    NEW TOWN HEIGHTS DLF KAKKANADWORK PROGRESS REPORT FOR THE MONTH OF NOV 2010

    Click to proceed..

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    2/12

    Dear Sir,

    We are glad to inform you that the construction activities are in full swing atNew Town Heights DLF Kakkanad, in all the launched towers. Please findbelow the Tower wise progress report.

    Tower 6 / Block N

    9th floor slab casting work in progress. Apartment block work completed till 4th floor and is progressing on the 5th floor.

    Tower 6 / Block P 9th floor slab shuttering work in progress.

    Apartment block work completed till 4th floor and is progressing on the 5th floor.

    Tower 6 / Block Q 10th floor slab casting completed. Column work for the 11th floor in progress. Apartment block work completed till 4th floor and is progressing on the 5th & 6th floors

    Tower 5 / Block K 8th floor slab casting work completed.

    Tower 5 / Block L 6th floor slab casting in progress

    Block work in progress

    Tower 5 / Block M 6th floor slab casting completed

    7th floor slab shuttering work in progress Block work in progress

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    3/12

    We are also attaching the site progress photographs along with this.

    Tower 4 / Block H

    Stitched slab work in progress

    Tower 4 / Block J

    1st level slab shuttering in progress

    Tower 3 / Block G 8th floor slab casting work in progress.

    Tower 2a / Block D 2nd floor slab casting work in progress.

    Tower 2b / Block E

    1st floor slab shuttering work completed.

    Tower 2b / Block F Ground floor slab casting completed.

    Tower 1 / Block A 7th floor slab casting wok in progress Block work in progress

    Tower 1 / Block B 11th floor slab casting in progress

    Block work in progress

    Tower 1 / Block C 5th floor slab casting in progress.

    Block work in progress

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    4/12

    TOWER 6, BLOCK N 9th

    floor slab casting work inprogress

    TOWER 6, BLOCK P 9thfloor slab shuttering work

    in progress.

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    5/12

    TOWER 6, BLOCK Q

    10th floor slab castingworks completed

    TOWER 5, BLOCK K 8th

    floor slab casting workscompleted

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    6/12

    TOWER 5, BLOCK L 6th floor slab casting

    work in progress

    TOWER 5, BLOCK M 6th floor slab casting

    completed. 7th floor slabshuttering work in

    progress

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    7/12

    TOWER 4, BLOCK H Pile cap works &

    stitched slab in progress

    TOWER 4, BLOCK J 1st level slab shuttering

    works in progress

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    8/12

    TOWER 3, BLOCK G 8th

    floor slab casting work inprogress

    TOWER 2a, BLOCK D 2nd

    floor slab casting work inprogress.

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    9/12

    TOWER 2b, BLOCKE 1st floor slab

    shuttering workscompleted.

    TOWER 2b,

    BLOCK F Groundfloor slab castingwork completed

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    10/12

    TOWER 1, BLOCK A 7th floor slab casting

    work in progress.

    TOWER 1, BLOCK B 11th

    floor slab casting in progress

  • 8/8/2019 New Town Heights DLF - Kakkanad (Work Progress Report for the Month of Nov 2010)

    11/12

    TOWER 1, BLOCK C 5th floor slab casting

    work in progress.

    Club House piling work inprogress