norjalilahidrismbd2006ttt

105
UNIVERSITI TEKNOLOGI MALAYSIA BORANG PENGESAHAN STATUS DISERTASI JUDUL : EFFECT OF WORK PROGRAMME IN EXTENSION OF TIME ENTITLEMENT SESI PENGAJIAN: 2005/2006 Saya NOR JALILAH BINTI IDRIS (HURUF BESAR) mangaku membenarkan tesis (PSM/Sarjana/Doktor Falsafah)* ini disimpan di Perpustakaan dengan syarat-syarat kegunaan seperti berikut: 1. Tesis adalah hakmilik Universiti Teknologi Malaysia 2. Perpustakaan Universiti Teknologi Malaysia dibenarkan membuat salinan untuk tujuan pengajian sahaja 3. Perpustakaan di benarkan membuat salinan tesis ini sebagai bahan pertukaranantara institut pengajian tinggi 4. **Sila tandakan (4) SULIT TERHAD TIDAK TERHAD (TANDATANGAN PENULIS) (TANDATANGAN PENYELIA) Alamat Tetap: 23 Jalan 74/26, Taman Sri Rampai, 53300 Setapak, Kuala Lumpur Malaysia. Tarikh: 5 th April 2006 Tarikh: CATATAN: * Potong yang tidak berkenaan ** Jika tesis ini SULIT atau TERHAD, sila lampirkan surat daripada pihak berkuasa/organisasi berkenaan dengan menyatakan sekali sebab dan tempoh tesis ini perlu. (Mengandungi maklumat yang berdarjah keselamatan atau kepentingan Malaysia yang termaktub didalam AKTA RAHSIA 1972) (Mengandungi maklumat TERHAD yang telah ditentukan oleh organisasi/badan dimana penyelidikan dijalankan) (Assoc. Prof. Dr. Maizon Hashim) PSZ 19:16 (Pind. 1/97)

Upload: suhaila-namaku

Post on 26-Mar-2015

256 views

Category:

Documents


10 download

TRANSCRIPT

Page 1: NorJalilahIdrisMBD2006TTT

UNIVERSITI TEKNOLOGI MALAYSIA

BORANG PENGESAHAN STATUS DISERTASI

JUDUL : EFFECT OF WORK PROGRAMME IN EXTENSION OF TIME

ENTITLEMENT

SESI PENGAJIAN: 2005/2006

Saya NOR JALILAH BINTI IDRIS (HURUF BESAR) mangaku membenarkan tesis (PSM/Sarjana/Doktor Falsafah)* ini disimpan di Perpustakaan dengan syarat-syarat kegunaan seperti berikut: 1. Tesis adalah hakmilik Universiti Teknologi Malaysia 2. Perpustakaan Universiti Teknologi Malaysia dibenarkan membuat salinan untuk

tujuan pengajian sahaja 3. Perpustakaan di benarkan membuat salinan tesis ini sebagai bahan pertukaranantara

institut pengajian tinggi 4. **Sila tandakan (4)

SULIT TERHAD TIDAK TERHAD (TANDATANGAN PENULIS) (TANDATANGAN PENYELIA) Alamat Tetap:

23 Jalan 74/26, Taman Sri Rampai,

53300 Setapak, Kuala Lumpur

Malaysia.

Tarikh: 5th April 2006 Tarikh:

CATATAN: * Potong yang tidak berkenaan ** Jika tesis ini SULIT atau TERHAD, sila lampirkan surat daripada pihak

berkuasa/organisasi berkenaan dengan menyatakan sekali sebab dan tempoh tesis ini perlu.

(Mengandungi maklumat yang berdarjah keselamatan atau kepentingan Malaysia yang termaktub didalam AKTA RAHSIA 1972)

(Mengandungi maklumat TERHAD yang telah ditentukan oleh organisasi/badan dimana penyelidikan dijalankan)

(Assoc. Prof. Dr. Maizon Hashim)

PSZ 19:16 (Pind. 1/97)

Page 2: NorJalilahIdrisMBD2006TTT

“I hereby declare that I have read this thesis and in my

opinion this thesis is sufficient in terms of scope and quality for the

award of the degree of Master of Science in Construction Contract Management”

Signature :

Name of Supervisor I : Assoc. Prof. Dr. Maizon Hashim

Date :

Signature :

Name of Supervisor II : En. Norazam bin Othman

Date :

Page 3: NorJalilahIdrisMBD2006TTT

EFFECT OF WORK PROGRAMME IN EXTENSION OF TIME

ENTITLEMENT

NOR JALILAH BT IDRIS

A project report submitted in partial fulfillment of the

requirement for the award of the degree of

Master of Science in Construction Contract Management

Faculty of Built Environment

Universiti Teknologi Malaysia

APRIL 2006

Page 4: NorJalilahIdrisMBD2006TTT

ii

I declare that this thesis entitle “Effect of work programme in extension of time

entitlement” is the result of my own research except as cited in the references. The

thesis has not been accepted for any degree and is not concurrently submitted in

candidature of any other degree.

Signature :

Name : NOR JALILAH BT IDRIS

Date : 5th APRIL 2006

Page 5: NorJalilahIdrisMBD2006TTT

iii

To my best friend..Zuraimi Johari

..and my twinkle little stars, Zahirulhaq and Zulaikha.

Page 6: NorJalilahIdrisMBD2006TTT

iv

ACKNOWLEDGEMENT

In preparing this thesis, I was in contact with many people, researchers,

academicians and practitioners. They have contributed towards my understanding

and thoughts. In particular, I wish to express my sincere appreciation to my

supervisor, Associates Professor Dr Maizon Hashim, for encouragement, guidance,

critics, and friendship. Also not forgotten to the other lecturers Dr. Rosli,

En.Jamaludin Yaacob and En.Norazam for being so helpful and understanding. I

am so very thankful to all my family especially to my beloved husband, Zuraimi

Johari for always be with me to light up my spirit and motivation, also to the most

beautiful kids Husni Zahirulhaq and Husna Zulaikha, having both of you makes me

feel complete. Without their continued support and interest, this thesis would not

have been the same as presented here.

I am also indebted to librarian at UTM Skudai and Jln Semarak, librarian at

Perpustakaan Negara, for their assistance in supplying the relevant literature and

helping to conduct the laboratory testing.

My fellow postgraduate students, Yong Mei Lee, Ling Teck Lee and Dennis

Oon should also be recognized for their support, guidance and care. My sincere

appreciations also extend to all my colleagues and others who have provided

assistance at various occasions. Their views and tips are useful indeed.

Page 7: NorJalilahIdrisMBD2006TTT

v

ABSTRACT

The aim of this research is to know how a construction work programme can

be a tool in reducing disputes which relate to extension of time (eot). Extension of

time entitlement is only granted to the successful claimant (contractor) who had

fulfill certain conditions in the application and one of the condition is the claimant

had successfully proved that the delay happened was not by his fault, it is either

caused by employer or was one of the neutral events.

Therefore it is important for the contractor to have sufficient records and

documents about a project’s progress so that he is able to prove the caused of the

delay occurred. Unfortunately, most of the contractors failed to do so because they

are more focus to the work on site rather than doing the management and

documentation work.

It is believed then that by having a proper method of work progamme and

updated progress of work can be so helpful in resolving the dispute, even the

preparation of it are not required in any of local standard form of contract.

This research are based on literature information about work programme and

it will supported by referring to court case where had considered work programme as

an important document in judgment. Even there are no specifications of method in

preparing a work programme but there are some important elements in the work

programme which may contribute to its purpose.

Besides having credits in resolving disputes, there are still weak points in the

work programme application which have to be studied and improved. It is found that

it is good to have work programme requirement in document contract for the better

future and quality of the industry.

Page 8: NorJalilahIdrisMBD2006TTT

vi

ABSTRAK

Penyelidikan ini adalah bertujuan untuk mengkaji sejauh mana penggunaan

perancangan kerja dapat membantu di dalam usaha mengurangkan kesulitan yang

timbul daripada tuntutan lanjutan masa. Lanjutan masa hanya dianugerahkan kepada

kontraktor yang berjaya membuat tuntutan dengan memenuhi beberapa kriteria, dan

kriteria utama ialah membuktikan penyebab bagi kegagalan menyiapkan kerja yang

memerlukan lanjutan masa adalah atas kesalahan pemilik ataupun persekitaran

semulajadi, bukan atas kesalahan kontraktor.

Oleh yang demikian, kontraktor yang memohon lanjutan masa ini akan

berusaha membuktikan bahawa punca kelewatan adalah bukan dari kesalahannya dan

dengan ini masalah sering timbul dimana tiada dokumen, rekod atau bukti yang

kukuh mengenai pihak yang sepatutnya bertanggungjawab ke atas sesuatu kelewatan

aktiviti yang memberi kesan kepada tempoh penyiapan sesuatu projek.

Walaubagaimanapun dipercayai bahawa perkara ini dapat diselesaikan dengan

mengaplikasikan penggunaan perancangan kerja, meskipun perlaksanaan

penggunaannya tidak terkandung di dalam kontrak.

Kajian ini dibuat berdasarkan beberapa kes mahkamah yang menggunakan

rekod perancangan kerja ini sebagai sandaran perbicaraan.Terdapat beberapa elemen

di dalam perancangan kerja yang dapat memantu dalam mengenalpasti punca

kelewatan itu berlaku. Dengan itu daripada rujukan kes-kes yang berkaitan

dipercayai dengan menguatkuasakan penggunaan perancanagan kerja ini dapat

membantu dalam perselisihan berkaitan dengan lanjutan masa. Walaubagaimanapun,

masih terdapat beberapa kelemahan di dalam perancangan kerja ini dimana usaha

untuk menyeragamkannya perlu untuk menjamin kualiti perlaksanaan pembinaan di

negara ini.

Page 9: NorJalilahIdrisMBD2006TTT

vii

TABLE OF CONTENTS

CHAPTER TITLE PAGE

1 INTRODUCTION 1

1.0 Introduction 1

1.1 Problem Statement 3

1.2 Objectives 4

1.3 Importance of the research 5

1.4 Scope 5

1.5 Methodology 6

2 EXTENSION OF TIME 7

2.0 Introduction 7

2.1 Extension of time provision 8

2.2 Delay 11

2.2.1 Delay caused by employer 14

2.2.2 Delay caused by neutral event 15

2.2.3 Delay caused by contractor 15

2.3 Basis events to establish eot entitlement 19

2.3.1 Time provision in contract 20

2.3.2 Due Diligence 28

2.3.3 Notice of delay 34

2.3.4 Construction Work Programme 37

Page 10: NorJalilahIdrisMBD2006TTT

viii

CHAPTER TITLE PAGE

3 CONSTRUCTION WORK PROGRAMME 39

3.0 Construction Planning 39

3.1 Definition of work programme 41

3.1.1 Who does project scheduling 42

3.1.2 How is scheduling done? 42

3.2 Purposed of Construction Work Programme 43

3.3 Type of Construction Work Programme 48

3.3.1 Gantt Chart 48

3.3.1.1 Gantt Chart Enhancements 49

3.3.1.2 Gantt Chart Role in Project Planning 50

3.3.2 PERT Chart 50

3.3.2.1 The Network Diagram 51

3.3.2.2 Steps in the PERT Planning Process 52

3.3.2.3 Benefits of PERT 55

3.3.2.4 Limitations 56

3.3.3 Critical Path Method 57

3.3.3.1 Steps in CPM Project Planning 58

3.3.3.2 CPM Limitations 60

3.4 Role of Work Programme in EOT Application 61

3.4.1 Determination EOT entitlement 61

Page 11: NorJalilahIdrisMBD2006TTT

ix

CHAPTER TITLE PAGE

4 WORK PROGRAMME AS A BASIS TO

ESTABLISH EOT ENTITLEMENT 67

4.0 Introduction 67

4.1 Work Programme in Standard form of Contract 68

4.1.1 PAM 1998 68

4.1.2 CIDB 2000 69

4.2 How work programme can contribute in eot entitlement 69

4.2.1 Logical Analysis 70

4.2.2 Critical Path Analysis 74

4.2.3 Causal Link 77

4.2.4 Regularly and Diligently 78

4.3 Weakness of Work Programme 79

4.3.1 Variety of methods 80

4.3.2 Contents of work programme 80

4.3.3 Presentation of work programme 81

5 CONCLUSION AND RECOMMENDATION 83

5.1 Introduction 83

5.2 Contribution in dispute resolution 84

5.3 Advantages and Disadvantages of Work Programme 85

5.4 Recommendation 86

5.5 Limitation 87

REFERENCES

Page 12: NorJalilahIdrisMBD2006TTT

x

LIST OF TABLE

TABLE NO TITLE PAGE

1 Summary of EOT descriptions 10

2 Contribution of delay 13

Page 13: NorJalilahIdrisMBD2006TTT

xi

LIST OF FIGURE

FIGURE NO TITLE PAGE

1 Research methodology flow 6

2 Alternative emphases in construction planning 41

3 Gantt chart format 48

4 Original bar chart showing technological logic 62

5 Project with variation to building 1 63

6 Project with variation to building 2 63

7 Project with concurrent variation to the two buildings 64

8 Project with variation to building 1 only 65

9 Project evaluate by the addition method 66

Page 14: NorJalilahIdrisMBD2006TTT

xii

LIST OF CASES

PAGE

Amalgamated Building Contractors Ltd v Waltham Holy Cross

UDC [1952] 2 All ER 452 23

Balfour Beatty Construction Limited v The Mayor and Burgess of

the London Borough of Lambeth(2002) 72,77

Barque Quilpue v Brown [1904] 2 QB 264. 24

Bremer Handelsgesellschaft mbh v Vanden Avenne-Izegem

(1978) 2 LLR 109 34

City Inn v Shepherd Construction Ltd [2003] ScotCS 146 36

Codelfa Construction Party Ltd v. State Rail Authority of New

South Wales (1982), 16

Engineering Construction Pte Ltd v Attorney General & Anar

[1997] 3 SLR 989 32

Gaymark Investments v Walter Construction (1999) Northern

Territory Supreme Court 143 35

GLC v Cleveland Bridge (1984) 34 BlR 50. 29

Henry Boot Construction (UK) Ltd v. Malmaison Hotel (Manchester)

Ltd. (1999) 75

Page 15: NorJalilahIdrisMBD2006TTT

xiii

PAGE

Hiap Tian Soon Construction Pte Ltd and Another v Hola Development

Pte Ltd and Another [2003] 1 SLR 667 32

Inserco Ltd v Honeywell Control Systems (1996) 27

John Barker Construction Ltd. v. London Portman Hotel Ltd (1996) 70

Jurong Engineering Ltd v Paccan Building Technology Pte Ltd

[1999] 3 SLR 667 32

Leighton Contractors (Asia) v Stelux Holdings Ltd (2004) 77

London Borough of Merton v Leach (1985) 32 BLR 51 34

Mobil Chemical Co. v Blount Brothers Corp. (1987), 19

Motherwell Bridge Construction Ltd v. Micafil Vakuumtechnik (2002) 75

Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd

(1970) 1 BLR 111 26,35

Rapid Building Group v Ealing Family Housing (1984) 24 BLR 5 25

Sim Chio Huat v Wong Ted Fui [1983] MLJ 151 27

Sindall LId v Solland and others [2003] All ER (D) 95 33

Page 16: NorJalilahIdrisMBD2006TTT

xiv

PAGE

Skanska Construction UK Limited v Egger (Barony) Limited (2004). 81

Thamesa Designs Sdn Bhd v Kuching Hotels Sdn Bhd [1993] 3 MLJ 25 27

The Royal Brompton Hospital NHS Trust v Frederick Alexander

Hammond and others: 74,79

The Royal Brompton Hospital NHS v Watkins Gray International

(UK) (2000) 76

Trident Engineering Company Limited v Mansion Holdings Limited 30

Turner Corporation Ltd (In Provisional Liquidation) v Co-ordinated

Industries Pty Ltd & Ors 1994 NSW LEXIS 35,36

Wells v Army & Navy Co-operative Society Ltd (1902) 86 L.T. 764 28

West Faulkner v London Borough of Newham (1994) 71 BLR 1 30

Page 17: NorJalilahIdrisMBD2006TTT

1

CHAPTER 1

INTRODUCTION

1.0 Background of study

Delay and additional cost in a construction project are an inevitable

consequence of the risk and uncertainty associated with the execution of any

construction project, which is likely to be unique and prototypical in nature. Whilst

the risk is reduces by certainty of design and relevant experience in the construction

of similar types of project, it is sadly all too common that the project will not be

completed within the agreed time of completion. Due to this scenario, it is important

to determine the cause of any events which have potential to be the main cause of the

delay which will affect the date of completion.

The appointment of engineer or architect as Superintendent Officer (SO) or

Contract Administrator (CA) is to act as an agent of the employer to administer the

contract on the employer’s behalf. The person who hold the CA and SO title is in

charge with the responsibility of deciding whether an event is one that gives rise to

an entitlement on the part of the contractor under the contract and whether that

Page 18: NorJalilahIdrisMBD2006TTT

2

events has caused delay and or is likely to affect the date for completion of the

work.

Contract period is a period within which the contractor not only must do the

work but it is also a license for the contractor to spend that time carrying out the

works. In addition, he may plan and do the work in whatever order he pleases.

Although he must make sufficient progress to achieve the completion date, there is

nevertheless usually an express obligation for the contractor to proceed regularly and

diligently with the work. In order to provide further comfort, the employer usually

requires the contractor to provide a programme (construction work programme) at

the commencement of the work to show the sequences and timing of the activities

involved in the construction of the project in sufficient detail for the S.O or C.A to

monitor the progress of the work. It is common to use this construction work

programme as a basic model against which to consider the effect of delays.

Nowadays, it is believed that by having a proper construction work

programme for a project is a smart way in dealing with incoming disputes, especially

disputes on extension of time. In Malaysian standard form of contract, only PAM 98

and CIDB 2000 had stated the requirement of preparing work programme in

document contract while PWD 203A is silent about it. It is stated under clause 3.4 of

PAM 98 and also in CIDB 2000 under clause 5.1. However, the work programme

requirement are debarred by clause 3.5 of the PAM 98 and clause 5.2 of the CIDB

2000 respectively from having any formal significance over contractual obligations.

The said clauses dilute the significant of the work programme and its contractual

effect arising from any aberrations to the programme

Rajoo (1999) stated that the effect of making the programme an express

requirement without it being a contract document is that while the contractor may in

breach for failure to submit a master programme, he may not be in breach if the

series of events are not followed as scheduled.

Page 19: NorJalilahIdrisMBD2006TTT

3

1.1 Problem statement

In a construction project, if delay occurred and it is believed that the

completion date will be affected, the contractor is responsible to inform the SO or

CA in writing, identifying the relevant events which caused the delay. It is stated

under clause 23.1 of PAM 98, clause 43 of PWD 203A and also under clause 24.2(a)

of CIDB 2000 form. In practice, it was found that the contractor normally will state

that the delays occurred was caused by employer or it was a neutral event. Due to

this, he is entitled to be granted an extension of time and the employer has no right to

liquidated damages if the delay were caused by his action. Therefore, it is important

for the parties involved to have a proper documented information about the project

progress, thus the question of who caused the delay will be answered. In a

construction project, delay is normal, therefore it is important to identify whether the

delay has the potential to affect the completion date by determining where the delay

lies in the critical path or not. For example, it is the employer’s fault if he failed to

give instruction to the supplier to start delivering material to the site, but does this

late instruction really lead to the project to be delayed? Of course there are

possibilities that some delays only affect the activities and not the entire project or

the critical path activities. It can be said that by having a work programme

incorporating critical path analysis, parties can’t simply pointing fingers to each

other for causing the delay.

Nevertheless, the obligations of the employer’s agent when considering the

contractor’s entitlement to an extension of time are usually defined in subjective

terms. For example in case of the PAM 98 Standard Form, in accordance with clause

23.2, architect shall consider the relevant events causing delay and by written notice

to the contractor give a fair and reasonable extension of time by fixing such later date

as the date for completion. The process of forming an opinion and deciding upon

what is fair and reasonable are both subjective requirement. To what based it can be

said as fair and reasonable extension of time?

Updated and verified work programme (quality work programme), will be

able to show the status or progress of any in contractor’s plan of proceeding the

Page 20: NorJalilahIdrisMBD2006TTT

4

works. It will also be a strong evidence in any dispute which may arise on issues of

responsibilities arising from delay to completion from changes of programme

sequences and duration of activities. The words quality work programme is a

subjective term which there is no specific method or requirement how a work

programme suppose to look like. In Malaysian standard form of contract there are no

guideline of how to prepare a work programme. Although Rajoo (1999) in The

Malaysian Standard Form of Building Contract (The PAM 1998 Form) had stated

the elements of work programme, it is not defined in any clause in any standard form

of contract. He stated that,

..the elements of Work programme is not defined in clause 3.4. As such, it

may take the form of a bar chart, critical path, precedence diagram, schedule,

network analysis or otherwise. A good work programme should show interfaces with

sub-contractors, dated, time frames, activities, stages and more..

Therefore, it is still an issue in this industry the right definition of a good work

programme and it had became one of the disadvantages in work programme usage

where a good work programme can’t be defined precisely.

1.2 Objectives

There are two objectives of this research which writer wish to achieve.

i. To identify how a construction work programme can contribute in reducing

disputes in extension of time.

ii. To determine the advantages and disadvantages of construction work

program usage in construction contract.

Page 21: NorJalilahIdrisMBD2006TTT

5

1.3 Importance of the research

This research is meant to highlight the importance of having a quality work

programme in construction contract. From the theoretical study, by having a quality

up graded and verified work programme, it can be a helpful tool in disputes resolving

such as critical path analysis which is a main content in a work programme.

The data and analysis in work programme promised valuable information for

identifying and modeling delays and their effect on progress and the use of

computerized work programme techniques for proving delay is become a practical

requirement nowadays. Nevertheless techniques are being considered by the courts

and it is now almost inevitable in litigation involving disputes over the extent of

project delays that a programming expert will be appointed. Therefore, it is good for

the parties involved in a construction project, especially contractor to have a proper

documented record such as work programme as a step to help in reducing disputes in

the future, although it is still not a legal requirement in standard form of contract in

Malaysia.

1.4 Scope

This research will mainly discuss on the work programme terms and

provision in Malaysian standard form of contract. There are Public Work Department

(PWD) 203A, Persatuan Arkitek Malaysia (PAM) 98 and Construction Industry

Development Board (CIDB) 2000. The discussion also will be supported with

international court cases, not only focusing on Malaysian court cases.

Page 22: NorJalilahIdrisMBD2006TTT

6

1.5 Methodology

This research methodology is divided into two types of methods. One is

mainly referring to the literature review which found in reference books, seminar

papers, articles, magazines and also from internet sources. The other method is to

analyse the information gained by compare, relate and support the earlier information

with standard form of contract and relevant court cases.

Figure 1 : Research Methodology Flow

Chapter 2

Literature Review

• Reference books • Seminar papers • Standard for of contract • Article papers • Internet sources Chapter 3

Chapter 4

Chapter 5

• Seminar papers • Standard form of contract • Court cases

Analysis Study

Page 23: NorJalilahIdrisMBD2006TTT

7

CHAPTER 2

EXTENSION OF TIME (EOT)

2.0 Introdution

In an agreement of completing a construction project, there obviously have at

least two parties involved, named an employer as client and a contractor. It is well

known that both parties are engaged to perform each task. The key word which

catches attention here is to perform task or to perform work. Every parties involved

in any agreement should have a crystal clear idea about each task or work that they

should perform.

It is important to understand the general obligations of employer and

contractor in a construction project whereby the contractor’s obligation is to

complete the project by the stipulated completion date in consideration for monetary

payment by employer. Should the contractor fail to complete by the completion date

and is in breach of his contractual obligation, he is liable for damages to the

employer. It is the common practice in Malaysia to stipulate an amount for liquidated

damages in the contract which will be payable by the contractor to the employer for

delay to project completion. Liquidated ascertain damages (LAD) is one kind of

Page 24: NorJalilahIdrisMBD2006TTT

8

monetary compensation which the contractor have to pay to the employer due to

delay caused by himself and normally the amount is per day which obviously stated

in earlier phase. This simplistic theoretical scenario is based on the premise that the

contractor is allowed to complete the agreed scope of work within the agreed time

frame without any interruption or hindrance (Hutching, 1998).

In construction project, the cost may be the primary concerns of the parties

involved. However, time requirement also plays a key factor to both employer and

contractor. Since time is said to be as important as cost, a provision on extension of

the time of completion is very welcomed by all parties due to avoid any further

problems or disputes. It is where an Extension of Time provision had been

introduced.

2.1 Extension of time provision

Nowadays, most of the construction contract contains an express provisions

under which the time or period allowed for the contractor to complete the works can

be extended. In Malaysia, all main Standard Form of Contract have their own

provision on Extension of time, for example in PWD 203A, the Extension of time

provision is under Clause 43,PAM 1998 the provision on EOT had been clearly

described under Clause 23 and also the CIDB 2000 had precisely everything about

EOT under its Clause 24.

The provision of Extension of Time will obviously benefit the contractor who

will not be liable to pay any monetary compensation or LAD for any delay during the

period which time is validly extended. Although it is to be said that the contractor

will benefit most, there are some opinions agreed that the actual benefit is actually

meant for the employer.

Page 25: NorJalilahIdrisMBD2006TTT

9

At common law, the contractor’s obligation to complete the works by the

specified date is removed if the employer delays the contractor in the execution of

the works. Thus if the CA issues an instruction which increase the amount of work to

be done, or its late in giving the contractor necessary instructions, the specified

completion date no longer applies. In this situation, time is said to be ‘at large’ and

the contractor’s obligation is merely to complete the works within ‘reasonable time’.

In order to fix what is ‘reasonable’, all the circumstances of the particular project

must be taken into account, but in many cases it will simply mean that the amount of

delay for which the employer is responsible will be added to the old completion date.

Society of Construction Law (SCL) in Delay and Disruption Protocol

(October 2002) define extension of time as additional time granted to the contractor

to provide an extended contractual time period or date by which work is to be, or

should be completed and to relieve it from liability for damages for delay (usually

liquidated damages).

From all the description above about extension of time, it is hope that it can

be easily understood by referring to the table 1 :

Page 26: NorJalilahIdrisMBD2006TTT

10

Table 1: Summary of EOT Descriptions

Questions Descriptions

What Extension of time is a provision to contractor to apply extra numbers

of days if there are events that believed to delay the works.

EOT clause aimed to allocating the risk of non-completion between the

employer and the contractor.

Why The benefit :

To contractor : to relieve the contractor of liability for damages for

delay (usually liquidated damages) for any period prior to the extended

contract completion date.

To employer : to establish a new contract completion date, and

prevents time for completion of the works becoming ‘at large’

When Contractor shall notify the SO or CA if there are any possibility the

works is likely to be delayed beyond the date for completion.

How Contractor are suppose to submit a notice of delay to SO or CA, the

procedure of the notice should be based as in the standard form of

contract involved.

Normally, entitlement of extension of time is no doubt given to the clearly approved

situation as below :

i. Contractor is not responsible for the delay, means the cause of the delay

wasn’t by contractor. It is whether the employer’s fault or the caused by

neutral events.

ii. The delay had possibility to contribute the delay of completion date, which

means it had effected the critical path activities and sequences of works.

Page 27: NorJalilahIdrisMBD2006TTT

11

2.2 Delay

It was stated earlier that almost all construction contract in Malaysia has an

express provision about extension of time. It is believed to be happened because its

kind of abnormal to have a project complete on time without any application of

extension of time even for a day.

A fundamental point is that the time for completion can only be extended where the

contract permits and strictly in accordance with the contract provision. If delay is

caused by some event which the contract does not cover, then the contractor cannot

claim an extension.

Generally, there are two categories of delays in a construction project:

a) Unanticipated and unforeseeable situations which cause delays to some

parts of a construction project and affects overall project completion date

b) Incidents where it affects the progress of a particular activity/task, but not

affecting overall project completion date (Thomas,1994)

The concept of delay arises out of the time limitations stated in the contract.

Extension of time only can be granted if the delay is critical, affects the date for

project completion and it falls within the language of the extension of time clause in

a particular contract. Some contract may contain clause where it allow a general

ground for extension of time, such as “..any other ground for extension of time

expressly mentioned in the Contract” under PAM 1998, Clause 23.7(xii).

It is thus important that the likely causes of delay are covered by an extension

of time clause, but the courts have made things more difficult by ruling that a general

words such as ‘other unavoidable circumstances’ do not cover delay which is due to

the fault of the employer. Oddly, although the ruling is well known, many contracts

continue to use general phrases of this kind.

It is a norm having a delay in any project, it can easily happened and can

caused by any parties, either it solely from contractor’s fault or from other parties

such as employer’s fault or other events.

Page 28: NorJalilahIdrisMBD2006TTT

12

Traditional extension of time clauses contain a list of delaying events for which the

contract administrator is empowered to grant extensions of time, and the forms

currently used in Malaysia are no exception to this.

The lists generally cover two types of delays:

a) Delays which are the responsibility of the employer (or his agent the

engineer or the architect), such as variations, late receipt of necessary

information from the engineer/architect, suspension of the works or a part

thereof, and delays by other persons employed directly by the employer.

As stated previously, it is essential for these grounds to be included if the

employer’s rights to have the works completed within the specified time

for completion, and claim liquidated damages are to be maintained.

b) Delays which are caused by neutral events which the employer has

accepted responsibility for, such as inclement weather, utility

undertakings and force majuere or special circumstances.

In summary, the following parties or events may contribute to the delay of a

construction project (F.Turner & Turner, 1999). Table 2 shows the contribution of

delay for construction parties.

a) Employer or his agents

b) Contractor / Subcontractors

c) Neutral events

Page 29: NorJalilahIdrisMBD2006TTT

13

Table 2: Contribution of Delay

Caused By: Events

Employer or his agents - Late Award

- Project Site

- Payment

- Variation of works

- Special materials

- Design

- Late instruction

- Discrepancy.

Contactor/Subcontractors - Poor management

- Poor workmanship

- Inadequate resources

Neutral Event -Force majeure

-Weather

- Civil Commotion and strike

When there is a delay to progress of work in a construction project, this delay

may or may not have an effect to completion date of the project. Where a delay to

progress does not affect the critical path, the completion date of a project will not be

affected (Adrian,1988). However, if delay to progress affects the critical path, the

project completion will be delayed.

A contractor who completes the work beyond the completion date is in

breach of his contractual obligation and is liable for liquidated and ascertained

damages to the employer. Where delay is due to the contractors’ own fault, for

example inefficiency, slow in progress, poor co-ordination and management, he will

be liable to pay damages to the employer.

However, if the delay due to a neutral event such as exceptional inclement

weather or as a result of the employers’ default such as late granting of possession of

Page 30: NorJalilahIdrisMBD2006TTT

14

site, than the contractor should be excused from such delay affect the project

completion date. In such instances, the contractor should be entitled to be given more

time to complete the project and may also be entitled to claim for any loss and

expenses incurred.

2.2.1 Delay Caused by Employer

Delay caused by employer can be divided into several categories (Rubin et,

al.,1999) :

a) Employer’s failure to meet his contractual obligations

I. Delay in Awarding the Contract

II. Delay in Providing Project Site

III. Dissimilar Site Conditon

IV. Delay in Payment

V. Delay in Obtaining Necessary Approval from Local Authorities

VI. Delay in Furnishing Special Materials

VII. Delay by Nominated Sub-contractors/Suppliers caused by Employer

b) Act of prevention or interference by the employer to the works

c) Variation to the work required by the employer

d) Failure by employer’s agents to perform their contractual duties on behalf

of the employer

e) Employer’s Licensees

Page 31: NorJalilahIdrisMBD2006TTT

15

2.2.2 Delay Caused by Neutral Events

Delays that are not caused by the parties to the contract and beyond the

control or power of any parties involved are considered as neutral events (Hackett &

Robinson, 2003). The generally accepted principle in construction contract is that

delays caused by neutral events are classified as excusable and non-compensable

delay (Rubin, 1999). The contractor is excused from late performance but he will not

be entitled to extra compensation for delays caused by neutral events.

Most of the construction contract dealt with delays caused by neutral events,

such as force majuere, exceptional inclement weather, civil commotion, strike or

lockout, fire, flood, etc. By introducing such provision in a contract, all parties’ risks

will be minimized.

The exception is that the contractor will not be entitled to extension of time if

the neutral events that cause the delay to the project are foreseeable and avoidable.

As in the Australian case of Codelfa Construction Party Ltd v. State Rail Authority of

New South Wales (1982), it was held that the contractor was not entitled to a time

extension for delays due to an injunction that prevented working three shifts as the

contractor had intended, as shown in approved work program. The court determined

that the contractor should have foreseen that three shifts would not have been

allowed in the project area.

2.2.3 Delay Caused by Contractor

As a general rule, contractor will not be entitled to claim extra money or time

if the delay is due to his own default. Contractor will be required to pay liquidated

damages or any monetary compensation to the employer if he delays the project

Page 32: NorJalilahIdrisMBD2006TTT

16

completion without a valid reason (Thomas,1993). Delay caused by contractor can be

classified into the following categories:

2.2.3.1 Failure to Appraisal the Site and Design

Most construction contract requires the contactor to carry our pre-tender site

inspection to enable the contractor to appraisal the site, and to ascertain the actual

site condition. By carrying out a reasonable and proper inspection of the site, the

contractor will be able to submit a more accurate and competitive tender excluding

high contingency factors (Bramble & Callahan,1992). Failure by contractor to

appraise the actual site condition or lack of proper site inspection puts the contractor

in a risky situation where he may under price his tender submission.

Most of the construction contract required the contractor to give written

notice should be find a discrepancy between contract drawings and contract bills.

The contractor may loose his entitlement to extension of time for any consequential

delay if he fails to notify the contract administrator upon discovery of any

discrepancy (Rajoo,1999)

2.2.3.2 Non-availability of Resources

Contractor’s non-availability or inadequate resources such as finances, work

force, plants, equipment and materials may prevent the work from completing in a

timely manner. The risk of managing these resources generally rests with the

contractor and delays caused by poor management or non-availability of these

resources are borne by the contractor.

Page 33: NorJalilahIdrisMBD2006TTT

17

A common scenario in a construction project is the main contractor delaying

payment to his sub-contractors when he is having financial or cash flow problem

during the course of construction. As a result, his sub-contractors may slow down

progress of work or even abandon the work halfway. This will delay construction

completion. In order to overcome such problems, most standard of form in

Malaysian construction contract incorporate a clause to allow direct payment from

employer to sub-contractors if the main contractor fails to pay the sub-contractors

for work done.

It is important that the contractor allow for sufficient work force to carry out

the work. Shortage of labour will not be an excusable delay unless it is caused by

unforeseeable event and the contractor has diligently and used his best endeavours to

looks for alternative labour sources to resolve the issue

Failure by the contractor to provide adequate plan and equipment at the

required time for carrying out work on site will delay project completion. The U.S

Department of Interior Board of Contract Appeals decided in the case of Frank

Rivera, Inc. (1984) that the contractor is responsible for delays which arise from his

own failure to provide proper equipment in accordance with the approved

dewatering plan.

The contractor will not escape from responsibility for delaying project

completion if there is delay in procuring construction materials unless the shortage

of material is unforeseeable and beyond the control of the contractor. Nevertheless,

the contractor owes a duty to the employer under the contract for supplier’s failure to

supply material or equipment that in turn delays project completion

Page 34: NorJalilahIdrisMBD2006TTT

18

2.2.3.3 Poor Management

The contractor needs to manage his resources in order to achieve that best

price, time and quality for the work. The contractor is required to coordinate the

works, select the best construction methods and techniques, and sequences of the

work based on the work programme prepared. Most often, delay in construction

project is caused by main contractor’s poor coordination or failure to interface the

work properly amongst the various trade sub-contractors (F.Turner & Turner,1999)

Poor management may also be caused by the lack of experienced site supervisor to

manage the site workers whereby activities are not well co-ordinate.

In the American case of Mobil Chemical Co. v Blount Brothers Corp.

(1987), the construction manager was held responsible for delayed completion

caused by poor management in early stages of the project. The contractor was

responsible for delays in mobilizing the project.

2.2.3.4 Poor Workmanship

In most of the Malaysian standard form of contracts, it is contractor’s

obligation to carry out the work in accordance with the contract drawings and

specification. The specification is used as a tool to control the quality or standard of

workmanship of the contractor.

Poor workmanship or nonconforming works entitles the employer to request

the contractor to demolish or remove the works and replace with new ones. The

contractor will not be compensated in terms of time and money for such delays to

the work (Rubin,1999). Poor workmanship is generally due to the lack of skilled

labourers engaged by the contractor.

Page 35: NorJalilahIdrisMBD2006TTT

19

2.2.3.5 Sub-Contractors or Suppliers

The main contractor is responsible to the employer for delays caused by his

sub-contractors and suppliers. This is because the contractual relationship is between

the employer and main contractor only. If the sub-contractors or suppliers’ delays

actually affect the overall project completion and the main contractor does not

contribute to the delay, then the sub-contractors and suppliers are liable to main

contractor. It is therefore important that the main contractor monitor the performance

of each of his own sub-contractor and supplier to ensure the works are properly

coordinated as delays by one may affect the work by others. At the end of the day,

the main contractor is liable to the employer irrespective of any one or a few sub-

contractors who cause delays although he can still bring an action against the

defaulting sub-contractors.

2.3 Basis events to establish entitlement of extension of time

This section will further discuss on the basic events and principles where the

contractor entitled to extension of time if he fully applied it. The most common

reason for contractor to get the time extended is if can proved that the delay wasn’t

caused by him. It is rather caused by the employer or from the affect of neutral

events.

Page 36: NorJalilahIdrisMBD2006TTT

20

Besides that, contractor also has right to granted extension of time if he has

much knowledge on contract and always keeps his move on the right track.

Contractor shall know what other things that entitled him to get fully extension of

time, which such as below :

i. Time provision in the contract

ii. Due diligence

iii. Notice of delay

iv. Work Programme

2.3.1 Time provision in the contract.

As a person who will hold a responsibility to complete the agreed work,

contractor should really understand and realize the important provision in the

contract. One of the primary terms in a contract is the time provision. A good

contractor will have a great awareness due to this provision, it is important to have a

clear idea what kind of time provision in the contract. Firstly, contractor should know

whether the date of completion of the project is stated and he also must understand

the terms of time extension in the contract. By having clear information about time

provision, it will help to reduce further disputes due to this problems.

In the next discussion writer would like to discuss more detail on time provision and

terms. The next discussion will touch on contract with and without time specified,

what the definition of time at large is and how it relates to the term of reasonable

time.

Page 37: NorJalilahIdrisMBD2006TTT

21

2.3.1.1 Contract with specified time

In the normal situation, where a time for completion is expressly stated in the

contract, the employer is entitled to damages if the contractor does not complete on

time. It is important for contractor to make sure enter a contract with provision of the

date of completion.

There are two different types of contract where time for completion is expressly

stated as a term of the contract. Firstly time may be of the essence or secondly time

may be extendable.

2.3.1.2 Time of essence

Time of the essence is one of the most misused contractual terms, particularly

in construction contract. Time is of the essence where failure to meet the particular

date is a fundamental breach of contract entitling the other party to treat the contract

as repudiated and claim damages.

Time is seldom of the essence in a construction contract because the effect of

such a provision is that the employer does not want the building at all and will treat

the contract as repudiated. Whilst one can think of circumstances where this may be

relevant for a building, for example the construction of the National Sports Stadium

to accommodate the Commonwealth Games on a certain date – there is no value to

the Employer in receiving the stadium one month late when the games ought to have

finished, such would be very rare.

Generally, however time is not considered to be of the essence in construction

contracts, because such contracts are different to most others in that the contractor

will have expended heavily in performing the contract prior to a delay in completion

Page 38: NorJalilahIdrisMBD2006TTT

22

and in constructing the works the employer will have become owner of the property

and thus have received a major and irretrievable benefit. Further it is clearly arguable

that liquidated damages clauses and extension of time provisions are inconsistent

with an interpretation that time is of the essence, both clauses indicating a preference

on the owner’s part to allow the contractor to complete and accept liquidated

damages as compensation.

In a situation where there is an extendable time for completion, and the

contractor is in delay, it is possible for an employer to make time of the essence by

serving a notice requiring completion by a certain date. He cannot do so, however, if

his own breach of contract is already affecting the contractor’s ability to complete.

This remedy would only be available in rare cases where the contractor’s failure to

complete is so persistent or flagrant as to evince an intention not to be bound by the

contract.

2.3.1.3 Time At Large

The majority of construction contracts provide a time for completion, and a

provision that failure to complete by that date will entitle the employer to liquidated

damages at a certain rate per day.

In the absence of any provision, the contractor will be responsible to

complete within that time, and he will have no excuse if events occur which cause

delays over which he has no control, such as weather, strikes, materials shortages or

unforeseen ground conditions.

However, the position is entirely different if the contractor suffers a delay

which is caused by the employer. Such delays are common and may be failure to

give possession of the site on the required day, the issue of variations requiring

additional works, or any other disturbance caused by the employer. It is- clearly

Page 39: NorJalilahIdrisMBD2006TTT

23

established that one party cannot impose a contractual obligation on the other where

he has impeded the other in the performance of that obligation. In Amalgamated

Building Contractors Ltd v Waltham Holy Cross UDC [1952] 2 All ER 452 Lord

Denning said:

“..the building owner cannot insist on a condition if it is his own fault that the

condition has not been fulfilled."

Brian Egglestone in his book 'Liquidated Damages and Extensions-in

Construction Contracts 1 at page 27 aptly sums up contractors' perceptions of time at

large as follows:

“The phrase 'time at large” is much loved by contractors.It has about it ring

of plenty; the suggestion that the Contractor has as much time as he wants to

complete the works"

Employers, architects and engineers have fundamentally different views.

They often view the claim that time is at large to be nothing more than an excuse

used by dilatory contractor who have failed to meet their completion obligations and

want to avoid the deduction of liquidated damages.

Essentially, time becomes at large:

(a) Where an act of prevention by the employer creates delay and that delay

is not covered by an extension of time provision; and, to a lesser extent:

(b) Where the provisions for extension of time have not been properly

administered or have been misapplied;

(c) Where there has been waiver of the original time requirements;

(d) Where there has been interference by the employer in the certifying

process.

In its simplest form time is said to be at large where there is no specific time

for completion or where a previously fixed time for completion no longer applies.

Page 40: NorJalilahIdrisMBD2006TTT

24

This can occur in two main ways. Firstly, where agreements for work to be, carried

out are entered into without a completion date, or period, being stated. Common

examples of this type of situation are found in letters of intent, which often contain

instructions to commence work without a completion time being agreed. Where

there is no subsequent agreement as to the time for completion then time will be said

to be at large.

The second situation occurs where a previously agreed time for completion

has been rendered inoperable. This can occur in a number of ways the most common

of which is where there is an act of prevention by the employer, which there is no

express provision within the contract for extending the completion date.

This derives from a fundamental principle of commercial law which has been

established for centuries but which was best articulated in Barque Quilpue v Brown

[1904] 2 QB 264.

In this case Lord Justice Vaughan Williams said:

“There is a term implied into every contract by each party that he will not do

anything to prevent the other party from performing a contract or to delay

him in performing it. I agree that generally such a term is by law

imported into every contract"

Where the employer or his agents does undertake some act or omission

which prevents the contractor completing the works by the date for completion, for

example, by failing to provide necessary drawings at the appropriate time, then he

can no longer maintain that the contractor finishes his works by the stipulated date

for completion. Time is set at large unless the contract provides for extending the

date in such circumstances.

To overcome this problem most forms of building contract acknowledge that

acts of prevention are a reality in construction and provide mechanisms for changing

Page 41: NorJalilahIdrisMBD2006TTT

25

the completion obligations when delays by the employer occur. These mechanisms,

referred to as extension of time clauses, give the engineer or architect the power to

grant extensions of time for delays caused by the employer or his agents. This

allows a definite time for completion to be maintained and preserves the employer's

rights to deduct liquidated damages if completion occurs after the extended date.

Given the importance of these matters it is perhaps surprising to discover that

some of the most commonly used forms of contract do not contain express

provisions to extend time for completion resulting from an employer's act of

prevention and some of these contracts are still in use in Malaysia.

The PAM98 form of contract is an amended version of the PAM 1969

edition, which is modeled upon the JCT 1963 Edition. The JCT 1963 was the form of

contract considered in the case of Rapid Building Group v Ealing Family Housing

(1984) 24 BLR 5. Due to the presence of squatters the Employer was unable to give

possession of the site on the prescribed date. Since there was no provision to extend

time for late possession, the Contractor was successful in his argument that that time

had become at large and accordingly the obligation for completion was altered to that

of a reasonable time, and the Employer lost his right to levy liquidated damages.

A similar argument was put forward in the case of Peak Construction

(Liverpool) Ltd v McKinney Foundations Ltd (1970) 1 BLR 111 heard before the

Court of Appeal in 1970. It was held that, as delays on the part of the City Council

in approving remedial works to the pilling were not catered for in the extension of

time provisions, the right to liquidated and ascertained damages was lost and time

became at large. The corporation was left with an entitlement to claim such common

law damages as a result of the Contractor failing to complete within a reasonable

time, as it was able to prove.

It is also clear from the case of Peak Construction that the extent of the delay

caused is not a relevant factor to be considered in assessing whether time has been

set at large.

Page 42: NorJalilahIdrisMBD2006TTT

26

Lord Justice Phillimore in this case summarized the law and the rationale

behind it as follows:

"I would re-state the position because I think it needs to be stated quite

simply. As I understand it, a clause providing for liquidated damages (clause

22) is closely linked with a clause, which provides for an extension of time

(clause 23). The reason for that is that when the parties agree that if there is

delay the contractor is to be liable, they envisage that the delay shall be the

fault of the contractor and, of course, the agreement is designed to save the

employer from having to prove the actual damage which he has suffered. It

follows, once the clause is understood in that way, that if part of the delay is

due to the fault of the employer, then the clause becomes unworkable if only

because there is no fixed date from which to calculate that for which the

contractor is responsible and for which he must pay liquidated damages.

However, the problem can be cured if allowance can be made for that part of

the delay caused by the actions of the employer, and it is for this purpose that

recourse is had to the clause dealing with extension of time. If there is a

clause which provides for extension of the contractor's time in the

circumstances which happen, and if the appropriate extension is certified by

the architect, then the delay due to the fault of the contractor is disentangled

from that due to the fault of the employer and a date is fixed from which the

liquidated damages can be calculated."

In this case it was also held that if the Employer caused any delay, no matter

how slight, and there was no appropriate provision to extend the time for completion

then time would be at large. The extent of the delay was not a factor in whether time

was rendered at large.

Similarly in the case of Inserco Ltd v Honeywell Control Systems (1996),

Inserco contracted to complete all work by 1 April 1991. Due to additional and

revised work, and lack of proper access and information, Inserco was prevented

from completing on time. There was no provision in the contract for extending the

completion date and time was held to be at large.

Page 43: NorJalilahIdrisMBD2006TTT

27

The Federal Court in Malaysia held in Sim Chio Huat v Wong Ted Fui [1983]

MLJ 151 that a housing developer who undertook to deliver houses erected by him to

a landowner, was not liable for liquidated damages because the landowner had

instructed for additional work to be done when their agreement contained no clause

for extension of time for completion. Time became at large and consequently there

was no date from which damages could run and therefore no liquidated damages

could be claimed.

The Supreme Court of Malaysia held in Thamesa Designs Sdn Bhd v Kuching

Hotels Sdn Bhd [1993] 3 MLJ 25 that the Employer was not entitled to deduct

liquidated damages because site possession was handed over late to the Contractor

and there was no extension of time provision for late possession.

Whilst the omission from the standard form is generally corrected by way of

special conditions of contract, in some instances it is not and on these occasions the

contractor will have grounds to argue that time has become at large due to the failure

of the employer to afford possession or other acts of prevention not expressly

provided for within the extension of time provisions.

Some contract draftsmen attempt to close this loophole by using general

"catch-all" expressions in the extension of time clause such as "other causes beyond

the contractor's control-. However the courts in the case of Wells v Army & Navy Co-

operative Society Ltd (1902) 86 L.T. 764 held that words such as these did not cover

delays caused by interference of the Employer or the Architect, and accordingly an

extension of time could not be granted and time was set at large. Therefore the

contract will need to give express provisions to extend time where the Employer has

prevented performance and general clauses will not suffice. An example of specific

provision that seems to cater for the employer's delays is included in the PAM 98

conditions at clause 23.7(ix) which states:

"any act of prevention or breach of contract by the Employer not mentioned in

this Clause 23.7”

Of course most major forms of construction contract are now drafted to

Page 44: NorJalilahIdrisMBD2006TTT

28

ensure that delay caused by the employer are clearly covered and further drafted to

incorporate some risk sharing between the employer and the contractor and often

entitle the contractor to extensions of time due to neutral events such as inclement

weather or other matters outside his, or the employer's control.

2.3.2 Due Deligence

The previous section has considered the obligations of the contractor to

complete the works within a specified time for completion, and in the event of his

failure to do so, the employer's right to liquidated damages.

However, delays may occur during the progress of the works that may cause

the employer damage but which do not delay the overall completion Such delays will

generally not entitle the employer to claim damages and so in an attempt to prevent

such delays occurring it is common for construction contracts to include terms that

define the manner in which the works are to be progressed.

Contracts normally use such terms as:

"...Proceed regularly and diligently..." (PWD 203A, clause 51 (a)(ii) and

PWD Form DB/T - clause 54.1 (b))

"... regularly and diligently proceed... "(PAM98, clause 21.1).

"...shall proceed... with due expedition... "(IEM, clause 38(a)).

". ..shall proceed with due diligence and expedition... "(CIDB, clause 17.1)

The definition of the terms 'diligence' and 'expedition' may be illustrated by

reference to the Shorter Oxford Dictionary thus:

Page 45: NorJalilahIdrisMBD2006TTT

29

Diligence - "the attention and care due from a person in a given ituation",

Expedition - "the act of expediting, to perform quickly, dispatch" .

The expression "due diligence and expedition~ was dealt with in GLC v

Cleveland Bridge (1984) 34 BlR 50. Here the Arbitrator's view (which was upheld

by the court) was:

“if the access date, key dates and completion date are varied or extended the

respondent could not in my view be said to be lacking in diligence if it paced

its work so as to ensure delivery consistent with the appropriate access and

key dates even though this might have the effect of increasing the sums

,eventually recoverable under the VIC provision” (Adjustment of Price

clause}".

The judge further stated that the expression 'due diligence' imposed

"an obligation on the contractor to execute the works with such diligence and

expedition as were reasonably required in order to meet the key dates and

completion date in the contract".

In the case of West Faulkner v London Borough of Newham (1994) 71 BLR

1,the Court of Appeal acknowledged the difficulty of defining "diligently" when the

proper construction of the term regularly and diligently was considered.

The courts in this case found that:

“... the word 'regularly' is not least a requirement to attend for work on a

regular daily basis with sufficient in the way of men, materials and plant to

have the physical capacity to progress the Works substantially in accordance

with the contractual obligations.

What in particular the word diligently contributes to the concept is the need to

apply that physical capacity industriously and efficiently toward that same

end. "

Page 46: NorJalilahIdrisMBD2006TTT

30

This approach was adopted in the recent Hong Kong High Court case of

Trident Engineering Company Limited v Mansion Holdings Limited wherein Deputy

Judge To elaborated by stating:

"So far as supply of materials is concerned, the contractor has to plan his

requirements ahead and ensure that the materials of the right quality and in

the right quantity are available at the right time. This is to enable the works to

progress continuously, industriously and efficiently. The most ideal situation

would be to arrange delivery to coincide with work progress so that the

materials will arrive at the site precisely when they are wanted and be lifted to

where they are required . If such precise delivery is not possible, at least the

contractor should ensure that a minimum stock is kept on site, which is

sufficient to provide for the time required for placing orders and delivery, plus

a reasonable provision for contingency. Otherwise, labor will be wasted while

waiting for materials and delay will result.

The term "regularly and diligently" must incorporate a wide spectrum of

diligence and regularity. At the one end of the spectrum are breaches, which

are just short of due diligence and regularity, such as falling slightly behind

the schedule or causing some minor interruption. At the other end are severe

breaches amounting non-performance, such as doing no more than keeping a

watchman on the site, or perhaps proceeding with a less than minimal

workforce while directing the major labour workforce to other more

profitable projects. Both are breaches of duty but with very different

consequences. The former is a minor breach sounding in damages while the

latter is a repudiatory breach as it evinces an intention on the part of the

contractor no longer to be bound by the contract. "

Notwithstanding the absence of a precise meaning of the terms used in

contracts, it seems clear that at the very least the contractor must organize and order

his works so as to achieve the completion dates.

Page 47: NorJalilahIdrisMBD2006TTT

31

Whilst this is the general rule the situation under the CI DB conditions of

contract is different. CI DB conditions clause 17.1 (a) requires that "the Contractor

shall proceed with the works with due diligence and expedition..." which is prime

facie a standard clause importing the obligations discussed above however the

clause goes on to state:

“..in accordance with the Contract and by reference to the works

programme and/or method statement or any revised or modified works

programme and/or method statement accepted by the Superintending

Officer pursuant to Clause 5. I'

It would thus appear that clause 17(a} of CI DB contract sets a yardstick in

the form of works programme and method statement for the parties to measure the

extent of due diligence and expedition. The works programme is one of the effective

tools in measuring the Contractor's due diligence and expedition as the S.O. is able

to compare the Contractor's actual progress against the as-planned works programme

apart from assessing the Contractor's available resources on site.

In the Singaporean case of Hiap Tian Soon Construction Pte Ltd and

Another v Hola Development Pte Ltd and Another [2003] 1 SLR 667, the High

Court followed the Court of Appeal's decision in Jurong Engineering Ltd v Paccan

Building Technology Pte Ltd [1999] 3 SLR 667 where 'reasonable diligence' could

only be determined by pacing the progress of the subcontractors work against the

sub-contract programme. The High Court treated the term 'reasonable diligence' as

the same as 'regularly and diligently' and therefore found that the contractor's

progress of work had consistently lagged behind the construction programme thus

falling below what was regularly and diligently. Moreover, the contractor persisted

in its delay despite reminders from the employer to expedite the work.

Although the contract only gave the employer a right to terminate the

contractor's employment for the failure to proceed regularly and diligently, the High

Court in following the Court of Appeal's decision in Jurong Engineering's case, held

that the contractor's breach of the obligation to proceed regularly and diligently

would give rise to damages as well as to a right to terminate the contractor's

Page 48: NorJalilahIdrisMBD2006TTT

32

employment.

The court cited the reason enunciated in Hudson's Building and Engineering

Contracts, Vol 2 (11th Ed, 1995) as where the nature of the work undertaken

indicated that work by other contractors of the employer were within the

contemplation of the contract as being dependent on the maintenance of a reasonable

rate of progress.

However, as the events in the works unfold, the works programme must be

revised to reflect and consider actual progress which have taken place including

external delaying events. The onus may lie on the S.O. to insist and instruct the

Contractor to revise the works programme from time to time. In the absence of such

updated programme, it may be near impossible for the S.O. to measure the

Contractor's due diligence and expedition.

It is interesting to note that in the case of Engineering Construction Pte Ltd v

Attorney General & Anor [1997] 3 SLR 989, the employer selected from the

contractors' fifth revised programme the excavation works as a critical activity by

which to measure the contractors' ability to work to the programme. Under this

revised programme, the contractors maintained that they would complete the

excavation works by 31 March 1992. The High Court held that whether or not the

contractors were proceeding with reasonable diligence would be determined in

accordance with the facts and circumstances of each case. In this case, it was held that

the target of completion of the excavation works set by the employer to measure

whether the contractors were proceeding with reasonable diligence or not, was not at

all unreasonable. The contractors failed to meet the target and were thus not

proceeding with the work with reasonable diligence.

Another factor which a C.A needs to take into account when measuring the

contractor's due diligence would be whether the contractor is entitled to any further

extension of time based despite the contractor having failed to notify the C.A of any

causes of delay. If the C.A fails to consider the contractor's further entitlement to

extension of time yet at the same time arrives at an opinion that the contractor fails to

proceed regularly and diligently, the C.A may put the interest of the employer at risk.

Page 49: NorJalilahIdrisMBD2006TTT

33

Such are the circumstances seen in the case of Sindall LId v Solland and

others [2003] All ER (D) 95 where the contractor entered into a contract with the

employer for renovation work. The date for completion had lapsed and was later

extended. Subsequently the extended date for completion lapsed and there were still

delays being caused by the employer including the employer's artist and tradesmen.

The C.A issued a notice of default to the contractor forming his view that the

contractor had failed to proceed regularly and diligently on the grounds that, inter

alia, the contractor had a low number of operatives on the site. The employer acted

on the C.A’s view and subsequently terminated the contractor's employment.

Humphrey Llyod J's in his obiter statement said:

“Were there not events which entitled Sindall (the contractor) to a further

extension of time? If there were such events then the Contract Administrator

may not have been right to have formed the view that the contractor was then

failing to proceed regularly and diligently"

The judge in the Sindall's case referred to Vinelott J's judgment1 in London

Borough of Merton v Leach (1985) 32 BLR 51 at pages 89-90 and stated that a

contract administrator had always to consider whether there were any factors known

to him which might justify an extension of time, even though the contractor failed to

give a notice of delay. This was particularly important if the C.A needed to determine

whether the contractor was proceeding regularly and diligently. It should be noted

that the contract in this case did not stipulate such notice as a condition precedent to

any entitlement to an extension of time. Hence, the application of Sindall's case may

be confined to such contracts.

Page 50: NorJalilahIdrisMBD2006TTT

34

2.3.3. Notice Of Delay

In most standard forms of contract there is a requirement for the contractor to

submit written notice of delays to the architect or engineer. Very often there is a time

limit on the submission of such notices. By submitting notice of delay in a proper

procedure can be the merit of contractor to granted time extension, but contractor

should be familiar with the procedure of notice submitting refereeing to the standard

of form he was involved in.

The starting point for the submission period is generally either the start of the

event giving rise to the delay, an objective test, or when it becomes reasonably

apparent that an event is likely to cause delay, a subjective test.

Most forms, internationally, do not expressly state that giving of such notice

is a condition precedent to the right to an extension of time, and the case of Bremer

Handelsgesellschaft mbh v Vanden Avenne-Izegem (1978) 2 LLR 109, confirmed

that unless it was expressly so stated the clause would not be a condition precedent.

Vinelott J gave the judgment on the construction of clause 23 of JCT 23

(similar to clause 43 of PWD 203A),i.e. the contractor was required to give a

notice if the contractor had known an event had resulted or would inevitably

result in delay. If the architect had known an event which would likely cause

delay, he must estimate the delay and extend the time for completion. He

owed that duty to both the contractor and building owner. It may be against

the owner's interest not to consider a cause of delay of which there is no

notice or a lack of it. Although the giving of notice by the contractor under

clause 23 was not a condition precedent to the architect considering any

possible time extension, the contractor's failure to give notice when it was

apparent that the work had been delayed would be a breach of contract.

Hence. considering this breach, the architect would assess the length of time

extension to which the contractor was entitled had he given the notice at the

proper time.

Page 51: NorJalilahIdrisMBD2006TTT

35

The reason for this arose from a fear that in the event of an employer's delay,

if the contractor failed to serve a notice and was thus prevented from claiming an

extension of time, it may be open to argument that time was at large because the

employer had prevented completion and no extension of time was possible. This

stemmed from the decision in Peak Construction (Liverpool) Ltd v McKinney

Foundations Ltd (1970) 69 LGR 1.

However, the Australian case Turner Corporation Ltd (Receiver and

Manager appointed) v Austotel Pty Ltd 1994 NSW LEXIS 12792 appears allay such

fears and held that:

"Jf a Builder, having a right to claim an extension of time fails to do so, it

cannot claim that the act of prevention which wouJd have entitled it to an

extension of time for Practical Completion resulted in its inability to complete

by that time. A party to a contract cannot rely upon preventing conduct of the

other party where it failed to exercise a contractual right which would have

negated the effect of that preventing conduct. "

However, a more recent Australian case of Gaymark Investments v Walter

Construction (1999) Northern Territory Supreme Court 143, concerns an appeal on

the arbitrator's award where disputes between the parties had been referred to

arbitration. The contract between the employer and the contractor provided for notice

as a condition precedent to any extension of time.

However, the contract did not provide for any discretionary power to the

owner's architect to grant extension of time notwithstanding the contractor's failure

to comply with the notice provisions. The arbitrator found that the employer had

caused delays to the works but, by virtue of the stringent notice provisions coupled

with the absence of any discretionary power to award extension of time, the

employer must be regarded as having elected to take the risk that if the employer

himself had caused delays and the contractor had not given the required notice, time

would have been set at large and liquidated damages could not have been recovered

by the employer under the prevention theory. The court agreed with the arbitrator.

Page 52: NorJalilahIdrisMBD2006TTT

36

Examples of standard forms of contract where notice is not a condition

precedent:

(a) None of the Malaysian Standard Forms require the giving of notice as

a condition precedent to the right to an extension of time.

(b) PWO Form OBIT (clause 45.1), PWD Form 203A (clause 43),

PAM69 (clause 23), PAM98 (clause 23), and IEM (clause 43), state that:

"Upon it becoming reasonably apparent that the progress of the Works is

delayed, the Main Contractor shall forthwith give written notice of the cause

of the delay to the [P.D./S.O./Architect/Engineer.] ... n

(c) CIDB conditions impose a time frame upon the Contractor for

issuance of a notice and reaction to that notice by the Superintending Officer

however compliance with this requirement is not a condition precedent to the

granting of an extension to the Time for Completion of the Works.

Example of a foreign standard forms of contract where notice is a condition

precedent. This can be found in the Singaporean SIA Conditions clause 23(2) which

states:

"It shall be a condition precedent to an extension of time by the Architect

under any provisions of this Contract including the present clause (unless

the Architect has already informed the Contractor of his willingness to grant

an extension of time) that the Contractor shall within 28 days notify the

Architect in writing of any event or direction or instruction which he

considers entitles him to an extension of timer together with a sufficient

explanation of the reasons why delay to completion will result. "

If the details submitted are insufficient to enable the Superintending Officer

to decide on an extension of time, then the Superintending Officer may require the

Contractor to provide further information which may reasonably be required.

Page 53: NorJalilahIdrisMBD2006TTT

37

2.3.4 Construction Work Programme

The burden of proof of delay rests on the contractor whether the application

be made before or after completion and whether the delaying events is the

employer’s fault or neutral. If the contractor intends to challenge liquidated damages

on the grounds of delay or aims to avoid liquidated damages, by obtaining an

extension from the C.A or an arbitrator, the contractor will have to produce evidence

that delay occurred and that the cause of the delay gave an entitlement to an

extension. Consequently it is up to the contractor to keep records as evidence of both

delay and cause. The strength of the contractor’s case will depend on the quality of

the records.

There is no doubt that a comprehensive programme marked up on a regular

basis to show actual start dates, durations and completion dates of significant

activities, is at least a credible record of progress even if it says nothing on the actual

causes of any delays. But by adding to the programme indicators on when

variations, revisions and the like were ordered, instruction were given, and other

events were encountered, the programme can provide a detailed picture which

should satisfy the test of good evidence.

In Malaysian standard form of contract, the requirement for preparing a work

programme in the document contract is stated in clause 3.4 of PAM 98 and clause

5.1 in CIDB 2000 while PAM 203A is silent about it. It had been mentioned before

the importance of having this document in construction project. The main advantage

is to foreseen the contractor’s planning of work and to determine the critical path or

critical activities in a project. This information is useful in knowing which party had

contributed to the delays and due to that, make an easier assessment for S.O or C.A

in granted time extension to contractor.

The contractor who fails to produce an effective and realistic programme

puts himself at a disadvantage on proof of entitlement to extension. First of all, he

must show that he has suffered delay and that this delay has affected completion of

the works, then he must show that the delay was caused by a relevant event and not

Page 54: NorJalilahIdrisMBD2006TTT

38

his own deficiency and difficulties.

To do this without a programme showing what was intended by way of

orderly progress and output, and records showing how progress and output were

comparing with the programme before the alleged delay, is a near impossible task.

As for C.A having to form his own view in such circumstances, he may have so few

definite facts on which to base his decision that the contractor can hardly complain

of unfair treatment.

Professor Wallace in Hudson’s Building and Engineering Contracts (1980)

explained the usefulness for the architect of the requirement of work programme :

The purpose of contractual requirement for a programme to be supplied by

the contractor is often misunderstood, and is primary to enable its owner, or his

Architect or engineer, to plan their own arrangements for giving possession,

supplying information and working drawings, and co-ordinating the work of other

contractors or nominated sub- contractors, and only secondarily for use in

connection with the contractor’s extension of time applications or monetary claims,

or to impose additional time obligations on it.

Page 55: NorJalilahIdrisMBD2006TTT

39

CHAPTER 3

CONSTRUCTION WORK PROGRAMME

3.0 Construction Planning

Construction planning is a fundamental and challenging activity in the

management and execution of construction projects. It involves the choice of

technology, the definition of work tasks, the estimation of the required resources and

durations for individual tasks, and the identification of any interactions among the

different work tasks. A good construction plan is the basis for developing the budget

and the schedule for work. Developing the construction plan is a critical task in the

management of construction, even if the plan is not written or otherwise formally

recorded. In addition to these technical aspects of construction planning, it may also

be necessary to make organizational decisions about the relationships between

project participants and even which organizations to include in a project. For

example, the extent to which sub-contractors will be used on a project is often

determined during construction planning.

Most people, describe a train of events is what the result would be. They can

put those events together in their minds, and argue from them that something will

Page 56: NorJalilahIdrisMBD2006TTT

40

come to pass. There are few people told a result, would be able to evolve from their

own inner consciousness what the steps were which led up to that result.

Like a detective, a planner begins with a result (i.e. a facility design) and

must synthesize the steps required to yield this result. Essential aspects of

construction planning include the generation of required activities, analysis of the

implications of these activities, and choice among the various alternative means of

performing activities. In contrast to a detective discovering a single train of events,

however, construction planners also face the normative problem of choosing the best

among numerous alternative plans. Moreover, a detective is faced with an observable

result, whereas a planner must imagine the final facility as described in the plans and

specifications.

In developing a construction plan, it is common to adopt a primary emphasis

on either cost control or on schedule control as illustrated in Figure 2. Some projects

are primarily divided into expense categories with associated costs. In these cases,

construction planning is cost or expense oriented. Within the categories of

expenditure, a distinction is made between costs incurred directly in the performance

of an activity and indirectly for the accomplishment of the project. For example,

borrowing expenses for project financing and overhead items are commonly treated

as indirect costs. For other projects, scheduling of work activities over time is critical

and is emphasized in the planning process. In this case, the planner insures that the

proper precedences among activities are maintained and that efficient scheduling of

the available resources prevails. Traditional scheduling procedures emphasize the

maintenance of task precedences (resulting in critical path scheduling procedures) or

efficient use of resources over time (resulting in job shop scheduling procedures).

Finally, most complex projects require consideration of both cost and scheduling

over time, so that planning, monitoring and record keeping must consider both

dimensions. In these cases, the integration of schedule and budget information is a

major concern.

Page 57: NorJalilahIdrisMBD2006TTT

41

Figure 2: Alternative Emphases in Construction Planning (Scheduling

Construction Projects, 1997)

3.1 Definition of work programme

Scheduling project work is an essential element of project management. A

project schedule makes clear to all participants when work is expected to be

completed. It also shows the time-related dependencies between different project

tasks.

In a complex project, several schedules may be necessary, covering different

levels of detail or different parts of the project.

Page 58: NorJalilahIdrisMBD2006TTT

42

3.1.1 Who does Project Scheduling

Setting overall completion dates must be done by the project sponsor and

stakeholders. The project manager assists in this by digesting information about

scope, deliverables, and resources, and estimating times for completion of project

tasks.

Once an overall schedule is set, the project manager is responsible for

monitoring the progress of the project and revising the schedule if needed. This must

be done in consultation with project team members who are doing the work.

Working with team members to produce accurate time estimates is one of the high

mysteries of the art of project management. The project manager must balance the

needs for honesty and realism with appropriate motivation to keep the project on

track despite inevitable surprises.

There will typically be give-and-take as a project proceeds among budget,

features, and schedule. It is essential for the project manager to keep all participants

informed as to current schedule status.

3.1.2 How is scheduling done?

The Gantt chart is a popular format for displaying schedule information.

Many software packages are available to assist in preparing Gantt charts and other

similar charts. The example of scheduling software is Primavera, Microsoft Project

and Atrimis.

Page 59: NorJalilahIdrisMBD2006TTT

43

3.2 Purposed of Construction Work Programme

The type of person use construction work programe and the uses they make

of those schedules are as diverse as is the construction industries itself. The owner

and his representatives will use the construction work programme to monitor

progress on the construction project. The contractor’s project manager, project

superintendents, engineers and subcontractors will also use the construction work

programme.

From here, the main purpose of construction work programme is to predict

the progress of following caracter :

i. Project Completion Time

ii. Task Time

iii. Conflict in work sequence

iv. Requirement of financing

v. Effect of proposed changes

vi. Delay in work

vii. To serve as a record of actual versus schedule completion

viii. Historical cost data

ix. To satisfy a contractual requirement

3.2.1 Project Completion Time

The project completion time is the date when a project will be completed. If

the project is being performed under the terms of a contract that specifies a contract

completion date, there may be financial penalties for late completion. If the schedule

indicates that the plan will result in late completion, then the construction manager

has been put on notice that he must revise that plan. Perhaps he can employ more

Page 60: NorJalilahIdrisMBD2006TTT

44

craftsmen, mobilize more equipment, work overtime, or perform tasks in a different

sequence.

3.2.2 Task Time

Task times are the times that specific tasks or activities will commence or

end. With this information, the manager can make arrangements to have material,

craftsmen, and equipment on hand when they will be needed. Procurement of

material is often a critical task. The manager can schedule the preparation of

procurement specifications and shop drawings, the architect's approval of these

documents and the fabrication and delivery of the material. If the schedule does

indicate that initiation of critical tasks will be delayed by the lack of some resource,

then the manager is alerted to the need to take extraordinary action to obtain that

resource in a timely manner.

3.2.3 Conflict in Work Sequence

Examination of the task times may reveal conflicts that will occur between

different trades or subcontractors because of limited work space. It may also reveal

that one trade is scheduled to start a task before another trade has done work that

must be completed before that task can be started.

Page 61: NorJalilahIdrisMBD2006TTT

45

3.2.4 Requirement for Financing

The rate of progress on the project determines the rate at which labor,

equipment, and material resources will be consumed and costs will be incurred. It

also affects the rate at which the contractor will receive progress payments. The

difference between costs incurred and paid and payments received represents the

contractor's cash flow on a project. During the early stages of a project, the cash flow

is negative, meaning that more cash has been paid out than has been taken in. The

contractor may need to borrow additional working capital if he doesn't have enough

liquid assets to cope with the problem.

3.2.5 Effect of Proposed Changes

Changes in the project scope, in the type of materials to be used or of any

kind may affect the starting and finishing dates of uncompleted tasks. These changes

may increase or decrease the overall project cost. If these changes are initiated by the

owner and if they result in increased costs to the contractor, then the contractor

should request additional compensation. One of the commonest causes for increased

project cost is the extension of the project duration. The cost component project

overhead, or is nearly proportional to project duration.

Page 62: NorJalilahIdrisMBD2006TTT

46

3.2.6 Delay in work

The schedule should be periodically updated to show both scheduled and

actual task times. It should show when work was delayed, whether by the

contractor's acts or omissions, or by changes in the project scope or design initiated

by the owner. If a task: actually starts later than its scheduled time, that delay may

affect costs incurred on other tasks. If the delay was caused by the owner, the

contractor is entitled to a time extension and additional compensation. If the delay

was caused by neither the owner nor the contractor, then the contractor may be

entitled to a time extension.

The project superintendent should maintain a project diary and should make

frequent job photographs. These records, together with the updated schedule, will

indicate to the contractor the amount and reasons for delay and increased costs, and

will aid him in negotiating fair compensation from the owner. Such records may be

valuable if the contractor wishes to defend himself against penalties that the owner

intends to assess for late completion. They may also assist the contractor in

justifying increased compensation, which is warranted because of changes initiated

by the owner.

3.2.7 To serve as a Record of Actual Versus Schedule Completion

It is customary in contract construction for the contractor to submit a

periodic invoice or request for partial payment as the work progresses. He will

receive progress payments that are based on the percentage completion of the

project at the time the invoice was submitted. Often the owner will withhold some

percentage of the contractor's earnings until the project is completed. The retainage

Page 63: NorJalilahIdrisMBD2006TTT

47

may be 10% of cumulative earnings until the project is 50% completed. There

after, if the project is on schedule, the retainage may he reduced to 5%. A detailed

schedule, one that has been properly posted with current project status, is one of

the most acceptable forms of evidence that the percentage completion claimed by

the contractor is accurate.

3.2.8 Historical Cost Data

A properly updated schedule may be a valuable source of cost and

scheduling data that estimators and schedulers can use for future projects.

3.2.9 To satisfy a contractual Requirement

Often, in contract construction, the owner of the future facilities has a

contractual right to be provided with a copy of the contractor's schedule. He may

also have a contractual right to direct the contractor to accelerate progress, perhaps

by working extended hours, if the schedule reveals that the job will not be finished

by the contract completion date, some owners may specify the form of the schedule

that they are to be provided

Page 64: NorJalilahIdrisMBD2006TTT

48

3.3 Type of Construction Work Programme

3.3.1 Gantt Chart

During the era of scientific management, Henry Gantt developed a tool for

displaying the progression of a project in the form of a specialized chart. An early

application was the tracking of the progress of ship building projects. Today, Gantt's

scheduling tool takes the form of a horizontal bar graph and is known as a Gantt

chart, a basic sample of which is shows in Figure 3:

Figure 3: Gantt Chart Format (Planning and Controlling Construction Projects-The

Best Laid Plans, 1996)

The horizontal axis of the Gantt chart is a time scale, expressed either in

absolute time or in relative time referenced to the beginning of the project. The time

resolution depends on the project - the time unit typically is in weeks or months.

Rows of bars in the chart show the beginning and ending dates of the individual tasks

in the project.

Page 65: NorJalilahIdrisMBD2006TTT

49

In the Figure 3, each task is shown to begin when the task above it completes.

However, the bars may overlap in cases where a task can begin before the

completion of another, and there may be several tasks performed in parallel. For such

cases, the Gantt chart is quite useful for communicating the timing of the various

tasks.

For larger projects, the tasks can be broken into subtasks having their own

Gantt charts to maintain readability.

3.3.1.1 Gantt Chart Enhancements

This basic version of the Gantt chart often is enhanced to communicate more

information.

• A vertical marker can used to mark the present point in time.

• The progression of each activity may be shown by shading the bar as

progress is made, allowing the status of each activity to be known

with just a glance.

• Dependencies can be depicted using link lines or color codes.

• Resource allocation can be specified for each task.

• Milestones can be shown.

Page 66: NorJalilahIdrisMBD2006TTT

50

3.3.1.2 Gantt Chart Role in Project Planning

For larger projects, a work breakdown structure would be developed to

identify the tasks before constructing a Gantt chart. For smaller projects, the Gantt

chart itself may used to identify the tasks.

The strength of the Gantt chart is its ability to display the status of each

activity at a glance. While often generated using project management software, it is

easy to construct using a spreadsheet, and often appears in simple ascii formatting in

e-mails among managers.

For sequencing and critical path analysis, network models such as CPM or

PERT are more powerful for dealing with dependencies and project completion time.

Even when network models are used, the Gantt chart often is used as a reporting tool.

3.3.2 PERT Chart

Complex projects require a series of activities, some of which must be

performed sequentially and others that can be performed in parallel with other

activities. This collection of series and parallel tasks can be modeled as a network.

In 1957 the Critical Path Method (CPM) was developed as a network model

for project management. CPM is a deterministic method that uses a fixed time

Page 67: NorJalilahIdrisMBD2006TTT

51

estimate for each activity. While CPM is easy to understand and use, it does not

consider the time variations that can have a great impact on the completion time of a

complex project.

The Program Evaluation and Review Technique (PERT) is a network model

that allows for randomness in activity completion times. PERT was developed in the

late 1950's for the U.S. Navy's Polaris project having thousands of contractors. It has

the potential to reduce both the time and cost required to complete a project.

3.3.2.1 The Network Diagram

In a project, an activity is a task that must be performed and an event is a

milestone marking the completion of one or more activities. Before an activity can

begin, all of its predecessor activities must be completed. Project network models

represent activities and milestones by arcs and nodes. PERT originally was an

activity on arc network, in which the activities are represented on the lines and

milestones on the nodes. Over time, some people began to use PERT as an activity

on node network. For this discussion, we will use the original form of activity on arc.

Page 68: NorJalilahIdrisMBD2006TTT

52

3.3.2.2 Steps in the PERT Planning Process

PERT planning involves the following steps:

I) Identify Activities and Milestones

The activities are the tasks required to complete the project. The milestones

are the events marking the beginning and end of one or more activities. It is

helpful to list the tasks in a table that in later steps can be expanded to include

information on sequence and duration.

II). Determine Activity Sequence

This step may be combined with the activity identification step since the

activity sequence is evident for some tasks. Other tasks may require more

analysis to determine the exact order in which they must be performed.

III). Construct the Network Diagram

Using the activity sequence information, a network diagram can be drawn

showing the sequence of the serial and parallel activities. For the original

activity-on-arc model, the activities are depicted by arrowed lines and

milestones are depicted by circles or "bubbles".

Page 69: NorJalilahIdrisMBD2006TTT

53

If done manually, several drafts may be required to correctly portray the

relationships among activities. Software packages simplify this step by

automatically converting tabular activity information into a network diagram.

IV). Estimate Activity Times

Weeks are a commonly used unit of time for activity completion, but any

consistent unit of time can be used.

A distinguishing feature of PERT is its ability to deal with uncertainty in

activity completion times. For each activity, the model usually includes three

time estimates:

• Optimistic time - generally the shortest time in which the activity can be

completed. It is common practice to specify optimistic times to be three

standard deviations from the mean so that there is approximately a 1% chance

that the activity will be completed within the optimistic time.

• Most likely time - the completion time having the highest probability. Note

that this time is different from the expected time.

• Pessimistic time - the longest time that an activity might require. Three

standard deviations from the mean is commonly used for the pessimistic time.

Page 70: NorJalilahIdrisMBD2006TTT

54

V). Determine the Critical Path

The critical path is determined by adding the times for the activities in each

sequence and determining the longest path in the project. The critical path

determines the total calendar time required for the project. If activities outside

the critical path speed up or slow down (within limits), the total project time

does not change. The amount of time that a non-critical path activity can be

delayed without delaying the project is referred to as slack time.

If the critical path is not immediately obvious, it may be helpful to determine

the following four quantities for each activity:

• ES - Earliest Start time

• EF - Earliest Finish time

• LS - Latest Start time

• LF - Latest Finish time

These times are calculated using the expected time for the relevant activities.

The earliest start and finish times of each activity are determined by working

forward through the network and determining the earliest time at which an

activity can start and finish considering its predecessor activities. The latest

start and finish times are the latest times that an activity can start and finish

without delaying the project. LS and LF are found by working backward

through the network. The difference in the latest and earliest finish of each

activity is that activity's slack. The critical path then is the path through the

network in which none of the activities have slack.

The variance in the project completion time can be calculated by summing

the variances in the completion times of the activities in the critical path.

Given this variance, one can calculate the probability that the project will be

Page 71: NorJalilahIdrisMBD2006TTT

55

completed by a certain date assuming a normal probability distribution for the

critical path. The normal distribution assumption holds if the number of

activities in the path is large enough for the central limit theorem to be

applied.

Since the critical path determines the completion date of the project, the

project can be accelerated by adding the resources required to decrease the

time for the activities in the critical path. Such a shortening of the project

sometimes is referred to as project crashing.

VI). Update as Project Progresses

Make adjustments in the PERT chart as the project progresses. As the project

unfolds, the estimated times can be replaced with actual times. In cases where

there are delays, additional resources may be needed to stay on schedule and

the PERT chart may be modified to reflect the new situation.

3.3.2.3 Benefits of PERT

PERT is useful because it provides the following information:

• Expected project completion time.

• Probability of completion before a specified date.

• The critical path activities that directly impact the completion time.

• The activities that have slack time and that can lend resources to critical

path activities.

• Activity start and end dates.

Page 72: NorJalilahIdrisMBD2006TTT

56

3.3.2.4 Limitations

The following are some of PERT's weaknesses:

• The activity time estimates are somewhat subjective and depend on

judgment. In cases where there is little experience in performing an

activity, the numbers may be only a guess. In other cases, if the person or

group performing the activity estimates the time there may be bias in the

estimate.

• Even if the activity times are well-estimated, PERT assumes a beta

distribution for these time estimates, but the actual distribution may be

different.

• Even if the beta distribution assumption holds, PERT assumes that the

probability distribution of the project completion time is the same as the

that of the critical path. Because other paths can become the critical path

if their associated activities are delayed, PERT consistently

underestimates the expected project completion time.

The underestimation of the project completion time due to alternate paths

becoming critical is perhaps the most serious of these issues. To

overcome this limitation, Monte Carlo simulations can be performed on

the network to eliminate this optimistic bias in the expected project

completion time.

Page 73: NorJalilahIdrisMBD2006TTT

57

3.3.3 Critical Path Method

In 1957, DuPont developed a project management method designed to

address the challenge of shutting down chemical plants for maintenance and then

restarting the plants once the maintenance had been completed. Given the complexity

of the process, they developed the Critical Path Method (CPM) for managing such

projects.

CPM provides the following benefits:

• Provides a graphical view of the project.

• Predicts the time required to complete the project.

• Shows which activities are critical to maintaining the schedule and which

are not.

CPM models the activities and events of a project as a network. Activities are

depicted as nodes on the network and events that signify the beginning or ending of

activities are depicted as arcs or lines between the nodes.

Page 74: NorJalilahIdrisMBD2006TTT

58

3.3.3.1 Steps in CPM Project Planning

I). Specify the Individual Activities

From the work breakdown structure, a listing can be made of all the activities

in the project. This listing can be used as the basis for adding sequence and

duration information in later steps.

II). Determine the Sequence of the Activities

Some activities are dependent on the completion of others. A listing of the

immediate predecessors of each activity is useful for constructing the CPM

network diagram.

III). Draw the Network Diagram

Once the activities and their sequencing have been defined, the CPM diagram

can be drawn. CPM originally was developed as an activity on node (AON)

network, but some project planners prefer to specify the activities on the arcs.

IV). Estimate Activity Completion Time

Page 75: NorJalilahIdrisMBD2006TTT

59

The time required to complete each activity can be estimated using past

experience or the estimates of knowledgeable persons. CPM is a deterministic

model that does not take into account variation in the completion time, so

only one number is used for an activity's time estimate.

V). Identify the Critical Path

The critical path is the longest-duration path through the network. The

significance of the critical path is that the activities that lie on it cannot be

delayed without delaying the project. Because of its impact on the entire

project, critical path analysis is an important aspect of project planning.

The critical path can be identified by determining the following four

parameters for each activity:

• ES - earliest start time: the earliest time at which the activity can start

given that its precedent activities must be completed first.

• EF - earliest finish time, equal to the earliest start time for the activity

plus the time required to complete the activity.

• LF - latest finish time: the latest time at which the activity can be

completed without delaying the project.

• LS - latest start time, equal to the latest finish time minus the time

required to complete the activity.

The slack time for an activity is the time between its earliest and latest start

time, or between its earliest and latest finish time. Slack is the amount of time

that an activity can be delayed past its earliest start or earliest finish without

delaying the project.

Page 76: NorJalilahIdrisMBD2006TTT

60

The critical path is the path through the project network in which none of the

activities have slack, that is, the path for which ES=LS and EF=LF for all

activities in the path. A delay in the critical path delays the project. Similarly,

to accelerate the project it is necessary to reduce the total time required for

the activities in the critical path.

VI). Update CPM Diagram

As the project progresses, the actual task completion times will be known and

the network diagram can be updated to include this information. A new

critical path may emerge, and structural changes may be made in the network

if project requirements change.

3.3.3.2 CPM Limitations

CPM was developed for complex but fairly routine projects with minimal

uncertainty in the project completion times. For less routine projects there is more

uncertainty in the completion times, and this uncertainty limits the usefulness of the

deterministic CPM model. An alternative to CPM is the PERT project planning

model, which allows a range of durations to be specified for each activity.

Page 77: NorJalilahIdrisMBD2006TTT

61

3.4 Role of Work Programme in EOT Application

Extensions of the time allowed for carrying out a project are important

considerations because of the nature of the contract, which forms the basis of so

many construction projects. Planning techniques are frequently used on a project for

the evaluation of possible extensions of time caused by changes to the project. There

are many prob1ems inherent in this. Some problems arise because the techniques

were not developed for retrospective analysis, other problems arise because the

techniques are wrongly applied. This section describes, with il1ustrative examples,

some methods which can be applied to evaluate extensions, the problems which

might be encountered and possible solutions to them. It should be remembered that

the calculated extensions of time should be used as negotiating positions rather than

statements of extensions. The information contained in the section is equally valid

for clients and contractors.

The objective of using any technique to evaluate a possible extension of time

is to produce a model of the project which, when it has alterations imposed on it,

behaves like a project managed. by an experienced contractor.

3.4.1 Determination EOT entitlement

Consider the example below. The scenario is quite complex and some time

should be spent understanding what is happening and way. The connections, which

represent the technology of the method, are represented in Figure 4. The connection

between the brick activities has not been included because it only represent the

contractor’s preferred method of work showing the intended progress of resources.

Consider the following variation to the project:

Page 78: NorJalilahIdrisMBD2006TTT

62

• The contractor fail to start building 1 until week 3 for reasons which are

not in dispute and for which the responsibility is accepted as the

contractor

• In week 2 building 2 suffers a delay, which is caused by the client.

Figure 4: Original Bar Chart Showing technological Logic (Planning and

Controlling Construction Projects-The Best Laid Plans, 1996)

The variations that arise can now be applied at the times at which they

became apparent. There is no clarity in the example as to when this was and

therefore it is suggested that a worst case scenario should be adopted in which it is

assumed that the delays are known about only just before they occur.

In this case, the failure to start building 1 would be known about at the start

of the project and the situation would be as shown in Figure 5. It is important to note

that the delay to the building would not have extended the project because an

experienced contractor would have been expected to take mitigating action, which in

this case would have meant increasing the number of bricklaying resources to enable

the two buildings to be worked on together. Whoever caused the delay might be

expected to pay for the extra resources required but would not be expected to pay for

Page 79: NorJalilahIdrisMBD2006TTT

63

an extension to the project. It is a matter of judgment as to whether or not the

provision of extra resources constitutes reasonable mitigating action; following the

example it is assumed to be so here.

Figure 5 : Project with variation to building 1 (Planning and Controlling

Construction Projects-The Best Laid Plans, 1996)

The second variation affected only building 2. It took effect in week 2 and,

for this exercise, it is assumed that it became known about at the start of week 2.

This is illustrated in Figure 6 which shows the state as known about at this time with

a reschedule done from start of week 2.The work actually carried out is shown in

black.

Figure 6 : Project with variation to building 2 (Planning and Controlling

Construction Projects-The Best Laid Plans, 1996)

Page 80: NorJalilahIdrisMBD2006TTT

64

It can be seen that this variation is quite important to the project. It extends

the project duration to 11 weeks and reduces the amount of time for which the

doubling of resources is required. This is brought about because the path which has

been extended contains only technological constraints. If this delay were caused by

the client then it is suggested. that the client should pay for an extension to the

project but should not pay for extra bricklaying resources.

Figure 7 shows the effects of the next stage of the delays. In this, there are

concurrent delays to building I and building 2 . They occur at the start of week 4.

The actual work done on the project is shown in black and it can be seen that one-

third of building 1 concrete structure is complete while half of the original building

2 concrete structure and all the previously known delay to it is complete.

Figure 7: Project with concurrent variation to the two buildings (Planning and

Controlling Construction Projects-The Best Laid Plans, 1996)

Rescheduling from the start of week 4 shows once again that the project is

delayed by a week and now is forecast to take 12 weeks. The variation which caused

this delay can clearly be seen to be the one which affected building 2. The variation

to building I had no effect at all on the project duration hut did have an effect on the

timing of the resource demands and, if it was extra work rather than delay, would

Page 81: NorJalilahIdrisMBD2006TTT

65

affect the project costs.

It would be important if this variation to building 1 occurred without the

concurrent delay to building 2. In this case, the reschedule would be as shown in

Figure 8 and the project would not have been delayed but the resource demands

would have to be altered in the future to enable the two brickwork activities to be

carried out simultaneously for 2 weeks.

All these stages have been carried out in a manner which models the behavior

of a reasonable contractor. That is, as the variations have become known, the work

has been rescheduled assuming the same technological logic and wherever possible

maintaining the concept of the work method which in this case meant using a single

bricklaying gang. The ownership of the delays to the project and the extra cost are

apparent from the analysis.

Figure 8 : Project with variation to building 1 only (Planning and Controlling

Construction Projects-The Best Laid Plans, 1996)

Page 82: NorJalilahIdrisMBD2006TTT

66

Figure 9 : Project Evaluate by the addition method (Planning and Controlling

Construction Projects-The Best Laid Plans, 1996)

On a more complex project, the same method should be followed and the

rescheduling process wou1d be the same in principle but rather more time-

consuming.

Page 83: NorJalilahIdrisMBD2006TTT

67

CHAPTER 4

WORK PROGRAMME AS A BASIS TO ESTABLISH EOT ENTITLEMENT

4.0 Introduction

The purpose of preparing a work programme in construction work is briefly

written by Rajoo (1999) as a tool to help architect or engineer to form an opinion of

when he will need to prepare information and aid the quantity surveyor to gauge the

employer’s cash flow profile on the project.

4.1 Work Programme in Standard form of Contract

Work programme is one of the new things introduced in Malaysian

construction contract, therefore only PAM 1998 and CIDB 2000 have this provision

in its standard form of contract while PWD 203A is silent about it. It can be seen that

Page 84: NorJalilahIdrisMBD2006TTT

68

the provision of work progamme are quite detailed discussed in CIDB 2000 form of

contract rather than PAM 98 form of contract.

Both PAM 98 and CIDB 2000 are not stated the provision of having work

programme under the extension of time clause, but there is stated under clause of

contract document. In other words, there are no direct link in clause of extension of

time and requirement of work programme.

4.1.1 PAM 1998

Requirement in preparing work programme in contract document is stated in

PAM 98 under clause 3.4. In PAM 98, the contractor under the clause is required to

provide two copies of work programme to the architect within 14 days after receiving

the Letter of Acceptance (L.A). Usually the programme is in graphic representation

of the detailed work activities and mobilization of resources towards that sequence of

activities. PAM 98 describes work programme as represents the contractor’s plan of

proceeding for the work, nevertheless the expected element in work programme are

not defined in the clause, but Rajoo (1999) stated that it may take the form of a bar

chart, critical path, precedence diagram, schedule, network analysis or otherwise. He

also described a good work should show interfaces with sub-contractors, dates, time

frame, activities, stages and more.

However under clause 3.5 and 3.6, there are stated that the work programme

is not consider as a part of contract documents and do not relieved the contractor

from his obligations and responsibilities.

Page 85: NorJalilahIdrisMBD2006TTT

69

4.1.2 CIDB 2000

The provision of work programme is stated under clause 5.1 in CIDB 2000

form of contract and it seems to be more detailed describe in clause 5.1 (a) which

defined the expected work programme should clearly identifying the sequence, logic

and critical path in which he propose to carry out the Works including the various

work activities and milestones to be achieved.

Both of PAM 98 and CIDB 2000 stated later in clause 3.5 and clause 5.2(a)

that work programme is not a part of contract document and shall not treated as one.

The said clauses dilute the significant of the work programme and its contractual

effect arising from any aberrations to the programme. The effect of making the

programme an express requirement without it being a contract document is that while

the contractor may be in breach for the failure to provide the programme, he may not

be in breach if the series of events are not followed as scheduled.

The two clauses from two different standard form of contract above are more

likely to each other, except that CIDB2000 contents more detail on the provision.

JCT Standard Building Contract 2005 at clause 2.27…if and whenever it become

reasonably apparent that the progress of the works or any section is being or is likely

to be delayed the contractor shall forthwith give written notice..

4.2 How work programme can contribute in eot entitlement

It has been proved by several court cases, it is an advantages to have a work

pogramme as a guidance to parties involved to understand the contractor’s plan of

proceeding for the work. Even there are different ways to produce a work

programme, but it still have one objective, that is to show in graphical form the

procedure and sequences of work that should be done. There are few elements and

Page 86: NorJalilahIdrisMBD2006TTT

70

points in work programme that make it strong and useful to the industry which will

be discuss further in the next discussion.

4.2.1 Logical analysis

Logical analysis is defined as decisions or result of an analysis which made

based on a logical ground. There are so many ways in construction to produce

information based on a logical ground, such as the usage of software or manual

method of calculation. The information gained is more

Logical analysis can be produced by using methodological method of work

programming such as critical path network as an example. Almost all of Malaysian

standard form of contract have a provision on giving a fair and reasonable time

extension to the contractor.

..the S.O shall soon as he is able to estimate the length of the delay beyond

the date or time aforesaid make in writing a fair and reasonable extension of

time for completion of the work…(Clause 43, PWD 203 A)

..the architect shall consider the relevant events causing delay and by written

notice to the contractor give a fair and reasonable extension of time..( clause

23.2, PAM 98)

…the S.O may in his absolute discretion, grant a fair, reasonable and

necessary extension of time..( Clause 24.5, CIDB 2000)

The term used (fair and reasonable) is considered as a subjective term which

no actual method or systematic calculation in stating the number of days. A

prominent case which discussed about this matter is John Barker Construction Ltd. v.

London Portman Hotel Ltd (1996).

Page 87: NorJalilahIdrisMBD2006TTT

71

This case is between a firm of building contractor named John Barker

Construction Ltd as the plaintiff carried out refurbishment works to the London

Portman Hotel, which is owned by the defendant, London Portman hotel Ltd in 1984.

The invitation to tender, dated 28 February 1994 stated that the contract would be let

on the JCT Standard Form of Building Contrcat (1980 edition)

The project was dealt under two contract, one was concerned the ground the

ground and first floor of the hotel and the other one was concerned the second to

eleventh floor of the hotel. The dispute and argument is more basically about the

unsatisfied extension of time given. The party involved in the contract were Gleeds,

acting on behalf of the defendant and acted as quantity surveyor, Mr. Miller of RPW

Ltd as the erchitect nominated in the building contract, Mr. Pickavance as the expert

witness of work programming and others. At the finding of this complicated case, Mr

Recorder Roger Toulson QC had stated that:

“…I accept that defendant had made a fair assessment of the extension of

time due to the plaintiff. It is fairly apparent that the defendant were

concerned by the overrun of the contract in time and costs, and I have no

doubt that the defendant was conscious of this, but I believe also that he

endeavoured to exercise his judgment independently. However, in my

judgment his assessment of the extension of time due to the plaintiff was

fundamentally flawed in a number of respects, namely :

i. Mr. Miller as behalf of the defendant did not carry out logical analysis

in a methodological way of the impact which the relevant matters had

or were likely to have on the plaintiff’s planned programme

ii. He made an impressionistic, rather than a calculated, assessment of the

time which he though was reasonable for the various items individually

and overall

On the evidence, I accept that at the time of the acceleration agreement the

plaintiff’s planned resources were reasonable for their planned programme. I

accept that the subsequent variation were likely to have and had a disruptive

Page 88: NorJalilahIdrisMBD2006TTT

72

effect on that programme, and that the exercise which plaintiff has done is a

fair way of calculating a reasonable extension of time…”.

From this case, it was said that in exercising his duty under clause 25 the

architect or C.A must undertake a logical analysis in a methodological way of the

impact of the relevant events on the contractor’s programme. The application of an

impressionistic rather than a calculated and rational assessment is not sufficient. The

terms of logical analysis in methodological way gave a significant impact in

approving extension of time in this case. Further, it was said that the extension is

flawed if the architect makes an impressionistic rather than a calculated assessment

bearing no logical or reasonable to the delay caused. At the same case, the judge also

said:

“ I accept that the assessment of a fair and reasonable extension involves an

exercise of judgment, but that judgment must be fairly and rationally based.”

The word rationally based is clearly defined as a logical analysis by using

some kind of methodological way or methods.

In Balfour Beatty Construction Limited v The Mayor and Burgess of the

London Borough of Lambeth(2002), the Critical Path Network (CPN) terms had been

stated in His Honour Judge Humprey Llyod QC judgment: “In the context of a

dispute about the time for completion a logical analysis includes the logic required

for in the establishment of a CPN (critical path network)”

The case between Balfour Beatty (BB) and defendant Lambeth was for the

refurbishment and remodeling of Falmouth House, Penwith Manor Estate,

Kennington Park Road, London under the JCT Standard Form of building contract

1998 edition. In the judge’s basis argument, it was found that:

i. BB programmed the work on a flat type basis (without identifying the

critical path) and at the very least BB should have measured progress

against these same flat types. That way it would have been possible to

Page 89: NorJalilahIdrisMBD2006TTT

73

compare the planned progress with the actual progress in a meaningful

way.

ii. BB’s programme do not comfort or comply with any of the recognized

and accepted delays analysis methods.

From the two prominent cases as mentioned above, it is clear that the

provision of fair and reasonable extension of time should not be taken as a subjective

matters which SO or CA can simply awarding reasonable period of time to the

contractor. It must be in calculated and logical method no matter what kind of work

programme they are going to use.

There are obvious that in Malaysian standard form of contract are not clarify

the terms of logical analysis, but from the judgment of the above mentioned two

cases, it can be considered the term in clause 43, PWD 203 A means something. It is

stated… S.O shall soon as he is able to estimate the length of the delay.. the words is

able to estimate should be taken in a wider perspective. What define the word able

here? It cant be just a simple estimation, it should be based on something stronger to

make the SO looks capable in doing his job. In John Barker case, it was alleged that

the architect had been negligent in awarding extension of time because it seems that

he is not able to award extension of time based on a logical analysis and

methodological way.

The other terms in Malaysian standard form of contract which sound like

subjective matters but could be in deeper meaning and understanding is in clause

24.5, CIDB 200,.the S.O may in his absolute discretion, grant a fair, reasonable and

necessary extension of time.. The word necessary here should be taken into more

detail understanding. It is surely not the intention of this clause to just simply said

that any award of extension of time is necessary by an authorized SO or CA. By

referring the cases above, necessary extension of time is supposed to be based on

logical analysis and again with methodological method, therefore the necessary word

needs a better definition to avoid any confusion assumption.

Page 90: NorJalilahIdrisMBD2006TTT

74

4.2.2 Critical Path Analysis

It is clear that in order to determine whether an event affected the completion

date, it is necessary to determine whether the event affected the critical path, so there

are delays occurred in the construction progress which are not affected the critical

path, therefore it doesn’t affected the completion date. Hence, this kind of delay if

caused by employer or neutral events are not considered as a basis to extension of

time entitlement. It seems that critical path analysis is a significant element in

preparing work programme. Unfortunately the terms of critical path analysis is not

directly stated in any of standard form of contract so it is not a breach of contract if it

is not prepared even it is a good basis to be referred to.

The importance of having work programme in construction progress which

can determine the critical events were stated in The Royal Brompton Hospital NHS

Trust v Frederick Alexander Hammond and others (2002), which the contract was

under JCT Standard Form of Contract, HHJ Richard Seymour QC said that :

..“It was plain from the evidence called at the sub-trial on behalf of the Claimant, in

particular that of Mr. Gibson, who of course is a programming expert, that there are

a number of established ways in which a person who wishes to assess whether a

particular event has or has not affected the progress of construction work can seek to

do that. Because the construction of a modern building, other than one of the most

basic type, involved the carrying out of a series of operations, some of which

possibly can be undertaken at the same times as some of the others, but many of

which can only be carried out in a sequence, it may well not be immediately obvious

which operations impact upon which other operations. In order to make an

assessment of whether a particular occurrence has effected the ultimate completion

of the work, rather than just a particular operations, it is desirable to consider what

operations, at the time the event with one is concerned happens, are critical to the

forward progress of the work as a whole. On the evidence of Mr.Gibson and Mr.

Luder (for the Claimant) the establishment of the critical path of a particular

construction project can itself be a difficult task if one does know how the contractor

planned the job..”

Page 91: NorJalilahIdrisMBD2006TTT

75

From the judge statement, it is far from clear that a critical path analysis is

always required or merited. In the case of certain types of delay it may be so plainly

obvious that a delaying event has affected the critical path that provided such an

event is properly evidenced and based in fact and is a relevant event then the

contractor will be entitled to the time.

The earlier case of Henry Boot Construction (UK) Ltd v. Malmaison Hotel

(Manchester) Ltd. (1999) which under JCT Standard Form of Contract had also

stated the importance of having critical path analysis in a construction project and yet

further confirmation of the requirement to establish the critical path. It was held by

Dyson J. that ,

“ the respondent was entitled to respond to the claim both by arguing that

the variations, late information and so on relied on by the claimant did not

cause any delay because they were not on the critical path and positively by

arguing that the true cause of delay was other matters”

This confirms the view that, in order to establish that an event has affected

the completion date, it must be shown that it falls on the critical path.

The later case on critical path terms found in Motherwell Bridge Construction

Ltd v. Micafil Vakuumtechnik (2002), Micafil was engaged as main contractor for the

construction of an autoclave under modified FIDIC 1998, a large steel vessel with an

internal volume of 650m3. The vessel was to be used in the manufacture of high

quality power cables.

Micafil undertook responsibility for the design of the vessel and sub-

contracted its construction to Motherwell Bridge. The project did not run smoothly.

During construction Motherwell Bridge raised many technical queries and there were

a number of significant design changes issued by Micafil. There were two major

formal amendments to the contract. Delays occurred and Micafil deducted liquidated

damages. Motherwell Bridge in turn claimed extension of time to extinguish the

claim for liquidated damages.

Page 92: NorJalilahIdrisMBD2006TTT

76

Judge Toulmin provided:

“ Crucial questions are (a) is the delay in the critical path, and if so, (b) is it

caused by Motherwell? If the answer to the first to the question is ‘Yes’ and

the second question is ‘No’ then I must assess how many additional working

days should be include”

The judgment of the case can be defined as if the delay touch on the

programmed critical path and it was not caused by the contractor, the contractor is

entitle to get reasonable time extension.

The passage from Henry Boot referred to above also points to some of the

principle defenses to a delay claim. In order to show that an event was not on the

critical path, the defendant has to argue that the claimant’s version of the critical path

is incorrect and must prove on the balance of probabilities that the critical path in fact

went elsewhere.

Other related case is The Royal Brompton Hospital NHS v Watkins Gray

International (UK) (2000), His Honour Judge Richard Symour QC concluded the

basic skills for the architect to practiced. First is the skill of construction knowledge,

the architect is encourage to have an in-depth knowledge of construction and the

inter-relation between trades and construction operations. The second skills which is

relevant with this topic is to understanding the programming techniques. Architect

usually have to adopt an appropriate programming techniques to analyze the effect

various events. By having the knowledge to analyze the link between cause and

effect make it easier task for architect to determine the delay had or had not caused

the critical path and it will lead to the extension of project completion date, and the

final skill is to have a deep knowledge in contractual matters.

Page 93: NorJalilahIdrisMBD2006TTT

77

4.2.3 Causal Link

One of the advantages by using method of programming, is people can see

the sequences works and the links involved, if there is ones. It is a significant task in

work programme to clearly state the links of cause and effect. It should show that in

any delay happened, what are the cause of it and the effect. Therefore, if the effect

has potential to delay the completion date, it can be defined as a critical path. If the

work programme had successfully proved the causal link, the application for the time

to be extended would be considered. This condition can be referred to a very recent

case in Hong Kong, Leighton Contractors (Asia) v Stelux Holdings Ltd (2004).

Stelux was the employer and Leighton the main contractor on a large building project

in Hong Kong which under the JCT Standard Form of Contract. One of the

Leighton’s argument was that Stelux had caused delay by releasing tender

information for the heating, air conditioning and electrical subcontract works late and

it was found that by the time the information has been provided and the relevant

subcontractors awarded, Leighton was still only commencing construction of the

basement slab.

On this basis, it was concluded that the late information could not have

caused actual delay. The judge concluded that there had to be some finding of a

causal link between the late submission of information and the potential delay to the

completion of the works. It was not enough for the contractor simply to show that the

information was late. Whichever delay analysis method was used it was therefore

necessary to take account of the progress of the works at the point that the claimed

delay event occurred.

It is clear to show us the importance to have causal links in the argument.

Without links, it is almost impossible to prove the connection between events and the

effect whether it has possibility to contribute in delaying the project.

The other case which had touch on the absent of link is Balfour Beatty

Construction Ltd v. The London Borough of Lambeth (2002). The main issue in this

case was not on causal link directly, but Judge Lloyd in his judgment had quoted on

Page 94: NorJalilahIdrisMBD2006TTT

78

importance of having the causal link. It was found that Balfour Beatty was unable to

identified the critical path on its programme as there were not a critical path analysis

but were a simpler bar chart without any links. In this case, it was clear that Balfour

Beatty did a little or nothing to present its case in a logical or methodical way. There

then was no attempt to provide a critical path analysis.

4.2.4 Regularly and diligently

The definition of doing work regularly and diligently had been discussed in

chapter 2. Almost all contract determination clauses in Malaysian standard form of

contract have stated failing to do works regularly and diligently is one of the events:

Clause 25.1(ii) of PAM 98..fails to proceed regularly and diligently with the

works

Clause 51.(a)(ii) of PWD 203A..if he fails to proceed regularly and

diligently with the works..

Clause 44.1(iv) of CIDB 2000..he fails to proceed with the design (to the

extent required by the contract) and/or the execution and completion of the

works with due diligence and expedition..

From the clauses above, one of the reason or event which can bring the

contract to the end by employer if it was proved the contractor were not doing the

agreed work regularly and diligently. The next question will be how the employer

can detect his contractor did not perform the works regularly and diligently? The

most logical answer to this is by referring to the project work programme.

Page 95: NorJalilahIdrisMBD2006TTT

79

As mentioned before failure to perform series of the events as scheduled is

not a breach of contract, but it may contribute to evidence of failure to proceed

‘regularly and diligently’.

It is also can be viewed in different way, which the contractor shall be

granted extension of time if he can prove he is doing the works regularly and

diligently. In another words, the contractor have a very good record and good

management by proving he is doing the works as scheduled in the work programme.

4.3 Weakness of work programme

In judgment of case The Royal Brompton Hospital NHS Trust v Frederick

Alexander Hammond and others (2002), it was found that there are one significant

weakness in using a work programme in construction. HHJ Richard Seymour QC

said that :

….the critical path may well change during the course contractor planned the job.

Not only that, but the critical path may well change during the course of the works,

and almost certainly will do if the progress of the works is affected by some

unforeseen event. Mr. Gibson (a programming expert) frankly accepted that the

various different methods of making an assessment of the impact of unforeseen

occurrences upon the progress of construction works are likely to produce different

results, perhaps dramatically different results. He also accepted that the accuracy of

any of the methods in common use critically, depends upon the quality of the

information upon which the assessment exercise was based. All of this does, of

course, emphasis the vital point that the duty of a professional man, generally stated

is not to be right but to be careful…

From the statement above, there are two obvious points of the weakness of

using a work programme, one is having different result fron different methods and

also the accuracy of the programme really depends on the quality of the information.

Page 96: NorJalilahIdrisMBD2006TTT

80

Even there are so many good points by practicing work programme in

construction progress had been discussed, there are also some disadvantages. In

every new thing introduced, there have to be several amendment before it become

completely useful to the users.

4.3.1 Variety of methods

In chapter 3, it had been discuss on the methods or strategies in preparing a

good work programme. There are a lot of methods which promise different result. It

was said that even by using the same information, the same activities it can come

with different result if the method is different.

It had been stated in above mentioned judgment of case, where was accepted

by one of the programming expert about this problem. It also will bring out

difficulties because there are no specific recommendation by any standards form of

contract in Malaysia in preparing the work programme.

4.3.2 Contents of work programme

There are no specific way how to prepare a good work programme, means

there are no standard form in the work programme contents. In PAM 98, there are no

clause about how a work programme should look like, or there are no guideline of an

expected work programme. The contents are usually depends on the requirement

from client or it is up to the programmer expertise.

Page 97: NorJalilahIdrisMBD2006TTT

81

There are no standardized in categorizing a good work programme or not. It

only said that the work programme with sufficient information is a good work

programme without knowing what are the expected information should be enclosed

in a work programme.

By having a multi style of work programme presentation, it will lead to a

various quality of work programme and this is finally will put parties involved in

problems of uncertainty document.

4.3.3 Presentation of the work programme

To prepare a high quality work programme, it is not only based on having a

good planner or programmer, it is also need a good teamwork and enforcement in

updating the progress and information.

A good work programme is not necessary full of information, but it has to be

clear and user friendly which means can be easily understand by readers who might

be have different background with different knowledge. This can be supported with

a case of Skanska Construction UK Limited v Egger (Barony) Limited (2004). Egger

is a subsidiary of an Austrian family owned company which produces chip board and

other timber based products at several factories throughout Europe. It entered into a

contract with Skanska for the design and construction of a factory to be built in East

Ayrshire in Scotland. Skanska agreed to undertake design development, management

and construction of the factory while Egger took direct responsibility for the supply

and installation of the specialist plant and equipment.

Judge Wilcox in his judgment in the case of Skanska Construction UK

Limited v Egger (Barony) Limited (2004) clearly preferred the evidence of

Skanska’s expert who had prepared an analysis which he described as “accessible”.

He described the characteristics of a good planning expert as someone who was

Page 98: NorJalilahIdrisMBD2006TTT

82

objective, meticulous as to detail and importantly, not hide-bound by theory when

demonstrable fact collided with computer programme logic.

Apparently, this could not be said of the evidences which been provided by

Egger’s programming expert. Judge Wilcox was severely critical of this evidence on

a number of levels. Firstly, he made clear his frustration with the too complexity of

the report (Egger’s). It had ran into several hundreds of pages supported by 240

charts. Egger’s expert had been supported by a team of assistants and it appears that

the report he had prepared was too complex and extensive for the court to easily

assimilate.

There are might be other cases which had touched on the presentation quality

of a work programme. What the above mentioned case had proved that complexity of

a work programme did not promise the quality of it. The more important is to keep

the information inside the work programme easily understood and can be a good tool

of data proving to any background of individual.

In summary, it is clear that a good understanding of the legal principles

governing the analysis of delay, the right choice of approach supported by good

factual evidence and the effective presentation of that evidence via a transparent

work programme analysis are now essential in order to maximize the likelihood of

success in adjudication, arbitration and litigation.

Page 99: NorJalilahIdrisMBD2006TTT

83

CHAPTER 5

CONCLUSION AND RECOMMENDATION

5.1 Introduction

Extension of time provision is not purposely for the sake of the contractor

only, it is also give a meaningful benefit for the employer. It is a win win situation,

where every parties involved will get the benefit and it will lead to a very good

relationship which finally result a good quality of works with minimum disputes. In

a construction progress, disputes can possibly happened everyday at every level and

any reason, this is where the importance of having a planned programme to foresee

the activities planned and the implementation of the works.

In chapter 2, it had stated that by having a good work programme is one of

the basis event to establish entitlement of extension of time, besides the awareness of

the contract with or without specific time for completion, doing works regularly and

diligently and by giving a proper notice of delay if it s believed a delay have a

potential to caused delay in date of completion.

Page 100: NorJalilahIdrisMBD2006TTT

84

Work programme is one of new finding methods in resolving disputes in

construction. The definition and the expected contents of a work programme had

been discussed in detail in chapter 3. Work programme is not directly mentioned in

standard form of contract in Malaysia but there are few clauses had included a work

programme as apart of document contract. But it is still not binding where there are

clauses debarred the earlier clauses which stated that work programme cannot be

treated as a contract. Therefore a contractor may be in breach for the failure to

provide the programme but he may not in breach if the series of events or activities

are not followed as scheduled.

5.2 Contribution in dispute resolution.

In answering the first objective of this research, (to identify how a

construction work programme can contribute in reducing disputes in extension of

time) there are few elements in work programme which can make the assessment of

extension of time easier, such as the critical path analysis or critical path method, a

logical analysis, a causal link and also can traced the works done with regularly and

diligently or not.

Critical path analysis is a strong evidence in proving the delay occurred will

or will not effect the date of completion. Most of the method in preparing a work

programme had included critical path analysis as a main element. The importance of

having critical path analysis; where user can identify activities and sequence of work

that will effect the completion date by occurr the critical activities or events. By

knowing the events or delay, it can determine who is responsible on the delay and

this will helping granting extension of time if it is proved not the fault of the

contractor. By having information through this method is more systematic.

Page 101: NorJalilahIdrisMBD2006TTT

85

Work programme also promise a logical analysis and the method of awarding

days for extension of time is made in a methodological way. It is not a assumption

from the expertise but it is more in proper calculated method. Hence, it will reduce

the queries on what basis the number of extension days had calculated

In a good work programme, it is also can determine the causal links between

the cause and effect of an activity. Only an event which has affected the links will be

considered. It can be said that the links is clearly can be seen by using a proper and

technical method in a work programme.

A contractor is entitled for extension of time if he can proved that he had used

his best endeavour and had tried his best to avoid the delay. He is also must proved

that he is doing the works with regularly and diligently. Even it is not a legal

provision to grant an extension of time but it at least can help the contractor to prove

that his background of working procedure is in proper manner and run smoothly

without causing any delay. By having an updated progress of work, the condition of

work on site can be traced and therefore it can determine the quality of work by

contractor.

5.3 Advantages and Disadvantages of Work Programme Usage

The second objective of this research is to determine the advantages and

disadvantages by using work programme in a construction contract. The main

advantages of work programme usage in construction contract are the elements

which had been discussed earlier (by having a logical analysis,by using the critical

path analysis, by proving the causal link and proving the works done is regularly and

diligently). There are also other advantages such as to make the monitoring work

easier for parties involved and to assist in preparing the mitigation plan.

Page 102: NorJalilahIdrisMBD2006TTT

86

Therefore, even there were judgments in court cases which prefer a good

work programme as one of the concrete evidence; it is still have weaknesses to be

avoided. The main disadvantage is the variety of methods in preparing work

programme, and due to that it will lead to a different result. Therefore it is also

believed that someone who is really expert should be appointed in handling the

preparation of work programme, and that means additional cost is required in

ensuring the presentation of a work programme is not just in high quality but

acceptable by others.

From all the argument above, it is clear that by having a good quality of a

work programme is become one of the important needs today, to face difficulties and

disputes in the industry, but the responsible parties still have to study the weakness of

the usage and put some afford to deal with it in producing a right method that can be

very useful to the industry.

5.4 Recommendation

Therefore, it is recommended that :

i. The requirement for a work programme in a document contract and updated

work programme in monthly meeting should be enforced.

ii. Since there are many methods in preparing a work programme, the parties

involved should form a standard methods to be used in a project.

iii. The knowledge on work programme should be treated as important

knowledge as others since it can contribute in reducing disputes in the

industry.

The usage of work programme in handling and reducing disputes in construction

industry is still in a beginner stage, even it promised a lot of benefits and it seem to

be admitted in court judgment, there are still weakness and disadvantages about it.

Therefore if it is really can be a tool in establishing extension of time entitlement, the

Page 103: NorJalilahIdrisMBD2006TTT

87

parties involved should form a standard format of a work programme and utilized it,

means keep updating it for ensuring the quality of information needed

5.5 Limitation of the research

In completing the research, there are few limitations occurred, such as

inadequate court cases which deal with work programme usage. Besides, there are no

Malaysia court case on the effect of the work programme in extension of time

entitlement, and due to that, the research is solely depends on the international court

cases. The other limitation is inadequate information on the work programme

protocol or information, it is because there are no provision about work programme

requirement in Malaysian standard form of contract.

Page 104: NorJalilahIdrisMBD2006TTT

REFERENCES

Allan Ashworth (2001), Contractual Procedures in the Construction Industry (4th

Edition). Longman.

Barry B. Bramble, Michael T. Callahan (1992). Construction Delay Claims, 2nd

Edition. New York: John Wiley & Sons, Inc

Brian Eggleston (1997). Liquidated Damages and Extension of Time in Construction

Contract,2nd Edition. London: Blackwell Sciences Ltd.

Dennis F. Turner & Alan Turner (1999). Building Contract Claims and Disputes,

2nd Edition. England: Addison Wesley Longman Limited

Donald Keating (1978). Building Contract, 4th Edition. London: Sweet & Maxwell

Duncan Wallace (1980). Hudson’s Building and Civil Engineering Contract. London

: Sweet & Maxwell

Edward M. Willis (1997), Scheduling Construction Projects. New York : John

Willey & Sons.

James J. Adrian (1988). Construction Claims – A Quantitative Approach. United

State: Prentice-Hall, N.J

John Murdoch, Will Hughes. (1996). Construction Contract: Law and Management,

2nd Edition. London: E & FN Spon.

Page 105: NorJalilahIdrisMBD2006TTT

Jonathan F. Hutching (1998). Construction Claims Manual for residential

Copntractor. NewYork : McGraw-Hill

Keith Pickavance (2000). Delay and Disruption in Construction Contract. London :

LLP Reference Publishing

Lim Chong Fong (2004). The Malaysian PWD Form of Construction Contract.

Malaysia : Sweet & Maxwell Asia

Michael Mawdesley, William Askew, Michael O’Reilly (1996). Planning and

Controlling Construction Projects-The Best Laid Plans. Longman.

Reg Thomas (1993).Construction Contract Claims. London: The Macmillan Press

Ltd.

Richard H. Clough, Glenn A. Sears, S. Keoki Sears (2000), Construction Project

Management, 4th Edition. New York: John Wiley & Sons, Inc.

Robert A. Rubin, Virginia Fairweather and Sammie D. Guy (1999).Construction

Claims Prevention and Resolution, 3rd Edition. New York: John Wiley &

Sons, Inc.

Robert Porter (1980), Building Contract Conditions, London : George Godwin

Limited.

Sundra Rajoo (1999).The Malaysian Standard Form of Building Contract (The PAM

1998 Form). Kuala Lumpur: Malayan Law Journal

Vincent Powell-Smith and John Sims (1989). Building Contract Claims. London :

BSP Professional Books.

Vincent Powell-Smith, Michael Furmston (1990). A Building Contract Casebook,

2nd Edition. London: BSP Professional Books