Centralized Range Procurement Project
Naval Special Warfare Command (NSWC)
9 SEP 2014
Presented by LTC Marshal Oller, US Army Operations Liaison to CDR, NSWC
Agenda
• NSWC Range Enterprise
• Problem Statement
• Current Range Supply Process
• Data Collection Plan
• Cost of Price Variation
• Voice of the Business
• Analysis of IMPACT Credit Card Transactions
• Future Range Supply Process
• Proposed End State
• Collaborative Way Ahead
2 Centralized Range Procurement
Project
NSWC Range Enterprise
Centralized Range Procurement Project
3
Problem Statement
4
Problem Statement Provide a multiyear centralized material acquisition contract that standardizes range enterprise procurement actions. The process to improve begins with a Range Manager identifying a material requirement and ends with delivery of the required item accompanied by the transactional data transmission. Improving this process will increase the Range Enterprise’s collective buying power, improve procurement responsiveness and reduce the Range Managers workload. Benefits to Business • Improved transactional visibility • Increased material consistency • Decreased workload on contracting officials • Reduced fraud, waste and abuse
Benefits to Customers • Automated ordering process • Reduced order cycle time • Simplified procurement process • Improved reporting and visibility
Centralized Range Procurement Project
SIPOC –Centralized Range Procurement Process (VOP)
• Home Depot
• Lowes
• Dixeland
• SAIC
• Grainger
• USN FISC
• GSA
• DOD Emall
• Range
Request
• Supply request
• Items
consumed in
training
• On hand
Supply Inventory
• Supply request
• Purchase
document
• Bill / Bill of
Lading
• Receipt
• Inventory list
• Monthly
statement
• Transaction
report
• Range
Manager
• Range Director
• NSWC N31 /
N3
• SEAL /
SWCCs teams
• Automated
process > 30
minutes
• Standard item
pricing and
delivery costs
• Transactional
visibility < 75%
• Reduced order
cycle time > 5
days
• Monthly
financial and
transactional
reports
Step 1: Range
Complex event
(Item expended)
Step 2:
Replenishment
stock depleted
(Requirement
identified)
Step 3: Shopping
list created,
validated
(procurement
method
determined)
Step 4: Orders <
$3K purchased
by KO; Orders >
$3K procured
using a supply
GPC
Step 5: Order
picked up /
shipped /
received and
inventoried at
supply hub
Step 6: Items
stored at
warehouse,
delivered to local
range complex or
transshipped to
another range
complex
Suppliers Inputs Process Outputs Customers Requirements
Data Collection Plan
Centralized Range Procurement Project
Performance Measure
Operational Definitions
Data Source How will the data be collected?
Who will collect data?
When will data be collected?
Sample size
How will data be used?
VOC Internal Customer Requirements
Range Directors input
Email / Verbal
Project Leader
Biweekly
100% Drive goals of project
VOB Internal Business Requirements
IMPACT CC reports, Transactional reports, Budget execution data
Automated reporting
Project Leader
Biweekly 100%
Drive goals of project
Procurement Efficiency
Reduction of price variability
IMPACT CC reports, Transactional reports, Budget execution data
Automated reporting
Team Member
Biweekly 100%
Assess procurement efficiency
Procurement Compliance
Reduction of IMPACT CC use
IMPACT CC reports, Transactional reports, Budget execution data
Automated reporting
Team Member
Biweekly 100%
Assess procurement compliance
Procurement Effectiveness
Evaluation of the BPA, the catalog list and vendor metrics
BPA, IMPACT CC reports, Transactional reports, Budget execution data, customer evals, COR evaluations
Email / Verbal, Automated reporting
Project Leader / Team Members
Quarterly 100% Assess procurement methodology and process variation
Centralized Range Procurement Project
7
Cost of Price Variation
Shopping Cart CATEGORY NOMENCLATURE AVERAGE LOW HIGH AVERAGE LOW HIGH Spread % of variation Cost of Price Variation
1 Wood Products 15/32 in plywood 318 60 576 16.46$ 12.82$ 20.10$ 7.28$ 44% 2,314.29$
2 Wood Products 23/32 in plywood 155.5 23 288 22.12$ 15.00$ 29.25$ 14.25$ 64% 2,215.57$
3 Wood Products 1x2x8 lumber 107.5 100 115 89.29$ 76.91$ 101.66$ 24.74$ 28% 2,659.94$
4 Wood Products 2x4x8 lumber 2075.5 1966 2185 2.76$ 2.21$ 3.31$ 1.10$ 40% 2,284.21$
5 Wood Products 2x4x16 220 120 320 66.41$ 5.16$ 127.66$ 122.50$ 184% 26,950.77$
6 Wood Products 2x4x92 ¼ 1101 1067 1135 2.64$ 1.92$ 3.35$ 1.44$ 54% 1,580.78$
7 Wood Products 2x6x8 lumber 2281.5 1537 3026 5.04$ 3.18$ 6.91$ 3.74$ 74% 8,521.92$
8 Wood Products 2x6x12 lumber 430.5 60 801 14.80$ 1.93$ 27.67$ 25.74$ 174% 11,080.50$
9 Wood Products 2x12x8 lumber 211.5 178 245 12.86$ 6.65$ 19.07$ 12.42$ 97% 2,626.20$
10 Doors 32" X 80" 1-3/8" SLAB 185 70 300 27.87$ 21.45$ 34.28$ 12.83$ 46% 2,373.55$
11 TARGETS 25 Meter Zeroing Target M4 Carbine 1325 1090 1560 0.79$ (0.10)$ 1.67$ 1.77$ 225% 2,340.60$
12 TARGETS 25m Zero Target MK17 Mod 0 SCAR-H SCAR-H (M80)5780 5520 6040 0.25$ 0.07$ 0.42$ 0.35$ 143% 2,038.76$
13 TARGETS operator standards 42840 33360 52320 0.32$ 0.21$ 0.43$ 0.22$ 69% 9,325.95$
15 TARGETS Trans II targets 32040 24120 39960 0.30$ 0.14$ 0.45$ 0.31$ 103% 9,801.13$
16 DOOR KNOBS Door knob 450 40 860 5.79$ 3.92$ 7.65$ 3.73$ 64% 1,678.39$
17 Locks privacy lock 397.5 350 445 7.97$ 5.86$ 10.07$ 4.21$ 53% 1,671.76$
18 MISC Batteries12 Volt, PS-121000U 200 200 200 154.00$ 118.00$ 190.00$ 72.00$ 47% 14,400.00$
19 MISC Filters20 X 25 X 1 750 500 1000 10.50$ 3.00$ 18.00$ 15.00$ 143% 11,250.00$
20 MISC HEPA FilterLRG 34 4 64 154.50$ 112.00$ 197.00$ 85.00$ 55% 2,890.00$
118,004.32$
$13 spread across the range enterprise for (1) door $33 $46
Voice of the Business
Centralized Range Procurement Project
• Improve procurement efficiency • Reduce price variation • Decrease staff work load • Ensure regulatory compliance • Increase range operations effectiveness
Shopping cart range of $203.91
Location Store Distance Cart Price
JEBLC, VA Lowes 10.2 544.15$
JEBLC, VA Home Depot 6.8 577.37$
JEBLC, VA Servemart / GSA / UNICOR43.0 671.84$
JEBLC, VA Grainger 12.3 746.30$
LA Posta, CA Lowes 43.3 560.16$
LA Posta, CA Home Depot 27.5 594.94$
LA Posta, CA Servemart / GSA / UNICOR44.2 736.85$
LA Posta, CA Grainger 28.3 748.06$
Stennis, MS Lowes 21.2 545.27$
Stennis, MS Home Depot 9.3 579.02$
Stennis, MS Servemart / GSA / UNICOR41.2 676.19$
Stennis, MS Grainger 40.9 746.22$
PCP, HI Lowes 5.5 572.35$
PCP, HI Home Depot 3.6 607.12$
PCP, HI Servemart / GSA / UNICOR7.5 745.57$
Centralized Range Procurement Project
Centralized Range Procurement Project
10
Control Chart
11 Centralized Range Procurement Project
Before Project Item
OPS STD TGT
TRANS II TGT
Steel Door
Slab Door
After Process Change
Control Chart
12 Centralized Range Procurement Project
Before Project After Process Change Item
Door Knobs
Privacy Locks
1X2X8
2X6X8
Control Chart
13 Centralized Range Procurement Project
Before Project After Process Change Item
2X12X8
1X4X8
2X4X8
15X32
Centralized Range Procurement Project
NSWG1 FY14 Q1-Q3 IMPACT Credit Card Transactions
Centralized Range Procurement Project
NSWG2 FY14 Q1-Q3 IMPACT Credit Card Transactions
Centralized Range Procurement Project
NSWG3 FY14 Q1-Q3 IMPACT Credit Card Transactions
Centralized Range Procurement Project
NSWCEN FY14 Q1-Q3 IMPACT Credit Card Transactions
18 Centralized Range Procurement Project
FY14 Q1-Q3 IMPACT Credit Card Transactions Histograms
19
Voice of the Process (To Be)
Centralized Range Procurement Project
20 Centralized Range Procurement Project
Proposed Centralized Range Procurement Vehicle (End state)
Collaborative Way Ahead
21 Centralized Range Procurement Project
Proposed End State – a Centralized Range Supply contract that services US Army, US Army Reserve, US Army NGB and Naval
Special Warfare Command Ranges in CONUS + Alaska and Hawaii
• Does the US Army, US Army Reserve and US Army NGB have the same problem? • Who is the initiative owner?
• What is the project scope?
• When - project timeframe?
• Define • Measure • Analyze • Improve • Control
• Where do we start?
• Component (USA, USAR, NGB) • Geographically (CONUS, IMCOM Region, State) • Complexity (Large, Medium or Small SRP Locations)
• How do we proceed?
• Working group • Tiger team • MBB / BB LSS project
Centralized Range Procurement Project
Naval Special Warfare Command (NSWC)
9 SEP 2014
Presented by LTC Marshal Oller, US Army Operations Liaison to CDR, NSWC