ntu risky geobusiness ppn.ppt · spent on subsurface exploration f 19 ... 1. subsurface or latent...
TRANSCRIPT
1
GEOTECHNICAL PROJECT RISK and UNCERTAINTY
ngin
eerin
g R
isk
1
En Nanyang Technological University
P. P. Nelson, NJITMarch 22, 2012
Topics
• Defining Project Risk Relative to BaselinesBaselines
• Risk Registries• Managing Risk• Project Controls• Process and Execution Risks
Ove
rvie
w
2
• Process and Execution Risks• Risks and CM for Underground Projects• Probabilistic Approaches
2
What is a Project?
A Project is Temporary and Unique
roje
ct D
efin
ition
….it is planned, has a definite beginning and end and is
Scope
Quality
Triple Constraint
3
Pr
p , g gnon-repetitive
To be Successful a Project must have a Plan… Plan what you do … A goal without a plan is a wish
Setting Project Metrics
Scope – Defining What it is and How it is going to get done
Time – Defining When it will start and When it will end
Cost – Defining Who will do it using What and How muchit will cost
Metrics must be meaningful for the stakeholder/owners, the project, the engineers, and the contractor(s)Pr
ojec
t Met
rics
4
p j , g , ( )
Project Baselines … used to track metrics and assess progress during project execution
P
3
Schedule Baseline starts with the WBS ends with Timeline
Precedence Diagram
1.2.1 Excavate
1.2.4 Pour
Concrete
1.2.5 Remove Forms
1.2.6 Backfill
1.2.2 Build
Forms
1.1 1.2 1.3
1.2.3 Mix Concrete
S h d l
1.2.1 Excavate
MF JA M J OS DNJ A
1.2.2 Build the Forms
1 2 3 Mi C thedu
le B
asel
ine
WBS
5
Schedule 1.2.3 Mix Concrete
1.2.4 Pour Concrete
1.2.5 Remove Forms
1.2.6 Backfill
Sch
Cost Baseline…how much and when to spend…
Precedence Diagram Estimate
J MF JA M J A OS DN
BudgetMF JAM J OS DNJ A
Excavate
Schedule PourRemoveBackfill
Mix
Cos
t B
asel
ine
6
TIME
RES
OU
RC
ES
Baseline
C
4
Build
….a project has phases and a life cycle…oj
ect L
ife C
ycle
UR
CES EXECUTION
Design Close
7
Pr
TIME
RES
OU
PLANNING
CONTROLLING
CLOSINGINITIATION
Risk in the Baselines
Cost T h l
Project Risk – “An uncertain event or condition that, if it occurs, has an impact on at least one project objective”.
RiskRiskRiskRisk
Schedule
CostQuality
Performance
Scope of work
Resources
VendorsInterfaces
Technology
Sources of Risks
Politics
Public Support
8
Risks with positive impacts are referred to as “Opportunities”
Known Risk – Can be Analyzed and ManagedUnknown Risk – Cannot be managed proactively
5
Risk Management
IdentifyRisk
Analyse Probability and
Impact
ApplyAvoidance or
Reduction
DefineContingency
Plans
Monitor &Manage
9
Build a Risk Registry
• Try to identify all realistic risks that should be considered. Provide:
a description of the risko a description of the risk o the probability of the risk occurring o a description of the potential impact of the
risk o the likely cost to the project or organization if
that risk occurs what actions should be taken now and by
10
o what actions should be taken now and by whom
o what contingency plans should be formulated now so that the organization is ready to act if the risk occurs.
6
i. PRE-DESIGN PHASE
Project Phases
i. PRE DESIGN PHASEii. DESIGN PHASE iii. BID AND AWARD PHASEiv. CONSTRUCTION PHASEv. POST-CONSTRUCTION PHASE
11
Note: Expansions of Phase Risks are appended to the end of this presentation
ITA Example Risk Matrix
FrequencyConsequence
Disastrous Severe Serious Considerable Insignificant
Very likely Unacceptable Unacceptable Unacceptable Unwanted Unwanted
Likely Unacceptable Unacceptable Unwanted Unwanted Acceptable
Occasional Unacceptable Unwanted Unwanted Acceptable Acceptable
12
Unlikely Unwanted Unwanted Acceptable Acceptable Negligible
Very unlikely
Unwanted Acceptable Acceptable Negligible Negligible
Guidelines for Tunneling Risk Management, ITA (TUST) vol. 19, 2004, pp. 217-237 http://www.caee.utexas.edu/prof/tonon/Courses_files/Geotech%20seminar_files/David%20Hatem/Tust_Vol_19_3_217-237.pdf
7
Geotechnical Hazard Risk Assessment Example
Title Description Scale
Probable
Likely to occur during the construction of the tunnel, possibly on more than one occasion 3
Likelihood
Probable one occasion 3
OccasionalLikely to occur at least once during construction of the tunnel 2
RemoteUnlikely to occur during construction of the tunnel 1
Title Description ScaleCatastrophic Total loss of a section of tunnel 5
Major damage or delay to tunnel or major environmental impact affecting
Consequence
13
Criticalj p g
the project 4
Serious
Some damage or delay to tunnel or some environmental impact affecting the project 3
MarginalRoutine maintenance or repair to tunnel; minor hindrance 2
Negligible Of little consequence to project 1Ref.: Hencher, 2012, “Practical Engineering Geology”, Spon Press
Geotechnical Hazard Risk Assessment Example
Catastrophic Critical Serious Marginal Negligible
Probable 15 12 9 6 3
Occasional 10 8 6 4 2
Remote 5 4 3 2 1
Score
10 to 15Very high risk - not acceptable for tunnel construction. Need to apply mitigation measures to eliminate or reduce risks.High Risk - apply mitigation measures to eliminate or reduce risk Residual risk indicates need for adaptive management
14
Ref.: Hencher, 2012, “Practical Engineering Geology”, Spon Press
6 to 9
1 to 5
risk. Residual risk indicates need for adaptive management control and response plans to be well developed with well trained personnel, materials and plant readily available.Low risk - may be accepted if required mitigating measures are in place under active management control.
8
Safety and Risk
• Safety and the Cliento Controls procurement, finances, and required participationo Sets overall strategy for health and safety on project –
including partnering and shared responsibilities for managing health and safetyhealth and safety
• Safety and Designerso Determine tunnel diameter, alignment, shaft diameter, depth
and locationsWorking space must be adequateContaminated land to be avoidedAll openings and changes in section should be designed for safe execution
o Set standards for fire, air, communications, ventilation – early involvement of contractor(s) in safety choicesP f i l d l t h ld i l d f t d h lth
15
o Professional development should include safety and health issues
• Safety and Contractors – greatest influence on project safetyo Plan work, assess risk, implement controlo Workforce training – importance of competence of front-line
supervisors and of workers
Risks can be introduced and impacts magnified during contract execution – starting from “hasexecution starting from has everyone read the contract?”
Problems arise from:1) not knowing the contract2) not keeping records
16
2) not keeping records3) bureaucracy (unneeded
complexity, slow response)4) posturing and personalities
9
Outcome from Problems
o Owner, Designer, CM and contractor get a bad reputation.
o Contractor gets defensive ando Contractor gets defensive and aggressive in changes and claims.
o Contractor/owner experience high legal / claims consultant costs.
o Contractor’s documentation is often better thatn the owner’s and
17
often better thatn the owner s and prove owner/CM is responsible in the end.
o No winners except the attorneys.
Risk and Construction Management ofUnderground Projects
18
Underground Projects
10
Geotechnical Site Investigations for Underground Projects
USNCTT (US National Committee on Tunneling Technology) 1984Technology), 1984
• Evaluated 84 tunnel projects• Over 60% had significant claims related to
“unanticipated soil conditions”• Less than 1% of project cost had been
spent on subsurface explorationf
19
• Overall, claims averaged 30% of engineer’s cost estimate for the project
• Claims were settled for 12% of the project cost
Problems and Claims Reported for Tunnels(as % of tunnel projects)
Problems ClaimsRunning ground 27% 9%Flowing ground 5 4Flowing ground 5 4Squeezing ground 19 8Groundwater inflow 33 6Noxious fluid 6 4Methane gas 7 2Existing utilities 1 0Pressure binding of shield 4 4
20
Pressure binding of shield 4 4Mucking 5 3Surface subsidence 9 3Face instability (soil) 11 5Obstructions (e.g. boulders, old foundations) 12 11Steering problems 4 0
11
USNCTT Recommendations
• It is in the owners best interest to conduct and report a thorough site p ginvestigation
• Include a comprehensive data report in the contract documents
• Disclaimers for validity of data are ineffective
21
ineffective• Need to establish a procedure for
equitable risk sharing to minimize impacts
Contract Options for Underground Risks
• Client takes all risks. Contractor is paid the cost of completing project in full. No incentive for the contractor to resolve problems cost-effectively when they arise
Low Risk for Contractor
effectively when they arise.
Risk of Unexpected
• Compromise Alternatives:o Agreed upon reference
ground conditions at starto Clause allowing additional
paymento Partnering, allowing either
gain or loss to both parties if conditions are better or
22
• Contractor takes all risks. Contractor likely to be unable (or unwilling) to price the risks – and so can go badly wrong.
Unexpected Ground
Conditions
High Risk for contractor
conditions are better or worse than anticipated.
12
Traditional Disputes Resolution
• Litigationo Causes friction and ill-willo Causes friction and ill willo Diverts capitolo Jury or judge has limited construction
experienceo Conflicting expert witness testimony
complicates resolution
23
po Factual data gets obscured by time – no
strong culture of creating an as-built case history
Recent Concepts in Risk Sharing: “A three legged stool”
• Disputes Review Board (GDR)• Escrowed Bid Documents
24
• Geotechnical Baseline Report (GBR)
Geotechnical Baseline Reports for Construction, ASCE, 2007, Underground Technology Research Council, ASCE/SME, Randy Essex (1997 version titled “Geotechnical Baseline Reports for Underground Construction”)
13
Disputes Review Board (DRB)
• Use for significant public or private projects (tunnels, buildings, bridges, p j ( , g , g ,etc)
• Forum to foster cooperation• Prompt and equitable resolution• Dissuade frivolous disputes and
l i
25
claims• Non-binding but admissible in court• Does not eliminate other owner’s
resolution method(s)
DRB Mechanics
• Three member Board• One member selected by the owner,
and one by the contractor• Third member selected by the first
two• All members approved by the owner
and contractor
26
and contractor• Organized early in the contract• Meet regularly throughout the
contract
14
Projects Using DRBs
ALL PROJECTS WITH DRBs
1 000
1,200
1,400
1,600
-
200
400
600
800
1,000
1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004
CONTRACT VALUE OF ALL PROJECTS US $ Billion
27 (www.drb.org)
-10.020.030.040.050.060.070.080.090.0
100.0
1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004
Escrow Bid Documents
• Escrowing of Bid Documents is intended to create a spirit of cooperation in an atmosphere of h d dhonesty and candor
• Escrowed bid documents are used to assist in the negotiation of price adjustments and change orders and in the settlement of disputes and claims.
• Remains property of contractor
28
Remains property of contractor• Accessible jointly by owner and
contractor at request of either• Held by third party and not subject to
Freedom of Information Act inquiries
15
Geotechnical Baseline Report
• Accompanied by comprehensive Geotechnical Data Report (GDR)
• Established anticipated o baseline• Established anticipated or baseline geotechnical conditions for bid
• Provides a clear and concise baseline for assessing differing site conditions (DSC)
29
• Incorporated as part of the contract• No exculpatory language disclaiming
responsibility for accuracy or completeness
Differing Site Condition Clause (DSC)
• The contractor shall promptly, and before such conditions are disturbed give a writtensuch conditions are disturbed, give a written notice to the Contracting Officer of 1. subsurface or latent physical conditions at the
site which differ materially from those indicated in the contract
2. unknown physical conditions at the site, of an l t hi h diff t i ll f
30
unusual nature, which differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract.
16
Differing Site Condition Clause (DSC)
• The Contracting Officer shall investigate the site conditionsinvestigate the site conditions promptly after receiving the notice. o If the conditions do materially so differ
and cause an increase or decrease in the contractor’s cost of, or time required for, performing any part of the work under
31
performing any part of the work under this contract, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.
Geotech Baseline issues
• Estimated amounts and distribution of different materials along alignmento High or low top of bedrocko Mixed-face conditions
• Different properties for intact materials• Properties of the ground mass behavior
o Potential for faults and shear zoneso Extent of material weathering
• Groundwater conditions expected• Construction impacts on adjacent facilities• Other geotechnical and man made sources of
32
• Other geotechnical and man-made sources of potential difficultieso Gaso Contaminated ground or groundwatero Obstructions
17
Contractual Assumptions
• Indicate the expected range of conditions, uncertainty, and baseline
iassumptiono May be maximum, minimum, average, or
typical valueo Note: if too conservative, may result in
an increased bid priceIf ti t i f 100 t 300 b ld b t th
33
If estimate is for 100 to 300 boulders but the baseline were set at 300, the owner would pay for 300 even if only 5 were encountered
• Baseline is not a warranty of conditions but is a basis for assessment of a DSC
Content of a GBR
• Project description• Sources of information• Project geologic setting• Ground characterization
o Soil and rock units and their physical characteristics
o Tables summarizing expected values of ti f b li
34
properties for baselineo Hydraulic properties and baseline inflow
volumeso Properties relevant to TBM performance
18
Content of a GBR (cont’d.)
• Design considerationso Ground classificationo Criteria for selection of primary ground supporto Criteria for design of final liningo Environmental limitations such as dewatering,
settlemento Need for ground performance instrumentation
• Construction considerationso Anticipated ground behavior, and sources of
delays
35
delayso Construction sequencing requirementso Specific anticipated construction difficulties or
risksMethods of managingInclude groundwater, ground control
When to do Risk Analysis for a GBRIf there is little uncertainty and the consequences of being wrong are minor, risk analysis is not necessary. On the other hand, if there is much uncertainty and/or the consequences of being wrong are high, it is essential to perform an extensive risk analysis.
36
19
Hazard Aspect Mitigation/Actions
Access/egress To site and work areas Safe routes and methods
Biological health hazards Burial sites, etc. Site investigation
Confined spaces
Asphyxiation, explosion, flooding, heat, humidity
Minimize need for working in confined spaces in design
Example Risk Register from the Channel Tunnel Project
Confined spaces ya) existing confined spaces b) confined spaces to be constructed
gReduce need to enter confined spaces Safe working practices
Contaminated land Contaminated ground, ground gas
Site investigation to identify Avoid disturbance Ventilation and monitoring Appropriate disposal
Demolition and site clearance To existing or new structures
Survey structures and condition Consider stability Plan and phase work to minimize disturbance Fencing and security Design to ensure practical and safe sequence Communication Site investigation
37
Earthworks Ground movements
Site investigationMinimize earthworks Consider effect on existing structures Adequate information to contractor
Excavation
Collapse or falls associated with ground movements Areas prone to flooding (e.g., cavernous limestone, old mine workings) Contaminated ground, ground gas, old mine workings
Geotechnical investigation to identify design constraints Minimize deep excavation Consider existing structures Adequate information to contractor Liaise with authorities re flooding Safety plan
Program Risk Assessment for Excavation by Drill and Blast (Young Dong Mountain Loop Tunnel, S. Korea, Halcrow)
No. Hazard Risk Mitigation Measures
L C R L C R
1Highly jointed rock mass (possibly in association with high-water pressure)
Ravelling ground, roof falls and sidewall or face instability with high amount of primary support
3 4 12
Reduce length of excavation/advance; face support and/or buttressing; partial face advance; reduce powder factor to lessen blast damage; increase rock support and install rock bolts and steel fiber reinforced shotcrete without delay; use probing and pre i
2 2 4
Risk Level Residual Risk Level
probing and pre-i
2 Fault ZonesSoft ground or mixed face conditions with potential roof falls and sidewall instability requiring high level of primary support
3 4 12
Reduce length of excavation/advance; face support and/or buttressing; partial face advance; reduce powder factor; increase rock support and install bolts, shotcrete, lattice girders and spiling without delay; probe hole drilling; use seismic methods to id
3 2 6
3Water ingress, possibly under high pressure up to 40 bar (4 MPa)
Water in cavities, joints and fissures in the rock mass entering excavation and causing instability of ground. Difficulties with shotcrete application
3 4 12
Drive tunnel upgrade for water to drain; provide poumpos to handle high flows and backup systems to deal with pumps and power failure; probe drilling to identify areas of high water flows and to carry out pre-injection grouting to styem the flow; excavati
2 2 4
4
Cavities in the rock mass (including mine works) possibly associated with water inflow
Instability of tunnel face, roof fall, and side wall instabiklity; flooding; need for major structural work or infilling
3 4 12
Use seismic methods to identify cavitied; probe hole drillingh to determine extent of cavities and provide access for grouting or other advance stabilization measures; reduce length of excavation advance.
2 3 6
38
5
Tunnel atmosphere and ventilation including accumulation of explosive and noxious gases
Explosion risk, possible accumulation of explosive and/or noxious gas; potential for asphyxiation. (Gases of concern include methane, carbon dioxide, carbon monoxide, sulfur dioxide, and hydrogen sulfide).
3 5 15
Provide adequate freshair to the face; provide atmospheric monitoring system; explosion-proof equipment; automatic stop control linked to instrumentation; standby generators to power fans; use appropriate explosives designed for tunnels with fire risk; av
1 4 4
6 Mechanical breakdown Failure of key equipment 3 3 9 Planned maintenance strategy; instrument and inspect to monitor condition; maintain spare parts.
3 1 3
7 Use of explosivesPremature detonation or uncontrolled explosion 2 5 10
Employ only qualified staff; comply with safety regulationsl use proper storage and transport facilities; use non-electric detonators; site security.
1 5 5
20
Initial Risk
Zoning Building
Flood Risk Management: Buying Down Risk
CodesOutreach
Evacuation Plan
Levee
Risk
ResidualRisk
Insurance
39
Everyone is a risk manager.All stakeholders can contribute to reducing risk!
Risk Reduction Tools (Cumulative)
Quantitative Risk Assessment
• Safety Assessment• Scenario Planning• Scenario Analysis
o Deterministic Scenario Analysiso Probabilistic Scenario Analysis
• Sensitivity Analysis• U t i t A l i
40
• Uncertainty Analysis• Modeling• Vulnerability Assessment
21
Principles
•What is probabilistic risk analysis (PRA)?o Structured approach to identifying failure modes and analyzing their effects
o Accounting scheme for combining uncertainties
o Approach to reasoning about uncertainties i th th f b bilit
41
using the math of probability.
•What it is not …o Inherently different from traditional practice
Principles
•Levels of probabilistic reasoning
TheoreticalAssessment
Model-basedAssessment
odel
Com
plet
enes
s
Ideal: theoreticalunderstandingwith many data
Purely theoretical, with few or no data
42
StatisticalAssessmentGuess
Data Completeness
Mo
Little understanding,but many data
Little understanding, few or no data
22
HazardHazard
InventoryInventory
VulnerabilityVulnerability LossLoss
Risk models
InventoryInventory
Some of the hazards (perils) modeled:EarthquakesFloodsHurricanesFire wildfire conflagration
43
Fire, wildfire, conflagrationTornadosTsunamisLandslidesOther extreme weather
Approaches to inventory modeling
• Geospatial databases (GIS)p ( )• Biggest advance in recent years; changing
quickly• Mostly publicly available records
o Impacted by DHS concerns• Many web-based (free or cheap) tools
44
HazardHazard
InventoryInventory
VulnerabilityVulnerability LossLoss
23
Approaches to vulnerability (reliability) modeling
• Failure modes and effects analysis (FMEA)• Event tree analysis• Fault tree analysis• Stochastic simulation (Monte Carlo)
HazardHazard
V l bilitV l bilit LL
45
InventoryInventory
VulnerabilityVulnerability LossLoss
You may be familiar with such an approach through HAZUS from FEMA for Earthquake Loss Estimation
46
24
The effect of level of information on cost uncertainty
CostCost
Cost
47
When does it pay to acquire additional information?
The Effect of Mitigation on Project Cost (adapted from Parsons et al 2004)
48
25
Data-Driven Tunnel Performance Simulation Approach
49
Data Base Levels Created
50
26
Data Base Project Parameters
51
TBM Performance Parameters
• AR = TBM Advance Rate = Machine advance per unit shift timeadvance per unit shift time
• PR = Penetration Rate = Machine advance per unit of time in operation(may also be expressed as advance per cutterhead revolution)
• U = Utilization = % of shift time that a
52
machine is actually in mining operation
AR = PR * Utilization
27
Advance Rate Project Analysis
53
Weekly Advance Rate for a TBM Drive in Granodiorite
PDFs for TBM Performance Parameters
Probability Density Function
54
Data Histograms and Probability Density Functions can be established for Advance rate, Penetration Rate and Utilization for Case History Projects – these can be sampled from in scenario
building and Monte Carlo simulation
28
Extreme Geotechnical Events
A Di t B t M j
55
Average Distance Between Major Geotechnically-Driven Stoppages in
TBM Mining, km/event
Other Approaches to TBM Performance Prediction
56
“Fuzzy Modeling Approaches for the Prediction of Machine Utilization in Hard Rock Tunnel Boring Machines,” Simoes and Kim, 2006, IEEE Industry Applications Conference, pp. 947 – 955.
29
Simulations of Tunnel Mining Using Sampled Data
57
Schematic Overlay Showing Results of Multiple Excavation Simulations
TTCT = Time To Complete Tunnel
For Each Simulation, Cost Can be Evaluated
Cost to Complete Tunnel CTCT, $Million
58
30
Case Study
During the construction of the spectacular Oresund bridge and tunnel, which connects Sweden to D k i k l i h d th tDenmark, risk analysis showed that the project was unlikely to meet its planned opening date upon which its financial viability was calculated.
Mitigating actions and alternative scenarios were considered leading to significant changes in approach. After the mitigating actions were applied the
59
the mitigating actions were applied, the risk analysis showed high confidence that Oresund could be opened three months early - which it was. Early opening easily paid for the specialist risk management work.
http://www.epmbook.com/risk.htm
Selected References
• Guidelines for Tunnelling Risk Management, ITA (TUST) vol. 19, 2004, pp. 217-237http://www.caee.utexas.edu/prof/tonon/Courses_files/Geotech%20seminar_files/David%20Hatem/Tust_Vol_19_3_217-237.pdf
• Hencher, S. 2012, “Practical Engineering Geology,” Spon Press.g g gy• Geotechnical Baseline Reports for Construction, ASCE, 2007,
Underground Technology Research Council, ASCE/SME, Randy Essex (1997 version titled “Geotechnical Baseline Reports for Underground Construction”)
• Washington State DOT, 2010 (January), “Project Risk management: Guidance for WSDOT Projects”
• ITA Technical Papers (ITA/AITES) has a very strong working group process, and many countries have their own societies that are very strong and technically involved):http://www.ats.org.au/index.php?option=com docman&task=cat view&gid=23&mosmsg=You+ar
60
p g p p p _ _ g ge+trying+to+access+from+a+non-authorized+domain.+%28www.google.com%29
o Contractual Sharing of Risk: The International Perspectiveo Geotechnical Risk Assessment and Management for Maintenanceo Contractual Sharing of Risk in Underground Constructiono Guidelines for Tunnel Risk Managemento ITA Recommendations on the Sharing of Riskso Risk Assessment and Risk Sharing in Tunnelling
31
• Extra Slides
61
• Extra Slides
62
32
i – PRE-DESIGN PHASE
Project justification/valueo Technical feasibilityo Economical feasibility/valueo Political circumstances/pressureso Delay in various approvals
Scopeo Management of the scopeo Clarity of owner’s objectives
Effect of interaction witho Competing projectso Statutory/regulatory (local, state, federal)
constraintso Public acceptance
Funding/financialo Sources of fundingo Political climate and public support
(especially public projects)o Potential opportunities and timelinesso Bond market and rates
o Effect of interaction with constituents on the scope (e.g., scope creep)
o Complexity and size of the projecto Sole source equipment and
service providerso Opportunity for equipment
discounts (concurrent projects/clients)
o Design and performance criteriao Constructabilityo Omissions
63
o Exchange rateo Inflation rateo Cash flow uncertaintieso Authorization/appropriation risk (congress)o Underestimation of budget and durationo Overestimation of project benefitso Adequacy of marketplace supply (vendors,
subs, labor, etc.)
o Selection of preferred alternatives based on limited design information
ii - DESIGN PHASEDesign consultants
o Designer’s qualifications, availability, teamwork spirit
o Designer’s understanding of cost/schedule management
o Incomplete designo Errors and omissions
Cost estimate and scheduleo Soundness of engineer’s estimateo Omitted quantitieso Financial costs risk/opportunityo Escalation assumptions
Unde estimation of design effo t/costso Errors and omissionso Design QA/QCo Accountability for designo System integrationo Coordination between section designerso Liability insurance, e.g., errors/omissionso Quality of design (proven vs. unproven,
constructable, biddable [multiple bidders])o Delays in design deliverables
Project/siteo Design and performance criteria
o Underestimation of design effort/costso Completeness and reasonableness of
scheduleo Schedule consistency with project
scopeo Level of schedule detail/integrationo Inadequate contingencyo Inadequate force account budget
Right of way acquisitiono Right-of-way appraisal and acquisitiono Delay in property acquisition/ court
64
o Design and performance criteriao Complexityo Subsurface conditions/hazardous materialso Unreliable data and test results (geotech,
hazardous materials, env’t conditions)o Inaccurate or inadequate surveyso Design changeso Scope changeso Scope creepo Impacts from abutters
o Delay in property acquisition/ court injunction preventing property taking
Regulatory conditionso Licenses, permits, approvalso Environmental regulations and
requirementso ADA requirements for public facilitieso Delay in various approvals
33
iii – BID AND AWARD PHASE
Project deliveryo Turnkey, design-buildo Design-bid-buildo DBOMo Joint venture
Si l i
Contractoro Experience and performance
on similar projectso Character, capacity, capital,
continuity (criteria used byo Single primeo Multi-primeo Public-private partnershipso Guaranteed Max Price/Gen
Contractor (GMP/GC)o CM @ Risk
Contracto Fixed priceo Unit priceo Cost reimbursable (even in fixed
continuity (criteria used by surety)
o Safety recordo Need for bonds, bond limits,
surety’s reputationo Familiarity with the areao Cost, schedule, and document
control practiceso History regarding claims and
change orderso History of delivering on-time
and on-budget
65
o Cost reimbursable (even in fixed price contracts, parts can be cost reimbursable)
o Dated or stale contract documents
o Contract package size (too big and it may limit the number and type of bidders)
o Lowest responsible bid vs. low bid
and on budgeto Subcontractor qualifications
and capacityo Subcontractor roles and
responsibilitieso QA/QC program (contractor
and subcontractors)
iii – BID AND AWARD PHASE (cont’d)
Market conditionso Number of bidderso Availability of supplies and subso Unemployment rate in
construction trades
Owner/CM involvemento Clear definition of CM (Agency)
scope and authorityo Owners review/evaluation of bids
– adequate staff/consultant knowledgeconstruction trades
o Workload of regional contractors
o General economic climate that can affect bidding behavior
o Material and energy priceso Inflation rate, interest rate
Regulatory conditionso Environmental and ADA
requirements
knowledgeo Underestimation of the level of
effort (soft costs)o Supplying of materialo Testing, inspection, safetyo Start-up and providing clear
access to the siteo MOUs and coordination with local
agencies, companies, and community groups
o Communication channels/MISGuarantees
66
requirementso DBE requirements and (local)
workforce participationo Taxes and dutieso Limitations on the use of
overseas materials and equipment
o Guaranteeso Contractors’ bonds or letters of
credito Designer’s liability insuranceo Consequential damageso Liquidated damageso Performance/qualityo Cost/schedule
34
iv – CONSTRUCTION PHASEInsurance
o Coverage and requirementso Wrap-up insuranceo Owner purchased insurance program
Site
Work scheduleo Abutting contractorso Limited work hours, restrictions
on some construction activities such as blasting, truckingSite
o Accesso Congestiono Differing Site Conditions including but
not limited to:Soil and rock conditionsWater table and flow (underground work)Hazardous waste
o Archeological finds, siteso Endangered species and other
environmental concerns
o Maintenance of traffic, restrictions on traffic flow and access to site
o Disruption to public and businesses
o Coordination with utilities and other agencies
o Coordination with suppliers (long-lead orders)
o Subcontractors’ delay, contractor’s failure to effectively
67
o Environmental mitigation and remediation
o Noise mitigation: supplemental structures, schedule restrictions
o Securityo New security concerns leading to
shutdowns, etc.o Abutting structures and their
conditionso Unanticipated settlements
contractor s failure to effectively manage subs
o Weather effects on scheduleo Cash flow and contractor
paymentso Process to handle change orders
and change controls in an expeditious manner
iv – CONSTRUCTION PHASE (cont’d)
Means and methodso New, untried techniqueso Noise, dust, fumes, excessive
vibrationso Utility relocation
Labor: Most of the risks involving labor is transferred to contractor; however, owner or CM could benefit by being aware of these, as th f t d l ff t
o Utility relocationo Errors in the design of
temporary facilitieso Construction errorso Accidentso Material shortages and large
price increaseso Delays in mobilization
(equipment and manpower)o Failure of major equipmento Hardware/software problems
these factors can adversely affect project schedule. Also, on Force Account contracts, labor cost can be a major risk to the owner.
o Strikeso Accidentso Large wage fluctuationso Sabotage, thefto Substance abuseo Unions
M i l
68
o Hardware/software problems (control systems, integration, etc)
Acts of God/force majeure, including but not limited to
o Inclement weather, Earthquake, Flood, Fire, Terrorism
o Material wasteso Insuranceo Productivity (especially in Force
Account contracts this can directly affect the owner)
35
v – POST-CONSTRUCTION PHASE
o Individual systems and full integrated testingOwner trainingo Owner training
o Full commissioningo Occupancy permit (building projects)o Warranty issueso Complete close-out of all financing,
funding, and permitting agreements and conditions
o Changing rules over duration of operation
o OM projects – loss of incentives to maintain
69
maintain