittal of Interim Payment Application No.08 01/11/2015 KEC-190-BBA 09/11/2015 Approved

271 SHCL/PMBRTW/CSC/2015/260 Submittal of the Technical Proposals for the Construction of Temporary Jetties

19/11/2015 None Reply

272 SHCL/PMBRTW/CSC/2015/263 Submittal of Supplementary Information of Seven Ring Cement (Khulna Factory)

07/11/2015 None Reply

273 SHCL/PMBRTW/CSC/2015/264 Submittal of Dredging Plan of the Janjira RTW Trial Section 07/11/2015 None Reply

274 SHCL/PMBRTW/CSC/2015/265 Submittal of Fifth Joint Interim Survey Report Initial Dredging Area from Sta. 7+540 to Sta.8+260 in South Bank

19/11/2015 None Reply

275 SHCL/PMBRTW/BBA/2015/179 Request for Practical Access to and Possession of Construction Site at Mawa side 11/11/2015 None Reply

276 SHCL/PMBRTW/CSC/2015/266 Proposal of the Fourth Geo-textile Material Supplier 23/11/2015 KEC-045-SIN 25/11/2015 Conditionally Approved

277 SHCL/PMBRTW/CSC/2015/267 Submittal of Method Statement of Pre-Construction Geophysical Survey 19/11/2015 None Reply278 SHCL/PMBRTW/BBA/2015/183 Request for the Adjustments in the Source of Index for Foreign Labour 22/11/2015 None Reply

279 SHCL/PMBRTW/CSC/2015/269 Request for Approval of CC Block Manufactured prior to 30th September 2015

19/11/2015 None Reply

280 SHCL/PMBRTW/CSC/2015/270 Submittal of HSE Training Report of SINOHYDRO 19/11/2015 None Reply

281 SHCL/PMBRTW/CSC/2015/271 Submittal of Final Copy of Construction Environmental Action Plan (Eighth Edition)

19/11/2015 None Reply

282 SHCL/PMBRTW/BBA/2015/184 Request to Stop the Operation of Dredgers from other Parties within RTW Construction Site for the Smooth Execution of this Project 22/11/2015 None Reply

dell
打字机文本
Page 69
dell
打字机文本
dell
新建图章
Page 73: New PADMAMULTIPURPOSE BRIDGE PROJECT · 2015. 12. 8. · Project Padma MultipurposeBridgeproject-River Training Works Client ... wassubmittedon1stNovember,2015; ... 13.02 4.52 22.31

283 SHCL/PMBRTW/CSC/2015/272 Submittal of Water Quality Test Report from Outlet of Disposal Area 19/11/2015 None Reply

284 SHCL/PMBRTW/CSC/2015/273 Submittal of Test Reports IX of 400 GSM Geo-bags and 600 GSM Geo-bags

01/12/2015 None Reply

285 SHCL/PMBRTW/CSC/2015/274 Submittal of Inspection Report III on Noise Measurement of Mawa Side 01/12/2015 None Reply

286 SHCL/PMBRTW/CSC/2015/275 Proposal of the Sixth Candidate of Laboratory Technician to be supplied 02/12/2015 Email: 12:02 29/11/2015 29/11/2015 Approved

287 SHCL/PMBRTW/CSC/2015/276 Submittal of Supplementary Information of the Fourth Geo-textile Material Supplier

01/12/2015 None Reply

288 SHCL/PMBRTW/CSC/2015/277 Sinohydro’s Suggestion regarding the works programme of Mawa after Revised Design

01/12/2015 None Reply

289 SHCL/PMBRTW/CSC/2015/278 Submittal of Revised Construction Programme of PMBP-RTW 01/12/2015 None Reply290 SHCL/PMBRTW/BBA/2015/186 Application of Vessels Removal in Mawa RTW Construction Area 30/11/2015 None Reply

291 SHCL/PMBRTW/CSC/2015/279 Response to CSC’s Instruction to Commence Preparations for Mawa RTW to be Constructed during the 20152016 Dry Season

01/12/2015 None Reply

292 SHCL/PMBRTW/BBA/2015/191 Written Confirmation of BBA’s Oral Instruction Concerning Honorable Prime Minister’s Visit on PMBP-RTW 02/12/2015 None Reply