new Perth StadiumCommunity Forum to Burswood & East Perth residents

4 & 5 February 2015

AgendaWelcome and introduction

new Perth Stadium and Sports Precinct – Ronnie Hurst, Project Director

• Project status

• Stadium and Sports Precinct facilities and design

• Construction program

• Management of nPS

Transport overview and status – Kym Hockley, Senior Transport Planner PTA

• Public transport strategy

• Victoria Park Drive

• Stadium Station

• Swan River Pedestrian Bridge

• Nelson Avenue Special Event Bus Stands

Q&As

DSR

• ‘Client’ Agency

• functional requirements

• stakeholder liaison

Strategic Projects

• Stadium Delivery Agency

• planning & delivery

Venues

West• Governance Agency

PTA & MRWA

• Transport Infrastructure

• planning & delivery

Project Team

STATE

GOVERNMENT

Pedestrian Bridge

contractor

TBC

Westadium

(DBFM contractor)

Stadium Station

contractor

TBC

ENTRY

ENTRY

The Sports Precinct – Transforming the East

REDEVELOPED GOLF CLUBHOUSE

COMMUNITY OVAL

SWAN RIVER PEDESTRIAN BRIDGE

AMPHITHEATRE

NETWORK OF

BIKE PATHS

PLAYGROUNDS &

BBQs

EASTERN ENTRY PLAZA

COMMUNITY ARBOUR

STADIUM STATION

The Sports Precinct – event and non-event day

VIEWS

A LA CARTE

BUFFET

RESTAURANT

FUNCTION

CENTRE

The Sports Precinct – event and non-event day

new Perth Stadium

Construction Program

2015 construction program

Early 2015

•Sand surcharge relocation

•Piling

•Dynamic compaction to Bridge landing area on Burswood Peninsula

•Installation of first of eight tower cranes

Mid 2015

•Structural core installation commences

•Structural steel installation commences

End 2015

•Piling complete

•First seating plats installed

•First roof trusses installed

•Landscaping of Precinct area commences

2016 construction program

Early 2016

•First seats installed

•Installation of the façade commences

End 2016

•Pitch work commences

•All roof trusses and the fabric roof in place

Mid 2016

•Last of 16 structural cores completed

•Internal fit-out commences

•All structural steel frames in place

2017 construction program

Early 2017

•Façade completed

•Hard landscaping commences

Mid 2017

•Installation of grass for the pitch completed

•Hard landscaping completed

•Internal fit out completed

End 2017

•All Stadium facilities commissioned

•Site handed over to the Stadium Operator

new Perth Stadium construction program

Construction information

• Work hours: Monday to Saturday 7am-6pm

• Sunday works and notifications

• Construction information – perthstadium.com.au

• Contact us: [email protected] or 9428 1961

Potential construction impacts

• Construction Environment Management Plan

• Noise and dust monitoring

• Traffic/parking

• River path access

• Trees and vegetation

Management of nPS

Stadium Operator responsibilities

• Day to day management of Stadium and Sports Precinct

• Secure content and manage events and functions

• Perform all of its functions alongside Westadium consortium

• Stakeholder engagement as appropriate (state agencies, local government,

local residents and local community)

Operator procurement process

• February 2015 – Expressions Of Interest (EOI) issued

• January 2016 – Contract award

• 2016/2017 – Transition to operations

new Perth Stadium

Transport

Transport solution

Public transport will move 83% of a

capacity crowd within one hour of

an event finishing

Victoria Park Drive

Concrete bridge deck pour in December 2014

Stadium Station

Overview

• 28,000 people

• Train leaves every 2mins

following an event

• Three island platform

• 120 railcars stowed in Burswood

and Victoria Park

Work status

• Design 85% complete

• Associated rail infrastructure 15%

complete

Stadium Station layout

Swan River Pedestrian Bridge

Swan River Pedestrian Bridge Working Group

Confirmed functional design elements

Police and Ambulance emergency vehicle access only if required

Access on non-event days

East Perth landing to channel pedestrians south along Nelson Avenue

Location provides best access to parking bays in East Perth and CBD shuttle

Swan River Pedestrian Bridge artist impression

Swan River Pedestrian Bridge-East Perth landing

Project schedule

December 2014

• Stadium and Sports Precinct construction commenced

Late 2015

• Swan River Pedestrian Bridge construction commences

• Stadium Station construction begins

Early 2016

• Operational planning commences with Stadium Operator

Late 2016

• Swan River Pedestrian Bridge and Bus Standsconstruction complete

Mid 2017

• Stadium Station construction complete, commissioning begins

• Rail operational plans finalised

Late 2017

• Stadium Station commissioning complete

• Stadium and Sports Precinct construction complete, transition to operations

March 2018

Stadium and Sports Precinct opens for start of AFL season and all public transport facilities are operational

@newPerthStadium new Perth Stadium newPerthStadium

www.perthstadium.com.au

Email: [email protected]

Phone: 9428 1961

Q&As