News from CALICE. Paul Dauncey Imperial College London. CALICE continues to grow. CALICE currently 138 physicists, 24 institutes, 8 countries Four new institutes have joined since the summer Seoul: digital HCAL front end electronics U. Texas Arlington: GEMs for the digital HCAL - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: News from CALICE

4 November 2002 Paul Dauncey - CALICE News 1

News from CALICE

Paul Dauncey

Imperial College London

Page 2: News from CALICE

4 November 2002 Paul Dauncey - CALICE News 2

CALICE continues to growCALICE currently 138 physicists, 24 institutes, 8 countries

Four new institutes have joined since the summer• Seoul: digital HCAL front end electronics• U. Texas Arlington: GEMs for the digital HCAL• NICADD (N. Illinois): scintillating tiles for the digital HCAL• Dubna (two groups): RPCs for the digital HCAL

There are potentially four new groups in addition• Boston, Chicago, Illinois: already informally working with

Argonne on RPCs for the digital HCAL• FNAL: new approach, possibly also RPCs for the digital HCAL

AFAIK, outside Asia, this leaves few non-CALICE groups• Europe: only Italian LCCAL (sci tile ECAL)• US: SLAC/Oregon (Si-W ECAL), Caltech (PbWO4 crystals)

Page 3: News from CALICE

4 November 2002 Paul Dauncey - CALICE News 3

CALICE scope increasing tooNew collaborators allow the project to expand• Silicon-tungsten still only ECAL option

• Although there is pressure to merge with the Italian LCCAL scintillating tile/silicon ECAL group

• Scintillating tiles still only analogue HCAL option• Regarded (externally, e.g. by DESY PRC) as baseline HCAL option

• Fine-grained HCAL with digital readout; now several options• RPCs: large US and Russian effort• Small scintillating tiles: only NICADD• GEMs: only UTA

Unfortunately, not all on the same schedule• New options starting from scratch; further behind• But desirable (and politicially necessary) to beam test all options• The schedule has changed; we need to handle this carefully

Page 4: News from CALICE

4 November 2002 Paul Dauncey - CALICE News 4

Silicon wafer production (Prague, Russia): 29 good wafers (out of 30) so far; 270 needed.

Very front end chip (Orsay) with 18 channels, CR-RC shaper and multiplexer. Prototype back from fabrication Sept; currently under test. PCB to hold chips and silicon wafers under design, production in 2003.

ECAL progress

Tungsten plates (Russia) have thickness and density within tolerance.

First carbon fibre mechanical structure (France) and insert; carbon fibre structure show good mechanical behaviour.

ECAL still on schedule for early 2004

Page 5: News from CALICE

4 November 2002 Paul Dauncey - CALICE News 5

Analogue HCAL progressDetailed study done of many combinations of scintillating tiles, wavelength-shifting fibres, mechanical coupling and photodetectors (DESY, Prague, Russia)

• Example of tile-fibre geometry dependence; varies from ~9 to ~25 p.e./MIP

Analogue HCAL ready by mid 2004

Page 6: News from CALICE

4 November 2002 Paul Dauncey - CALICE News 6

Digital HCAL: RPCs, GEMs, SciTilesRPCs: glass resistive plates, anode pads outside gas gap

SciTiles: hexagonal tiles, spray-painted white with WLS fibres

GEMs: foil with 75m holes above 11 cm2 pads

RPCs ready by mid 2004, SciTiles by end 2004, GEMs by early 2005 (a few layers only)

Page 7: News from CALICE

4 November 2002 Paul Dauncey - CALICE News 7

HCAL readout electronicsAnalogue option• Front end electronics; three ASICs being considered

• One is Orsay VFE chip as used for ECAL (with minor modifications)

• Back-end electronics; no bid within collaboration yet• Use of UK back end electronics still being discussed• Choice of Orsay VFE chip would make this straightforward• Other options might not work with UK readout boards

Digital options• Front end electronics; under development (France/Korea)

• Simple Q-V “conditioner” circuit feeding FPGA directly• Could be used for any/all options (if pedestals and gains are uniform)

• Back-end electronics; again, no bid yet• Reuse UK readout boards? Bypass ADCs so act as LVDS-VME interface• Leads to common DAQ system

Page 8: News from CALICE

4 November 2002 Paul Dauncey - CALICE News 8

Beam test statusBeam test schedule is changed due to HCAL schedule• Our proposal said 6 months from ~Apr to Sep 2004• Now, analogue and RPC options only available by mid 2004• SciTile and GEM options need to be tested in 2005

Schedule is now 1 year, from mid 2004 to mid 2005• Not necessarily continuous, not necessarily at one site

Still no site decision!• CERN now less likely, given schedule change• FNAL setting up new beamlines in 2003 (if effort available)

• Favoured option if available (especially if FNAL become collaborators)

• Russians pressing hard for Protvino• They have said they will cover cost of beamline setup• But there are safety concerns

Page 9: News from CALICE

4 November 2002 Paul Dauncey - CALICE News 9

Implications for the UKHow do we change our schedule? Several pressures• ECAL aims to still be ready by early 2004

• Need to be able to read it out on bench to check OK• May even go for ECAL-only beam test at DESY

• Delay in approval has meant no RAL ID effort• Electronics original schedule had completion by Dec 2003• Probably too tight now; need several extra months

• PPRP will need explanation about schedule• If we slip, we have to explain why it is OK, given previous stance• We will also need to request funding for FY05/06

My proposal for this• Delay electronics schedule by three months to Mar 2004• Expand into FY05/06 as “exploitation” only• Think of some way to convince PPRP this is not a big deal…