Page 1: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 1November 04Jason Tarrant

SCT EC Interconnects

Progress of SCT EC Interconnects» Services (Required for Disc Insertion 2004 / Integration 2005)

– Design

– Manufacture

– Assembly

» PPF1 (Required for Integration 2005 / Some parts for Disc Insertion 2004)

– Design

– Manufacture

Page 2: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 2November 04Jason Tarrant

SCT EC Interconnects

SCT EC Services - Design

Page 3: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 3November 04Jason Tarrant

SCT EC Interconnects

Cooling Progress» On Cylinder Interconnect

– Inlet (capillary)– Exhaust– LMT Cooling

» Connections– PPF0 connections– STFT connections– PPF1 connections

» Off Cylinder Interconnect– HEX assembly– Heater Assembly

Page 4: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 4November 04Jason Tarrant

SCT EC Interconnects On-Cylinder Interconnect

» Inlet– Swagelock @ PPF1 - x72 3 or 6mm versions

CERN Supply

– PPF1 – HEX – x72, 9 different types recent change of 2mm ID to 3mm ID 5mm OD 9 models / drawings required (includes filter), ~1 week

– Filter - x72 Paul having tested @ CERN

– Hex – x72 QMUoL

– STFT connections – x72 Paul having tested @ RAL

– Capillaries - x208 Nominal 2.5m long, to be tuned, CERN / QMUoL All Capillary stock @ CERN, even with extra required for D7 & D8 LMT cooling

– Connections at PPF0 – x208 230 Confirmed to be delivered to RAL 10th November, then around 15th November to CERN

Page 5: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 5November 04Jason Tarrant

SCT EC Interconnects» Exhaust

– PPF0 connection – x72 ‘Quick’ samples being manufactured Already tested see later

– Tube – x72, 9 different types All tube (for all interconnects) ‘in-stock’ Bent tubes manufactured by Newtown Engineering for Pre-Production prototype of D1 interconnect

– Elbows (interconnect only) & reducers – x72 & x144 ‘Quick samples on order (12th November) QMUoL make all Elbows?

– STFT connections - x72 Paul having tested @ RAL

– HEX– Heater Assembly – x72, 9 versions

CERN supply with ‘pressed-on’ copper / CuNi end for soldering to HEX

– Swagelock @ PPF1 – x72 CERN Supply

Page 6: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 6November 04Jason Tarrant

SCT EC Interconnects

On-Cylinder Interconnect…» LMT Cooling

– 2 spare ways from D9 with back-up of 1 spare way from D7 & D8– Drawings complete & out for quote (12th November)– Tube acquired from redundant Barrel stock– Long lengths split into smaller sections around bends (more joints vs.

ease of manufacture)

Page 7: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 7November 04Jason Tarrant

SCT EC Interconnects PPF0 connectors

» Based on Helicoflex» Already tested (I.Wilmut)» Only hole for connection changes from original

design

STFT connectors» Tapered PEEK seal based on Pixel design» 9 inlet & 9 exhaust to be tested soon then full

production

PPF1 connectors» Standard Swagelock bulkhead» To be supplied by CERN as part of PPF1 fluid

installation

Page 8: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 8November 04Jason Tarrant

SCT EC Interconnects

Off Cylinder Interconnect» Hex Assembly

– HEX drawings being modified for recent inlet tube diameter change 2 types of HEX Higher level assembly shows connection of inlet & Heater to PPF1 About 1-2 weeks of work

– Exhaust Tube, HEX Tube, Inlet & Exhaust connectors, supplied by RAL (Filter to supply)

– Inlet Tube sourced by QMUoL + manufacture of elbow to connect to Heater

» Heater Assembly– CERN Supply to QMUoL

» Combined Assembly– HEX & Heater to be assembled @ QMUoL then sent to CERN (Large

batch?)

Page 9: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 9November 04Jason Tarrant

SCT EC PPF1

PPF1 Design» Rerouted to enable HEX to be mounted in SCT-TRT Gap

and & Heaters in Cryostat cable tray

DCS board& cables

Exhaust Tubes

1175 Break line

Bulkhead Plate(pre installed)

StandardSwagelockBulkheadConnectorsPP2 side pre installed

Routing offto PPF1

Routingfrom SCT

Filters

Type 2Type 1

Inlet Tubes

Page 10: November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)

CCLRC 10November 04Jason Tarrant

SCT EC PPF1

Outstanding» Routing of tube from PPF1 – PP2 to be adjusted (could

be done upon assembly» Parts to be supplied to CERN by Feb 05 / June 05