NUCLEAR POWER CORPORATION OF INDIA LTD (A Government of India Enterprise) KUDANKULAM NUCLEAR POWER PROJECT Kudankulam PO, Radhapuram Taluk, Tirunelveli Dist Tamil Nadu – 627 106. Phone: 04637 – 282334, 282308, 282350 Telefax : 04637 – 259904 E-Mail: [email protected] TENDER SECTION Proforma –I Name of work : Main plant street lighting and area lighting at KKNPP site Tender No: NPCIL / KKNPP / E&I / 84 / 2009 S.No Subject Details 1. Name & Address of Company 2. Name of the contact person 3. E-Mail id 4. Phone No: 5. Fax No. 6. Mobile No The person / Company who downloaded the tender document should submit the Proforma by fax / E-mail to NPCIL-KKNPP before tender submission within 2 days of downloading. This is to us to send pre-bid meeting clarifications and other communications before submission of tender. Authorized Signatory with seal

Upload: vantram

Post on 31-Mar-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

NUCLEAR POWER CORPORATION OF INDIA LTD (A Government of India Enterprise) KUDANKULAM NUCLEAR POWER PROJECT

Kudankulam PO, Radhapuram Taluk, Tirunelveli Dist Tamil Nadu – 627 106. Phone: 04637 – 282334, 282308, 282350 Telefax : 04637 – 259904

E-Mail: [email protected] SECTION

Proforma –I

Name of work : Main plant street lighting and area lighting at KKNPP site

Tender No: NPCIL / KKNPP / E&I / 84 / 2009

S.No Subject Details

1. Name & Address of Company

2. Name of the contact person

3. E-Mail id

4. Phone No:

5. Fax No.

6. Mobile No

The person / Company who downloaded the tender document should submit the Proforma by fax / E-mail to NPCIL-KKNPP before tender submission within 2 days of downloading. This is to us to send pre-bid meeting clarifications and other communications before submission of tender.

Authorized Signatory with seal

KUDANKULAM NUCLEAR POWER PROJECT

Summary and checklist of enclosed documents (Bidders are requested to place this in cover no:1)

S. No

Bidder should fill in the following details (not write as enclosed) and furnish documentary proof as per Annexure-I of NIT and flagged for easy reference

1. Name of work Main plant street lighting and area lighting at KKNPP site

2. Tender No. NPCIL / KKNPP/ E&I / 84 / 2009 3. Estimated cost Rs.290.11 lakhs 4. Name of tenderer

5. Registration details:

PSUs/Government department/Large Industrial House

6. Cost of tender document Rs.1560/- (Furnish details DD incase downloaded from web)

7. EMD of Rs.100000/- (Furnish DD/BG/FD/TD details)

Solvency Certificate issued by Scheduled Bank in last six months.

Amount > Rs.116.04 lakhs Date of issue Banker’s Details

8

Average Annual Turnover in last three years (Should be at least Rs.232.08 lakhs) Year Turnover in lakhs Rs. Average annual turn over in

lakhs Rs. 2005-06

2006-07

9

2007-08

10 Furnish the details of successfully completed work/works of similar in nature, executed in

the last five years to satisfy the following. To assess the quantum & nature of work done, the work order, BOQ and completion certificate for the above work must be enclosed. Three similar completed works, each costing not less than Rs.116.04 lakhs.or Two similar completed works, each costing not less than Rs.145.05 lakhs or One similar completed work costing not less than the amount equal to Rs.232.08 lakhsName of the work-1: Work order Number-1 BOQ enclosed Yes / No

Date of issue: TDS during the same period Yes / No

Amount: All documents attested Yes / No

Completion Certificate-1 Name of completion certificate issuing authority

Date of issue: Designation

Amount: Contact number

Name of the work-2: Work order Number-2 BOQ enclosed Yes/No

Date of issue: TDS during the same period Yes/No

Amount: All documents attested Yes/No

Completion Certificate-2 Name of completion certificate issuing authority

Date of issue: Designation

Amount: Contact number

Name of the work-3: Work order Number-3 BOQ enclosed Yes / No

Date of issue: TDS during the same period Yes / No

Amount: All documents attested Yes / No

Completion Certificate-3 Name of completion certificate issuing authority

Date of issue: Designation

Amount: Contact number

11. Have you filled the rates in words & figures in schedule of quantities of the tender book?

Yes / No

12 Have you submitted all tender drawings & tender documents along with quote?

Yes / No

13. Have you filled & signed with seal the following:-

13.a Form of tender under section-II Yes / No

13.b Undertaking Section-III B Yes / No

13.c Tender form in Section IV Yes / No

13.d Section VIII Yes / No

14 Yes / No Is there a covering letter to the tender submission?

Yes / No 15 Any Deviation, If so has it been is brought out in the covering letter?

Yes / No 16 Are the documents submitted in 3 separate sealed covers as per clause No:19 of NIT?

Yes / No 17 Is the documents submitted in Cover-I flagged and kept in proper order?

Yes / No 18 Whether the tenderer has signed with seal in all the pages of the document?

Yes / No 19 a) Are you related to any official of NPCIL?

b) If yes Please indicate the Name, Designation & Office details of the same.

Signature of the Contractor with Seal

NUCLEAR POWER CORPORATION OF INDIA LIMITED (A Government of India Enterprise)

Kudankulam Nuclear Power Project

TENDER NO: NPCIL / KKNPP / E&I / 84 / 2009

Sub: “Main Plant Street Lighting and Area Lighting at KKNPP site”

SL NO.

SECTION CONTENTS PAGES

PART-1

1. SECTION -I Tender Notice & Annexure-1 1-25

2. SECTION -II Form of Tender and General Rules & Directions for the Guidance of Contractor. 1-5

3. SECTION -III Special Instructions. 1-7 &1-33 &1-1

4. SECTION -IV General Conditions of Contract 1-138

5. SECTION -V Technical Specifications 1-5

6. SECTION -VI Schedule of Drawings. 1-1

7. SECTION -VII Schedule of Supply of Materials. 1-1

PART-II

8. SECTION -VIII Schedule of Quantities / Financial Schedule 1-2 & 1-7

Tender Issued to M/s. ………………………………………………… By. …………………………………………………

SECTION I

TENDER NOTICE

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 1 of 25

NUCLEAR POWER CORPORATION OF INDIA LIMITED (A Government of India Enterprise)

Kudankulam Nuclear Power Project Kudankulam PO, Radhapuram Taluk, Tirunelveli Dist Tamil Nadu – 627 106.

Phone: 04637 – 282334, 282350, 282308 Telefax: 04637 – 259904 E-Mail: [email protected]

www.npcil.nic.in

NOTICE INVITING TENDER

TENDER NO: NPCIL / KKNPP/ E&I / 84 / 2009 1. Sealed Tenders are invited in two parts on behalf of the Nuclear Power Corporation

of India Ltd, Kudankulam Nuclear Power Project by Chief Construction Engineer from Contractors, who are eligible as per the minimum requirements defined in

clause 1 of the qualification criteria (Annexure 1) and who have executed works for

PSUs or Government department or with large industrial house (Work executed for

private body will be considered only if contractor / firm produces tax deduction at

source certificate) for “Main Plant Street Lighting and Area Lighting at KKNPP site”.

The work is estimated to cost as mentioned in para1, column (1). This estimate

however, is given merely as a rough guide.

Estimated cost

Earnest Money Deposit

Cost of Tender

Document

Period of Contract

Sale Period

Date of submission/ opening

Date of Pre-bid meeting

(1) (2) (3) (4) (5) (6) (7)

Rs.290.11 lakhs Rs.100000/-

Rs.1560/- (Rs. 1500 + 4% VAT)

12 Months

01.12.09

to 14.12.09 between 10:00 hrs and 16:00

hrs

By 13:00hrs

on 23.12.2009 and Part-1 opened on same day

at 14.30 hrs

14:00 hrs on

17.12.2009

2. Completion time as mentioned in para1, column (4) is including monsoon period.

3. The bid shall be submitted in the original bid document (as issued by the corporation

/ downloaded from the internet) superscribing the name of work in accordance with

clause 19 of Notice inviting tender (NIT).

4. Chief Construction Engineer of the Nuclear Power Corporation of India Ltd. shall

be the “Accepting Authority" hereinafter referred to as such for the purpose of this

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 2 of 25

Contract.

5. Bidding documents may be purchased from the office of ENGINEER-IN-CHARGE

(TENDER SECTION), D BLOCK, SECOND FLOOR, ROOM NO: 05, OFFICE COMPLEX, KKNPP between the period and time as mentioned in para1, column

(5) by paying a non-refundable fee as mentioned in para1, column (3) in the form of

pay order or Demand Draft on any Scheduled Commercial bank payable at SBI Anuvijay Township (Branch code: 4387) in favour of “NPCIL. Interested Bidders

may obtain further information at the same address. The bidding documents can

also be downloaded from the internet (Site address www.npcil.nic.in), where in the

purchase price of the documents shall be submitted along with the bid in the form of

pay order / demand draft.

6. Bids must be accompanied by bid-security / EMD amount specified for the work in

clause 18 of NIT, payable at SBI Anuvijay Township (Branch code: 4387) in

favour of “NPCIL. Bid Security/EMD will have to be in any one of the forms as

specified in the bidding documents and shall have to be valid for 30 days beyond

the validity of the bid.

7. Bids must be dropped in the box placed in the TENDER SECTION, D-BLOCK,

SECOND FLOOR, ROOM No: 05, OFFICE COMPLEX, KKNPP upto 13.00 hours

on the day as mentioned in Para 1 column (6). The bid (in case of two part tender,

part one) will be opened on the same day at Para 1, column (6), in the presence of

the Bidders who wish to attend. If the office happens to be closed on the date of

receipt of the bids as specified, the bids will be received and opened on the next

working day at the same time and venue.

8. Pre-bid Meeting- Date & Time:

A pre-bid meeting will be held on as per Para 1, column(7) at the office of ENGINEER-IN-CHARGE(TENDER SECTION), D BLOCK, SECOND FLOOR, OFFICE COMPLEX, KKNPP to clarify the issues and to answer questions on any

matter that may be raised at that stage as stated in Clause 15 of Notice Inviting

Tender.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 3 of 25

9. Scope of Bid: 9.1 The Nuclear Power Corporation of India Limited (referred to as Corporation or

NPCIL in these documents) invites bids for the work (as referred above). The

successful Bidder should complete the works on or before the scheduled period of

completion as specified in the NIT.

9.2 Scope of work : “Supply of galvanized street light poles, cables, light fittings,

erection of the poles, light fittings & cables. 10. Eligible Bidders: 10.1 Bidding is open to all eligible Bidders meeting the eligibility criteria as defined

in qualification criteria specified in Annexure I of this Notice Inviting Tender.

10.2 Bidders not meeting the minimum qualification criteria and also non submitting

documentary evidence in acceptable form as specified in Annexure I of this Notice

Inviting Tender. shall be summarily rejected.

11. One Bid per Bidder: 11.1 Each Bidder shall submit only one bid for one tender. A Bidder who submits or

participates in more than one Bid will cause the Bidder’s participation to be

disqualified for all the proposals.

12. Cost of Bidding: 12.1 The Bidder shall bear all costs associated with the preparation and submission of

his Bid, and the Corporation will in no case be responsible and liable for these costs.

13. Site visit: 13.1 The Bidder and any of his authorized personnel or agents will be granted permission

by the Corporation to enter upon its premises and lands for the purpose of site visit.

However the bidder shall express condition that he, his personnel, and agents will

be responsible against all liability in respect thereof, including death or personal

injury, loss of or damage to property, and any other loss, damage, costs, and

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 4 of 25

expenses incurred as a result of the inspection.

13.2 The Bidder should inform the Corporation at least 3 days in advance about the

proposed site visit.

13.3 The Bidder, at his own responsibility and risk is encouraged to visit, inspect and

survey the Site and its surroundings and satisfy himself before submitting his bid as

to the form and nature of the Site, the means of access to the Site, the

accommodation he may require, etc.,

13.4 In general, Bidders shall themselves obtain all necessary information as to risks,

contingencies and other circumstances which may influence or affect their bid. A

Bidder shall be deemed to have full knowledge of the Site, whether he inspects it or

not and no extra claims due to any misunderstanding or otherwise shall be allowed.

13.5 The costs of visiting the Site shall be at the Bidders’ own expense. Any report

shared at the site, by the Corporation is subject to verification by the contractor. Any

deviations of information in the report and the actual site will not be the responsibility

of the corporation.

14. Content of Bidding Documents: 14.1 Submission of a bid by a Bidder implies that he has read this notice and all other

contract documents and has made himself aware of the scope and specifications of

the work to be executed and of conditions and rates at which stores, tools and plant,

etc., will be issued to him by the Corporation and local conditions and other factors

having a bearing on the execution of the works.

14.2 The Bidder shall submit the Bid, which satisfies each and every condition laid down

in the bid documents, failing which, the bid is liable to be rejected. 14.3 This Notice Inviting Tender shall form part of the Contract document. 14.3 The documents listed below comprises one set of bid document,

Section – I Notice Inviting Tender

Section – II Form of Tender and General Rules & Directions for the Guidance of

Contractor.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 5 of 25

Section - III Special Instructions.

Section – IV - General Conditions of Contract

Section – V Technical Specifications / Data sheets

Section – VI Drawings

Section – VII Schedule of Supply of Materials.

Section – VIII Schedule of Quantities / Financial Schedule

15. Pre-bid meeting Details: 15.1 The Bidder or his officially authorized representative is invited to attend a pre-bid

meeting, which will take place as referred in clause 8 of NIT.

15.2 The purpose of the meeting is to clarify issues and to answer questions on

matters that may be raised at that stage.

15.3 The Bidder is requested to submit their questions / queries / clarifications in

writing or by email / fax to reach the Corporation before the meeting.

15.4 Minutes of the meeting, including the text of the questions raised (without identifying

the source of enquiry) and the responses given will be transmitted without delay to

all purchasers of the bidding documents. Any modification of the bidding

documents which may become necessary as a result of the pre- bid meeting shall

be made by the Corporation exclusively through the issue of an Addendum only

and not through the minutes of the pre-bid meeting.

16. Amendment of Bid Documents: 16.1 Before the deadline for submission of bids, the Corporation may modify the bidding

documents by issuing addenda.

16.2 Any addendum so issued shall be part of the bid documents as well as Contract

document and shall be communicated in writing or by email / fax to all the

purchasers of the bidding documents. Prospective Bidders shall acknowledge

receipt of each addendum by email / fax to the Corporation.

16.3 To give prospective Bidders reasonable time to take an addendum into account in

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 6 of 25

preparing their bids, the Corporation may extend the date for submission of bids, if

necessary.

17. Language of the Bid: 17.1 All documents relating to the bid shall be in the English language, unless stated

otherwise.

18. Bid Security or EMD: 18.1 The bid shall be accompanied by bid security/ EMD amount as mentioned in Para1,

column (2).The bid security amount / EMD may be paid in any one of the following

forms:

a) Deposit at call receipt of a Scheduled Commercial Bank, duly pledged in favour

of Manager(F&A), KKNPP.

b) Demand draft of any Scheduled Commercial Bank drawn in favour NPCIL

payable at State Bank of India at Anuvijay Township (Branch code: 4387).

c) Bank Guarantee from a Scheduled Commercial Bank irrevocable and operative

30 days after the validity of the offer (as per standard proforma attached).

d) Fixed Deposit Receipt issued by Scheduled Commercial Bank endorsed in

favour of NPCIL.

18.2 Bid Security/EMD of successful Bidder will be returned after submission of the

performance guarantee amount. Bid Security of unsuccessful Bidders will be

returned to them within 14 days from the date of acceptance of bid of the successful

Bidder.

18.3 The Bid Security may be forfeited, if

a) the Bidder withdraws / modify his Bid or any item thereof after opening of bid

b) the successful Bidder fails within the specified time limit to commence the work.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 7 of 25

19. Submission of Bid Documents: 19.1 The bid submitted by the Bidder shall comprise the following:

a) Documents in acceptable form in support of Minimum requirements as per

qualification criteria specified in Annexure 1 of this NIT.

b) The purchase price of the bid documents in case it is downloaded from

internet.

c) Bid Security / EMD

d) Tender document – Part-1

e) Priced Bill of Quantities –Part-II

Tenderer may please note, the tender submission should be in 3 separate sealed covers as

follows, indicating Tender No & cover No on each cover,:

A) Part I – Technical Bid

Cover No: 1 this cover should contain

a) Summary & Check list of enclosed documents

b) All relevant documents and certificates as per Annexure-I of NIT

arranged and flagged in the following order.

Company details & Registration

Solvency

Audited profit and loss statement for the last 3 years

Experience certificate compressing of work order, completion

certificate & TDS if applicable.

c) Purchase price of the bid documents in case it is downloaded from

internet.

d) Tender Document Part -1, section -1 to VII along with all drawings if

any.

Cover No: 2

• This cover should contain the Bid security / EMD in the acceptable

form as per clause 18 of NIT.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 8 of 25

B) Part II – Commercial Bid

Cover No:3

• This cover should contain the Part-II - priced bill of quantities dully filled

and signed.

All the envelopes should be sealed & superscribed with appropriate Envelope

number and heading as defined above.

20. Bid Prices, Rates & Taxes: 20.1 The Bidder should quote his rates in figures as well as in words. The total amount

shall be written both in figures and in words. The bid shall be liable for rejection if

not quoted in words.

20.2 In the case of item rate tenders, only rates quoted shall be considered. In case of

lumpsum tender, only lumpsum quoted amount shall be considered.

20.3 All duties & taxes and other levies payable by the contractor under the contract or

for any other cause, as applicable at the time of submission of the bid shall be

included in the rates, prices and total Bid Price submitted by the Bidder.

20.4 The rates and prices quoted by the Bidder are subject to adjustment during the

execution of the Contract in accordance with the provisions of sub-clause 11.2

[Payment for Variations] of the General Conditions of Contract.

21. Currencies of Bid and Payment: 21.1 The unit rates and the prices shall be quoted by the Bidder in Indian Rupees, unless

otherwise specified in the Special Conditions of Contract.

22. Bid Validity: 22.1 The bids submitted shall remain valid for acceptance for a period of 120 days from

the date of opening of the bid. The Bidder shall not be entitled during the said period

of validity, to revoke or cancel his bid or vary / modify the bid given or any item

thereof. In case of Bidder revoking or canceling his bid, varying any terms in regard

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 9 of 25

thereof, the full amount of bid security/EMD paid by the Bidder along with the bid

shall be forfeited by NPCIL.

23. Alternative Proposals by Bidders: 23.1 Bidders shall submit offers that comply with the requirements of the bidding

documents, including the basic technical design as indicated in the drawing and

specifications. Alternatives will not be considered.

24. Format and Signing of Bid: 24.1 The Bidder shall prepare the documents comprising the bid as described in Clause

19 of NIT. 24.2 The Bid shall be typed or written in indelible ink and shall be signed by a person or

persons duly authorised to sign on behalf of the Bidder. No over writing is allowed in

the bid documents. 24.3 The Bid shall contain no alterations or additions, except those to comply with

instructions issued by the Corporation, or as necessary to correct errors made by

the Bidder in which case such corrections shall be initialed by the person or persons

signing the bid.

24.4 All pages in the tender document shall be signed by the tenderers and returned

along with their offer for this work. 25. Sealing and Marking of Bids: 25.1 The bid shall be submitted in a sealed envelope containing bid documents as

specified in clause 19 of NIT, and superscribed by the following:

(a) be addressed to Corporation at the following address:

ENGINEER-IN-CHARGE(TENDER SECTION), ROOM NO:05, SECOND FLOOR, D BLOCK, KUDANKULAM NUCLEAR POWER PROJECT, KUDANKULAM-627106. RADHAPURAM TALUK, TIRUNELVELI DISTRICT.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 10 of 25

TAMIL NADU and

(b) bear the following identification: -

- Bid for as mentioned in para 1 [name of work]

- Tender No. as mentioned in front page of NIT

- DO NOT OPEN BEFORE as mentioned in para 1 column(6) [time and date

for bid opening]

-Name and address of the Bidder.

25.2 If the envelopes are not sealed and marked appropriately, the Corporation will

assume no responsibility for the misplacement or damage of the envelopes.

26. Deadline for Submission of the Bids:

26.1 Bids will be received by the Corporation at the address and time specified in NIT

(refer clause 7). In the event of the specified date for the submission of bids being

declared a holiday by the Corporation, the Bids will be received upto the specified

time on the next working day.

26.2 The Corporation may extend the deadline for submission of bids by issuing an

amendment, in which case, all rights and obligations of the Corporation and the

Bidders previously subject to the original deadline will then be subject to the new

deadline. The intimation for extended deadlines will be sent to Bidders preferably

one week prior to the original deadline.

26.3 Any Bid received by the Corporation after the deadline prescribed above will be

returned unopened to the Bidder.

26.4 In exceptional cases (where only one bid is received within the deadline), bids

received after the deadline, due to genuine delay, but before the time of opening of

the bid may be considered on approval from the competent authority. However the

right to approve and accept late bids solely rests with the authority / corporation

after ascertaining the delay.

27. Modification and Withdrawal of Bids: 27.1 Bidders may modify or withdraw their bids by giving notice in writing before the

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 11 of 25

deadline prescribed in Clause 26.1 and 26.2 above.

27.2 Each modification or withdrawal notice shall be prepared, sealed, marked, and

delivered in accordance with Clauses 24 & 25 of NIT, with the outer and inner

envelopes additionally marked “MODIFICATION” or “WITHDRAWAL” as

appropriate, by the respective Bidder. 27.3 No bid shall be modified after the deadline for submission of Bids. 27.4 Withdrawal or modification of a Bid between the deadline for submission of bids and

the expiry of the original period of bid validity as in Clause 22.1 of NIT above or as

extended pursuant to Clause 26.2 of NIT may result in the forfeiture of the Bid

security pursuant to Clause 18 of NIT.

28. Bid Opening:

PART-I

28.1 On the due date and appointed time as specified in clause 7 of NIT, the Corporation

will open cover 1 and 2 of all bids received, including modifications made pursuant

to clause 27 of NIT in presence of the Bidders or their authorized representatives

who choose to attend. In the event of the specified date for Bid opening being

declared a holiday by the Corporation, the Bids will be opened at the appointed time

and location on the next working day. 28.2 Envelopes marked “WITHDRAWAL” shall be opened and read out first. Bids for

which an acceptable notice of withdrawal has been submitted pursuant to Clause 27

of NIT shall not be opened. 28.3 If all Bidders have submitted unconditional Bids together with requisite Bid security,

then all Bidders will be so informed then and there. If any Bid does not contain Bid

security in the manner prescribed in the Bid documents, then that Bid will be

rejected and the Bidder informed accordingly. The sealed envelope containing

priced BOQ will be returned to him without opening. All other valid Bids shall be

considered for evaluation.

28.4 The Bidder’s name, Bid modifications and withdrawals, and such other details as the

Corporation may consider appropriate, will be announced by the Corporation at the

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 12 of 25

time of opening. 28.5 The Corporation shall prepare minutes of the Bid opening, including the information

disclosed to those present in accordance with Sub-clause 28.3 above. 28.6 PART-II: The date of opening of Part-II of Techno-Commercially qualified bidders shall be

intimated separately. The bid prices, any discount and such other details as the

Corporation may consider appropriate, will be announced by the Corporation at the

time of opening.

29. Clarification of Bids: 29.1 To assist in the examination and comparison of Bids, the Corporation may, at its

discretion, ask any Bidder for clarification of his Bid, including breakdown of unit

rates. The request for clarification and the response shall be in writing or by email /

fax, but no change in the price or substance of the Bid shall be sought, offered, or

permitted except as required to confirm the correction of arithmetic errors

discovered by the Corporation in the evaluation of the Bids in accordance with

Clause 32 of NIT.

29.2 Subject to sub-clause 32 of NIT, no Bidder shall contact the Corporation on any

matter relating to his bid from the time of the bid opening to the time the contract is

awarded.

29.3 Any effort by the Bidder to influence the Corporation’s bid evaluation, bid

comparison or contract award decisions, may result in the rejection of his bid.

30. Examination of Bids and Determination of Responsiveness: 30.1 Prior to detailed evaluation of Bids, the Corporation will determine whether each

Bid(s) meets (a) the minimum requirements as defined in clause 1 of Qualification

Criteria(Annexure 1); (b) has been properly signed by an authorised signatory

(accredited representative) holding Power of Attorney in his favour, which shall

interalia include a provision to bind the Bidder for settlement of dispute as per GCC;

(c) is accompanied by the required Bid security and; (d) is responsive to the

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 13 of 25

requirements of the Bidding documents.

30.2 A responsive Bid is one which conforms to all the terms, conditions and specification

of the Bidding documents, without material deviation or reservation. A material

deviation or reservation is one (a) which affects in any substantial change in scope,

quality or performance of the Works; (b) which limits in any substantial way, the

Corporation’s rights or the Bidder’s obligations under the Contract; or (c) whose

rectification would affect unfairly the competitive position of other Bidders presenting

responsive Bids.

30.3 Over-writing on rate(s) / total amount not clearly indicating single meaning may be a

cause of rejection of bid.

31. Correction of Errors: 31.1 Bids determined to be responsive will be checked by the Corporation for any

arithmetic errors. Errors will be corrected by the Corporation as follows:

(a) When there is a difference between the rates in figures and in words, the

rates which correspond to the amounts worked out by the Bidder, shall be

taken as correct

(b) When the amount of an item is not worked out by the Bidder or it does not

correspond with the rates written either in figures or in words, then the rate

quoted by the Bidder in words shall be taken as correct

(c) When the rate quoted by the Bidder in figures and in words tallies but the

amount is not worked out correctly, the rates quoted by the Bidder shall be

taken as correct and not the amount

[ In event no rate has been quoted for any item(s), leaving space both in

figure(s), word(s) and amount blank, it will be presumed that the Bidder has

included the cost of this/ these item(s) in other items and rate for such

item(s) will be considered as zero and work will be required to be executed

accordingly ]

(d) In the case of percentage rate tender, the Bidders are required to quote their

rates both in amount as well as in the percentage below/above the rates

entered in the schedule. In such cases in the event of arithmetical error

committed in working out the amount by the Bidder, the tendered percentage

and not the amount should be taken into account.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 14 of 25

31.2 The amount stated in the Bid will be adjusted by the Corporation in accordance with

the above procedure for the correction of errors and shall be considered as binding

upon the Bidder. If the Bidder does not accept the corrected amount the Bid will be

rejected, and the Bid security/EMD may be forfeited.

32. Evaluation and Comparison of Bids: 32.1 The Corporation reserves the right to accept or reject any offer.

32.2 In evaluating the Bids, the Corporation will determine for each Bid, the evaluated Bid

Price by adjusting the Bid Price by making any correction for errors pursuant to

clause 31 of NIT (Correction of errors).

32.3 The estimated effect of the price adjustment conditions under Variations and

Deviations of the Conditions of Contract, during the period of implementation of the

Contract, will not be taken into account in Bid evaluation.

32.4 If the Bid of the successful Bidder is seriously unbalanced in relation to the

Engineer-in-charge or his representative’s estimate of the cost of work to be

executed under the contract, the Corporation may require the Bidder to produce

detailed rate analyses for any or all items of the Bill of Quantities, to demonstrate

the internal consistency of those rates with the implementation/construction

methods and schedule proposed.

32.5 Any deviation in the commercial terms shall be suitably loaded before evaluation 33. Award Criteria: 33.1 The Corporation shall award the Contract to the Bidder whose evaluated offer / bid

has been determined to be the technically suitable and financially lowest and is

substantially responsive to the Bidding Document, provided further that the Bidder is

determined to be qualified to execute the Contract satisfactorily.

34. Notification of Award and Signing of Agreement: 34.1 The Bidder whose Bid has been accepted will be notified of the award by the

Corporation prior to expiration of the Bid validity period by issue of Work order. The

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 15 of 25

notification may also be made through letter, wherein the work order shall follow.

34.2 The work order will constitute the formation of the Contract subject only to the

furnishing of a performance guarantee within 30 days of work order.

34.3 An agreement shall be made and signed by both the parties. The Agreement will

incorporate all correspondence between the Corporation and the successful Bidder.

34.4 Upon furnishing by the successful Bidder of the Performance guarantee, the

Corporation will promptly notify the other Bidders that their Bids have been

unsuccessful and release their Bid security.

35. Corrupt or Fraudulent Practices: 35.1 the corporation requires that Bidders / Suppliers / Contractors under this contract,

observe the highest standard of ethics during the procurement and execution of this

contract. In pursuance of this policy, the corporation:

(a) defines, for the purpose of these provision, the terms set forth below as

follows:-

i. “Corrupt practice” means the offering, giving, receiving or soliciting of any

thing of value to influence the action of a public official in the

procurement process or in contract execution; and

ii. “fraudulent practice” means a misrepresentation of facts in order to

influence a procurement process or the execution of a contract to the

detriment of the Corporation, and includes collusive practice among

Bidders (prior to or after bid submission) designed to establish bid prices

at artificial non-competitive levels and to deprive the Corporation of the

benefits of free and open competition.

(b) Will reject a proposal for award of work if it determines that the Bidder

recommended for award has engaged in corrupt or fraudulent practices in

competing for the contract in question.

(c) Will declare a Bidder ineligible, either indefinitely or for a stated period of

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 16 of 25

time, to be awarded a contract/contracts if at any time it determines that the

Bidder has engaged in corrupt or fraudulent practices in competing for, or in

executing, the contract.

36. Disclosures: 36.1 Any change in the constitution of the contractor’s firm, where it is a partnership firm,

joint venture or consortium partnerships as declared in the bid should be disclosed

to the corporation, at any time between the submission of bids and the signing of the

contract. The same shall be disclosed during the currency as per the GCC clause

number 1.9(changes in constitution)

37 Concessions for Mega Power Projects: NOT APPLICABLE FOR THIS TENDER 38 Due to security reason entry of official visitors to project site, are allowed only on

prior written requisition from Authorized Officers. Therefore tenderers intending to

visit the site for purchase of document / attend pre-bid meeting / submit the tender,

should inform the tender section at least one day before by fax or E- mail, the name,

age, company name and identity card (issued by government only, like PAN card,

driving license , voters ID card, etc..) carried by their authorized person, to enable

us to make the entry requisition in advance. The approximate distance from main

gate to Office complex (as mentioned in clause No:5&7) is 2KM, there is no

departmental transport available. The contractor shall make their own transport

arrangement if necessary.

38.1. On all communications, the tender Number reference may please be given. 38.2. Bidders are requested to visit the NPCIL website periodically, for updates, new tenders etc. 39 Agencies who proposed to download the above tender document may please

intimate by E-mail or fax to us the name and address of the agency, name of the

contact person with phone no and mobile no and E-mail.

-sd-

Chief Construction Engineer For and on behalf of The Nuclear Power

Corporation of India Ltd.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 17 of 25

Annexure I – PRE-QUALIFICATION CRITERIA

1. MINIMUM REQUIREMENT 1.1 Average Annual financial turnover during the last 3 years, ending 31st March of

the previous financial year, should be at least 80% of the estimated cost AND

1.2 Experience of having successfully completed similar works during last 5 years

ending last day of month previous to the one in which applications are invited should

be either of the following:

a) Three similar completed works, each costing not less than the amount

equal to 40% of the estimated cost or

b) Two similar completed works, each costing not less the amount equal to

50% of the estimated cost or

c) One similar completed work costing not less than the amount equal to

80% of the estimated cost.

Similar work for the purpose of this contract shall mean:

Supply, Laying and Termination of power cables, Erection of Electric poles

etc.

1.3 Solvency of atleast 40% of Estimated Value issued by Bank in last six months.

1.4 The contractor should submit the documentary proof related to Minimum

Requirement as stated above in a separate envelop along with the bid.

2. GENERAL ELIGIBILITY CRITERIA 2.1 A Bidder may be a natural person, private entity, government-owned entity, or any

combination of such entities supported by a letter of intent to enter into an

agreement or under an existing agreement in the form of a joint venture of

Association (JVA) or Consortium. In the case of a joint venture or association or

consortium.

Unless otherwise specified, all partners shall be jointly and severally liable, and

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 18 of 25

the JVA or Consortium Agreement shall nominate a lead partner who shall have

authority to conduct all business for and on behalf of any and all the partners of

the JVA/Consortium is awarded the contract, during contract execution.

In such case, generally the Lead Partner shall take full responsibility of

successful completion / fulfillment of all the contract conditions.

In case of Consortium agreement the technical / financial capabilities of each of

the party shall be determined on case to case basis.

2.2 A Bidder shall not have conflict of interest. All Bidders found to have a conflict of

interest shall be disqualified. A Bidder may be considered to have a conflict of

interest with one or more parties in this bidding process, if :

a Bidder participated as a consultant in the preparation of the design or technical

specifications of the works that are the subject of the bid; or

a Bidder was affiliated with a firm or entity that has been hired (or is proposed to

be hired) by the Corporation or as Engineer-in-Charge for the contract.

2.3 Government-owned entities in the Corporation’s country shall be eligible only if they

can establish that they are legally and financially autonomous and operate under

commercial law. Also, they shall not be dependent agencies of the Corporation.

2.4 Bidders shall provide such evidence of their continued eligibility, satisfactory to the

Corporation, as the Corporation shall reasonably request any time within the

currency of the contract (including defect liability period).

2.5 Firms shall be excluded if:

as a matter of law or official regulation, the Corporation’s country prohibits

commercial relations with that county, provided that such exclusion does not

preclude effective competition for the supply of goods or related services

required; or

by an act of compliance with a decision of the United Nations Security Council

taken under Chapter VII of the Charter of the United Nations, the Borrower’s

country prohibits any import of goods or contracting of Works or services from

that country or any payments to persons or entities in that country.

2.6 The Bidder shall submit attested copies of original documents defining the

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 19 of 25

constitution or legal status, place of registration, and principal place of business;

written power of attorney of the signatory of the Bid to commit the Bidder; along with

the bid.

3. CONTRACT ELIGIBILITY CRITERIA

Further, the contract eligibility includes the following:-

3.1 Experience on similar completed works executed during the last five years; and

details like monetary value, clients, proof of satisfactory completion

3.2 Registration, if any, with specified departments (CPWD, State PWDs, MES,

Railways, PSUs etc.,) /organizations, class / type of registration or previous pre-

qualification(s) for similar projects.

3.3 Documentary evidence of adequate financial standing, Certified by Bankers, Audited

Profit & Loss A/c and Balance Sheet, Annual turnover in last five years access to

adequate working capital.

3.4 Construction Equipment proposed to be deployed for the project and proof of its

availability; equipment proposed to be purchased or leased.

3.5 Key personnel available and proposed to be engaged for management and

supervision of the Project, their qualifications and experience. Valid certificates by a

recognized University, technical Board, or Ministry of Government of India would

only be taken cognizance of.

3.6 Project planning and quality control procedures to be adopted.

3.7 Information regarding projects in hand, current litigation, orders regarding exclusion/

expulsion or black listing, if any.

3.8 Bidders who meet minimum criteria will be qualified only if their available bid

capacity is more than the bid value. The bid capacity of the contractor shall be

determined by the following formula

Bid Capacity = (A X N X 2) – B

Where

‘A’ = maximum value of works executed in any one year during last

five years

‘B’ = Value of existing commitments and on going works to be

completed in the next ‘N’ years

‘N’ = Number of years prescribed for completion of the subject

Contract

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 20 of 25

INFORMATION REGARDING QUALIFICATION OF BIDDERS The information to be filled in by the Bidder in the following pages will be used for purposes

of Pre-qualification as provided above.

1. For Individual Bidders (format for clause 2.6 of Annexure 1 – Prequalification

criteria)

1.1 Constitution or legal status of Bidder (Attach copy)

Place of registration : _________________________________________________

Principal place of business : ___________________________________________

(Power of attorney of signatory of Bid)

1.2 Value of work Completed during the last five years

(in Rs. Lacs)

Particular Year Value

Year 1

Year 2

Year 3

Year 4

Total value of Work

executed in the last five

years **

Year 5

** Immediately preceding the financial year in which bids are received. Attach

certificate from Chartered accountant.

1.2.1 Financial reports for the last five years: balance sheets, profit and loss statements,

auditors’ reports (in case of companies / corporation) etc., List them below and

attach copies. (Format for clause 3.3 of Annexure 1 – Prequalification criteria)

1.3.1 Work executed as prime contractor (in the same name) on works of a similar nature

* over the last five years. ** (format for clause 3.1 of Annexure 1 – Prequalification

Criteria)

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 21 of 25

Project Name

Name & Address of Client

Description of work

Contract No.

Value of work (Rs. Lakhs)

Date of issue of work order

Stipulated period of completion

Actual date of completion

Remarks explaining reason for delay

* Attach completion certificate (s) from the Engineer-in-charge or his

representative(s) in-charge.

1.3.2 Quantities of work executed as prime contractor (in the same name and style) in the

last five years. ** (format for clause 3.1 of Annexure 1 – Prequalification criteria)

Quantity of work performed Remarks Year

Description of item of work --------------- --------------- -------------- ---------------

Indicate contract Reference

Year 1

Year 2

Year 3

Year 4

Year 5

1.4 Information on Bid Capacity (works for which bids have been submitted and works

which are yet to be completed) as on the date of this bid calculated as per clause 3.8 of Annexure 1 – Prequalification criteria.

(A) Existing commitments and on-going works: (format for clause 3.7 of Annexure 1 –

Prequalification criteria)

Description of work

Place & State

Contract NO. & Date

Name and Address of Client

Value of Contact ( Rs. Lakhs)

Stipulated Period of completion

Value of work remaining to be completed (Rs. lakhs)

Anticipated date of completion

Remarks

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 22 of 25

(B) Works for which bids already submitted (format for clause 3.7 of Annexure 1-

Prequalification criteria)

Description of work

Place & State Name and Address of Client

Stipulated period of Completion

Date when decision is expected

Remarks if any

1.5 (a) The Bidders should list all essential equipments proposed to be deployed for

carrying out the works. (Format for clause 3.4 of Annexure 1 – Prequalification

criteria)

Item / Equipment

Requirement No. / Capacity

Owned / leased / to be procured

Nos. / Capacity

Age / Condition

Remarks ( From whom to be purchased)

* * * * *

* * * * *

1.5 (b) The Bidder shall provide adequate information to demonstrate clearly that the

Contractor has the capability to meet the requirements for the key equipments for

the key equipments. A separate Form (as defined below) shall be prepared for each

item of equipment listed by the Bidder.

Item / equipment

Name of manufacturer Model and power rating Equipment Information

Capacity Year of manufacture

Current status Current location

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 23 of 25

Details of current commitments

Source Indicate source of the equipment

Owned Rented Leased Specially manufactured

Omit the following information for equipment owned by the Bidder

Owner Name of owner

Address of owner

Telephone Contact name and title

Fax Telex

Agreements Details of rental / lease / manufacture agreements specific

to the project

1.6 Qualifications and experience of key personnel proposed to be deployed for

administration and execution of the Contract incl. QA and Industrial Safety

personnel. Attach biographical data.

Position Name Qualification Years of Experience (general)

Years of experience in the proposed position)

* * * *

* * * * *

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 24 of 25

1.6(a) Number of certified Trades persons to be employed at the site of project

1.7 Proposed sub-contracts and firms involved

Sections of the works

Value of sub-contract Sub-contractor (name and address)

Experience in similar work

* * * *

* * * *

* * * *

* * * *

1.8 Evidence of access to financial resources to meet the qualification requirements :

cash in hand, lines of credit, etc. List them below and attach copies of support

documents. (Format for clause 3.3 of Annexure 1 – Prequalification criteria)

1.9 Name, address and telephone, telex and fax numbers of the Bidders’ Bankers who

may provide references if contacted by the Corporation. (Format for clause 3.3 of

Annexure 1 – Prequalification criteria)

1.10 Information on litigation history in which the Bidder is involved. (format for clause

3.7 of Annexure 1 – Prequalification criteria)

Client & Address Cause of dispute Amount Remarks and the present status

1.11 Specify proposed sources of financing net of current commitments, available to

meet the total construction cash flow demands of the subject contract or contracts.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - I Notice Inviting Tender Page 25 of 25

No. Source of financing Amount (INR equivalent)

1.

2.

3.

4.

1.12 Proposed work method and schedule the Bidder should attach descritptions,

drawings and charts as necessary to comply with the requirements of the Bidding

documents. (Format for Clause 3.6 of Annexure 1 – Prequalification Criteria)

1.13 The contractor shall submit a declaration note stating that he has read and

understood the clauses in the NIT & General conditions of contract and the

information / evidence provided for Minimum requirements and the prequalification

criteria are true and fair.

SECTION II

FORM OF TENDER, GENERAL

RULES AND DIRECTIONS FOR

THE GUIDANCE OF

CONTRACTORS

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - II Form of Tender and General rules & Directions for the Guidance of Contractor Page 1 of 5

SECTION – II

NUCLEAR POWER CORPORATION OF INDIA LTD. (A Government of India Enterprise)

Kudankulam Nuclear Power Project.

ITEM RATE TENDER AND CONTRACT FOR WORKS

FORM OF TENDER AND GENERAL RULES AND DIRECTIONS FOR THE GUIDANCE OF CONTRACTOR

1. This form will state the amount of security deposit to be deposited by the successful

tenderer and the percentage, if any to be deducted from the bills. Copies of the

specifications, designs and drawings and any other documents required in

connection with the work signed for the purpose of identification by the Engineer

shall also be open for inspection by the contractor at the office of the “Engineer”

during office hours.

2. In the event of the tender being submitted by a firm, it must be signed separately by

each member thereof, or in the event of absence of any partner, it must be signed

on his behalf by a person holding a power of attorney authorizing him to do so, such

power of attorney to be produced with the tender, and it must disclose that the firm is

duly registered under the Indian Partnership Act.

3. Receipt of payments made on account of a work, when executed by a firm, must

also be signed by several partners except where the contractors are described in

their tender as a firm, in which case the receipts must be signed in the name of the

firm by one of the partners, or by some other person having authority to give

effectual receipt for the firm.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - II Form of Tender and General rules & Directions for the Guidance of Contractor Page 2 of 5

FORM OF TENDER

I/We hereby tender for the execution for Nuclear Power Corporation of India Ltd. of the

work specified in the under written Memorandum within the time specified in such

memorandum at the rate specified therein, and in accordance in all respects with the

specifications, designs, drawings and instructions in writing referred to in Rule 1 hereof and

in clause 12 of the General Conditions of Contract and with such materials as are provided

for, by and in all respects in accordance with, such conditions so for as possible.

MEMORANDUM

a) General Description :“ Main plant street lighting and area lighting at KKNPP site”. b) Estimated Cost : Rs.290.11 Lakhs c) Time of completion : 12 Months

d) Earnest money deposit / Bid security : Rs.100000/- e) Security deposit : 10% of the Contract Value

On award of the work, Earnest Money deposit/Bid security at the time of tender will be

treated as part of Security Deposit.

1. Total Security Deposit (SD) shall be calculated as under

(i) Contract value up to Rs.100 Crores - 10% of Contract Value.

(ii) Contract value more than Rs. 100 Crores - 5% of Contract Value subject

to a minimum of Rs 10 Crores.

Note: The contract value for the purpose of this clause shall be taken as the value of the

contract awarded.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - II Form of Tender and General rules & Directions for the Guidance of Contractor Page 3 of 5

i. Security Deposit as calculated based on above parameters shall be split in the

following of two parts and furnished accordingly:

a. Performance Guarantee to be submitted on award of work (50% of Security

Deposit), and

b. Retention money to be recovered from Running Bills (50% of Security Deposit).

ii. Performance Guarantee: The Contractor shall deliver the Performance Guarantee

to the Corporation within 30 days after issue of work order. The Performance

guarantee shall be issued by an entity and from within the country approved by the

Employer, and shall be in the form of Bank Guarantee or FDR or any other form of

deposit stipulated by the Corporation.

iii. Failure of the successful bidder to comply with furnishing the performance guarantee

within 30 days as stated above shall constitute sufficient grounds for cancellation of

the award of work.

iv. Retention Money: Retention Money shall be deducted at the rate of 6% of the value

of work done from Running Bills till the 50% of Security Deposit amount so

calculated as above, is built up. Total of Performance Guarantee & Retention Money

should not exceed the amount of security deposit calculated as above.

v. When the retention money reaches the limit of 5 lakhs, the Contractor, if he so

desires, may convert the amount into a Bank Guarantees as aforesaid.

vi. In case a Fixed Deposit Receipt of any bank is furnished by the Contractor to the

Corporation as part of the Security Deposit and the bank goes into liquidation or for

any other reasons is likely to be unable to make payment against the said Fixed

Deposit Receipt, the loss caused thereby shall be borne by the Contractor and the

Contractor shall forthwith or on demand furnish additional security to the Corporation

to make good the deficit.

vii. The Corporation may deduct any sum of money payable by the Contractor under the

terms of this Contract or any other Contract or any other account whatsoever from

his security deposit. In the event of his security deposit amount being reduced by

reasons of such deduction as aforesaid, the contractor shall within 10 days of receipt

of notice of demand from the Engineer-in-Charge make good the deficit.

viii. FDR / Bank Guarantee shall be accepted only from Scheduled commercial banks in

India.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - II Form of Tender and General rules & Directions for the Guidance of Contractor Page 4 of 5

ix. No interest will be paid on Security Deposit (Performance Guarantee and Retention

Money).

2. Refund of Security Deposit: 2.1 The retention money will be refunded to the Contractor after one month from the

date of issue of Completion Certificate on receipt of request from the contractor, if

as per the Engineer-In-Charge the balance amount of security deposit Performance

Guarantee) is sufficient to cover the Liabilities.

2.2 After the expiry of the Defects Liability Period, the balance amount of security

deposit i.e. the Performance Guarantee shall be refunded by the Engineer-in-

Charge to the Contractor. However, if any work remains to be executed under

Clause 9 [Defects Liability], the Engineer-in-Charge shall withhold the estimated

cost of such rectification work until it is executed.

SHOULD THIS TENDER BE ACCEPTED IN WHOLE OR IN PART, I/WE HEREBY AGREE:

RULE (i)

To abide by and fulfill all the terms and provision of the said conditions annexed

hereto and all the terms and provision contained in the notice inviting tenders so

far as applicable, and /or in default thereof to forfeit and pay to NUCLEAR

POWER CORPORATION OF INDIA LTD. the sum of money mentioned in the

said conditions..

A sum of Rs.100000/- is hereby forwarded by deposit at call receipt of

scheduled Bank, Guaranteed bond of a Scheduled Bank, or State Bank of India

Guaranteed by the Reserve Bank of India as Earnest Money. If I/We fail to

commence the work specified in the above memorandum, I/We agree that the

said Corporation shall without prejudice to any other right or remedy, be at

liberty to forfeit the said Earnest Money absolutely, otherwise the said earnest

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - II Form of Tender and General rules & Directions for the Guidance of Contractor Page 5 of 5

money shall be retained by the Corporation towards security deposit mentioned

against clause (e) of the above mentioned Memorandum.

(ii)

To execute all the works referred to in the tender documents upon the terms and

conditions contained or referred to therein and to carry out such deviations as

may be ordered, at the rate quoted in the tender document for respective items

of work so long as the entire total cost of the work executed by me/us under this

contract is within the limits of +25% and –25% of the contract amount entered

into the agreement and evaluated at the rates quoted in the tender document

and those in excess of that limit at the rates to be determined in accordance with

the provisions contained in Clauses of General Conditions of Contract.

Dated the …………………………… day of ……………………………………………… 2009

+ Witness …………………………….. *Signature…………………………

Address ………………………………

………………………………

………………………………

Occupation………………………………

The above tender is hereby accepted by me for and on behalf of the Nuclear Power Corporation of India Ltd.

Dated the …………………………… day of ………………………..……………… 2009

** ………………………………………

* Signature of contractor before submission of tender. + Signature of witness to contractor’s signature. ** Signature of the Officer by whom accepted.

SECTION III

SPECIAL INSTRUCTIONS

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - III Special Instructions Page 1 of 7

SECTION – III SPECIAL INSTRUCTIONS

1.0 These special instructions supplement the General Conditions of Contract

(GCC) and shall be part of the Contract document. Wherever these special

instructions are at variance with the corresponding conditions, stipulations, and

specifications elsewhere in the tender document, these special instructions

shall prevail.

2.0 The site is located at about 30 KM by Road on North East of Kanyakumari near

Kudankulam Village in Radhapuram Taluk of Tirunelveli District.

3.0 The Tenderers are advised to inspect the site and acquaint themselves about

the site conditions, availability of materials, labour, water, electric power, roads,

weather and geological conditions etc. before submitting their tenders. It will

be deemed that the tenderers have taken into consideration these factors while

quoting their rates and no claim on account of any ambiguity will be

entertained.

4.0 The Tenderers shall note that if any clarification regarding specifications,

conditions of contract, schedule of quantities, scope of work etc., is required,

he should contact the office of the ENC (TS), Kudankulam Nuclear Power

Project, Kudankulam, Radhapuram Taluk, Tirunelveli District.

5.0 The Contractor shall layout his work and shall be responsible for all

measurements in connection therewith. The Contractor shall be held

responsible for the proper execution of the work.

6.0 The time allowed for carrying out the work as entered in the tender shall be

strictly observed by the Contractor and shall be deemed to be the essence of

the contract on the part of the Contractor and shall be reckoned from which the

work is reckoned to have started as per work order. The entire work shall be

completed with in stipulated time as mentioned in the tender document.

'Monsoon or inclement weather/ rough sea conditions etc will not be a reason

for any extension of time.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - III Special Instructions Page 2 of 7

7.0 During the execution of work the Contractor shall keep the entire site in neat

and tidy condition and will remove all debris and waste materials from the site

regularly.

8.0 All royalties, excise duties and other taxes on the materials brought by the

contractor to the site will be paid by him.

9.0 Income tax, VAT/WCT and other statutory levy etc., on this contract as notified

by Central/State Govt. from time to time and recoverable by NPCIL at the time

of release of bills, shall be recovered from running account bills as well as final

bills for this work, in the prescribed manner. Service tax as applicable shall be

borne by the contractor and should be registered under service Tax for the

service offered under this work.

10.0 The Contractor shall make his own arrangement for the security and safety of

his materials at the site of work at his own cost.

11.0 Entry permit with identity will be issued in favour of the contractor and his

employees on application made to Engineer in charge in KKNPP site and the

cost of identity cards will be borne by the contractor.

12.0 The contractor shall follow strictly the security regulations prevailing at KKNPP

site from time to time especially in regard to working hours movement of

materials, entry permit etc.

13.0 Electric power will not be supplied by NPCIL. If required by the contractor, it will

be made available on a chargeable basis as per prevailing TNEB Tariff,

applicable from time to time, from existing NPCIL Sub station at a single point

at a nominal system voltage of 415 volts, 3 phase, 4 wire, 50 Hz.

14.0 WATER SUPPLY :

NPCIL will not be able to supply water for works at site to the Contractor. The

Contractor shall make his own arrangements to provide the same at his own

cost.

15.0 All the materials to be used in the work shall be got approved by the Engineer-

in-charge before they are brought to site. If the materials delivered at site are

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - III Special Instructions Page 3 of 7

found defective or below IS standards any work executed with such supply will

be rectified/strengthened or rejected as per the decision of the Engineer-in-

charge at the cost of the Contractor. The sub-standard materials will also be

removed from the site at the Contractor’s cost.

16.0 ESCALATION:

Escalation is applicable as per clause No: 11.3 of G.C.C.

17.0 The contractor shall comply with various provisions of the contract labour

(Regulation and Abolition) Act and rules formed there under especially to

obtain licence before commencing the work. Further the contractor shall

comply with the provisions of labour laws such as Workmen’s Compensation

Act, Minimum Wages Act and other laws applicable.

18.0 The contractor shall not sub contract the work to any other person.

19.0 The contractor shall at all time take Precautions for the safety of his employees

in performance of the contract and NPCIL will not take any responsibility or

liability in case of accident/death of licencee’s employees.

20.0 Contractor, on written request and on submission of detailed measurement

bills, will be eligible for one payment per month.

21.0 Tenderer shall submit along with the tender details of their past experience

including value of each work and name of clients and other relevant

information.

22.0 Defect liability period shall be 12 months from the certified date of completion

of contract.

23.0 The successful bidder shall take out at his own cost, the following insurance

polices for the contract period effective from the date of commencement of the

work with an insurer acceptable to NPCIL for an appropriate amount and

documents in this regard should be submitted to the Engineer-in-charge before

start of work.

a) Public Liability policy (Non industrial risks) /Third Party Insurance b) Workmen Compensation policy in respect of all his workmen

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - III Special Instructions Page 4 of 7

engaged in the work.

c). Group Insurance to cover contractor, Engineers and supervisors

employed by the contractor. If already covered documentary proof to

be produced.

24.0 Mode of measurement when not specified in the tender (specifications and

schedule of quantities) shall be in accordance with relevant Indian Standard

Specifications and where not spelt out in ISS, Engineer’s decision shall be final

and binding on the Contractor. In case of any dispute arising out of the mode

of measurement, the Engineer’s decision on this shall be final and binding on

the Contractor.

25.0 The bids submitted shall remain valid for acceptance for a period of 120 days

from the date of opening of the bid.

26.0 The work shall be carried out strictly in accordance with the Contract

specifications. In the absence of any specification for any work or material,

relevant Indian Standard Specifications will be applicable and where these

Standard Specifications do not exist, relevant Specifications apply. The

decision regarding acceptability of relevant IS, will be solely at the discretion of

Engineer-in-charge and shall be binding on the Contractor.

27.0 The contractor shall be required to comply with various provisions of the safety

code Prescribed in tender document/agreement. All the safety provisions and

rules provided in Section – III A (“Guide of AERB for works contract”) and

Atomic Energy (factories) Rules must be strictly followed.

28.0 The Contractor may use the roads formed by NPCIL in the vicinity of the works

for transport and haulage of materials subject to the approval of Engineer for

such use. Additional haulage roads as are required by the Contractor, shall be

constructed by him at his own cost. Location of such roads shall however be

subjected to the prior approval of the Engineer. All roads at the work site,

including any road formed by the Contractor will be made use of by the project,

other Contractors and agencies at site and the Contractor shall not be entitled

to any payment or compensation on this account.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - III Special Instructions Page 5 of 7

29.0 CONTRACTOR TO PROVIDE LABOUR AND ASSISTANCE:

The Contractor shall provide necessary labour and assistance to the Engineer

for checking layout, alignments, levels and other survey works connected with

execution of work and also for taking measurement for finished works at no

extra cost to NPCIL.

30.0 If labour licence is required to be obtained, a certificate from the principal

Employer, based on the maximum number if workmen you propose to employ

for this work will be issued to you on your written request to enable you to

obtain the labour licence.

31.0 SITE FAMILIARIZATION:

The tenderer shall ensure that he has satisfied himself as to the nature and

location of the work, the general and local conditions, particularly those bearing

upon transportation, disposal, handling and storage of materials, availability of

labour, water, electric power, roads and uncertainties of weather, or similar

physical conditions of the site, the confirmation and conditions of the ground

character, the quality and quantities of surface and sub-surface materials to be

encountered, including the sub-soil water level, the character of

equipment/facilities needed, preliminary and during the progress of the work,

site features for the off-shore works, requirement of special plant, machinery,

equipment, personnel etc. for the off-shore works and all other matters which

can in any way affect the work or its cost thereof under this contract. Any

failure of the Contractor to acquaint himself with all the available information

concerning these conditions will not relieve him of the responsibility of

estimating properly, the difficulty or cost of successfully performing the work.

Non-familiarity with the site conditions will not be considered a reason either for

extra claims or for not carrying out the work in strict conformity with the

drawings and specifications.

32.0 MAINTENANCE OF CLEAN SITE CONDITIONS:

During the execution of work the Contractor shall keep the entire site in neat

and tidy condition and will remove all debris and waste materials from the site

regularly and maintain the site in hygienic condition without any extra payment.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - III Special Instructions Page 6 of 7

Accumulation and piling of materials /debris will not be permitted except only at

the locations approved from time to time for this purpose.

33.0 PLANT & MACHINERY:

(a) The tenderer should deploy all plant and machinery required to carry out

the work with out any delay.

(b) Contractor shall deploy adequate resources like manpower and

machineries separately for exploring the possibility of taking up works

simultaneously in multiple locations.

34.0 PAYMENT OF EXTRA ITEMS: The rates for altered, additional or substituted item of work shall normally be

worked out in accordance with Clause 11.2 of the General condition contract.

35.0 REMOVAL OF TEMPORARY WORKS, PLANT AND SURPLUS

MATERIALS: Prior to final acceptance of the completed work but excepting as otherwise

expressly directed or permitted in writing, the Contractor shall at his own

expense, remove from the site and dispose of the temporary structure including

all false work and scaffolding, crib work, all plant and material and debris to the

satisfaction of the Engineer.

36.0 RIGHTS OF OTHER AGENCIES: The Contractor shall note that several other agencies may also be

simultaneously working within and around the structures covered under the

present contract.

The Contractor shall permit as directed by the Engineer from time to time, such

works to be carried out, without any hindrance and shall fully co-operate with

the other agencies working therein. In case of dispute in such co-ordination,

the Engineer’s decision shall be final and binding on the Contractor.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - III Special Instructions Page 7 of 7

37.0 FAIR WAGES: The wage paid to the labourers shall not be less than the higher of fair/minimum

wages as fixed under any law, statutory rule or order from time to time to that of

the State/Central Government. However, increase in the wages due to any

statutory act or by rules framed there under by the Government or by local

authorities during the currency of the contract or during any valid period of

extension of contract shall not be considered reason for any reimbursement or

extra claim. The bidder is deemed to have taken this aspect into consideration

in his unit rates for various items of work covered under this contract.

-----------

SECTION III-A

GENERAL SAFETY GUIDE

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 1 of 33

SAFETY GUIDE FOR WORKS CONTRACT

1. INTRODUCTION Many of the works of Department of Atomic Energy at its various sites are executed

by the contractors. During these works, contractors personnel are likely to the

exposed to different types of hazards. Similarly, unsafe acts of contractors

personnel may generate hazards for Departmental staff and/or workmen of other

contractors working at the site. Such unsafe acts may also pose danger to the

existing installations and even to members of public. This guide is prepared to

facilitate safe working during execution of contract works. It is hoped that units of

DAE may issue this guide as a part of contract documents while awarding contracts.

2. GENERAL SAFETY PROVISIONS 2.1 The Contractor shall take all safety precautions during the execution of awarded

work and shall maintain and leave the site safe at all times. At the end of each

working day and at all times when the work is temporarily suspended, he shall

ensure that all materials, equipment and facilities will not, cause damage to

existing property, personal injury or interfere with the other works of the project or

Station. The contractor shall comply with all applicable provisions of the safety

regulations, clean up programme and other measures that are in force at the site.

2.2 The Contractor shall provide and maintain all lights, guards, fencing, warning

signs, caution boards and other safety measures and provide for vigilance as and

where necessary or as required by the Engineer-in-charge or by any duly

constituted authority for the protection of workers or for the safety of others. The

caution boards shall also have appropriate symbols.

2.3 Adequate lighting facilities such as flood lights, hand lights and area lighting shall

be provided by the Contractor at the site of work, storage area of materials and

equipment and temporary access roads within his working area.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 2 of 33

The contractor shall obtain written approval of the Engineer-in-charge to the

lighting scheme and place of tapping prior to its installation.

2.4 The contractor shall plan his operations so as to avoid interference with the other

Departmental works, other contractors or Sub-Contractors at the site. In case of

any interference, necessary coordination shall be sought by the contractor from the

Department for safe and smooth working.

2.5 The Contractor and his sub-contractor, if any shall comply with the instructions

given by the Safety Engineer or his authorized nominee regarding safety

precautions, protective measures, house keeping requirements, etc. The Safety

Engineer with due intimation to Engineer-in-Charge shall have the right to stop the

work of the Contractor, if in his opinion proceeding with the work will lead to an

unsafe and dangerous condition. Engineer-in-Charge shall get the unsafe

condition removed or provide protective equipment at the contractors cost. The

contractor can employ his own safety Engineer or nominate one of his officers for

liaison with Departmental Safety Engineer for ensuring compliance of all safety

rules. Contractor shall ensure that all his workmen are aware about the nature of

risk involved in their work and have adequate training for carrying out their work

safely.

2.6 The contractor shall be held responsible for non-compliance of any of the safety

measures and delays, implications, injuries, fatalities and compensation arising out

of such situations of incidents.

3. TRAFFIC

3.1 The contractor shall conduct his operations so as to interfere as little as possible

with the use of existing roads at or near locations where the work is being

performed.

3.2 When interference to traffic is inevitable, notice of such interference shall be given

to the Engineer-in-charge well in advance (at least 48 hours) with the details of

start of the work and time required, storage of materials, and details of the

proposed methods of providing the required facilities for safe and continuous use

of roads and obtain his clearance.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 3 of 33

3.3 The contractor shall, at his own expense, make such approved temporary

provisions as are required to maintain atleast one lane of traffic by bridging the

excavation, providing ramps over surface obstructions or providing suitable

temporary bye-pass around the obstructions. The Contractor shall exercise full

care to ensure that no damage is caused by him or his workmen, during the

operation, to the existing water supply, sewerages, power or telecommunication

lines or any other services or works. The contractor shall be required to provide

and erect before construction, substantial barricades, guard-rails, and warning

signs. He shall furnish, place and maintain adequate warning lights, signals, etc.,

as required by Engineer-in-charge. 4. SAFE MEANS OF ACCESS 4.1 Adequate and safe means of access and exit shall be provided for all work places,

at all elevations. Using of scaffolding members (avoiding a ladder) for approach to

high elevations shall not be permitted.

4.2 Suitable scaffolds shall be provided for workmen for all works that cannot safely be

done from the ground, or from solid construction except such short duration

work as can be done safely from ladders. Ladder shall be of rigid construction

having sufficient strength for the intended loads and made either of good quality

wood or metal and all ladders shall be maintained well for safe working condition.

An extra mazdoor shall be engaged for holding the ladder if ladder is not securely

fixed. If the ladder is used for carrying materials as well, suitable foot holds and

hand holds shall be provided on the ladder. The ladder shall be given an

inclination not steeper than 1 in 4 (1 horizontal and 4 vertical). Ladders shall not

be used for climbing carrying materials in hands. While climbing both the hands

shall be free.

4.3 Scaffolding or staging more than 3.5m above the ground or floor, swung or

suspended from an overhead support or erected with stationary support shall have

a standard guard rail properly attached, bolted, braced or otherwise secured at

least 1.0m high above the floor or platform of such scaffolding or staging. The

guard rail shall extend along the entire exposed length of the scaffolding with only

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 4 of 33

such opening as may be necessary for the delivery of materials. Standard railing

shall have posts not more than 2m apart and an intermediate rail halfway between

the floor or platform of the scaffolding and the top rail. Such scaffolding or staging

shall be so fastened as to prevent it from swaying from the building or structure.

Scaffolding and ladder shall conform to relevant IS specification (IS: 3696-1966).

Timber/Bamboo scaffolding shall not be used.

4.4 Working platforms of scaffolds shall have toe boards at least 15cm in height to

prevent materials from falling down. 4.5 A sketch of the scaffolding proposed to be used shall be prepared and approval of

the Engineer-in-Charge obtained prior to start of erection of scaffolding. All

scaffolds shall be examined by Engineer-In-Charge before use. 4.6 Working platform, gangways and stairways shall be so constructed that they shall

not sag unduly or unequally and if the height of the platform or gangway or

stairway is more than 3.5m above ground level or floor level, they shall be closely

boarded, shall have adequate width for easy movement of persons and materials

and shall be suitably guarded as described in 3.3 above.

4.7 The Planks used for working platform shall not project beyond the end supports to

a distance exceeding four times the thickness of the planks used. The planks shall

be rigidly tied at both ends to prevent sliding and slippage. The thickness of the planks shall be adequate to take load of men and materials

and shall not collapse.

4.8 Every opening in the floor of a building or in a working platform shall be provided

with suitable means to prevent fall of persons or materials by providing suitable

fencing or railing, the minimum height of which shall be 1.0m, along with 15 cm

high sheet obstruction at floor level along the railing.

4.9 Safe means of access shall be provided to all working platforms and other elevated

working places. Every ladder shall be securely fixed. No single portable ladder

shall be over 9m in length. For ladders upto 3m in length the width between side

rails in the ladder shall in no case be less than 300mm. For longer ladders this

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 5 of 33

width shall be increased by at least 20mm for each additional metre of length.

Step spacing shall be uniform and shall not exceed 300 mm. 4.10 Adequate precautions shall be taken to prevent danger from electrical lines and

equipment. No scaffolding, ladder, working platform, gangway runs, etc. shall exist

within 3 metres of any uninsulated electric wire. Whenever electric power and

lighting cables are required to run through, (pass on) the scaffolding or electrical

equipments are used, such scaffolding structures shall have minimum two earth

connections with earth continuity conforming to IS code of practice.

5. EXCAVATION, TRENCHING AND EARTH REMOVAL 5.1 All Trenches 1.2 m or more in depth shall at all times be supplied with at least one

ladder for each spacing of 30m in length or fraction thereof. Ladder shall be

extended from bottom of the trench to at least 1m above the surface of the ground.

5.2 The sides of the trench which are 1.2m or more in depth shall be stepped back to

give suitable slope (angle of repose) or securely held by timber bracing, so as to

avoid the danger of sides from collapsing. The excavated material shall not be

placed within 1.5m of the edges of the trench or half of the depth of the trench,

whichever is more. Cutting shall be done from top to bottom. Under no

circumstances mining or under-cutting shall be done.

5.3 The Contractor shall ensure the stability and safety of the excavation, adjacent

structures, services and the works.

5.4 Open excavations shall be fenced off by suitable railing and warning signals

installed at night at well lit places so as to prevent persons slipping or falling into

the excavations.

5.5 All blasting operations shall be carried out on the basis of procedures approved by

Inspector of Explosives. All works in this connection shall be carried out as per IS

code of Practice. Barricades, Warning Signs etc. shall be placed on the

roads/open area. Prior approval of such operation shall be obtained from Safety

Engineer Engineer-In-Charge of works.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 6 of 33

5.6 a) For removal of earth from an earth mound a written permission shall be

obtained from the Engineer- In-Charge of the work and the Engineer- In-

Charge of the earth mound.

b) As far as practical, earth shall be removed mechanically.

c) Wherever manual removal of earth is involved, earth shall be removed

from the top by maintaining the proper slope equal to the angle of re-

pose of the earth.

d) Such work shall be constantly supervised by the contractor’s

responsible person and frequently inspected by the departmental

representative to ensure that no under-cutting is done.

6. CONCRETNG

Shuttering and supporting structures shall be of adequate strength and approved by

Engineer-in-Charge. This shall be ensured before concrete is poured. The

procedure approved by Engineer-in-Charge shall be followed for mixing, transporting

and pouring of concrete.

7. DEMOLITION

Before any demolition work is commenced and also during the progress of the work:

a) All roads and open area adjacent to the work site shall either be closed or

suitably protected. Appropriate warning signs shall be displayed for cautioning

approaching persons.

b) Before demolition operations begin, the Contractor shall ensure that the power

on all electric service lines is shut off and the lines cut or disconnected at or

outside the demolition site. If it is necessary to maintain electric power during

demolition operation, the required service lines shall be adequately protected

against damage. Persons handling heavy materials/equipments shall wear

safety shoes. c) No floor, roof or other part of the building shall be overloaded with debris or

materials as to render it unsafe. d) Entries to the demolition area shall be restricted to authorized persons only.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 7 of 33

8. PERSONAL PROTECTIVE EQUIPMENT:

All necessary personal protective equipment as considered necessary by the

Engineer-in-charge shall be kept available by contractor for the use of the persons

employed on the site and maintained in a condition suitable for immediate use. Also

the contractor shall take adequate steps to ensure proper use of equipment by those

concerned. The personal protective equipments are to be provided by the

contractor.

a) All persons employed at the construction site shall use safety helmets. For other

types of works, persons working in that area shall also use safety helmets, if

advised by safety Engineer/Engineer-in-charge.

b) Workers employed on mixing asphaltic materials, cement and lime mortars shall

use protective goggles, protective foot wear and hand gloves. Use of proper

respirators shall be an advantage.

c) Persons engaged in welding and gas cutting works shall use suitable welding

face shields. The persons who assist the welders shall use suitable goggles.

Protective goggles shall be worn while chipping and grinding.

d) Stone breakers shall use protective goggles. They shall be seated at sufficiently

safe intervals of distance.

e) Persons engaged in or assisting in shot blasting operations and cleaning the

blasting chamber shall use suitable gauntlets, overalls, dust-proof goggles, boots

and protective hood supplied with fresh air at the minimum rate of 9 m3/hr.

f) All persons working at heights more than 4.5m above ground or floor and

exposed to risk of falling down shall use safety belts, unless otherwise protected

by cages, guard railings, etc. In places where the use of safety belts is

impractical, suitable net of adequate strength fastened to substantial supports

shall be employed.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 8 of 33

g) All powered two-wheeler motorcycle and scooter drivers and their pillion riders

shall wear crash helmets inside the project/plant sites.

h) When workers are employed in sewers and inside manholes which are in use,

the contractor shall ensure that the man-holes are opened and are adequately

ventilated atleast for an hour. After it has been well-ventilated, the atmosphere

inside the space shall be checked for the presence of any toxic gas or oxygen

deficiency and recorded in the get register before the workers are allowed to into

the man-holes. The man-holes opened shall be cordoned off with suitable railing

and provided with warning signals or caution boards to prevent accidents. There

shall be proper illumination in the night.

9. PAINTING

9.1 The Contractor shall not employ women on the work of painting with products

containing lead in any form. Only men above the age of 18 years shall be

employed on the work with lead paint. The following precautions shall be taken

during the work.

Supplied air respirators shall be provided for use by the workers when paint

is applied in the form of spray, or a surface having lead paint is dry rubbed or

scraped. Overalls shall be supplied by the contractors to the workmen and adequate

facilities shall be provided to enable the painters to wash at the cessation of

work. All painting jobs, especially those in which lead paints are used shall be kept

under industrial hygiene surveillance.

9.2 Smoking, open flames or sources of ignition shall not be allowed in places where

paints and other flammable substances are stored, mixed or used. A caution

board, with the instructions written in national/regional language, “SMOKING IS

STRICTLY PROHIBITED” shall be displayed in the vicinity where painting is in

progress or where paints are stored. Symbols shall also be used for caution

boards.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 9 of 33

fire extinguishers/sand buckets shall be kept available at places where

flammable paints are stored, handled or used.

o n a confirmed space, adequate

entilation shall be provided. If adequate ventilation cannot be provided, workers

9.3 ions used for painting shall not be allowed to come

contact with the skin. The workers shall use plastic gloves and/or suitable

ation shall be provided especially when working with hot resin

mixes.

and eliminate its effects.

frequently.

10. L

Suitable

When painting work is done in a closed room r i

v

shall wear suitable respirators.

Epoxy resins and their formulat

in

barrier creams.

Adequate ventil

Increased personal hygiene shall be practiced to control inadvertent contract with

the resin

Workers shall thoroughly wash hands and feet before leaving the work. Work

clothes be changed and laundered

IFTING MACHINES AND TACKLES

including their attachments, anchorage and

supports shall conform to the following standards or conditions.

a) L nstruction, sound

material and adequate strength and free from any defects and shall be kept in good

ering materials or as a means of suspension shall

be of good quality and adequate strength and free from any defect.

b) ly qualified. No

erson under the age of 21 years shall be in charge of any hoisting machine or give

signal to operator of such machine.

10.1 Use of lifting machines and tackles

ifting machines and tackles shall be of good mechanical co

repair and in good working order.

Every rope used in hoisting or low

Every crane operator or lifting appliance operator shall be proper

p

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 10 of 33

case of a lifting machine having a variable safe

working load, each safe working load and the conditions under which it is applicable

d)

arge whenever he brings

any machinery to site of work and get it verified by the Engineer-in-charge,

e)

ith such means as will reduce to the minimum the

risk of any part of a suspended load becoming accidentally displaced or lowered.

11. W

c) In case of every lifting machine (and of every chain, ring, hook, shackle, swivel and

pulley block used in hoisting or as means suspension) the safe working load shall be

ascertained and clearly marked. In

shall be clearly indicated. No part of any machine or any gear referred to above in

this paragraph shall be loaded beyond the safe working load except for the purpose

of testing. This shall be approved by the Safety Engineer.

In case of departmental machines, the safe working load shall be notified by the

Engineer-in-charge. As regards Contractor’s machines, the contractor shall notify

the safe working load of the machine to the Engineer-in-ch

supported by a valid test certificate by the competent person.

Thorough inspection and load testing of lifting machines and tackles shall be done by

a competent person atleast once every 12 months and records of such inspection

and testing shall be maintained.

10.2 Motors, gearing transmission, couplings, belts, chain drives and other moving parts

of hoisting appliances shall be provided with adequate safeguards. Hoisting

appliances shall be provided w

ELDING AND GAS CUTTING

Welding and gas cutting operations shall be done only by qualified and authorize

11.1 d

persons and as per IS Specifications and code of Practice.

11.2 Welding and gas cutting shall not be carried out in places where flammable or

11.3 Welding and gas cutting equipment including hoses and cables shall be

maintained in good condition.

combustible materials are kept and where there is danger of explosion due to

presence of gaseous mixtures.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 11 of 33

11.4 done in elevated positions, precautions shall be

taken to prevent sparks or hot metal falling on persons or flammable materials.

11.5 othing consisting of fire resistant gauntlet gloves,

leggings, boots and aprons shall be provided to workers as protection from heat

1.6 Adequate ventilation shall be provided while welding in confined space or while

11.7 n emptied, cleaned thoroughly and it is made

certain that no flammable material is present.

11.8 it shall be obtained for working at volnearable areas and operating

11.9 ditional safety precautions shall be

taken:

I) of earth conductor but a separate

earth conductor shall be connected to the machine directly from the job.

II rsonnel contact with the electrode or other live parts of electric welding

equipment shall be avoided.

III)

Barriers shall be erected to protect other persons from harmful rays from the work.

When welding or gas cutting is

Suitable type of protective cl

and hot metal splashes. Welding shields with filter glasses of appropriate shade

shall be worn as face protection.

1brazing, cutting or welding zinc, brass, bronze, galvanized or lead coated

materials.

Welding and gas cutting shall not be done on drums, barrels, tanks or other

containers unless they have bee

Fire extinguisher shall be available near the location of welding operations. Fire

safety perm

areas before flame cutting/welding is taken up.

For electric (Arc) welding the following ad

When electrical welding is undertaken near pipe lines carrying flammables,

such pipe lines shall not be used as part

) Pe

Extreme caution shall be exercised to prevent accidental contact of

electrodes with ground.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 12 of 33

e cables are not damaged by movement of

materials.

12. GRIND

IV) The welding cables shall not be allowed to get entangled with power cables.

It shall be ensured that th

ING:

12.

reduc

12.2 Grinding wheels of specified diameter only shall be used on a grinder-portable or

order not to exceed the prescribed peripheral speed.

1 All portable grinders shall be used only with their wheel guards in position to

e the danger from flying fragments should the wheel break during the use.

pedestal-in

12.3 Goggles shall be used during grinding operation.

13. ELECTRICITY

Guide lines for providing temporary power supply at the site and general safety

sed Annexure.

4. HOUSE KEEPING

procedures for using electricity are given in the enclo

1

4.1 The contractor shall at all times keep his work spot, site office and surroundings

r electrical cables shall be so routed as to allow safe traffic by all

concerned.

14.3 onvenience to any person or the public. The Engineer-in-charge may

require the contractor to remove any materials which are considered to be of

hem to be removed at the contractor’s cost.

1

clean and tidy from rubbish, scrap, surplus materials and unwanted tools and

equipment.

14.2 Welding and othe

No materials on any of the sites of work shall be so stacked or placed as to cause

danger or inc

danger or cause inconvenience to the public. If necessary, the Engineer-in-charge

may cause t

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 13 of 33

14.5 ontractor fails to improve

upon the housekeeping after having been notified.

15. F

14.4 At the completion of the work, the Contractor shall have removed from the work

premises all scaffoldings, surplus materials, rubbish and all huts and sanitary

arrangements used/installed for his workmen on the site.

The Engineer-in-charge has the right to stop work if the C

IRE SAFETY ll necessary precautions shall be taken to prevent oA utbreak of fires at the

construction site. Adequate provisions shall be made to extinguish fires should they

mber, bamboos, coal, paints,

etc., shall be the minimum required in order to avoid unnecessary

mulation of combustibles at site.

t, sparks, flame or direct rays of the sun. The containers of paint

(c) Engineer-in-charge shall be located

(d)

16. SAFETY W

still break out.

(a) Quantities of combustible materials like ti

accu

(b) Containers of paints, thinners and allied materials shall be stored in a

separate room which shall be well ventilated and free from excessive

hea

shall be kept covered or properly fitted with lid and shall not be kept open

except while using.

Fire extinguishers as approved by the

at the construction site at appropriate places.

Adequate number of contract workmen shall be given education and

training in fire fighting and extinguishing methods.

ORK PERMIT

16.1 In order ration (such as entry into

confi

present, es, blasting etc.,)

its (SWP) shall be raised. The SWP’s shall also to be

obtained for any other work as recommended by Safety Engineer.

to ensure safety of work for hazardous ope

ned spaces, welding/cutting on equipment/pipes where explosion hazard is

works on high voltage and main medium voltage lin

Special Safety work perm

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 14 of 33

17. W

16.2 The Contractor shall strictly ensure all the safety conditions and requirements

stipulated in the Safety work permit. The decision of the Safety Engineer shall be

final in this regard.

ORK IN RADIATION AREA he contractor shall follow the stipulated procedure regarding work T in the radiation

area and other works related with radiography.

18. W

ORK IN AND AROUND WATER BODIES hen the work is donW e near any place where there is risk of drowning, all necessary

rescue equipment such as life buoys and life jackets shall be provided and kept

ry steps taken for prompt rescue of any person in

e of the work. Persons who do not

now swimming shall not be engaged alone for any work where risk of drowning

ackets shall be provided.

19.

ready for use and all necessa

danger and adequate provision shall be made for prompt first-aid treatment of all

injuries likely to be sustained during the cours

k

exists. Sufficient number of life buoys or life j

MEDICAL FACILITIES

1 The contractor shall arrange adequate facilities for medical aid and treatment for

his staff and workers engaged on the work site including the first-aid facilities if

they are not available at the project site.

19.

19.2 First-aid appliances including sterilized dressing, cotton wool and antiseptic cream

le at a readily accessible places at every work site. These

shall be maintained in good order under the charge of a responsible person.

19.3 ablished and be manned by a trained

compounder. An ambulance shall be available during the entire period of work for

shall be made availab

At large work places where hospital facilities are not available within easy reach of

the works, first-aid posts shall be est

attending to injury cases.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 15 of 33

20. SAFETY OFFICER/SAFETY COORDINATOR

he contractor shall have a Safety Officer or a supervisor to be designated as a

afety Coordinator in order

T

S to specifically look into the implementation of different

safety requirements of the contract work. The person thus designated will in general

co-ordinate with the Engineer-in-charge on matters of safety and in particular ensure

that the Safety Guide is complied with fully. His name shall be displayed on the

te.

21.

Notice Board at a prominent place at the work si

REPORTING OF ACCIDENT

1 All accidents leading to property damage and/or personnel injuries shall be

reported to the Engineer-in-charge immediately who shall inform SARCOP to be

followed up with detailed accident reports in prescribed form.

21.

21.2 Contractor shall also submit a monthly statement of accidents to Engineer-in-

showing details of accident, nature of injury including

disability, days lost, treatment required, etc., and the extent of property damage.

22. P

charge by 4th of every month

UBLIC PROTECTION

The Contractor shall make all necessary provisions to protect the public. He shall be

th

p d

cost which may be awarded in any such suit, action or proceeding to any such

ich may be fixed as a compromise by any such person.

23.

bound to bear the expenses for defence of every action or other proceedings at law

at may be brought by any person for injury sustained owing to neglect of any

recaution required to taken to be protect the public. He shall pay any damage an

person, or the amount wh

OTHER STATUTORY PROVISIONS Notwithstanding the above clauses from 1 to 21 there is nothing in these to exempt

the Contractor from the provisions of any other Act or Rules in force in the Republic

of India. In particular all operations involving the transport, handling, storage and

use of explosives shall be as per the standing instructions and conform with the

Indian Explosives Act, 1884 and the explosive Rules, 1983. Handling, transport,

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 16 of 33

storage and use of compressed gas cylinders and pressure vessels shall conform

Static and Mobile Pressure Vessels (Unfired) with the Gas Cylinder Rules 1981 and

Rules 1981. In addition, The Indian Electricity act 1910 and Indian Electricity Rules

1956, the Atomic Energy Act, 1962, the Radiation Protection Rules, 1971, Radiation

Protection Manual of Nuclear Facilities and the Atomic Energy (Factories) Rules,

1988 and various rules and Act related to mining shall also be strictly complied with.

* * * * * *

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 17 of 33

ANNEXURE

GUIDELINES AND GENERAL PROCEDURES FOR SUPPLY AND USE OF ELECTRICITY AT SITE

1. GENERAL

Following safety requirements shall be complied with before the contractor uses

the power supply.

1.1 T

1.2 It shall be the responsibili rovide and maintain complete

installation on the load side of the supply point with regard to the safety

requirements at site. All cabling and installation shall comply with the appropriate

statutory requirements given below and shall be subject to approval of the

De

After installation of the electrical power wiring works by the contractor, form of

completion m SGCW-1) shall be submitted by the

contractor licenced electrical contractor and /or

supervisor ntractor’s license and/or competency

certificate ectricity Board/Government Electricity

Organisatio

1.the contractor shall furnish along with the tender, the estimated load

he Contractor shall submit a list of licenced electrical staff to be posted at site.

ty of the Contractor to p

partmental Engineer-in-charge/Electrical Engineer.

a) Indian Electricity Act, 1910.

b) Electricity (Supply) Act, 1948.

c) Indian Electricity Rules, 1956.

d) National Electric Code, 1985.

e) Other relevant rules of Local Bodies and Electricity Boards.

certificate as per IS:732 (For

duly signed by the authorized valid

along with one copy of the co

of supervisor issued by the El

ns as per the enclosure.

The power supply shall be regulated as per the terms and conditions of the supply of

the respective electricity boards.

3 (a) For purposes of electrical load and power planning by the electrical section,

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 18 of 33

d during various periods/months of the contract

with the details of the construction electrical equipment/machinery with

r supply in the standard proforma enclosed (form

SGCW -2).

point in th

1.4 in earth electrode and

h prior permission. Method of

I.S.

Speci

1.5 All thr th double earthing. All light fixtures

nd portable equipment shall be effectively earthed to main earthing.

1.6

1.7 connect any additional load without prior permission of

Departmental Electrical Engineer. For obtaining additional power required, test

.8 Joints in earthing conductors shall be avoided. Loop earthing of equipment shall

requirement of electric power for the execution of the contract works in terms of

maximum Kilo Watt or KVA deman

period along

their individual load details and location/locations of power supply required for

availing temporary electric powe

(b) The electric power supply will be generally made available at one e

works site of the Contractor by the department.

(c) Where distribution boards are located at different places the Contractor

shall submit schematic drawing indicating all details like size of wires, Over

Head or cable feeders, earthing etc., The position and location of all

equipments and switches shall be given.

The Contractor shall make his own arrangements for ma

tappings thereof. The existing earth points available at site can be used at the

discretion of the Departmental Electrical Engineer wit

earthing, installation and earth testing results shall conform to relevant

fications (IS-3043).

ee phase equipment shall be provided wi

a

All earth terminals shall be visible. No gas pipes and water pipes shall be used for

earth connection. Neutral conductor shall not be treated as earth wire.

The Contractor shall not

reports of the tests mentioned in (d) of Form SGCW-1 shall be submitted.

1not be allowed. However tappings from an earth bus may be done.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 19 of 33

a) Insulation resistance test.

cd) Earth electrode resistance.

all conform to relevant IS Specifications.

The contractor shall submit a test report for his complete installation every 2 months

section in the specimen test report. One such test

llation shall be submitted before onset of monsoon.

2. r general guidance of the Contractor and shall be

ad as specific requirement, in addition to complying with Indian Electricity Act,

2.1

1.9 The entire installation shall be subjected to the following tests before energisation of

installation including portable equipment.

b) Polarity test of switches.

) Earth continuity test.

The test procedures and their results sh

or after rectifying any faulty

report for the complete insta

The following are provided fo

re

Indian Electricity Rules and IS Specifications.

Installation

a) Only persons having valid wireman’s licence/competency certificate

rvisor.

cal equipment and installations shall be installed and maintained as to

prevent danger from contact with live conductors and to prevent fires

c) Materials for all electrical equipment shall be selected with regard to working

shall be employed for carrying out electrical work and repair of electrical

equipment, installation and maintenance at site. The job shall be

supervised by a qualified licenced Supe

b) Electri

originating from electrical causes like short circuits, overheating etc.

Installation shall not cause any hindrance to movement of men and

materials.

voltage, load and working environment. Such equipment shall conform to

the relevant standards.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 20 of 33

d) roads shall be as per the statutory requirements as listed in

clause 1.2 of Annexure.

e) extra grounding connection shall be made in

appliances/equipment where chances of electric shock is high.

f) of proper rating. It is also recommended that high

rupturing capacity (HRC) fuses be used in all circuits. For load of 5 KW or

g) dequate size

shall be run along the cables/wires and earthed effectively. Metallic poles

h) Wires and cables shall be properly supported and an approved method of

i) rthing etc.

lain cement

Concrete (PCC) tile or any other approved means.

k) uitable cable

glands. Multistranded conductor cables shall be connected by using cable

lugs/sockets. Cable lugs shall preferably be crimped. They shall be of

The minimum clearance to be maintained for all overhead lines along roads

and across

Grounding conductor of wiring system shall be of copper or other corrosion-

resistant material. An

Electric fuses and/or circuit breakers installed in equipment circuits for short

circuit protection shall be

more earth leakage circuit breaker shall be provided in the circuits.

Wherever cables or wires are laid on poles, a guard wire of a

as a general rule shall be avoided and if used shall be earthed individually.

Anticlimbing guards and danger notices shall be provided on poles. Each

equipment shall have individual isolating switches.

fixing shall be adopted. Loose hanging of wires & cables shall be avoided.

Lighting and power circuits shall be kept distinct and separate.

Reinforcement rods or any metallic part of structure shall not be used for

supporting wires and cables, fixtures, equipment, ea

j) All cables and wires shall be adequately protected mechanically against

damages. In case the cable is required to be laid under ground, it shall be

adequately protected by covering the same with bricks. P

All armoured cables shall be properly terminated by using s

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 21 of 33

l) ric cables, metal circuits

and their fittings, metallic fittings and other non-current carrying parts of

m)

etc. shall be so fixed that they shall

be easily accessible. Changes shall be done only after the approval of the

n) size and

shape for protection of all the switch board, equipment etc. against rain.

o) Iron clad industrial type plug outlets are preferred for additional safety.

p)

q) be provided close to equipment for easy

disconnection of electrical equipment or conductors from the source of

proper size and shall correspond to the current rating and size of the cable.

Twisted connections will not be allowed.

All cable glands, armouring and sheathing of elect

electrical equipment and apparatus shall be effectively grounded.

All the Distribution Boards, Switch Fuse units, Bus bar chambers, ducts,

cubicles etc. shall have MS enclosures and shall be dust, vermin and water

proof. The Distribution Boards, switches

Departmental Electrical Engineer.

The contractor shall provide proper enclosures/covers of approved

Exposed live parts of all electrical circuits & equipment shall be enclosed

permanently. Crane trolley wires and other conductors which cannot be

completely insulated shall be placed such that they are inaccessible under

normal working conditions.

Open type Distribution Boards shall be placed only in dry and ventilated

rooms; they shall not be placed in the vicinity of storage batteries or

otherwise exposed to chemical fumes.

Isolating switches shall

supply when repair or maintenance work has to be done on them.

r) In front of distribution boards a clear space of 90 cm shall be maintained in

order to have easy access during an emergency.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 22 of 33

t) As far as possible electrical switches shall be excluded from a place where

where there is possibility

of explosion hazard shall be explosion proof.

u) supplies shall be

provided with PVC insulated, PVC sheathed twin/three/four core wires to

n boards. Only sheet steel

mounting or iron frame work shall be used.

v)

w)

ires shall not be used for any

temporary power supply connections. Taped joints in the wires shall not be

x) The bulbs/lamps used for illumination and testing purpose shall have cover

y) stallation of new electric system and or other extensive alterations to

existing installations, thorough inspection shall be made by Departmental

s) Adequate working space shall be provided around electrical equipment

which require adjustment or examination during operation.

there is danger of explosion. All electrical equipment such as motors,

switches and lighting fittings installed in work room

All connections to lighting fixtures, starters or other power

have better mechanical protection for preventing possible damage to

equipment or injury to personnel. Taped joints shall not be allowed and the

connections may be made in looping system. Electric starter of motors,

Switches shall not be mounted on woode

All the lighting fixtures and lamp holders shall be of good quality and in good

condition. Badly repaired or broken holders, etc. shall not be used.

Only PVC insulated and PVC sheathed wires or armoured PVC insulated

and sheathed cables shall be used for external power supply connections of

temporary nature. Weather proof rubber w

used.

or guard to protect them from accidental breakages. Only 24 V supply

system shall be used for hand lamps etc, while working inside metallic tanks

or conducting vessels.

After in

Electrical Engineer before the new system or new extension is put in use.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 23 of 33

z) wer factor falls below 0.85, necessary capacitor units

shall be provided by the contractor.

2.2 Opera

Contractor shall ensure that power factor for their loads shall be maintained

at 0.85. In case the po

tion & Maintenance

a) All persons who work with electrical installation/equipment shall be aware of

p

r

struct the proper procedure, specify and enforce the

use of necessary protective equipment such as adequately insulated pliers,

c) k shall be allowed to be dumped below or in the

vicinity of the bare overhead line conductors.

d)

rance of

Safety supervisor.

e) commenced on electrical

installations/equipment, the circuits shall be de-energised and ascertained to

i) That there shall be no danger from any adjacent live parts and

the electrical hazards, use of protective devices and safe operational

rocedures. They shall be given training in fire fighting, first aid and artificial

esuscitation techniques.

b) The supervisor shall in

screw drivers, fuse pullers, testing lamps and similar hand tools. Only

wooden ladders shall be used to reach the heights in electrical work.

No material or earth wor

Separate work permits shall be issued for individual group leaders working on

the same system which shall be returned after the completion of the work to

Safety Supervisor and no system shall be energised without the clea

Before any maintenance work is

be dead by positive test with an approved voltage testing device. Switches

shall be tagged or the fuse holders withdrawn before starting the work.

Adequate precautions shall be taken in two important aspects viz.

ii) That there shall be no chances of re-energisation of the

equipments on which the persons are working

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 24 of 33

f) The other

g) ample when

ay be used. Thus, if

ccidental shock were to cause muscular contractions one would not ‘freeze’

h) e avoided when standing on wet floor

or when hands are wet.

i)

j) When two persons are working within reach of each other, they shall never

k) When structural repairs, modification or painting work are to be undertaken,

e carried.

ity. Broken

sockets/plugs shall be replaced immediately with good ones. Only joint free

n) Floors shall be kept free from trailing electrical cables to avoid tripping

While working on or near a circuit, whenever possible the use of one hand

may be practiced even though the circuit is supposed to be dead.

hand may preferably be kept in pocket.

When it is necessary to touch electrical equipment (for ex

checking for overload of motors) back of the hand m

a

to the conductor.

Operation of electrical equipment shall b

Before blown fuses are replaced, the circuit shall be locked out and an

investigation shall be made for the cause of the short circuit or overload.

work on different phases of the supply.

appropriate measures shall be taken for the protection of persons whose

work may bring them into the proximity of live equipment/circuit.

l) It shall be ensured that the insulation and wire size of extension cords are

adequate for the voltage and current to b

m) While tapping electricity from the socket, plug top must be used. It shall be

ensured that no extension boards are over loaded while tapping. Only

standard three pin plugs shall be used for tapping electric

cables shall be used for connecting equipment/apparatus.

hazard.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 25 of 33

o)

p) Temporary electrical connections shall be removed as soon as the stipulated

n boards and the other facilities he may have erected.

q) ping of power by others from distribution boards under the

r)

e shall be used during maintenance works on the electrical

equipment.

2.3 Port

Power supply to all the machines and lighting fixture shall be switched off

when not in use.

work is over. After completion of the works, the contractor shall dismantle the

distributio

Unauthorised tap

control of the contractor shall be prohibited at all circumstances.

No flammable materials shall be stored in any working area near the switch

boards.

s) Safety work permits shall be used for switching off the main feeder and

equipment by the contractor.

t) “MEN ON LINE” “ DO NOT SWITCH ON” “DANGER” or “CAUTION” board as

applicabl

able electrical equipment

shall be maintained for inspection recording, the testing dates

and results of the equipments.

shall be provided with three core cable and three

pin plug. The third pin of the plug shall invariably be earthed. It shall be

c)

opper wire in one length. No joints shall

be allowed in this flexible wire. In case single length of wire is not

a) Portable electrical equipment shall be regularly examined, tested and

maintained to ensure that the equipment and its leads are in good order.

Register

b) All portable appliances

ensured that the metal part of the equipment shall be effectively earthed.

All connections to portable equipment or machines from the

panel/distribution board/extension board shall be taken using 3 core

double insulated PVC flexible c

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 26 of 33

d)

sufficient for a particular location then the supply can be tapped by

providing another extension board comprising of switch and socket.

Flexible cables for portable lamps, tools, and apparatus shall be regularly

examined, tested periodically and maintained to ensure safety.

* * * * * *

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 27 of 33

FORM NO. SGCW -1

FORM FOR COMPLETION CERTIFICATE

(Prescribed under Cl.1.2 of Annexure)

We certify that the installation detailed below has been installed by me/us and tested and

at to the best of my/our knowledge and belief, it complies with Indian Electricity Rules,

1956 as well as IS:732-963 code cal Wiring Installations. (System

voltage at exceeding 650 Volts (Revised).

Electric Installation at … ……….

Load of wiring ---- ------------ ---------------------

i) Light Points

iii) Plug points (3 pin)

cable

Earthin

Descrip trode, size of earth wire and number of electrodes provided:

1. Insulation resistance for the whole installation.

I/

th

of practice for Electri

………………………………………………

Voltage and system of supply ………………………………………………………….

Particulars of work Number Total Type of system ---------

ii) Fan Points

iv) Motors

If the work involves installation of overhead lines and/or underground

___________________________________________________________________

g:

tion of earthing elec

Test results:

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 28 of 33

i) Between conductors

2. Resistance of earthing electrode or earthing system.

um earthing resistance of installation ___________________________

ignature of Supervisor Signature of Contractor Name and Name and address of Supervis of Contractor.

ii) Between each conductor and earth

3. Maxim

S address or.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 29 of 33

FORM NO CW-2

‘A’ APPLICATION FOR SERVICE ONNECTION BY CONTRACTOR (Prescribed under Cl.1.3 of Annexure)

(to be filled in triplicate)

1 Name & Address of Contractor :

2 Reference to Tender & Work :

3 Co

4 Connected load details (please attach

5 Max. demand anticipated :

6 Nature of service connection required

ble

the tender) :

Department whether SD is paid :

e deposited : 10 Name of Supervisor/Electrician in

Cha nce :

.SG C

Order

mpletion period :

Details in a separate sheet) :

(Whether single or three phase) :

7 Place where service required

a) Works :

b) Colony :

8 If supply of electricity is free or chargea(Please enclose extract of conditions from

9 Details of meter provided

a) If meter required from the

b) Details of SD (Security Deposit) :

c) Whether meter is tested or not, if tested, attach test report, if not, Details of testing fe

rge of installation and maintena

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 30 of 33

1 Ele ed Agains :

12

4 First Aid facility/box available for use, if any :

(Signature of the Contractor)

e: ame:

‘B’ CERTIFICATE BY THE CONTRACTOR

1 ctrical licence No. of person mentiont col.10

Electrical safety appliances available for use :

13 Fire extinguishers available for use :

1

Dat N

we am/are agreeable to the bills, in respect of this service connections being raised on the

asis the connected load furnished above, in case the actual consumption falls below the

one stipulated by the ten

Address:

…………………………………………………

Certified that my/our installations have been carried out in accordance with I.E. Rules and

that I/We have employed competent persons to handle the installations.

I/

b

der conditions.

(Signature of the contractors)

Name:

Date:

………………………………………………

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 31 of 33

GINEER

‘C’ CERTIFICATE BY THE CONTRACT CONTROL EN Verified the particulars and forwarded to the Engineer In Charge.

er)

Name:

Section: Civil/Electrical/Mechanical

……………………………………………………………………………………………...

‘D’ CERTIFICATE BY THE ENGINEER IN CHARGE

Certified that the particulars furnishe re true to the best of my knowledge

and belie

Signature:

Name:

Designation with section:

E SAFETY ENGINEER

(Signature of Contract control Engine

d by the contractor a

f and that I have satisfied myself as to the safe conditions of electrical installations

for which the service connection is applied for.

Date:

‘E’ CERTIFICATE BY TH

Signature of Safety Engineer.

Name:

…………………………………………………

Certified that I have inspected the electrical installations referred herein and after satisfying

myself about the safe conditions of the installation, I hereby recommended that the service

connection be given to the contractor.

Date:

………………………………………………

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 32 of 33

‘F’ AUTHORISATION BY THE ELECTRICAL ENGINEER Service connection may be/may not be given for the reasons noted hereunder.

Signature of Electrical Engineer.

Name:

ate:

Designation:

D

‘G’ ‘REPORT OF COMLIANCE’ Service connection is give by me on

3.

1. ) Initial readings:

1. c) Locations:

d) Mater sealings

Signature Electrical Engineer

(Metering and Billing)

Name:

Designation:

1. a) Meter Nos.

2.

2.

b

3.

2.

3.

of

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III A Safety guide Page 33 of 33

ate:

nd copy to Safety Engineer

nd 3rd copy to Electrical Engineer

lities are completed

and Report of Compliance(G) are filled

up by the Electrical Engineer after power

supply is given

D

Note:

1st copy to Contract Control Engineer After all the forma

2

a

SECTION III-B

UNCONDITIONAL UNDERTAKING

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section – III- B Undertaking Page 1 of 1

SECTION – III-B

Undertaking / Confirmation / Acceptance by bidder Bidders are required to confirm the following failing which, their bid shall be considered incomplete and shall be summarily rejected. 1.1 We hereby confirm that the work under subject tender shall be executed in

the desired time schedule.

1.2 We agree to augment all types of resources to meet the agreed time

schedule and the details of the same shall be worked out and submitted to

NPCIL for acceptance.

1.3 Our bid is hereby submitted unconditionally, accepting NPCIL’s all “terms

and conditions” stipulated in the subject tender.

1.4 The safety guide as mentioned in section-III A has been read and

understood by me.

Signature: Seal of the Company:

SECTION IV

GENERAL CONDITIONS OF CONTRACT

SECTION IV

General Conditions of Contract is

attached separately

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - IV Schedule A, B & C GCC Page 1 of 4

Schedule-A

S. No

Clause Reference No.

ITEM STIPULATION

1. NIT 37.1 Applicability of Mega Power Project Concession No

2. 1.1.1 Accepting Authority PD

3. 2.1.3 Time by which possession of site will be given Immediate

4. 4.14.1 Availability of Electricity Yes

5. 4.14.1 The rate at which electricity will be charged Rs.5.00/unit

6. 4.19.2 Number of trees to be planted by the contractor Nil

7. 4.22.1 Number of Apprentices to be trained by the

contractor

Nil

8. 4.23.2 Availability of Departmental water supply No

9. 4.23.2 (i) Water charges NA

10. 4.24.2 Land availability for contractor's colony No

11. 5.6.3 Penalty, for not providing arrangements and facilities as per safety guidelines

Rs.100.00 per violation

12 5.6.4 Industrial Safety Training to be provided by

Corporation

No

13 5.6.14 Minimum number of safety professionals to be

employed by Contractor

As per norms

14 5.6.15 Penalty, for not deploying the minimum number of

safety professionals

NA

15 7.8.1 Applicability of the Incentive clause No

16 7.8.2 Maximum percentage of the contract value, which

shall be paid as incentive

NA

17 7.9.3 Compensation for suspension (entire work)beyond 30 NA

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - IV Schedule A, B & C GCC Page 2 of 4

days (per day rate )

18 9.1.1 Defect Liability Period

For the contracts other than maintenance contracts mentioned below

12 Months

For contracts such as housekeeping, annual repairs, dismantling roads, horticulture, service contracts etc.

Nil

19 9.1.6 Applicability of liability towards Latent defect No

20 11.3.4 Various Component expressed as a percentage of contract value

Unskilled labour component (lu) 13.96%

Skilled labour component (ls) 4.66%

Material component -

Cement (M) -

steel (N) -

All the other materials (O) 66.38%

P.O.L Component (P) -

Nearest Petrol pump to be considered for petrol

prices (P.O.L)

IBP Dealer, Kudankulam

12.1.4 The rate of interest to be charged for mobilisation 21. advance

NA

22 12.2.1 Applicability to submit the bills and measurement in Computerised form No

23. 12.5.1 Interest for delayed payment 12.25% per annum

15.1.1 Amount of Third party liability to be covered in 24. Insurance

10% of the contract value

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - IV Schedule A, B & C GCC Page 3 of 4

SCHEDULE ‘B’

MATERIAL ISSUED TO THE CONTRCTOR

(The Engineer-in-Charge to indicate permissible wastage before issue of tender duly approved by the Competent Authority) S. No.

Particulars Unit Rate at which Material will be issued

Maximum invisible wastage (Non-Returnable)

Maximums permissible wastage (Returnable in case of free issue)

Qty. to be issued (approx.)

1 2 3 4 5 6 7 1 2. 3

Street light fittings 4C X 16 sqmm/4C X 25sqmm/ Aluminium cable 3C X 2.5 sqmm/3C X 4sqmm copper cable

Nos Meter Meter

Free Free Free

Nil 2% 2%

Nil Nil Nil

150 5000 1200

• This percentage can vary as per the cutting plan approved by Engineer-in-Charge

Signature of Issuing Officer : Signature of Contractor: Date : ………………………. Date : ………………………..

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - IV Schedule A, B & C GCC Page 4 of 4

SCHEDULE ’’C’’

TOOLS AND PLANT TO BE HIRED TO THE CONTRACTOR

Sl.No Particulars Number available

Hire charges per Unit

per working

day Rs

Frequency of

Maintenance

Value per Unit

Place of

Issue

Number Reqd. by

the contractor

1 2 3 4 5 6 7 8

---Nil--- Tools and Plants are not expected to be hired out to the Contractor If, however, any tools and plants are available at the time of performing the work the same may be hired out at rates to be decided by the Engineer-in-Charge. The Corporation reserves the right not to hire out any T & P and to withdraw at any time such T & P hired out. The Contractor shall ask the Engineer-in-Charge the value of tools & Plants for which these have to be insured and carry out the insurance accordingly in case insurance not available with NPCIL Signature of Issuing Officer . . . . . . . . . . Signature of Contractor . . . . Date : ....................... Date : .......................

1

ADDENDUM :

Clause Ref. No. Existing Clause Revised Clause 7.9.3(ii) If the total cumulative period of all

such suspension exceeds 30 days the contractor shall, in addition, be entitled to compensation for the period of suspension beyond 30 days, as mentioned in the Schedule A. However, the contractor shall submit within 10 days his claim to the engineer-in-charge for every 15 days of suspension, over and above 30 days.

If the cumulative period of all suspension(s) exceeds 30 days, the Contractor shall, in addition, be entitled to compensation for the period of suspension beyond initial 30 days, in respect of wages for the employees and workers, idling charges for plants, machineries and equipments, etc. physically available at the site. However, the Contractor shall, at the earliest within a maximum period of 15 days, from the date of suspension, submit its claim to the Engineer-In-Charge, for every 15 days of suspension, over and above the initial 30 days period of suspension, along with all documentary evidence available in respect of the employees, workmen, plants, machineries and equipments remaining idle during such period of suspension. In this regard, the Engineer-In-Charge shall after giving an opportunity of being heard to the Contractor, assess, calculate, decide and settle the claims so submitted by the Contractor and that the decision of Engineer-In-Charge shall, in this regard, be final and binding upon the Contractor.

2

Clause Ref. No. Existing Clause Revised Clause 11.3.2 For Contract(s) where completion

period as stipulated in NIT or work order is less than and upto 12 (twelve) months and where there is a delay which is attributed to the Corporation, due to which the period of the contract exceeds 12 months, the contract price adjust-ments is applicable for the extended period (For example, where the original contract period is 10 months and there is extension for 3 months, then adjustment is payable for one month i.e. 13th month only). However, the subscript value of “0” defined in 11.3.4 above shall be the indices of the month in which the mid period (50% in terms of days) of the extended contract period falls on.

For Contract(s) ------------------ ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- ------------------------------------------------- However, the subscript value of “0” defined in 11.3.4 above shall be the indices of the month in which the mid period (50% in terms of days) of the original contract period falls on.

15.1.1 The Contractor shall provide in the joint names of the Corporation and the Contractor, insurance cover from the date of commencement of work to the end of the Defects Liability Period. The Contractor is liable to take Contractor’s all risk policy for the whole contract value. The insurance amount shall also cover third party liability to the extent, if any as specified in Schedule A. In addition to this the contractor shall also take Workmen Compensation Policy for workmen.

The Contractor shall provide in the joint names of the Corporation and the Contractor, insurance cover from the date of commencement of work to the end of the Defects Liability Period. The Contractor is liable to take Contractor’s all risk policy for the whole contract value. Apart from Contractor’s all risk policy, the contractor shall also take insurance policy to cover third party liability for 10% of the contract value subject to a maximum of Rs 50 lakhs. In addition to this the contractor shall also take Workmen Compensation Policy for workmen.

Sl.No.17 of Sch.Aagainst Clause7.9.3

Compensation for suspension (entire work) beyond 30 days (per day rate) : Rs. _____ / day.

Deleted

Sl.No. 24 of Sch Aagainst clause15.1.1

Amount of third party liability to be covered in insurance Rs.______

Deleted

15.5 of NIT Attendance at the pre-bid meeting is mandatory for all the bidders.

Attending the pre bid meetings is in the interest of bidders to understand the scope of work of the tender. It is insisted upon that bidders shall attend the pre bid meetings. However, incase the bidders do not attend the pre bid meetings, it would be presumed that they have understood the scope of work.

SECTION V

TECHNICAL SPECIFICATIONS

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

  

Section - V Technical specification Page 1 of 5

 

SECTION – V

TECHNICAL SPECIFICATION

1.0 Scope of work:

1.1 General:

The scope of work shall generally as given in the tender schedule and in the drawings.

The intension of the specifications, tender schedule and the drawings is to give finished

work of approved and standard quality and all duly tested and commissioned. All minor

items if details usually not shown or indicated but necessary for the completion of the

system including testing, commissioning and handing over shall be deemed to have

been included in the work and in the rates quoted by the Contractor.

1.2 Regulation & Standards

The installation shall conform in all respects to respective Indian standards and shall

also be in conformity with the current Indian Electricity Rules. Indian Electricity Act.

National Electric Code and Regulations of the Local Electrical Supply Authority in so for

as these become applicable to the installation. Wherever this specification calls or a

higher standard of material and / or workmanship than those required by any of the

above regulations then this specification shall take precedence over the said regulations

and standard. In general, the material equipments and workmanship not covered by the

above shall conform to the relevant Indian Standards.

1. IS 3043 - Code of practice for earthing

2. IS 7098 - XLPE insulated cables

3. IS 694 - PVC insulated cables

4. IS 1161 - Steel tubes

5. IS 2713 - Swaged tubular steel poles

6. IS 2629 - Galvanizing

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

  

Section - V Technical specification Page 2 of 5

 

7. IS 2633 - Galvanizing

8. IS 5216 - Guide for safety procedures and practices in Electrical

works

9. IS 1913 - Electric light fittings general & safety requirements

10. IS 226 - Structural steel materials

2.0 Street light poles:

The Contractor shall supply approved make street light poles having designation: 410 –

SP 57, single cross arm and double cross arm as per SOQ, steel tube confirm to IS

1161 / 1979- UTS 410 MPa (42 kgf/ mm2) grade YST – 240. Swaged tubular steel

poles confirming to IS 2713 and fully HOT dip galvanized as per relevant IS. The

thickness of galvanization shall not be less than 120 microns. The poles after

manufacture shall be thoroughly cleaned both inside and outside for any burrs. The

portion that goes below the ground viz the planting depth should be painted with black

bituminous paint confirming to IS 158, through out internally and externally including

6mm thick base plate.

2.1 Installation of street light poles

Installation will be done as per schedule specification & drawings. The scope includes

supply & providing of 2 Nos of 1.2 mtr 50mm dia bend GI Pipe, painting of GI poles with

double coats of aluminum paint, numbering of poles etc, all as directed by Engineer in

Charge to complete the job in all respects.

3.0 LV Power Cables:

3.1 The cables will be used for connection for power circuits of the auxiliary electrical

systems.

3.2 The insulation & sheath materials shall be resistant to oil, acid and alkali and shall be

tough enough to withstand mechanical stress during handling.

3.3 Armouring shall be of galvanized flat steel for multi core cables.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

  

Section - V Technical specification Page 3 of 5

 

3.4 Core identification or multi core cable shall be provided by colour coding.

3.5 Drums length & Tolerance

The cable shall be supplied in wooden drum each containing minimum 500 mts.

Length. Allowable tolerance on individual drum length is + 5%

3.6 Routine tests

Routine tests shall be carried out on each and every drum and 3 sets of certificates shall

be furnished along with supply of cable

3.7 Cable Laying

Cables will be laid in existing trenches/ pipes shown by Engineer without any kinks and

bends. The bending radius and laying will be done as per relevant Indian standards. If

the cable is laid on wall/floors, the contactor shall supply 25x3mm GI saddles and

clamping of cable with required fasteners to suit the site requirement in the scope of

contractor.

3.8 Termination & Connection

The Contractor shall supply approved make of compression glands as mentioned in

schedule aluminum lugs to suite the site requirement, crimping paste erc. Contractor

shall terminate & connect all the cable laid by him.

4.0 Excavation of cable trench & pole pits:

Scope includes excavation of cable trench/ pole pits into any type of soil/ jack

hammering in to disintegrated rocks all as required at Site, Refilling of cable trench with

excavated soil and ramming etc. As directed by Engineer in Charge.

4.1 Excavation works will be started after approval of the routing by Engineer in Charge,

getting permission from Safety Section by applying excavation permit.

5.0 Installation of RCC Hume pipes:

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

  

Section - V Technical specification Page 4 of 5

 

After excavation in road crossing to the required depth hume pipes will be installed with

Collars. Cement plastering has to be done for collars and the ends will be provided

with jute bags for non entry of forign particles. After refilling of trench, ramming with

boulders etc, have to be done. 250 mm thick 1:2:4 mix concrete has to be provided for

leveling of the excavated portion with road level all as directed by Engineer.

6.1 Solar Lights:

Solar light shall be supplied, installed and commissioned complete including solar

modules, batter, 6 mtr length 75 mm dia medium duty GI pipe (ISI), 36 W CFL lamp and

all accessories with following specification.

Solar light shall contain the following,

1) Solar module : 12 V-74 Watt-2 nos

2) Battery (Tubular) : 12 V – 150 AH (Exide / Amarraja)

3) Lamp : 36W CFL (4 pin)

4) Inverter : Quasi sine wave

5) Charger controller : Built in (Over / Low battery protection)

6) Light out put : 2800 lumens

7) Battery box : GI

8) Charging Hrs : 5-6 Hrs Peak sun @ 100 mw/cm2

9) Operating Hrs : 12 Hrs (Automatic) dusk to dawn

10) Backup hours : 36 HRs (3 Nights operation time)

11) Life time of Battery : 5-6 Years

12) Lamp life : 8000 burning hrs.

13) Electronics : 10-15 yrs

14) Life time of solar modules : 30 Yrs

7.0 All other items will be carried out as per SOQ using high quality materials as per

relevant IS to complete the job in all respects all as directed by Engineer in charge.

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

  

Section - V Technical specification Page 5 of 5

 

8.0 APPROVED LIST OF MAKES OF MATERIALS

SI.No

Description of materials

Brand Name

1 1100V grade XLPE UG cabe Torrent/UNistar/Ravin cables/Nicco

2 Steel tubular swaged poles Kumaran industries / Jindal/Bombay

tubes & poles/Bajaj/ shah

Engineering/Subham

3

Lighting fixtures Crompton Greaves /

Philips/ Bajaj/GE

4 GI pipes Jindal / BEC

5

650V gr. Flexible cable Finbolex / Brookes/ Torrent/ RR

cable/Ravine

6 Anchor fastners Hilti / Fischer

7 Cable Glands SMI / Comet

8 Cable Lugs Dowells / Jainsons / Multi

9 Solar Light Sunlit /Tata solar

SECTION VI

SCHEDULE OF DRAWINGS

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

SECTION-VI

SCHEDULE OF DRAWING

SL

No TITLE No of

SHEETS

1 Foundation details 1

Section - VI Schedule of Drawing Page 1 of 1

SECTION VII

SUPPLY OF MATERIALS

Kudankulam Nuclear Power Project Main plant street lighting and area lighting at KKNPP site

Section - VII Supply of materials Page 1 of 1

SCHEDULE ‘B’

MATERIAL ISSUED TO THE CONTRCTOR

(The Engineer-in-Charge to indicate permissible wastage before issue of tender duly approved by the Competent Authority) S. No.

Particulars Unit Rate at which Material will be issued

Maximum invisible wastage (Non-Returnable)

Maximums permissible wastage (Returnable in case of free issue)

Qty. to be issued (approx.)

1 2 3 4 5 6 7 1 2. 3

Street light fittings 4C X 16 sqmm/4C X 25sqmm/ Aluminium cable 3C X 2.5 sqmm/3C X 4sqmm copper cable

Nos Meter Meter

Free Free Free

Nil 2% 2%

Nil Nil Nil

150 5000 1200

* This percentage can vary as per the cutting plan approved by Engineer-in-Charge Signature of Issuing Officer : Signature of Contractor: Date : ………………………. Date : ………………………..