SOFT GROUND IMPROVEMENT BY PREFABRICATED VERTICAL DRAIN
(PVD)
NOR AISAH BINTI KHALID
A project reportsubmitted in fulfilment of the
requirements for the award of the degree of
Master of Enineering (Civil-Geotechnics)
School of Engineering
Faculty of Civil Engineering
Universiti Teknologi Malaysia
DISEMBER 2018
iii
DEDICATION
This thesis is dedicated to my father, who taught me that the best kind of
knowledge to have is that which is learned for its own sake. It is also dedicated to my
mother, who taught me that even the largest task can be accomplished if it is done
one step at a time.
iv
ACKNOWLEDGEMENT
The completion of this thesis, I’m very gratefull to ALMIGHTY “ALLAH S.W.T”.
Without his grace and blessing this study would not have been possible. Firstly, I
would like to thank the department of civil engineering for giving me the opportunity
to produce this thesis by providing facilities such as equipment machine to enable me
to make a sample and done the testing. I also like to thank to my supervisor,
Associate Prof. Ir. Dr. Azman Bin Kassim who have provided guidance and detailed
explanation to me from start until the thesis was completed. Besides, I want to thank
my examiner, Muhammad Azril Hezmi and Dr Norzurairahetty Mohd Yunus. I
would like to state the highest gratitude towards my parents had a lot of support and
encouragement morally and financially in producing this paper. Thanks are also
owed to whosoever had contributed to this work either directly or indirectly. Your
support to successful accomplishment of this project will never forget from my
memory. My most gracious appreciation to my friends. Who were hardworking in
produced this thesis and are willing to exchange ideas in helping me prepare this
special work.
v
ABSTRACT
Soft soil improvement in the project requires the consideration of the
preloading programme. This method long track record of success and may be
a unexpected time delay. Then one of the solutions is to use surcharge that fill
must extend horizontally at certain depth beyond the perimeter of the planned
construction. Surcharge must remain in place for months or years, thus
delaying construction. Since this project needs to be completed within 2 years
and the time given to increase the soil strength is 6 months only. Based on
that reason, Prefabricated Vertical Drain (PVD) was added to expedite this
process. It decreases the overall time required for completion of primary
consolidation and also decreases the amount of surcharge load required to
achieve the same desired amount of consolidation over a given period of
time.At BH 9 and BH10, without surcharge the untreated ground would
required about 2.5 year time to eliminate most of settlement. To achieve
99.3% and 99.2 % degree of consolidation the estimated time required is
about 1.5 year. PVD was adopted to expedite the consolidation settlement.
The consolidation degree 99.3 % were required to ensure that anticipated
consolidation settlement of 895mm and 901mm due to permanent fill alone
and compensation settlement permanent fill are completely eliminated and no
excess pore water pressure left in the soil for BH9 and 860.56mm and
868.066mm for BH10. With the introduction of PVD and surcharge fill of
1m, the required degree of consolidation, Ureq of 99.3% (borehole 9) and
99.2% (borehole 10) was expected to be expedited within a designed rest
perod of 6 months. However the evaluation against settlement monitoring
results indicated that the corresponding achieved degree of consolidation over
6 months time was about or more than 90% but less than 99.3%
vi
ABSTRAK
Penambahbaikan tanah lembut dalam projek memerlukan pertimbangan
program preloading. Kaedah ini mencatat rekod kejayaan yang panjang dan mungkin
merupakan kelewatan masa yang tidak dijangka. Kemudian salah satu daripada
penyelesaiannya adalah dengan menggunakan Surcharge yang mengisi mesti
horizontal consolidation pada kedalaman tertentu di luar perimeter pembinaan yang
dirancang. Surcharge harus tetap di tempat selama berbulan atau tahun, sekali gus
melambatkan pembinaan. Oleh kerana projek ini perlu disiapkan dalam masa 2 tahun
dan masa yang diberikan untuk meningkatkan kekuatan tanah adalah hanya 6 bulan.
Berdasarkan sebab itu, Prefabricated Vertical Drain (PVD) telah ditambah untuk
mempercepat proses ini. Ia mengurangkan masa keseluruhan yang diperlukan untuk
menyelesaikan penyatuan utama dan juga mengurangkan jumlah beban Surcharge
yang diperlukan untuk mencapai jumlah pemampatan yang diinginkan yang sama
sepanjang tempoh tertentu. Pada BH 9 dan BH10, tanpa surcharge tanah yang tidak
dirawat memerlukan sekurang-kurangnya 2.5 tahun untuk menghapuskan
kebanyakan penyelesaian. Untuk mencapai tahap penyatuan 99.3% dan 99.2%,
anggaran masa yang diperlukan ialah 1.5 tahun. PVD telah digunakan untuk
mempercepat penyelesaian penyatuan. Penyatuan 99.3% diperlukan untuk
memastikan bahawa penyelesaian konsolidasi yang dijangkakan dari 895mm dan
901mm disebabkan oleh pemanggilan tetap dan penyelesaian pemendapan kekal
sepenuhnya dihapuskan dan tiada tekanan air liang berlebihan yang tersisa di dalam
tanah untuk BH9 dan 860.56mm dan 868.066mm untuk BH10 . Dengan pengenalan
PVD dan Surcharge mengisi 1m, tahap penyatuan yang diperlukan, Ureq 99.3%
(BH9) dan 99.2% (BH10) dijangka dipercepatkan dalam perod istirehat yang
dirancang selama 6 bulan. Walau bagaimanapun penilaian terhadap keputusan
pemantauan penyelesaian menunjukkan bahawa tahap penyatuan yang sama yang
dicapai dalam tempoh 6 bulan adalah kira-kira atau lebih daripada 90% tetapi kurang
daripada 99.3%.
vii
TABLE OF CONTENTS
TITLE PAGE
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENT ivv
ABSTRACT v
ABSTRAK vi
TABLE OF CONTENTS vii
LIST OF TABLES ixx
LIST OF FIGURES x
LIST OF ABBREVIATIONS xi
LIST OF SYMBOLS Error! Bookmark not defined.
LIST OF APPENDICES xxiv
CHAPTER 1 INTRODUCTION 1
1.1 Problem Background 4
1.2 Problem Statement 5
1.3 Objective of study 5
1.4 Scope of study 5
CHAPTER 2 LITERATURE REVIEW 7
2.1 Ground Improvement 6
2.1.1 Physical Stabilization 7
2.1.2 Chemical Stabilization 9
2.2 Surcharge Preloding 11
2.3 Drain properties 17
2.4 Properties of filter 19
2.5 Prefabricated Vertical Drain (PVD) Design 20
viii
CHAPTER 3 RESEARCH METHODOLOGY2Error! Bookmark not defined.
3.1 Case Study 2Error! Bookmark not defined.
3.2 Soil investigation 24
3.3 Subsoil condition 27
3.4 Geotechnical Design
3.4.1 Primary consolidation Settlement Analysis 33
3.4.2 Horizontal Consolidation Settlement Analysis 36
3.5 Ground improvement work 38
3.6 Instrumentation 41
3.7 Prefabricated Vertical Drain Installation 44
CHAPTER 4 RESULT AND DISCUSSION
4.1 Primary Consolidation Settlemnt without
PVD (BH9) 48
4.2 Horizontal Consolidation Settlement analysis
with PVD and time-rate of settlemnt 56
4.3 Consolidation settlement anlysis without
PVD (BH10) 60
4.4 Horizontal Consolidation Settlment analysis
with PVD and time-rate of settlement (BH10) 67
CHAPTER 5 CONCLUSION AND RECOMMENDATIONS 73
5.1 Conclusion 7Error! Bookmark not defined.
5.2 Recommendation 74
REFERENCES 75
ix
LIST OF TABLES
TABLE NO. TITLE PAGE
Table 3.1 Description of borehole 8 34
Table 3.3 Description of borehole 9 36
Table 3.4 Design parameter for consolidation settlement analysis 42
Table 3.5 The radial drainage properties adopted into the
horizontal consolidation analysis with PVD 46
Table 3.6 Ground improvement 48
Table 3.7 Method for ground improvement. 49
Table4.1 Final settlement = 892.464m 65
Table 4.2 Settlement curve with surcharge 66
Table 4.4 : With preloading alone or withoud Prefabricated
vertical loading (PVD), the analysis result of
primary consolidation settlement are summarized 68
Table 4.5 The specific time that achieved required uh is then
the optimal time for such drain spacing 70
Table 4.6 The following table is the estimated required resting
time with various spacing of Preafabricated
vertical drain (PVD) 71
Table 4.7 The computation of time-rate of settlement by
integrating prealoading and PVD 72
Table 4.9 Value of settlement without surcharge versus time 78
Table 4.10 Value of settlement Versus Time for Surcharge 79
Table 4.11 The specific time that achieved required uh is then the
optimal time for such drain spacing 84
Table 4.12 The following table is the estimated required resting time
with various spacing of Preafabricated vertical drain (PVD) 84
Table 4.14 : The computation of time-rate of settlement by integrating
prealoading and PVD 85
x
LIST OF FIGURES
FIGURE NO. TITLE PAGE
Figure 2.1 Principle precompression 11
Figure 2.2 Plot of U against ∆σ(ρ)/∆σ(f) for values of
∆σ’(p)/σ’o 12
Figure 2.3 Soil close to be midplane will continue to settle1Error! Bookmark not defined.
Figure 2.4 Plot of midplane degree of consolidation against Tv 14
Figure 2.5 (a) and (b) : Sand drains 15
Figure 2.6 Conceptual illustration of band-shaped PVD and
equivalent diameter of drain well
( Indraratna et al.,2005a ) 17
Figure 2.7 Assessment of equivalent diameter of band-sshaped
vertical drains (indraratna et al., 2005a) 18
Figure 2.8 A typical cross-section of band shaped drain
(Holtz et al., 1991) 18
Figure 3.1 Proposed site is in Lahad Datu, Sabah, Malaysia 23
Figure 3.2 Location of borehole 8 24
Figure 3.3 Location of Borehole 9 25
Figure 3.4 Location of borehole 10 26
Figure 3.5 Soil Profile 40
Figure 3.6 Sketch of ground improvement at BH 9 50
Figure 3.7 Sketch of ground improvement at BH 10 50
Figure 3.8 Synthetic core 52
Figure 3.9 Geotextile filter jacket 52
Figure 3.10 Anchor Plate and Wick Drain. 53
Figure 3.11 Mandrel together with Anchor Plate 54
Figure 3.12 Prefabricated Vertical Drain Installation 55
xi
Figure 3.13 Illustration of construction sequence 58
Figure 4.4 Settlement Curve without Surcharge 64
Figure 4.2 Settlement Curve for Surcharge (895.021mm) 67
Figure 4.3 Settlement Curve for Surcharge ( 901.442mm) 67
Figure 4.4 Graph for settlement curve with and without PVD 73
Figure 4.5 Degree of consolidation curve for with and without PVD 73
Figure 4.6 Settlement Curve without Surcharge ( 860.56mm) 79
Figure 4.7 Settlement curve for surcharge (868.066mm) 80
Figure 4.8 Settlement curve for surcharge 81
Figure 4.9 With preloading alone or withoud Prefabricated
vertical loading (PVD), the analysis result of
primary consolidation settlement are summarized. 82
Figure 4.10 : Degree of consolidation with and without PVD 87
xii
LIST OF ABBREVIATIONS
Cc - Compression Index
Ch - Horizontal coefficient of consolidation
CR - Compression ratio
Cr - Recompression Index
Cv - Vertical coefficient of consolidation
De - Diameter of equivalent cylinder of soil
dm - Diameter of mandrel
ds - Diameter of smear zone
dw - Equivalent well diameter
eo - Initial void ratio
F - Factor considering three compenet
F(n) - Drain spacing factor
F(r) - Well resstance factor
F (s) - Smear effect factor
H - Thickness of compressible layer
Hd - length of drainage path
Ho - initial thickness of compressible soil layer
Kh - Hotrizontal permeability coefficient
Ks - Reduced permeability coefficient in the smear zone
Kv - Vertical permeability coefficient
Ldrain - Length of vertical drain
N - Spacing ratio
OCR - Over consolidation ratio
P’c - Preconsolidation pressure
P’o - Initial effective stress
Qw - Discharge capacity of drain
S - Drain or well spacing
S - Smear ratio
Sc - Primary consolidation settlement
Sn - Settlement at specific time
Sp - Final primary settlement
St - Magnitude of settlement at specific time
Sult - Ultimate primary settlement
F - Time or duration
Th - Horizontal time factor
Tv - Vertical time factor
xiii
Uav - Average or overall degree of consolidation
Uh - Degree of horizontal consolidation
Ureq - Required cegree of consolidation
Uv - Degree of vertical consolidation
Uw - Pore water pressure
σt - Total vertical stress
γbulk - Bulk density
Pcp - Primary consolidation settlement due to permanent
embankment load
Pc(p+f)- - Primary consolidation settlement due to surcharge preloading
xiv
LIST OF APPENDICES
APPENDIX TITLE PAGE
Appendix A Drawing that contain location of Borehole 76
Appendix B Detail borehole including type and depth of
soil and SPT-N value 77
Appendix C Drawing Detail of Chainage 78
1
CHAPTER 1
INTRODUCTION
1.1 Problem Background
Ground Improvement Technology may be utilized as a treatment for the
unacceptable subsurface conditions specially in soft clay. Soft ground improvement
is for soft soil that have low bearing capacity and high compressibility of these
deposits affect the long term stability of major infrastructure such highway
embankment. Therefore it is imperative to stabilize these soil before commencing
construction to prevent unacceptable settlement. One of oldest and simplest methods
is removal and replacement simply to remove and replace the soil. Soils that will
have to be replaced include contaminated soils or organic soils this method is usually
practical only above the groundwater table.
In the past, various method was use for the ground improvement. Its
categorizes into two which is by chemical stabilization and mechanical stabilization.
For the Chemical Stabilization. The method include the Lime Stabilization, Cement
Stabilization and Fly Ash Stabilization. For the Mechanical Stabilization, its include
vibroflotation, Dynamic Compaction, Blasting, Precompression and Sand Drain.
Well known that compressibility and shear strength of soil can be greatly improved if
water content in soil can be significantly reduced. One common method improving
soft soil is to be reduce the water content of soil through consolidation. For
consolidation to occur it must be an increases the effective stress. This can be
achieve by increase the total stress or reduce pore water pressure. Some recent
development of soft soil consolidation and soft soil improvement are review. Over
the year preloading have been use to more conventional the original compacted sand
drain.
2
According to soil classification system, soil improvement through
consolidation or preloading belong to the category of ground improvement
without admixture in cohesive soil. Preloading is best suited for soft, fine-
grained soils that will experience excessive settlement under a structure’s
load. Fill soil utilized for preloading is typically delivered to the area with
dump trucks. Dozers are then used to push the soil into a mound. The
mound’s height depends on the pressure required to achieved desired
improvement. In very soft sites, piezometers and inclinometers may be
required to avoid the abrupt placement of fill.
However, depending how preloading is applied, this method can be
subdivided into preloading using fill, preloading using fill, preloading using
vacuum pressure and combination between combined fill and vacuum
preloading method. Because of the min risk of damage to utilities from lateral
ground movement and significant reduction in the price of flexible, the
combination between combined fill and vacuum preloading method has been
choosen. Since most compressible low-lying soils have very low permeability
and are often thick, a length time period is usually needed to achieved the
desired primary degree of consolidation. One drawback of this surcharge
technique is that not suitable to be applied for a sufficiently long period
which may at time become impractical due to stringent construction schedule
and deadlines. From that reason combination of preloading and surcharge h
When surcharge pressure is applied which is to increase the effective stress is
depends on the dissipitation of pore water. Their installation can significantly
reduce the preloading period Once sufficient consolidation has occurred, the
fill can be removed and construction process takes place. The surcharging
method places soil fill on-site to pre-consolidate existing soil prior to
construction. Combination preloading and surcharge is one of the most
successful technique for improving shear strength of low-lying area because
it load the ground surface to induce a greater part of ultimate settlement t. In
order to control the development of excess pore pressure a surcharge is
usually raised as a multi-stage exercise with rest period between the loading
stage. In this instances, the height of surcharge can be excessive for an
economic perspective and stability consolidation. Since soft soils have low
3
permeability, the desired consolidation takes very long time to occur, even
with very high surcharge load. Therefore with tight construction schedules,
combination of preloading and surcharge may not be a feasible solution.
Hence, sand or vertical drains may be used to accelerate consolidation
process by reducing the drainage paths length.
Therefore Prefabricated Vertical Drain (PVD) become part of these
core technologies. Prefabricated Vertical Drain (PVD) have been used
successfully in many soil improvement and highway embankment in the
world. Design and construction method for soft soil improvement .
Prefabricated Vertical Drain (PVD) have also been used for some other
relatively new method such as dynamic consolidation for clay. In both case
the main purpose of using Prefabricated Vertical Drain (PVD) is apply
drainage part that the time taken for the consolidation of soft soil or
dissipitation of excess pore-water pressure can be substantially reduced.
Prefabricated Vertical Drain (PVD) can be install quicker with min
environmental implication and quarrying requirements. Prefabricated Vertical
Drain (PVD) also known as wick drains consist of channeled synthetics core
wrapped in geotextile fabric. They are flexible, durable, inexpensive and have
an advantage over sand drains is that they don't need drilling. as been applied
to shorten the time period.
4
1.2 Problem Statement
At sites where an inadequately performing subsurface material may
negatively impact the stability, function or construction system. Ground
Improvement Technology serves to improve or stabilize the subsurface material’s
performance or to improve the load conditions applied to the unsatisfactory
subsurface material. Soft soil improvement in the project requires the consideration
of the preloading programme. This method long track record of success and may be a
unexpected time delay. Then one of the solutions is to use surcharge that fill must
extend horizontally at certain depth beyond the perimeter of the planned
construction. Surcharge must remain in place for months or years, thus delaying
construction. Since this project needs to be completed within 2 years and the time
given to increase the soil strength is 6 months only. Based on that reason,
Prefabricated Vertical Drain (PVD) was added to expedite this process. It decreases
the overall time required for completion of primary consolidation and also decreases
the amount of surcharge load required to achieve the same desired amount of
consolidation over a given period of time. More than that it increases the rate of
strength gain due to consolidation of soft soils when short-term stability is of
concern.
1.2.1 Research Objectives
The objectives of the research are :
1. Interprete borelog from the site investigation about the soil conditions for
design purposes.
2. Calculate settlement due to preloading.
3. Calculate settlement due to preloading surcharge and prefabricated vertical
drain (PVD)
5
1.3 SCOPE OF STUDY
This study is based on soil investigation work from Lahad Datu,
Sabah, Malaysia. The sample collected consist three (3) number of borehole
that can be interprete about the type of soil and the depth of soft clay. These
data are listed to determine soil profile. The scope of analysis and discussion
are limited to the objective of study which is the settlement value correlation
with the time from variation condition of ground improvement either by
preloading, combination preloading surcharge and preloading surcharge
combined with Prefabricated Vertical Drain (PVD). Instrumentation
Prefabricated Vertical Drain (PVD) was selected in the field is desirable as it
provided insight to the consolidation distribution development with depth.
Calculation and analysis for the design criteria were carrying out by applying
manual calculation and misrosoft excel that will come out with the graph
settlement vs time and degree of consolidation vs time.
79
REFERENCES
Nurulizuwane Mat Saruji (2015), S.-H. (2003) ‘Primary Consolidation Settlement
analysis using Preloading Technique and Prefabricated Vertical Drain.Master
Thesis’, Universiti Teknologi Malaysia, Skudai.
Binbin Xu and Wei Si (2017), Surcharge Preloading Consolidation Analysis of
Coastal Road Considering Permeability of Dredged Soil, IOP EBook. Earth
and Environment Science 61(2017) 012128.
Buddhima Indraratna, Cholachat Rujikiatkamjorn and Xueyu Geng (2012).
Performance ana Prediction of surcharge and Vcuum consolidation via
Prefabricated Vertical Drains with Special References to Highway, Railways
and Ports. In N. Denies H. Noel (Eds.). International Symposium on Ground
Improvement(pp. 11-145-II-168)..
Gofar, N and Kassim KA. (2005) Introduction to Geotechnical Engineering-Part I,
Prentice Hall. Chapter 4.
Chu, J., Indraratna, B.,Yan, S.& Rujikiatkamjorn C. (2014). Overview of Preloading
Method for Soil improvement. Proceeding of the institution of Civil
Engineers: Ground Improvement, 167(3), 173-185
Goughnour, R. R. (1997 Lateral Drainage for Vertical Drain Systems. Ground
Improvement Ground Reinforcement Ground Treatment Development 1987-
1997 ASCE
Hansbo, S. (1979). Consolidation of Clay by Band Shaped Prefabricated Drains.
Ground Engineering, 16- 25.
Bergado D. T. , H. Asakami, M.C. Alfaro and A.S. Balasubramaniam, (1991)
“Smear effects of vertical drains on soft bangkok clay”. Journal of
Geotechnical Engineering, ASCE, 117 No.10, pp1509–1530.
Jian Chu, Dennis T. Bergado, Eun Chul Shin and Jinchun Chai,. (2012).
‘Embankments on Soft Ground and Ground Improvement. Geosynthethics
Asia 5th Asian Regional Conferences on Geosynthetics, 13 to 16 December
2012.
Jamiolkowski, M., Lancellotta, R., and Wolski, W. (1983 ‘“Precompression
and speeding up consolidation”. Proc. 8th ECSMFE, pp1201-1206
80
Chu, J. and Raju, V.R. (2013 Prefabricated vertical drains. In Ground Improvement,
Ch4, Eds Krich, K. and Bell, A.L., Taylor and Francis.
Holtz, R.D., Jamiolkowski, M., Lancellotta, R. and Pedroni, R. (1991).
Prefabricated Vertical Drains: Design and Performance, CIRIA Ground
Engineering Report, Butterworth-Heinemann Ltd., London.