Riverbanks Zoo and Garden Phase II, Seals and Sea Lions
03.14-03.18
2016
RIVERBANKS ZOO AND GARDEN PHASE II, SEALS AND SEA LION EXHIBIT:
EXHIBIT POOL, VIEWING & HOLDING BUILDINGS
-
Perspective of the New SSL Exhibit from the Main Entrance Plaza
-
Perspective of the North End Of the SSL Exhibit
-
Perspective of the Stadium Seating Area Looking East
-
Perspective of the Stadium Seating Area Looking South
-
Perspective of the Northwest Corner of the Viewing Building
-
Exhibit Pool Window at the Entrance to the Viewing Building
-
The Interior of the Viewing Building Ready to Receive Guests
-
The Interior of the Viewing Building Ready to Receive Guests
-
Perspective of the Southwest Corner of the Viewing Building
-
Perspective of the South Entrance to the Viewing Building
-
The Rustic Fencing Progresses Between Viewing and Tortoise
-
Pedestrian Walkway Tie-In to the South Plaza at the Viewing Building
-
Perspective of the Stadium Seating Area From the Viewing Deck
-
Perspective of the Western Portion of the Viewing Deck
-
Perspective of the Southern Portion of the Viewing Deck
-
Perspective of the Holding Building from the Upper Viewing Deck
-
Perspective of the Holding Building from the Upper Viewing Deck
-
Perspective of the Viewing Building from the Holding Building
-
Perspective of the Viewing Building from the Holding Building
-
Perspective of the Viewing Building from the Holding Building
-
Eastern Perspective of the Holding Building
-
Holding and Quarantine Pools Filled with the LSS Start Up
-
Interior of the Holding Building Ready to Receive Animals
-
Northwestern Perspective of the Holding Building
-
Hard and Softscape Completed Around the Buildings
-
Fencing Completed Between LSS and Bird Buildings
-
Concrete and Asphalt Placement Completed at Access Road
-
Riverbanks Zoo and Garden Phase III, Pedestrian Bridge
03.14-03.18
2016
RIVERBANKS ZOO AND GARDEN PHASE III, PEDESTRIAN BRIDGE PROJECT
-
Foundations for the South Elevator Tower have been Placed
-
Elevator Pit CIP Walls Stripped and Ready for Waterproofing
-
Bridge Abutment Foundation Completed for the South Side
-
Micropiles Begin for the North Elevator Tower Footings
-
Perspective of the New Front Entry from the North Tower Site
-
One Week Look Ahead The Life Support Systems Commissioning process is to be completed this week; with
Owner Training for the Defender Filters and Ozone Generators completed yesterday. The
Final Inspections from the City of Columbia as well as the Fire Marshal where received this
week. Owner and Architect Inspections and Punch for the completed Hardscape work is
scheduled for next week. Preparations for the turn over of Phase II, Holding and Viewing
Buildings to the Owner are ongoing.
The Pedestrian Bridge Project is
making progress with the Foundation
Footings placed and vertical cast in
place wall erection beginning for the
South Tower. Micropiles are being
installed starting today for the North
Tower, and should be completed next
week. The additional storm piping for
the North Site was completed
yesterday. Pyramid Masonry to begin
next week and will start erection of the
CMU walls on the South Tower.
-