NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST LOGISTIČKIH CENTARA 2.10.2019. POSLOVNI FORUM HGK ŽK RIJEKA PERSPEKTIVE JUŽNIH VRATA EUROPE www.portauthority.hr 1

Upload: others

Post on 23-Jan-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

NOVI INVESTICIJSKI CIKLUSVeliki infrastrukturni projekti

• PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST LOGISTIČKIH CENTARA

2.10.2019.

POSLOVNI FORUM HGK ŽK RIJEKAPERSPEKTIVE JUŽNIH VRATA EUROPE

www.portauthority.hr 1

Page 2: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 2

Uvod

RIJEKA SUŠAK BAKAR

OMIŠALJ RAŠA

LUČ

KA

PO

DR

JA

BAZENI

• LUR je osnovana 1996. radi obavljanja poslova upravljanja, planiranja i strateškog razvoja riječke luke

• Riječka luka višenamjensko je lučko područjerasprostranjeno na 5 bazena gdje se obavlja rukovanje s različitim vrstama tereta

• Lučke operacije provode se od strane različitih nositeljakoncesijskih ugovora

• Ukupno 53 koncesionara i 81 (zaključenih) ugovora o koncesiji

• Međunarodni koncesionari u glavnim lučkim aktivnostima

• Upravljanje i razvoj lučkog područja

• Kontrola dolaska i odlaska brodova (VTS Rijeka – sektor manevriranja)

Page 3: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 3

CEF

• CEF (Connecting European Facility) je financijski instrument za razdoblje od 2014. do 2020. godine osnovan za dodatna ulaganja u infrastrukturne prioritete Europske unije u području prometa, energetike i digitalne tehnologije.

• Ukupna vrijednost razvojnih projekata Lučke uprave Rijeka koji se sufinanciraju iz Instrumenta za povezivanje Europe (CEF) iznosi 132,8 mil. EUR-a.

• Projekti se odnose na modernizaciju željezničke infrastrukture i izgradnju novih intermodalnih kapaciteta u luci Rijeka, rekonstrukciju pristaništa za generalne terete i implementaciju informatičkog sustava lučke zajednice Port Community system.

• Svi projekti će biti realizirani 2020. odnosno 2021. godine.

Page 4: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 4

POPIS PROJEKATA LUČKE UPRAVE RIJEKA SUFINANCIRANIH PROGRAMOM CEF-a:

1. Razvoj multimodalne platforme u luci Rijeka i povezivanje s kontejnerskim terminalom Jadranska vrata (POR2CORE-AGCT)

2. Unaprjeđenje infrastrukture luke Rijeka – Zagreb Deep Sea Container Terminal

3. Unaprjeđenje infrastrukture luke Rijeka – bazen Rijeka (POR2CORE-Rijeka Basin)

4. Unaprjeđenje infrastrukture luke Rijeka – terminal za generalne terete – Bazen Raša (POR2CORE-GCT)

5. Unaprjeđenje infrastrukture luke Rijeka – terminal za rasute terete Bakar (POR2CORE-BCTB)

6. Unaprjeđenje infrastrukture luke Rijeka – informatički sustav lučke zajednice (POR2CORE-PCS)

7. Unaprjeđenje infrastrukture luke Rijeka – produbljenje južnog veza na AGCT (POR2CORE-AGCT dredging)

Page 5: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 5

Transport corridor:MediterraneanTransport mode: MaritimeCall Year:2015Member state:CroatiaImplementation schedule:July 2015 to December 2020Estimated total cost:€35.556,000Maximum EU contribution:€30.222,600Co-financing:85%CoordinatorPort of Rijeka AuthorityPartnersPort of Rijeka Authority & HŽ InfrastrukturaStatus:Ongoing

OPIS PROJEKTA

• Rekonstrukcija željezničkog kolodvora

• Nadogradnja željezničke infrastrukture

• Nadogradnja željezničke infrastrukture za povećanje ukrcajno/iskrcajnih kapaciteta luke Rijeka u otpremi kontejnera željeznicom

Port of Rijeka multimodal platform developmentand interconnection to Adriatic Gate Container Terminal (POR2CORE-AGCT)

Page 6: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 6

Upgrade of the Rijeka Port infrastructureZagreb Deep Sea Container TerminalPOR2CORE-ZCT

Transport corridor:MediterraneanTransport mode: MaritimeCall Year:2016Member state:CroatiaImplementation schedule:October 2016 to December 2020Estimated total cost:€31.587,125 Maximum EU contribution:€26.849,056Co-financing:85%Coordinator:Port of Rijeka AuthorityPartnersPort of Rijeka Authority & HŽ InfrastrukturaStatus:Ongoing

OPIS PROJEKTA

• Rekonstrukcija teretnog dijela željezničkog kolodvora Rijeka i produljenje 12 kolosijeka i izvlačnjaka

• Izrada priključka kolosiječnih postrojenja i izgradnja kabelske kanalizacije

• Izgradnja četiri kolosijeka duljine 400 m na novom dijelu kontejnerskog terminala na Zagrebačkom pristaništu te dva kolosijeka za portalne dizalice

Page 7: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 7

Upgrade of the Rijeka Port infrastructure - Rijeka Basin (POR2CORE-RijekaBasin)

Transport corridor:MediterraneanTransport mode: MaritimeCall Year:2017Member state:CroatiaImplementation schedule:October 2017 to December 2020Estimated total cost:€33.614.466Maximum EU contribution:€28.614,466Co-financing:85% CoordinatorPort of Rijeka AuthorityStatus:Ongoing

OPIS PROJEKTA

• Rekonstrukcija postojećih kolničkih i skladišnih površina, kolosijeka, staza dizalica i prateće komunalne infrastrukture

• Partneri u projektu: Lučka uprava Rijeka i Luka Rijeka d.d.

Page 8: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 8

Upgrade of the Rijeka Port infrastructure - General cargo terminal – Raša Basin(POR2CORE-GCT)

Transport corridor:MediterraneanTransport mode: MaritimeCall Year:2016Member state:CroatiaImplementation schedule:January 2017 to December 2020Estimated total cost:€6.914,000Maximum EU contribution:€3.132,042Co-financing:45,3% CoordinatorPort of Rijeka AuthorityStatus:Ongoing

OPIS PROJEKTA

• Rekonstrukcija južnog dijela obale u dužini cca 90m i rekonstrukcija drugog dijela obale na sjevernom dijelu od 74m

• Pozitivan učinak na sigurnost i kvalitetu usluge te povećanje kapaciteta u prekrcaju generalnog tereta

Page 9: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 9

Upgrade of the Rijeka Port infrastructure – Bakar bulk cargo terminal (POR2CORE-BCTB)

Transport corridor:MediterraneanTransport mode: MaritimeCall Year:2017Member state:CroatiaImplementation schedule:October 2017 to December 2019Estimated total cost:€6.094,664Maximum EU contribution:€5.180,464Co-financing:85% CoordinatorPort of Rijeka AuthorityStatus:Ongoing

OPIS PROJEKTA

• Rekonstrukcija kolosijeka, prometnih i skladišnih površina i prateće komunalne infrastrukture na području terminala za rasute terete Podbok –bazen Bakar

• Poboljšanje povezanosti cjelokupnog bazena Rijeka sa željezničkom mrežom u zaleđu te posredno prema europskim koridorima uklanjanjem postojeće dotrajale i operativno neprikladne željezničke infrastrukture

Page 10: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 10

Upgrade of the Rijeka Port infrastructure – Port Community System (POR2CORE-PCS)

Transport corridor:MediterraneanTransport mode: MaritimeCall Year:2017Member state:CroatiaImplementation schedule:December 2017 to December 2020Estimated total cost:€1.660,000Maximum EU contribution:€1.411,000Co-financing:85% CoordinatorPort of Rijeka AuthorityStatus:Ongoing

OPIS PROJEKTA

• Projektiranje i izgradnja jedinstvenog standardiziranog informatičkog sustava lučke zajednice koji je kompatibilan sustavu CIMIS (Hrvatski integrirani pomorski informacijski sustav).

• Implementacijom PCS-a poboljšava se efikasnost komunikacije između članova lučke zajednice, izbjegava se višestruki unos informacija, optimizira kolanje i pravovremeni prijem informacija te osiguravaju podaci od neovlaštenog dostupa.

Page 11: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 11

Upgrade of the Rijeka Port infrastructure - AGCT dredging (POR2CORE-AGCT dredging)

Transport corridor:MediterraneanTransport mode: Maritime Call Year:2018Member state:CroatiaImplementation schedule:October 2018 to June 2020Estimated total cost:€13,911,549Maximum EU contribution:€2,782,310Co-financing:20% Coordinator:Port of Rijeka AuthorityStatus:Ongoing

OPIS PROJEKTA

Sredstvima će se financirati prilagodba luke kako bi se povećali kapaciteti i mogućnost primanja većih plovila.

Glavni cilj projekta je uklanjanje uskog grla na kontejnerskom terminalu Jadranska vrata, a u svrhu poboljšanja učinkovitosti rukovanja teretom na terminalu te mogućnosti vezivanja većih brodova.

Page 12: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 12

ZAGREB DEEP SEA KONTEJNERSKI TERMINAL (ZDSCT)

Componenta RGP ZAGREB DEEP SEA KONTEJNERSKI TERMINAL –1. Faza

Opis komponente Izgradnja 400 m obale

Ukupna investicija 112,5 mil. €

Status komponente Završetak izgradnje 23.05.2019.

• Ukupna investicija: 186,8 mil. €

• Zajam Svjetske banke: 144,0 mil. €

• Državni proračun: 42,8 mil. €

Page 13: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 13

Faza 1 + 1A:Otvaranje: 2023Duljina obale: 400 metaraDubina: -20,0 metaraPovršina: 13,6 hektaraPrizemni smještaj: 1.968 TEU GSKapacitet: > 400.000 TEUIntermodalni prostor: 2,5 hektara

Faza 2:Otvaranje: Odgovornost investitoraDuljina obale: dodatnih 280+ metaraDubina: -20,0 metaraPovršina: dodatnih 3,7 hektaraPrizemni smještaj: dodatnih 504 TEU Kapacitet:> 400.000 - 600.000 TEU, ovisno o tehnologiji TO

Specifikacije terminala omogućuju rukovanje 500 000 TEU u fazi 1,

a 1.200 000 TEU u fazi 2, ovisno o tehnologiji Terminal operatera

Phase 1Phase 2

Phase 1A

RIJEKA GATEWAY PROJECTZAGREB DEEP SEA CONTAINER TERMINAL

Page 14: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 14

Rokovi

1Najava Poziva za podnošenje zahtjeva za sudjelovanje

03/2019

2Podnošenje zahtjeva za

sudjelovanje05/2019

3Evaluacija i ispunjavanje popisa

kratkih lista06/2019

4 Konkurentski dijalog 07-10/2019

5 Podnošenje ponude 11/2019

6 Pregovori / potpisivanje ugovora 01/2020

Koncesioniranje

RIJEKA GATEWAY PROJECTZAGREB DEEP SEA CONTAINER TERMINAL

Page 15: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 15

CONNECTING ROAD D-403Državna ceste D403 od čvora Škurinje do luke Rijeka

Vrijednost projekta 70 milijuna eura

Financiranje OPCC: 85%Državni proračun: 15%

Opis projekta Izgradnja izravne cestovne veze između ZDSCT i

autoceste

Status projekta Javna nabava za izvođača radova - u tijeku

Page 16: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 16

ILC Matulji

Pozadinski Off-Dock CT

ILC Matuljiudaljenost od ZDSCT = 18 km

• Ukupna površina 1,500.000 m2

• Cestovna i željeznička povezanost

• Planom utvrđeno 300.000 m2 za intermodalne aktivnosti

Page 17: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 17

ILC Matulji

Pozadinski Off-Dock CT

• Ukupna površina 160 ha

• Cestovna i željeznička povezanost

• Planom utvrđeno 30 ha za intermodalne aktivnosti

• Status Slobodne zone

• Izrađena studija “Pre-Feasibility Study and Conceptual Design for an Off-Dock Intermodal Facility”

• Studija financirana iz zajma Svjetske banke u okviru Rijeka Gateway Projekta

• Komponente studije: Analiza tržišta Koncepcija Off-Dock

terminala Financijska analiza

Page 18: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

www.portauthority.hr 18

ILC Matulji

Pozadinski Off-Dock CT

Faza 1: 2024 - 2027

Ukupna investicija Faza 1: 52,9 mil. EUR

Faza 2: 2028 - 2032Ukupna investicija Faza 2: 23,14 mil. EUR

Faza 3: 2033 - 2043Ukupna investicija Faza 2: 18,07 mil. EUR

ULAGANJA U INFRASTRUKTURU I OPREMU PO FAZAMA : 94,11 mil. EUR-a

Page 19: NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti · 2019-10-09 · NOVI INVESTICIJSKI CIKLUS Veliki infrastrukturni projekti • PANEL: PROMETNA INFRASTRUKTURA I POVEZANOST

Port of Rijeka AuthorityRiva 1, 51000 RijekaRepublic of Croatia

T +385 51 351 177Email: [email protected]. portauthority.hr